Brown v Queensland Building and Construction Commission [2016] QCAT 6
CITATION: Brown v Queensland Building and Construction
Commission [2016] QCAT 6
PARTIES: Deborah Brown
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: GAR356-13
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Gardiner
DELIVERED ON: 7 January 2016
DELIVERED AT: Brisbane
ORDERS MADE: 1. The decision of the Queensland Building
and Construction Commission dated 2
September 2013 is confirmed.
2. The application for costs is dismissed.
CATCHWORDS: BUILDING – REVIEW – Where application
made to review decision in 2013 to not issue a
notice to rectify to builder – Where an extension
of time granted – Where only two minor defects
outstanding – Whether notice to rectify should
be issued
Queensland Building and Construction
Commission Act 1991 (Qld), ss71; 72
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
[1] On 1 August 2010, siblings Deborah and Christopher Brown employed the
builder Noosa Constructions Pty Ltd to construct a kit home for them on
-- 1 of 6 --
2
Fraser Island. Construction finished in December 2010 but there were
disputes between the parties concerning defective or incomplete work.
[2] On 17 June 2011 Ms Brown lodged a complaint with the Queensland
Building and Construction Commission (as it is now). On 24 June 2011,
the Commission advised Ms Brown that the matters were of a contractual
nature and not determined as defective work. The Commission declined
to issue a notice to rectify.
[3] At this point, Ms Brown elected to pursue the builder and not review the
decision of the Commission. This action proceeded through QCAT and
after an appeal, this matter was concluded by a decision handed down on
9 October 2012.
[4] On 21 February 2012 Noosa Constructions Pty Ltd changed its name to
Laguna Constructions Pty Ltd.
[5] On 23 May 2013, Ms Brown lodged a further complaint with the
Commission. The complaint referred to work completed in December
2010.
[6] On 2 September 2013 the Commission made a decision to request
Laguna Constructions Pty Ltd to rectify or complete some work at the
property. There were a number of items the builder was not requested to
rectify because either they were category 2 defects notified outside six
months of the completion date or, there was insufficient evidence to show
the builder had undertaken defective work.
[7] On 14 October 2013, Ms Brown filed an application to review Commission
decisions in 2011, 2012 and on 2 September 2013. Ms Brown also filed
an application to extend time to file this reviews.
[8] On 9 January 2014, the Commission made a further decision in respect of
the functions performed by the certifier.
[9] On 18 August 2014, Ms Brown made a further application to extend time
to review the 2011 decision and the 2014 decision.
[10] On 30 September 2014, the Tribunal dismissed the application to extend
time on the 2011 decision but allowed an extension of time in relation to
the decision dated 9 January 2014 to 24 October 2014.
[11] On 23 October 2014, Ms Brown filed a further review application with
QCAT about the decision concerning the certifier dated 9 January 2014.
That application will be dealt with in separate reasons on GAR010-15.
[12] A review is a fresh hearing to produce the correct and preferable
decision1. The Tribunal can confirm, amend or set aside the decision and
substitute its own or return it to the original decision maker2. The Tribunal
1 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 20.
2 Ibid, s24(1).
-- 2 of 6 --
3
is also required to fulfil its functions to achieve the objects of the QCAT Act
by encouraging early resolution, minimising costs and conducting quick
proceedings in an informal way in circumstances consistence with
achieving justice3. The parties in this matter elected to have the hearing
dealt with on the papers – without an oral hearing.
The Review of the Decision of 2 September 2013
[13] In submissions filed by Ms Brown on 15 September 2015, she attaches a
report dated 22 October 2014 of her building expert Mr Gil McGlinn from
the building firm G.J. & M McGlinn. That report lists 15 alleged defects.
Ms Brown uses this list as the basis for her review of the decision of the
Commission.
[14] In her submissions, Ms Brown disputes the findings by the Commission
that some of the defects complained of by her were contractual in nature.
She also alleges that some matters found to later be defective, were
rejected by the Commission as “out of time”.
[15] Mr McGlinn’s list, complied for Ms Brown, was the basis of a joint conclave
of experts with the Commission convened by the Tribunal on 19 March
2015. This conclave was attended by Mr McGlinn and his son Mr Gilbert
McGlinn and an expert from the Commission, Mr Daniel Stephensen, now
an area manager but previously a building inspector.
[16] A joint experts report was filed in the Tribunal on 2 April 2015. The 15
defects reported initially by Mr McGlinn were examined by the experts and
each of these will now be addressed in these reasons.
Item 1 External Steel Posts needing concrete capping as base
[17] All experts agree that Laguna Constructions Pty Ltd had entered into a
contract with a third party to perform remedial works to the base of the
steel support posts and on that basis, the item was considered resolved.
Item 2 Roof Battens requiring sealing where they penetrate the external walls
[18] Mr Stephensen advised he had inspected the gap widths. He satisfied Mr
McGlinn and Mr Gilbert McGlinn that this item was not considered to be
defective work.
Item 3 Leaking showers
[19] Mr Stephensen advised remedial works by the builder had failed in both
showers and that Laguna Constructions Pty Ltd had entered into a
contract with a third party to perform further remedial works to the
showers. On that basis, Mr McGlinn and Mr Gilbert McGlinn considered
the item was resolved.
3 Ibid, s4.
-- 3 of 6 --
4
Item 4 Main Joist under ensuite compromised
[20] Mr McGlinn and Mr Stephensen confirmed that this item had been rectified
by the builder and was no longer of concern.
Item 5 Cornices separating in kitchen, dining and living rooms
[21] Mr McGlinn and Mr Gilbert McGlinn confirmed that this item had been
rectified by the builder and was no longer of concern.
Item 6 Kitchen benchtops separating at joins
[22] Mr Stephensen said he had no knowledge of this matter.
[23] Mr McGlinn and Mr Gilbert McGlinn said they had informed Ms Brown to
contact the kitchen supplier concerning this matter and that it was outside
the scope of the builder Laguna Constructions Pty Ltd to rectify.
Items 7 & 8 Wall tiles in both showers laid against bowed walls creating a
safety hazard.
[24] Mr Stephensen said the walls were out of plumb in two shower recesses
causing gaps of between 3 and 10 mm. Mr McGlinn and Mr Gilbert
McGlinn said if flexible sealant was applied to the gaps in question, the
issue would be resolved as an item of concern.
Item 9 Fire Rated Verandah beams
[25] This item was considered by all experts to be an item of concern in the
other review application concerning the certifier.
Item 10 Ceiling insulation on the second floor
[26] Mr Stephensen advised that after his investigations he was satisfied that
insulation had been installed and that energy efficiency requirements were
complied with. He had provided an independent report confirming this to
Ms Brown.
[27] On this basis, Mr McGlinn and Mr Gilbert McGlinn did not consider this to
be defective work.
Item 11 Rain water guttering on plan omitted
[28] This issue had been settled between Ms Brown and the builder by way of
a cash agreement.
Item 12 Floating floor nailed down
[29] A re-inspection of a previous bulging floor by Mr Stephensen showed that
this issue had been rectified by the builder by April 2012 and that a three
nail fixing does not constitute a defect.
-- 4 of 6 --
5
[30] Mr McGlinn and Mr Gilbert McGlinn agreed with Mr Stephensen that the
item is not considered defective building work.
Item 13 damaged track of aluminium door
[31] All experts did not consider this as defective building work. Mr McGlinn
and Mr Gilbert McGlinn considered it fair wear and tear.
Item 14 Trim timber poor quality, painting sub-standard
[32] This item was considered by the Commission to be a category 2 defect
that fell outside time limits to direct the builder to rectify.
Item 15 Expansion in hallway ceiling in wrong place causing the ceiling to crack
[33] Mr Stephensen advised this was a new item of concern for the
Commission. After viewing photographs supplied by Mr McGlinn and Mr
Gilbert McGlinn, Mr Stephensen considered the expansion joint was
installed in the wrong location and would have been more beneficial if
installed where the crack occurred. This item was considered by the
Commission to be a category 2 defect that fell outside time limits to direct
the builder to rectify.
[34] Mr McGlinn and Mr Gilbert McGlinn confirmed that this item would have
been a category 2 defect.
Perimeter Termite Inspection System
[35] The joint report noted that in the Commission Request to Rectify to the
builder dated 2 September 2013, the perimeter termite inspection system
was discussed by the parties. Mr Stephensen said the Commission
engaged a third party technical consultant to investigate and supply a
report. This inspection was held on 10 March 2015 and it was established
that the termite inspection system was compliant with manufacturing
specifications and not defective.
Discussion
[36] Of the 15 defects alleged by Ms Brown, only two items (14 and 15) were
considered defects. These items were considered by the Commission to
be a category 2 defects that fell outside time limits to direct the builder to
rectify.
[37] Under section 72(1) of the Queensland Building and Construction
Commission Act 1991, the Commission has power to direct a builder to
rectify defective building work within a stated period. The Commission is
not required to give the direction if it is satisfied that, in all the
circumstances, it would be unfair to the builder to give that direction4. In
considering this element of unfairness, regard is had by the Commission
4 Queensland Building and Construction Commission Act 1991 (Qld), s72(5)
-- 5 of 6 --
6
to the Commission’s defects policy, which provides time guidelines for
category 1 and category 2 defects.
[38] Category 2 defects are defined in the policy as building work that is faulty
or unsatisfactory because it does not meet reasonable standards for
construction and finish or has caused a “settling in period” defect in a new
building.
[39] For category 2 defects, the policy provides the time frame to be 6 months
after the building work was completed or left incomplete or 7 months, if the
owner notified the contractor of the defect within 6 months of the building
work being completed or left incomplete. As this time period has passed,
the Commission considers these defects are now Ms Brown’s
responsibility.
[40] The only defective items left are two category 2 items from a decision of
the Commission of September 2013. These are poor quality door trim, an
expansion joint in the hallway ceiling badly positioned.
[41] Ms Brown has provided no further expert evidence concerning alleged
defects and it appears that apart from these two minor matters, all other
defects have been resolved to the satisfaction of all the experts from both
sides of this review.
[42] Considering the passage of time and the limited and minor nature of the
remaining defects, I am not satisfied the correct and preferable decision is
to overturn the decision of the Commission made 2 September 2013.
[43] The decision of the Commission dated 2 September 2013 is confirmed.
[44] As Ms Brown has failed in her application to change the decision of the
Commission under review, her application for costs is also dismissed.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2016/006