Brown v Queensland Building and Construction Commission (No 2) [2016] QCAT 7
CITATION: Brown v Queensland Building and Construction
Commission (No 2) [2016] QCAT 7
PARTIES: Deborah Brown
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: GAR010-15
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Gardiner
DELIVERED ON: 7 January 2016
DELIVERED AT: Brisbane
ORDERS MADE: 1. The decision of the Queensland Building
and Construction Commission dated 9
January 2014 is confirmed.
2. The application for costs is dismissed.
CATCHWORDS: BUILDING – REVIEW – Where application
made to review decision made in 2014 that a
certifier engaged in unsatisfactory conduct or
professional misconduct – Where an extension
of time granted – Where no inspection made of
requirements of Bushfire Attack Level 29 by
certifier – Whether unsatisfactory conduct or
professional misconduct
Building Act 1975 (Qld), s 204
Troy Richardson’s Building Approvals &
Inspections v QBSA [2013] QCAT 113;
Schwede v QBSA [2009] QCCTB 157 referred
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
-- 1 of 7 --
2
REASONS FOR DECISION
[1] Siblings Deborah and Christopher Brown constructed a kit home on Fraser
Island, completed in December 2010, using the services of a local builder.
[2] On 8 February 2012 Ms Brown lodged a complaint with the Queensland
Building and Construction Commission (as it is now) concerning the
conduct of the certifier Luke Nicholas Owen-Jones with respect to the site.
[3] The Commission says the effect of the complaint was that Ms Brown
alleged Mr Owen-Jones issued a Form 21 Final Inspection Certificate
when the dwelling did not comply with the requirements of Bush Fire
Attack Level (BAL) 29 of Australian Standard 3959-2009 for the
construction of buildings in bushfire prone areas.
[4] Initially the Commission says the complaint did not identify Ms Brown’s
specific concerns and at the Commission’s request, Ms Brown provided a
list of her specific issues.
[5] While Ms Brown did not consider BAL29 was generally complied with, her
specific concerns related to the deck made of pine not kwila; no nylon
brushes of external door seals on the garage door; sealing of roof gaps;
lack of signoff for an inspection of the slab; inadequate stormwater pit and
lack of insulation in the roof.
[6] This complaint was investigated by the Commission and on 9 January
2014, the Commission advised Ms Brown of its decision. The decision
was that Mr Owen-Jones engaged in unsatisfactory conduct under section
204(1) of the Building Act 1975 (Qld) (‘Building Act’).
[7] Mr Michael Pehrson, Senior Audit and Investigations Officer (Certification)
with the Commission identified1 that he believed Mr Owen-Jones had not
inspected the work as required by the inspection guidelines in the final
stage of 1a buildings for the construction requirements for bushfire prone
areas. In particular, he should have confirmed the correct timber was
used in the upper level deck framing and that the ends of the roof sheet
over the ensuite were in-filled to stop hot ember penetration.
[8] The Commission was satisfied Mr Owen-Jones breached the code of
conduct for building certifiers by not complying with legislative
requirements and not ensuring inspections are carried out.
[9] The Commission reprimanded Mr Owen-Jones under section 204(4) of the
Building Act and directed Mr Owen-Jones to provide specified documents
to the Fraser Coast Council and to the Commission.
[10] On 18 August 2014, Ms Brown made an application to extend time to
review 2014 decision concerning the certifier.
1 In the Information Notice dated 9 January 2014.
-- 2 of 7 --
3
[11] On 30 September 2014, the Tribunal allowed an extension of time in
relation to the decision concerning the certifier to 24 October 2014.
[12] On 23 October 2014, Ms Brown filed a further review application with
QCAT about this decision.
[13] A joint conclave of experts with the Commission was convened by the
Tribunal on 19 March 2015. This conclave was attended by Mr Laurence
Eves from the Fraser Coast Regional Council and the expert from the
Commission, Mr Michael Pehrson.
[14] A joint experts report was filed in the Tribunal on 2 April 2015. In relation
to the certifier, the background to the report shows that Ms Brown was
concerned that the development approval lodged with the Council showed
the site as assessed and approved as a BAL29 site and that the dwelling
didn’t comply with the requirements of the Australian Standard.
[15] During its investigations into the complaint lodged by Ms Brown, the
Commission engaged Mr Adrian Hansen, an expert in the assessment of
bushfire prone areas to assess the site in relation to the correct Bushfire
Attack level. Mr Hansen recommended the removal of some saplings and
overhanging trees. After the builder undertook this, Mr Hansen confirmed
and certified the site as BAL19 instead of 29.
[16] The experts agreed that the original certifier Mr Owen-Jones should issue
a new development approval that confirmed the Bushfire Attack Level of
BAL19. Mr Owen-Jones had been directed by the Commission in the
original decision of 9 January 2014 to lodge the new assessment and
Form 16 certificate with the Fraser Coast Regional Council so that the
information would be archived on the property file.
[17] The submission of the Commission in this matter dated 20 October 2015
record that the certifier complied with these directions2.
[18] A review is a fresh hearing to produce the correct and preferable
decision3. The Tribunal can confirm, amend or set aside the decision and
substitute its own or return it to the original decision maker4. The Tribunal
is also required to fulfil its functions to achieve the objects of the QCAT Act
by encouraging early resolution, minimising costs and conducting quick
proceedings in an informal way in circumstances consistent with achieving
justice5. The parties in this matter elected to have the hearing dealt with
on the papers – without an oral hearing.
The Review of the Decision of 9 January 2014
[19] In submissions filed by Ms Brown on 15 September 2015, she addresses
her other concerns about the conduct of the certifier. These issues reflect
2 See paragraph 18.
3 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 20.
4 Ibid s24(1).
5 Ibid s4.
-- 3 of 7 --
4
those raised by Ms Brown in her original complaint to the Commission in
February 2012 and they are responded to by the Commission in its
submissions filed 21 October 2015.
Item 1 Non-compliance with All BAL29 provisions
[20] Ms Brown identifies this as a general complaint for the Commission to
investigate. She provides no specifics under this complaint. Her major
concern has been addressed as discussed above.
Item 2 Non-compliant deck and eaves
[21] With the reclassification of the site to BAL19, and on the basis of Mr
Hansen’s report that the builder had sealed the ends of the ensuite eaves,
the site now complies with the requirements of BAL19 and the use of pine
is allowed under that standard6.
Item 3 Roller door brush and seals
[22] Inspection by the Commission of the roller door on 25 October 2012
showed that the roller door had a complying rubber seal installed that
sealed the door under the relevant standard and that the external garage
door had a solid core, a storm seal installed and a timber member sill
making it compliant with the relevant standard7.
Item 4 Sealing roof gaps.
[23] As indicated above the builder had sealed the ends of the ensuite so this
item had been rectified and was no longer of concern.
Item 5 Form 21 does not have sign off for slab stage
[24] In its submissions, the Commission stated it did not have a full copy of the
Form 21 so could not comment on this item8. However, the Commission
had a copy of the From 16 inspection certificate for the slab confirming the
inspection had been done. The Commission further submitted that this
item was irrelevant to the decision the Commission had made concerning
the certifier.
[25] Having examined the Commission’s grounds for the decision it made
concerning the certifier (the BAL classification), I am satisfied that this item
is irrelevant to this matter.
6 Submission of the Commission dated 20 October 2015, paragraph 14.
7 Ibid.
8 Ibid.
-- 4 of 7 --
5
Item 6 Inadequate Storm Water Pit
[26] This was determined by the Commission to not be defective building
work9. Ms Brown has not provided any further evidence concerning this
item to suggest this matter is relevant to the conduct of the certifier.
Item 7 Ceiling Insulation
[27] Ms Brown alleges in her submissions that ceiling insulation has not been
installed by the builder on the 1st and 2nd floor ceilings and that the certifier
has provided a certificate confirming the correct insulation has been
installed. She accepts that roof insulation was installed10.
[28] The Commission submits11 the builder did not install bulk ceiling insulation
and reflective foil under the roof sheet as required by the contract.
Instead, the builder installed foil backed, blanket type insulation under the
roof sheeting and no bulk ceiling insulation. The certifier accepted a Form
16 from the builder stating the energy efficiency requirements were met.
[29] The Commission engaged an independent report from Andrew Barrett, an
independent energy efficiency expert, who concluded that the building was
compliant with energy efficiency requirements.
[30] The changes by the builder are suggested by the Commission to be a
contractual matter for Ms Brown. The Commission says there is no
evidence that the certifier engaged in unsatisfactory conduct or
professional misconduct as defined by the Building Act in relation to this
item.
[31] On other matters addressed by the Commission in its submissions (the
position of the house on the lot, original work rejected as contractual), the
Commission says there is no evidence the certifier engaged in
unsatisfactory conduct or professional misconduct as defined by the
Building Act.
Discussion
[32] Under sub-sections 204(1) and (2) of the Building Act, after a complaint
has been lodged concerning a certifier, the Commission must decide
whether or not the certifier has engaged in unsatisfactory conduct or
professional misconduct and give notice to the complainant and the
certifier of its decision.
[33] “Unsatisfactory conduct” and “professional misconduct” are terms defined
in the dictionary to the Building Act. “Unsatisfactory conduct” includes
conduct that is contrary to a function under the Building Act including, for
example, disregarding relevant and appropriate matters. It also includes a
9 Ibid paragraph 31.
10 submission of Ms Brown dated 15 September 2015, page 12.
11 submission of the Commission dated 20 October 2015, paragraph 32.
-- 5 of 7 --
6
breach of the Code of Conduct for Building Certifiers12. Standard 10 of the
Code requires a building certifier to ensure inspections are carried out to
ensure building work complies with the development permit.
[34] “Professional misconduct” is relevantly conduct that shows incompetence,
or a lack of adequate knowledge, skill, judgment, integrity, diligence or
care in performing building certifying functions, such that it compromises
the health or safety of a person or the amenity of a person’s property or
significantly conflicts with a local planning scheme and is contrary to a
function under the Building Act or another Act.
[35] The Commission refers to the decision of Troy Richardson’s Building
Approvals & Inspections v QBSA13 where the learned member relied on
the following passage from Schwede v QBSA14. In the Schwede decision,
the member commented that:-
Plainly, professional misconduct is a very serious matter: it is conduct that
shows serious incompetence, lack of knowledge, judgement, integrity,
diligence or care; it is conduct that compromises the safety of persons using
buildings, the amenity of a property or significantly conflicts with local
planning laws; it is unlawful conduct – in the sense of conduct contrary to
the Acts regulating the functions of private certifiers; it is corruption in the
sense of seeking or taking benefits in return for breaching the regulating Act
or seeking to corrupt other private certifiers in the same way; it is defiance
of the orders of the tribunal or the BSA; it is fraud, dishonesty, unethical and
improper conduct.
[36] The Commission has devoted considerable time and resources to
investigating Ms Brown’s concerns both in this matter and in the related
matter concerning the construction of the building itself. There are few
remaining concerns and they are either limited or irrelevant to the review
applications.
[37] The Commission submits that the conduct of Mr Owen-Jones as certifier
satisfies the test of unprofessional conduct in his not undertaking a
personal inspection of the site but does not satisfy the higher test of
professional misconduct as discussed in the Richardson decision above.
[38] I accept and agree with this submission. I am satisfied Mr Owen-Jones’
conduct was either incompetent or a lack of adequate judgment, integrity,
diligence or care in performing building his certifying functions, such that it
compromised the health or safety of Ms Brown or the amenity of her
property. It certainly significantly conflicted with the requirements of
BAL29.
[39] I am not satisfied the correct and preferable decision is to overturn the
decision of the Commission made 9 January 2014 and that decision is
confirmed.
12 Code of Conduct for Building Certifiers effective 14 November 2003 under s 32 of the
Building Act 1975 (Qld).
13 [2013] QCAT 113 at para19.
14 [2009] QCCTB 157 at para 65.
-- 6 of 7 --
7
[40] As Ms Brown has failed in her application to change the decision of the
Commission under review, her application for costs is also dismissed.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2016/007