Colton Coal Pty Ltd v Aldershot and District Against Mining Inc. & Ors [2016] QLC 73 (2016) 37 QLCR 403
LAND COURT OF QUEENSLAND
CITATION: Colton Coal Pty Ltd v Aldershot and District Against
Mining Inc. & Ors [2016] QLC 73
PARTIES: Colton Coal Pty Ltd
(applicant)
v
Aldershot and District Against Mining Inc.
(objector)
and
Max Adlam, Jim Blackmore, Jane Jones, William
McKillop, Colin Reynolds, Suzanne Reynolds, Christine
Rodhouse, Philip Martin Rodhouse, John Sharp,
Marilynn Sharp, Michael Ward, Peter Ward and
Shirley Ward
(objectors)
and
Chief Executive, Department of Environment and
Heritage Protection
(statutory party)
FILE NO/s: MRA499-14 & EPA500-14 (MLA50273) (Colton A)
MRA501-14 & EPA502-14 (MLA50274) (Colton B)
MRA503-14 & EPA504-14 (MLA50280) (Colton C)
DIVISION: General Division
PROCEEDING: Hearing of application for grant of mining leases under s
268 of the Mineral Resources Act 1989 and objections
decision hearing under s 220 of the Environmental
Protection Act 1994
DELIVERED ON: 17 November 2016
DELIVERED AT: Brisbane
HEARD ON: 15, 16, 17, 18 August & 13 September 2016
HEARD AT: Brisbane
MEMBER: WA Isdale
-- 1 of 46 --
2
ORDER/S: 1. In accordance with s 269 of the Mineral Resources
Act 1989, the Court recommends to the Honourable
the Minister administering the Mineral Resources Act
1989 that the applications be granted in whole.
2. In accordance with s 222(1)(b) of the Environmental
Protection Act 1994, the Court recommends to the
Honourable the Minister administering the
Environmental Protection Act 1994 that the
application be granted, but on stated conditions that
are different to the conditions in the draft
environmental authority issued on 1 September 2014
to the extent that Table D1 – Noise limits referred to
in Condition D1 be replaced with the following
revised table:
I. Table D1 – Noise limits
CATCHWORDS: ENERGY AND RESOURCES – MINERALS – MINING
FOR MINERALS – ENVIRONMENTAL PROTECTION
LEGISLATION – where there is an objection to the grant of
the mining tenures being applied for – where there are
objections to the draft environmental authority – where the
Court hears the objections – where the Court makes
recommendations to the Ministers concerning the mining
tenures and the draft environmental authority
Mineral Resources Act 1989, s 265, s 268, s 269
Environmental Protection Act 1994, s 220, s 222, s 223
Adani Mining Pty Ltd v Land Services of Coast and Country
Inc. & Ors [2015] QLC 48
-- 2 of 46 --
3
De Lacey & Anor v Kagara Pty Ltd (2009) 30 QLCR 57
Endocoal Limited v Glencore Coal Queensland Pty Ltd and
Department of Environment and Heritage Protection [2014]
QLC 54
Xstrata Coal Queensland Pty Ltd & Ors v Friends of the
Earth - Brisbane Co-Op Ltd & Ors (2012) 33 QLCR 79
APPEARANCES: D O’Brien QC instructed by HopgoodGanim for the
applicant
G Houen for the respondents
S Barclay and KM Clayton for the statutory party
Background
[1] The applicant wishes to mine coking coal at a 1,025.1264 ha site about 10 km to
the north of Maryborough. Approximately 5 million tons of coal are in prospect of
being extracted by open-cut mining of about 350 ha. The coal is planned to be
prepared on site and then transported by railway to Gladstone for export. About
770 ha will be disturbed by the project. It is proposed that there would be one train
per day carrying around 2,200 tons of payload.
[2] Aldershot is a township of about 1,050 residents and, Mr Houen submitted, around
500 homes. In her objection, exhibit 11, Jane Jones states that there are 1,042
people and 285 homes. In exhibit 51, Brian Linforth says there are about 1,150
people in about 245 residences. The township is about 10 km north of
Maryborough off the Bruce Highway and around 2 km from the boundary of the
proposed mine. The spoil dump will be the part of the mine nearest the residents.
Some of the residents have formed the respondent incorporated body, Aldershot
and District Against Mining Inc., (AADAM) which, as a corporation, is a legal
person and an objector.
[3] One matter which was referred to in the hearing was that there is no reticulated
water provided in the community and the residents rely on rainwater stored in
tanks. The case presented to the Court on behalf of AADAM did not specify how
many rainwater storage tanks may potentially be affected by the dust from the
proposed mine.
[4] Only AADAM objects to the mining lease applications, MLA 50273 (860.7 ha),
MLA 50274 (162.9 ha) and MLA 50280 (1.5264 ha), known as Colton A, B and C
-- 3 of 46 --
4
respectively. It also objects to the draft Environmental Authority (EA). The
applicant and the statutory party are in favour of the applications and EA.
[5] In the case of the draft EA for the proposed project, the other objectors are a
number of individuals who have chosen to rely on their written objections made in
the process. They have chosen not to give or call evidence at the hearing but to
rely on the concerns which they have already expressed. These persons are Max
Adlam (exhibit 16), Jim Blackmore (exhibit 12), Jane Jones (exhibit 11), William
McKillop (exhibit 16), Colin Reynolds and Suzanne Reynolds (exhibit 10), Philip
Martin Rodhouse and Christine Rodhouse (exhibit 15), John Sharp and Marilynn
Sharp (exhibit 13), Michael Ward, Shirley Ward and Peter Ward (exhibit 14).
[6] The chief executive of the environmental regulator, the Department of
Environment and Heritage Protection, which is the statutory party, was
represented by counsel at the hearing. The applicant was represented by Queen’s
Counsel and AADAM was represented by Mr G Houen, agent.
This Court’s role in the process
[7] The Land Court performs an administrative function in the present proceedings. It
does not decide a dispute but instead is permitted by law to make
recommendations. The decision-making power rests with the relevant Minister.
Mineral Resources Act 1989
[8] In the case of applications for mining tenures, the Mineral Resources Act 1989
(MRA) provides, in section 265, that objections are to be referred to the Court.
That process was followed and under s 268(1) of the MRA the Court is required to
hear the applications and objections. Under s 269 the Court is required to forward
the objections, the evidence adduced at the hearing, any exhibits and the Court’s
recommendation to the Minister. The section sets out what the recommendation
must consist of and what the Court must consider. It is useful to set out s 269 in
full since it is central to what the Court is required to do.
269 Land Court's recommendation on hearing
(1) Upon the hearing by the Land Court under this part of all matters in
respect of an application for the grant of a mining lease, the Land Court
shall forward to the Minister—
(a) any objections lodged in relation thereto; and
(b) the evidence adduced at the hearing; and
(c) any exhibits; and
(d) the Land Court’s recommendation.
-- 4 of 46 --
5
Note—
For other relevant provisions about forwarding documents, see
section 386O.
(2) For subsection (1)(d), the Land Court’s recommendation must consist
of—
(a) a recommendation to the Minister that the application be
granted or rejected in whole or in part; and
(b) if the application relates to land that is the surface of a
reserve and the owner of the reserve has not consented to
the grant of a mining lease over the surface area, the
following—
(i) a recommendation to the Minister as to whether the
Governor in Council should consent to the grant over
the surface area;
(ii) any conditions to which the mining lease should be
subject.
(3) A recommendation may include a recommendation that the mining
lease be granted subject to such conditions as the Land Court
considers appropriate, including a condition that mining shall not be
carried on above a specified depth below specified surface area of the
land.
(4) The Land Court, when making a recommendation to the Minister that
an application for a mining lease be granted in whole or in part, shall
take into account and consider whether—
(a) the provisions of this Act have been complied with; and
(b) the area of land applied for is mineralised or the other
purposes for which the lease is sought are appropriate;
and
(c) if the land applied for is mineralised, there will be an
acceptable level of development and utilisation of the
mineral resources within the area applied for; and
(d) the land and the surface area of the land in respect of
which the mining lease is sought is of an appropriate size
and shape in relation to—
(i) the matters mentioned in paragraphs (b)
and (c); and
(ii) the type and location of the activities
proposed to be carried out under the
lease and their likely impact on the
surface of the land; and
(e) the term sought is appropriate; and
(f) the applicant has the necessary financial and technical
capabilities to carry on mining operations under the
proposed mining lease; and
(g) the past performance of the applicant has been
satisfactory; and
(h) any disadvantage may result to the rights of—
(i) holders of existing exploration permits or
mineral development licences; or
(ii) existing applicants for exploration permits or
mineral development licences; and
-- 5 of 46 --
6
(i) the operations to be carried on under the authority of the
proposed mining lease will conform with sound land use
management; and
(j) there will be any adverse environmental impact caused by
those operations and, if so, the extent thereof; and
(k) the public right and interest will be prejudiced; and
(l) any good reason has been shown for a refusal to grant the
mining lease; and
(m) taking into consideration the current and prospective uses
of that land, the proposed mining operation is an
appropriate land use.
(5) Where the Land Court recommends to the Minister that an
application for the grant of a mining lease be rejected in whole or in
part the Land Court shall furnish the Minister with the Land Court’s
reasons for that recommendation.
(6) If—
(a) the application is for the grant of a coal mining lease; and
(b) under section 318BA, a preference decision is required;
the Land Court can not recommend that the lease not be
granted so as to give preference to petroleum development.
An inspection or view
[9] Section 268(4) of the MRA provides that the Court “may direct an inspection or
view of the land the subject of the application”. There was imaging and mapping
of this area provided in the evidence. There was also imaging and mapping of
areas beyond the land the subject of the applications for mining tenures. On behalf
of AADAM it was submitted that with the aid of a boat and helicopter or by road
the Court should carry out an inspection. It was suggested that the applicant ought
to bear the costs associated with this. The applicant was not prepared to do this
and there was no support for the idea of an inspection or view from the applicant
or the statutory party. The Court was not prepared to order an inspection in the
existing circumstances. It urged the parties to make good use of maps and
photographs, including overhead imagery, and indicated that the application for a
site visit could be renewed as evidence progressed if an improved case for such an
order could be shown. The Court indicated that it wanted agreement from the
parties about what ought to be inspected in order to avoid an unstructured activity
which could involve considerable waste of time and money. No agreement was
ever reached.
[10] The Court put time aside for hearing evidence at Maryborough and potentially
conducting a view in conjunction with that. As the case proceeded, no party had
any witness whose evidence needed to be heard at Maryborough and the
-- 6 of 46 --
7
submission on the part of AADAM, although repeated, did not improve. In the
circumstances of the case, the Court did not direct an inspection or view as it was
not satisfied that this was necessary to carry out its tasks.
Environmental Protection Act 1994
[11] Under the Environmental Protection Act 1994 (the EP Act), the administering
authority acted in accordance with the EP Act and referred the objections to the
Court. The hearing under the MRA and the EP Act were conducted at the same
time.
[12] The EP Act sets out the nature of the objection decisions and what the Court must
consider. These sections are in the following terms:
222 Nature of objections decision
(1) The objections decision for the application must be a
recommendation to the EPA Minister that—
(a) the application be granted on the basis of the draft
environmental authority for the application; or
(b) the application be granted, but on stated conditions that
are different to the conditions in the draft; or
(c) the application be refused.
(2) However, if a relevant mining lease is, or is included in, a significant project
and, under section 210, Coordinator-General’s conditions were included in
the draft, any stated conditions under subsection (1)(b)—
(a) must include the Coordinator-General’s conditions; and
(b) must not be inconsistent with a Coordinator-General’s
condition.
(3) The Land Court must, as soon as practicable after the decision is
made, give a copy of the decision to each of the following—
(a) the MRA Minister;
(b) if a relevant mining lease is, or is included in, a
significant project—the State Development Minister.
223 Matters to be considered for objections decision
In making the objections decision for the application, the Land Court must
consider the following—
(a) the application documents for the application;
(b) any relevant regulatory requirement;
(c) the standard criteria;
(d) to the extent the application relates to mining activities
in a wild river area—the wild river declaration for the
area;
-- 7 of 46 --
8
(e) each current objection;
(f) any suitability report obtained for the application;
(g) the status of any application under the Mineral
Resources Act for each relevant mining tenement.
Level 1 Objectors
[13] The objectors who are natural persons chose to rely on their written objection only
and to not participate in the Court process. These are Level 1 Objectors as referred
to in Land Court Practice Direction 3 of 2015.
[14] All of the material provided by these objectors was considered by the Court. Their
concerns covered noise, dust on solar panels and dust getting into tank water and
its potential for respiratory and toxic effects.
[15] Although these objectors did not give or call evidence, the evidence which was
provided to the Court was considered in the light of their concerns.
The hearing – witnesses, exhibits and an e-trial
[16] The hearing of evidence took place in Brisbane and this occupied four days of
Court time. Written submissions and oral submissions came later. The applicant
called five witnesses. These were:
1. Mr Shane Elkin, regarding noise impacts.
2. Mr Simon Welchman, concerning air quality.
3. Mr Michael Batchelor, a mining engineer.
4. Mr Stephen Charles Eames, Director, Colton Coal.
5. Dr John Thorogood, regarding water ecology.
[17] AADAM called one witness, Mr Max Winders, an engineer.
[18] Further, on behalf of AADAM, Mr Brian Linforth provided an affidavit, exhibit
118, confirming his witness statement. Ms Aileen Harrison confirmed her witness
statement by affidavit which became exhibit 117. There was no challenge to their
statements, which were exhibits 51 and 52 respectively.
[19] The statutory party called Mr Timothy Mervyn Brain, a compliance delivery
manager of the statutory party.
-- 8 of 46 --
9
[20] There were 126 exhibits, some consisting of many pages. The material was
provided in electronic form so that it could be easily and quickly accessed in
Court. This shortened the time needed to conduct the hearing as documents could
be quickly displayed to the parties and the Court.
[21] In exhibit 51, Mr Linforth states, as has been noted, that Aldershot is home to
about 1,150 people in about 245 residences. He refers to matters regarding dust,
noise, rainwater tanks and the Mary River. The contents of his statement were not
disputed before the Court. In it he explains that AADAM is not against all mining
but is against mining that would have significant negative impacts.
[22] In exhibit 52, Aileen Harrison explains the effects of the New Acland coal mine on
her and her family and their business and health. None of this was disputed. It is
noted that Mr Linforth states in exhibit 51 that no agricultural land would be
directly affected by the proposed project.
[23] The hearing focused on the areas where the parties were in dispute. A
consideration of the evidence in the light of the matters which the Court must
address enables all of the objections to be considered together in their context.
The applicant’s case
[24] The applicant pointed out that historically there have been small mines in the
Burrum coal fields in this area. What is proposed is a relatively small open cut
mine, as compared to the size of other open-cut coal mines. Probably about 5
million tons of coking coal will be mined. The closest residence is about 2 km
from the boundary of the proposed lease. The pit will start about 4 km from the
closest house and, after about 10 years, be 3 km away. The spoil dumping area
will be the closest source of dust.
[25] It was submitted that any water discharged into the Mary River would be
“chemically benign” and could only be discharged, because of conditions in the
draft EA, when there is significant flow in the river and when the water to be
discharged meets the standard set for it. It was stressed that the water used for
washing the coal is not to be discharged. What may be discharged is the rainwater
that falls onto the site and which is stored in a dam. It is recognised that the ground
will be disturbed by the mining activities so there will be sediment which the dam
will catch. The three tenures sought are all part of the one project and may usefully
-- 9 of 46 --
10
be considered together. There is only one objection, from AADAM, to the
applications for the mining tenures.
The witnesses called on behalf of the applicant
[26] Mr Shane Robert Elkin was called on behalf of the applicant. He produced a
report, exhibit 35, a response report, exhibit 39, and a joint expert report, exhibit
110. Mr Elkin is a mechanical engineer and a registered professional engineer in
Queensland. He has considered the potential airborne noise impacts of the
proposed mine. His opinion is that, with the use of appropriate site-based
management measures, acceptable noise levels can be achieved at neighbouring
noise-sensitive locations. He is an acoustic consultant with relevant experience and
believes that the acoustic quality objectives are appropriate.
[27] There is only one matter of disagreement between Mr Elkin and Mr Paul King, a
mechanical engineer who is the respondent’s expert. Mr King is of the opinion that
real-time noise monitoring should be installed prior to commencement of mining
operations and continued throughout the mining. Mr Elkin disagrees and is of the
view that non-real-time noise monitoring should be used. If non-compliance with
noise limits becomes an issue, real-time monitoring should be used to manage the
adverse impacts of noise.1
[28] The predominant wind direction is from the south-south-west, which is away from
the sensitive receptors, the people of Aldershot. Mr Elkin made clear in cross-
examination that real-time monitoring available on the internet would be likely to
trigger a lot of false positives and that the information needs to be analysed and
interpreted by a professional before being published.2
[29] Mr Simon John Welchman was called on behalf of the applicant. His report
became exhibit 33. His response report is exhibit 36 and his joint report with Mr
Paul King dated 15 October 2015 is exhibit 108. These experts have no areas of
disagreement.3 The joint report is succinct and it is worth setting out its substance.
The report is in the following form:
1 Ex 110, pages 7 and 8.
2 T 2-25, lines 10-31.
3 Ex 108, pages 5, para 17.
-- 10 of 46 --
11
“INTRODUCTION
1. In accordance with the Order of the Court, Mr King and Mr
Welchman met on 1 October 2015 to discuss whether the air
quality issues associated with the Colton Coal Project can be
resolved, in whole or in part.
2. On 28 January 2010, Colton Coal applied for the grant of ML
50273 and 50274 principally for the purpose of open cut coal
extraction. On 2 November 2010, Colton Coal applied for ML
50280 for the principal purpose of providing tenure for part of the
rail infrastructure that is required to service the mine.
3. The Colton Project is located in the Fraser Coast Regional Council
area in southern Queensland approximately 10 km north of
Maryborough and 300 km north of Brisbane. The project will
consist of the development of a 5 million tonne inferred coking
coal resource of the Burrum coal measures. The project is planned
to mine up to 1.2 million tonnes per annum (Mtpa) of run of mine
coal by open cut methods to produce on average 0.5 Mtpa of
product metallurgical coal for export. The project production life
is estimated to be 8 to 10 years.
4. The Colton Coal Project is proposed to be an open cut coal mine
using excavators, bulldozers, trucks and other equipment for
overburden and interburden removal. Coal will be mined
using small excavator type machinery, trucks and other
equipment.
5. The Department of Environment and Heritage Protection (EHP)
issued a draft Environmental Authority (EA) including conditions
dated 1 September 2014. The draft EA was the subject of public
notification and a number of submissions were made in respect of
it.
6. Objections have been lodged by the following parties:
• Aldershot and District Against Mining Inc.;
• John and Marilyn (sic) Sharpe;
• Phillip (sic) Martin Rodhouse and Christine Rodhouse;
• Colin Reynolds and Suzanne Reynolds;
• William McKillop and Max Adlam;
• Michael Ward, Shirley Ward and Peter Ward;
• Jim Blackmore; and
• Jane Jones.
-- 11 of 46 --
12
DOCUMENTS RELIED UPON
7. In preparing this Joint Expert Report we have primarily relied upon
the following documents:
• Colton Coal Mine Project Environmental Management Plan,
prepared for Colton Coal Pty Ltd by AARC, May 2014 (EM
Plan)
• Mining Lease Application numbers 50273, 50274, 50280
• Two detailed air quality assessments were prepared for the
Colton Coal Project, namely:
o Colton Mine Project, Air Quality Impact &
Greenhouse Gas Assessment, prepared for AARC,
ASK Consulting Engineers Pty Ltd, 16 August 2011
(ASK AQ Report, Annexure J of the EM Plan)
o Colton Coal Mine, Supplementary Air Quality
Assessment, prepared for AARC, ASK Consulting
Engineers Pty Ltd, 1 April 2015 (ASK
Supplementary AQ Report). The ASK
Supplementary AQ Report is attached as Annexure
‘B’ to this Statement of Evidence
• Statements of Evidence prepared by Simon Welchman and
dated 1 May 2015 and 3 September 2015
• Statement of Evidence prepared by Mr Paul King and dated
13 July 2015
• The reasons for objection of the submitters
• The draft Environmental Authority issued by EHP dated 1
September 2014.
OBJECTIONS
8. Mr King and Mr Welchman agree that the reasons for objection of
the submitters can be summarised as follows:
• Adverse impact on tank water
• Air quality assessment is inadequate
• Heavy metals associated with coal
• Draft EA fails to properly address proximity to Aldershot.
-- 12 of 46 --
13
AREAS OF AGREEMENT
9. Mr King and Mr Welchman agree that the air quality assessment
studies conducted by ASK Consulting Engineers Pty Ltd and
supplemented by peer review and dispersion modelling conducted
by Katestone Environmental Pty Ltd (Katestone) show
compliance with the relevant air quality objectives.
10. Mr King and Mr Welchman agree that the air quality assessment
study conducted by Katestone was conducted appropriately and
in accordance with regulatory requirements. Mr King and Mr
Welchman agree that the assessment has been correctly made
against the appropriate air quality objectives, which are detailed
in Mr Welchman’s First Statement of Evidence at Table 2.
11. Mr King and Mr Welchman agree that the air quality assessments
(ASK, Katestone and MWA Review) demonstrate that it is
possible to undertake the Colton Coal Project and, at the same
time, manage dust emissions to achieve compliance with
regulatory air quality requirements, and on this basis not result
in adverse impacts on the sensitive receptors in the surrounding
area including those sensitive receptors at Aldershot.
12. Mr King and Mr Welchman agree that the grounds of objection
are not supported by the air quality assessment studies that they
have conducted. In particular, Mr King and Mr Welchman agree
on the basis of the air quality studies conducted, that:
• The air quality assessments of the Colton Coal Project have
assessed appropriate air quality indicators and provide a reliable
basis for determining appropriate conditions of approval
• The dust associated with the Colton Coal Project is not likely to
adversely affect tank water at existing sensitive receptors
• The metals associated with the Colton Coal Project are not likely
to adversely affect air quality at existing sensitive receptors
• The dust associated with the Colton Coal Project is not likely to
adversely affect the operation of solar panels at existing sensitive
receptors in Aldershot
• The dust associated with the Colton Coal Project is not likely to
adversely affect the operation and maintenance of swimming
pools at existing sensitive receptors
• The gaseous emissions associated combustion engine related
emissions from the Colton Coal Project are not likely to adversely
affect air quality at existing sensitive receptors
• The gaseous emissions associated with blasting have not been
assessed in detail through the various studies, albeit the ASK
reporting identified appropriate strategies to manage such
emissions to acceptable levels
-- 13 of 46 --
14
• The Draft EA conditions relating to air quality are appropriate
given the scale of the project and the proximity of nearest
sensitive receptors.
13 Mr King and Mr Welchman agree that the indicative air quality
controls identified in the EM Plan and in the reporting of ASK and
Katestone provide a reasonable basis to achieve the air quality
objectives. The preparation of a formal Air Quality Management
Plan will inform operators of their day to day responsibilities and
actions in managing air quality impacts.
14. Mr King and Mr Welchman agree that additional reduction in dust
levels could be achieved, if it was required e.g. due to particularly
adverse conditions (such as unusual weather), by modifying key
dust producing activities. Mr Welchman’s Second Statement of
Evidence investigated reducing the intensity of overburden
haulage during the night and offsetting such a reduction with
increased daytime haulage. Mr Welchman found that the peak 24-
hour average concentration of PM10 was significantly reduced by
this operational amendment. Whilst such a variation in activities
was not found to be necessary at all times for the project to
appropriately and adequately manage its dust emissions and to
achieve compliance with the air quality objectives, the
investigation shows that there is additional scope to reduce dust
emissions in adverse circumstances.
15. Mr King and Mr Welchman agree that the compliance monitoring
regime required in the Draft EA conditions is adequate to inform
the operators of ongoing air quality impacts such that the mine
operators manage activities to not cause elevated levels of PM10
and PM2.5. Mr King and Mr Welchman agree that the PM10 and
PM2.5 objectives have been formulated such that if a mining
activity achieves compliance with the objective for PM10,
compliance with the PM2.5 objective will also be achieved.
16. Mr King and Mr Welchman agree that Colton Coal should
develop an Air Quality Management Plan for its operations. An
Air Quality Management Plan is a necessary tool for mine
operators to manage day to day operations to mitigate the potential
for air quality impacts. The Air Quality Management Plan would
be subject to regular review and amendment as the mine
operations progress. The Air Quality Management Plan should
include ongoing dust monitoring, a complaints receipt and
response handling procedure, and a suite of potential air quality
emission mitigation measures to inform and assist mine operator
as to the actual measures that may be implemented.
AREAS OF DISAGREEMENT
17. There are no areas of disagreement.
DECLARATION
-- 14 of 46 --
15
18. The Experts acknowledge that they have read and understood
relevant extracts of the Land Court Rules 2010 (Qld) and the
Uniform Civil Procedure Rules 1999 (Qld). The Experts
acknowledge that they have an overriding duty to assist the Court
and have discharged that duty. The Experts have not received any
instructions to accept, adopt or reject any particular opinion in
preparing this joint report.
19. The Experts confirm that:
(a) The factual matters stated in this report are, as far as we are
aware, true
(b) We have made all the enquiries that we consider appropriate
(c) The opinions in this report are genuinely held by the Experts
(d) The report contains references to all matters that we consider are
significant.”
[30] Mr Welchman made clear in cross-examination that he and Mr King concluded
that the proposed “activity can be controlled to avoid adverse impacts”4 and that
the “draft EA conditions were adequate to manage the activity.”5
[31] When questioned about whether the rainwater-based water supply of the Aldershot
residents was in danger of contamination from heavy metals in dust he stated that
“the levels are not likely to go anywhere near drinking water guidelines.”6 In Mr
Welchman’s expert opinion “the data says it won’t occur and I can’t see how it
would occur.”7 This expert evidence is not contradicted by Mr King.
[32] In cross-examination by Mr Houen, in relation to this important matter of drinking
water safety, the following exchange occurred:8
“Would it be – am I right in thinking that a lot of it would depend on
the nature of the overburden at the particular site?---I – based on my
calculations for Colton Coal and in that – in the instance of Colton
Coal, I don’t believe that the – the – there is a likelihood that
overburden dust landing on peoples’ roofs and – and being transported
into tanks would cause water contamination. I – I don’t believe that’s
the case.
Can you understand that if you’re – that, from the people who live in
Aldershot – that that isn’t going to satisfy them because they’re well
aware that there will be dust from the mine on their roofs and getting
washed into the tanks? That - - -?---I – I can understand a concern
4 T 2-40, line 23.
5 T 2-40, line 24.
6 T 2-42, lines 8-9.
7 T 2-42, lines 15-16.
8 T 2-44, lines 1-35.
-- 15 of 46 --
16
exists. Based on my calculations and the work that was done, those
concerns aren’t founded on any – on – on – on the data. They’re not
supported by the data.
And as to the extent that you’re involved as a consultant and an expert
and perhaps advisor to Colton Coal, you wouldn’t support a – a –
baseline testing of the rainwater tanks, followed by some monitoring to
establish that your conclusion is right?---No, I wouldn’t support that.
No.
No. Notwithstanding that it’s a matter of great concern to them as
residents?---I understand it’s a matter of concern. I don’t believe the
concern is – is warranted, given my assessment.
Can you appreciate that, taking that on its merits – your assurance –
that doesn’t satisfy them?---Well, I – I don’t know their opinion. I – I
take it from you, that doesn’t satisfy them?
Absolutely?---Right. Okay. I understand that.
Do you see any – any merit in a precautionary principle being adopted
in that if Colton is the one that’s definitely going to have an effect on
their rainwater tanks, that they be given the benefit of baseline testing
and some monitoring to establish that in fact your opinion is
correct?---I – I’ve – I think I’ve covered this already. I – my attitude is
that the results of my assessment show that those concerns aren’t
warranted. So I – that’s – that’s my attitude.”
[33] Mr Michael James Batchelor was called on behalf of the applicant. Mr Batchelor
is an engineer with particular expertise in minesite water management. His report
is exhibit 40 and his joint report with Mr Winders is exhibit 111. Exhibit 40 is a
report in response to Mr Winders’ report. The parts of the joint report, exhibit 111,
which set out the areas in which these two experts agree and disagree is most
instructive and worth setting out. The experts report in the following terms:
“Introduction:
i. This appeal relates to the conditions set by the State in its draft
Environmental Authority (EPML00367613) for the Colton Coal
Project at Maryborough.
ii. Matters of relevance to this JER relate to mine water management,
which includes provision for the discharge of water into the Mary
River via a submerged outfall.
iii. Both experts have prepared individual reports for the court
outlining their opinions on relevant issues as well as areas of
disagreement between the two experts.
iv. Recognising the complexity of some issues, the intent of this JER
is to establish a basis of 'common ground' upon which the parties
can subsequently jointly consider and resolve more specific issues
that may be in dispute.
-- 16 of 46 --
17
Areas of agreement:
Management of water from different mine site sources
1 It is good practice for a mine water management system
(WMS) to separate water from different sources according
to their expected chemical and physicochemical properties.
For example, water which has had low level contact with
mining operations (leading to minor changes to chemical
and physicochemical properties) should be separated from
water which has had notable changes in water quality.
Effect of source of release water on the results of site water balance
modelling
2. The Site Water Management Assessment report (WRM,
April 2014) includes the results of water balance
modelling to simulate the behaviour of the WMS. The
modelling was used to assess:
• The likelihood of uncontrolled releases from the Worked
Water System (WWS);
• The frequency and duration of releases from the Intermediate
Water System (IWS) to the Mary River.
3. The water balance modelling was based on the assumption
that only IWS surface runoff captured in the Mine Water
Dam would be released, but water captured in the WWS
would not.
4. The release of water to the receiving environment will not
be authorised from either water management sub-system
unless the release conditions specified in the draft
Environmental Authority (EA) are satisfied.
5. If water stored in the WWS meets the release conditions in
the EA, Colton Coal may opt to release it to the Mary
River via the pipeline at the Mine Water Dam.
6. If the Site Water Management Assessment assumed
Colton Coal did regularly release water to the Mary River
from the WWS as well as from the IWS, the likely effect
on the water balance modelling would be to:
• Increase the estimated frequency and duration of releases to
the Mary River.
• Reduce the estimated volumes of water accumulating in the
WWS.
Storage containment capacity of WWS
7. Colton Coal proposes that water captured in the WWS
would be stored in the various WWS dams for later reuse
in meeting site water demands.
-- 17 of 46 --
18
8. Mine water containment systems are generally designed
and operated to achieve two outcomes following
prolonged heavy rainfall:
1. enable the active pits to be dewatered so that
operations can continue;
2. reduce the risk of uncontrolled discharge to the
receiving environment to an acceptable level.
Areas of Disagreement:
Quality of water captured in the WWS and IWS
9. MW states that no evidence has been provided that
modelling of water quality, within the storages
comprising the mine water management system and of the
released water to and from those storages, has been
simulated over the life of the mine. As a realistic risk
assessment of the impact of releasing mining-sourced
waters into the Mary River should include simulation of
the above variations in relevant water quality parameters,
as well as variations in the volumes of water likely to be
released with such water quality variations, MW
considers that insufficient simulation has been
undertaken and reported upon to clearly demonstrate that
the proposed water management plan will protect
currently-recognised environmental values and water
quality objectives of the Mary River estuary.
10. MW considers that, if water quality modelling had been
included in the risk assessment, it would have shown
that the resultant risks to the environment could have
been further minimized by simulating practical revisions
of the water management plan.
11. MW points out that simulation of water quality within
the water management system should be a fundamental
part of the monitoring and review process required to be
undertaken to satisfy relevant conditions in the draft
environmental authority. Accordingly, MW considers
that presentation of the results of simulating the water
quality variations within and out of the currently-
proposed system should be a pre-requisite to the Court's
consideration of the adequacy or otherwise of the water
quality conditions included within the current draft
environmental authority.
12. MB acknowledges that variations in the concentrations
of potential contaminants in the dams making up the
MWS are to be expected. However, he believes that
modelling of water quality within the storages comprising
the MWS would not materially change the outcomes of
the design and impact assessment of the project for the
following reasons:
-- 18 of 46 --
19
• Water captured in the WWS will present the
highest potential risk of harm to the receiving
environment. The WWS has already been
designed on the basis that the water it contains
may not be suitable for release and will
therefore require full containment without
release. Hence the modelling of the WMS does
not include releases from the WWS.
• The draft EA release conditions have been set to
ensure that when water is released, the
Environmental Values of the receiving
environment are protected. If the water quality
does not meet this standard, its release will not
be permitted. If this was the case, the outcome
would be to reduce estimated frequency and
duration of releases to the Mary River and to
reduce the potential impacts on the River.
• The likely geochemical properties of runoff
from the overburden dump were characterised in
the Mary River Discharge Investigations
(Hydrobiology, May 2014), based on laboratory
testing of the overburden material by EGi and
CSIRO. That report concluded that metal
concentrations (with the possible exception of
Cd and Se) in the Mine Water Dam were unlikely
to exceed the ANZECC trigger values. As a
result, water in the IWS would not be expected
to present a risk of harm to the receiving
environment. This is consistent with experience
at other coal mines, where overburden runoff is
typically suitable for release if erosion and
sediment control measures are properly
implemented. It is therefore unlikely that
releases to the Mary River from the IWS would
be significantly limited by exceedance of the
draft EA water quality conditions.
13. MB agrees that during operations, process simulation of
water quality undertaken as part of monitoring and
review would be useful in ensuring the relevant
conditions in the draft environmental authority can
always be met.
Release of water from the IWS
14 MW States that Colton Coal's proposed release of water
from the WMS to the Mary River via a pipeline is one
option for managing water in the Mine Water Dam.
Another option would be for the Mine Water Dam to
-- 19 of 46 --
20
instead serve the function of a sediment dam, with water
being allowed to flow to the nearby headwater tributaries
of the Susan River.
15 MB responds that this alternative arrangement is possible,
and was considered during conceptual design of the
WMS, but the Mary River pipeline option was preferred
because the dilution offered by Mary River flows would
reduce impacts on the receiving waters.
Release of Water from the WWS
16 MW states that Colton Coal is likely to routinely transfer
water from the WWS to the Mine Water Dam -
ultimately for release. This greatly increases the
complexity of the water management system, and could
result in the release of acid mine drainage water to the
Mary River.
17 MB responds that the system has not been designed to
operate in this way. The clearly stated aim of the proposed
water management system is to separate the WWS and
IWS. Transferring water from the WWS to the Mine
Water Dam would be entirely inconsistent with this aim.
18 MB further responds that:
• the WWS storage capacity was sized so that
WWS water could be contained on site;
• while the draft EA does not preclude the release
of water to the Mary River, Colton Coal would
need to carefully test water in the receiving
environment and the WWS to be confident the
release would be compliant. Releases are likely
to occur only under exceptional circumstances;
• in the event that potentially acid-forming
overburden material generated highly acidic
water in the WWS, its release would be
prohibited by the pH release limit in condition
F4 of the draft EA.
Consequence Category
19 MW is of the opinion that the Mine Water Dam should
be assigned a "High" Consequence Category due to:
• the Environmental Values of the Mary River
receiving waters;
• the potential for transferring WWS water to the
Mine Water Dam and to the Mary River;
• the potential for the Mine Water Dam to contain
acid mine drainage water;
• the harm that the release water may therefore
cause to the Environmental Values of the Mary
-- 20 of 46 --
21
River.
20 MB responds that:
• The Environmental Values of the Mary River
and the consequent impacts of releases are being
addressed by other experts.
• It is not envisaged that (in the event that it was
released) WWS water would be discharged into
the Mine Water Dam, it would instead be
pumped directly to the inlet of the Mary River
pipeline.
• Water could only be released if it was compliant
with the EA release conditions. In which case the
criteria for "High Consequence" dams would not
be triggered.
• Based on the geochemistry of the out-of-pit
overburden, the Mine Water Dam is unlikely to
contain acid mine drainage water.
• The draft EA release conditions include a limit
on pH (which would prevent acid water from
being released).
Water Reuse
21 MW is of the opinion that the site water management
system should have been designed such that:
• releases are not made to the Mary River, and
• water captured in the WWS should be used as
part of a beneficial reuse scheme.
22 MB responds that he is aware that Colton Coal has
attempted to pursue reuse opportunities with other
parties, but that at this stage such an option is not part of
the project to which the draft EA applies.”
[34] Mr Batchelor’s evidence was that the worked water system, if operated as
specified, would not result in an overflow into the Susan River under all historical
rainfall conditions since 1890.9
[35] Cross-examination of Mr Batchelor was attended by some issues of relevance.10 It
was established that, if acid sulphate soil impacted the quality of the water being
considered for release, it would not be allowed to be released if it was outside of
the EA release conditions.11 The pipeline, about 5.5 km in length, is not required
9 T 2-54, lines 12-28.
10 T 2-60, lines to T 44-61 lines 1-2.
11 T 2-62, lines 12-18.
-- 21 of 46 --
22
to be purged before a sample is taken12 so it was suggested that a sample might not
be valid, if taken at the discharge point, until some time had elapsed.13
[36] This point focuses on sampling at the discharge point. According to item (ii) of the
introduction to exhibit 111, the discharge point into the Mary River is “a
submerged outfall”. Item F10 of exhibit 9, the draft EA, refers to mine-affected
water “when measured at the monitoring points specified in Table F1”.14 That
Table shows “MRP1”. The Monitoring Point is described in Table F1 as
“Sampling point drawing water out of Mary River discharge pipeline”.15 It does
not appear that there is any requirement to measure at the submerged outfall, with
the resultant problem introduced by the length of the pipe. Mr Batchelor said there
could be a sample taken at the pipe inlet.16 It seems that a sample point drawing
water out of the pipeline near its inlet is both contemplated and suitable. The point
made about sampling at the outlet point has no force.
[37] Mr Stephen Charles Eames was called on behalf of the applicant. He is now the
general manager of corporate development of the parent company New Hope
Corporation Limited and a director of Colton Coal Pty Ltd. In cross-examination,
Mr Eames was asked whether there is an intention to follow the present
application, if it is approved, with a further application for a much enlarged Colton
Coal mine. Mr Eames said that there are no plans for another application “at this
point in time.”17
[38] Dr John Anthony Thorogood was called on behalf of the applicant. He is an
aquatic ecologist. He has prepared a report, exhibit 32, response reports, exhibits
37 and 41, and a joint report with Mr Winders, exhibit 107. The joint expert report,
exhibit 107, sets out the areas of agreement and disagreement and it is useful to set
out the principal parts of it. It is in the following terms:
“Introduction
i. This appeal relates to the conditions set by the State in its draft
Environmental Authority (EPML00367613) for the Colton Coal
Project at Maryborough.
12 T 2-65, lines 35-40.
13 T 2-65, lines 37.
14 Ex 9, page 18, F10.
15 Ex 9, page 14, Table F1.
16 T 2-66, lines 20-23.
17 T 2-76, lines 45-46.
-- 22 of 46 --
23
ii. Matters of relevance to this JER relate to the proposed discharge of
water from the mine to the Mary River.
iii. Recognising the complexity of some issues, the intent of this
preliminary JER is to establish a basis of 'common ground ' upon
which we can subsequently jointly consider and resolve more specific
issues.
We agree that
iv. the development of the proposed mine should be considered within an
ecologically sustainable framework.
v. the receiving environment should be protected through integrated
management that is:
underpinned by an understanding of the receiving environment
and the establishment of environmental objectives,
based on the development and implementation of appropriate
management strategies, and
accountable.
vi. whilst a uniform standard of environmental protection may be applied
across an industry, the unique circumstances of each project should be
reflected in the management strategies applied to achieve this
standard.
vii the proposed release point is approximately 9 km upstream of waters
designated as having High Ecological Value, the upstream boundary
of the Great Sandy Strait Marine Park, and the upstream boundary of
the Susan River Fish Habitat Area.
viii the proposed release point lies within the mid-reaches of the Mary
River estuary, where waters are described in the Environmental
Protection (Water) Policy 2009: Mary River environmental values
and water quality objectives (July 2010) as 'moderately disturbed'.
ix the draft Environmental Authority prescribes the conditions (of river
flow) under which mine water may be released and the minimum
quality of water that may be released, and that the release of mine
water must be monitored and reported on.
x the draft Environmental Authority prescribes that the release of excess
mine water may only occur during periods of significant natural flow
within the river (>150 ML/day).
We disagree on the following matters:
A Risk-based Approach to Environmental Management
xi JT considers that a risk-based approach (where the likelihood
and consequence of various potential impacts are objectively
considered) is appropriate to assessing the likely impacts
associated with, and managing, the regulated discharge of
water from the Colton Coal project. A risk-based approach to
environmental management underpins the approach taken by
every Australian state and the Commonwealth (see Appendix
A).
-- 23 of 46 --
24
xii MW considers that the risk-based approach of the proposed
water management plan, which would allow untreated mine
water discharge to be frequently discharged into the Mary
River estuary, while possibly suitable for existing mines
discharging into inland streams of lesser ecological value, is
inappropriate in this instance.
xiii JT responds that the draft Environmental Authority specifies
the conditions (of river flow) under which mine water may
be released and the minimum quality of the water to be
released.
Uncertainty in Impact Assessment
xiv JT considers that some degree of uncertainty is acceptable
(expected) in impact assessment, and must be reflected in a
project's environmental management strategies. This view is
consistent with the State's Environmental Protection Act
(1994), the National Water Quality Management Strategy
and ANZECC Guidelines. Monitoring is considered an
integral element of environmental management (under the
Act), reflecting a clear acceptance of a degree of uncertainty
with respect to impact assessment.
xv MW disagrees that uncertainty is acceptable in this instance
as the proposed water quality management plan could be
revised to remove uncertainty from the impact assessment.
Adaptive Management
xvi JT considers that adaptive management allows monitoring to
support changes in practices where required, allowing best
practice environmental management to be implemented as
technologies evolve. Department of Environment and
Heritage Protection policies support this view, advising that
an adaptive management approach 'allows for best practice
environmental management to be implemented as
technologies develop over time ' and that under a regimen of
adaptive management, 'environmental licences issued to
operators can be changed to take into account new research,
monitoring or modelling which suggests the potential for
unintended or unexpected impacts on the environment. '
xvii MW disagrees that adaptive management is appropriate for
the protection of the estuary's ecological values and that the
water management plan, as currently stated, should be
upgraded to ensure that the need for adaptive management is
minimal.
xviii JT responds that the draft Environmental Authority specifies
the conditions (of river flow) under which mine water may
be released and the minimum quality of that water. That is, it
is the Environmental Authority, not the mine's 'water
management plan' that determines the nature of impact (if
any) of the release of mine water to the Mary River.
xix MW also considers that the Receiving Waters Monitoring
Plan is unlikely to identify the likely need for adaptive
-- 24 of 46 --
25
management as it is limited to looking for changes in specific
water quality parameters and not aimed at identifying
adverse changes to ecological values of the estuary which
may prove to be long-term or irreversible.
xx JT responds that 'adaptive management' may be broadly
applicable to the management of the proposed mine. It may
for example, be applied to the length of time water is held in
the Mine Water Sediment Dam prior to release (to facilitate
the settling of suspended solids). It may also be applied to
the Receiving Environment Monitoring Program (REMP)
prescribed in the draft Environmental Authority. The REMP
reflects an understanding that any impact relating to the
release of mine water, to flora and fauna, must (logically) be
mediated via water quality. The REMP does not proscribe
the monitoring of 'ecological values' and in fact states that
'the REMP should encompass any sensitive receiving waters
or environmental values downstream .....’. Environmental
Values ascribed to the mid-reaches of the Mary River estuary
include 'aquatic ecosystems '. Colton Coal has yet to finalise
a REMP design document.
Environmental Authority
xxi While it is agreed that an Environmental Authority should
take into account the nature of the proposed activity, the
values, sensitivities and resilience of the receiving
environment, and the regulations, policies and objectives
articulated by government, MW considers that the
regulations, policies and objectives articulated by
government need to be considered for relevance on a site-
specific basis. Of particular relevance in this case are the
interpretation of policies for the release of mine waters into
inland streams and the environmental values of the Mary
River estuary and the Great Sandy Region, which are quite
different to those of inland streams.
xxii MW considers that the draft environmental authority (EA) is
deficient in that it is based upon applying a generic policy,
developed for the adaptive management of existing and
expanding mines discharging large volumes of contaminated
water into inland river systems, to a new mine discharging
into an estuary with readily identifiable environmental
values.
xxiii JT responds that the draft Environmental Authority, whilst
reflecting the industry-wide application of policy (the
Department of Environment and Heritage Protection's
'Model Water Conditions for Coal Mines in the Fitzroy
Basin' provide an obvious example) also reflects the specific
nature of the proposed activity and the specific values,
sensitivities and resilience of the receiving environment. The
Environmental Authority appropriately reflects the
characteristics of the proposed mine and the receiving
waters.
xxiv MW considers that the draft EA is also deficient in that its
conditions only require post-flood event water quality
monitoring as a basis for identifying the need or otherwise
-- 25 of 46 --
26
for the adaptive management of releases of pollutants into an
estuary for which recent government policies and regulations
are seeking improvements in both water and sediment
quality.
xxv JT responds that MW's contention is not supported by a
careful reading of the draft Environmental Authority. The
draft Environmental Authority reads, (extracted from
condition F19), ' this must include monitoring the effects of
the mine periodically (under natural flow conditions) and
while mine effected water is being discharged from the site’.
Under the draft Environmental Authority, mine (effected)
water may be discharged at any time there is a rate of flow
greater than 150 ML/day over the Mary River and Tinana
barrages.
xxvi MW considers that the draft EA is incorrect in allowing the
mine to be regularly dewatered through a submerged outfall
in a location already impacted upon by a sub-standard
sewage treatment plant’s outfalls into an estuary where
current government policies require further reductions in the
pollutant loads discharged from urban, agricultural and
mining sources to protect seagrass and coral - seagrass being
the more significant in this instance.
xxvii JT responds that both the proposed means of discharge and
the draft Environmental Authority reflect the Environmental
Values and Water Quality Objectives of the mid-reaches of
the Mary River and downstream. The release of mine water
in accordance with the draft Environmental Authority will
not adversely impact seagrasses or corals.
xxviii JT considers that the release of 0.2 m3/s of uncontaminated
waters to the Mary River during periods of significant
natural flow (>300 ML/day) would not result in
environmental harm.
Bioaccumulation and Environmental Flows
xxix JT considers that the risk of bioaccumulation cannot be
increased where introduced water contains contaminants at
lower concentrations than the receiving waters.
xxx JT considers that environmental flows cannot be
detrimentally impacted where introduced water is less
contaminated than the receiving waters.”
[39] Dr Thorogood was asked about the four hour inspection of the Mary River estuary
by boat that Mr Winders made on 7 December 2015 and which is reported in
exhibit 57. Asked about the value, if any, of that inspection without
instrumentation Dr Thorogood said:
“Well, to be blunt, I think it really has no scientific basis and, therefore, no
scientific merit.”18
18 T 3-14, lines 30-34.
-- 26 of 46 --
27
[40] In cross-examination, Dr Thorogood said that:
“… it is entirely reasonable to expect that the water being discharged will
typically be less turbid than the water that is discharged to.” 19
[41] In relation to the concept of using reverse osmosis to treat the water before it is
discharged into the Mary River, Dr Thorogood said:
“I have no background or particular expertise in the treatment of water per
se. The only further comment I would make is that in as much as using a
sledgehammer to crack a proverbial walnut would seem to be excessive,
using reverse osmosis to remove the essentially benign concentration of
metals from the water that’s proposed to be discharged would be excessive
and if – you know, I’m not a lawyer either but if we turn to the EP Act, you
can see that it very clearly encourages an appropriate management response
to identified threats and the application of reverse osmosis simply wouldn’t
be appropriate to a threat this negligible.” 20
[42] In relation to the testing of discharge water, Dr Thorogood said:
“…in practical circumstances the testing would normally be expected to
be undertaken at the – at the start of the pipe rather than the end
because the end is literally underwater in the Mary River.” 21
[43] He said that:
“The discharge from Colton Coal will have negligible nutrients and,
typically, very low suspended solids.”22
[44] Dr Thorogood said that if, as a precaution, it is desired to have the discharge water
diluted and dispersed as quickly as possible, it would be done under conditions of
significant natural flow. This strategy of discharge to a flowing river has been
adopted because it has been seen to work in the Fitzroy River.23
AADAM’s case
[45] AADAM called one witness, Mr Maxwell Francis Winders. The exhibits
associated with Mr Winders are numbered 49, 57, 58, 59, 60, 107, 109, 111 and
115. Exhibit 49, attachment 3, is the report of Mr Arunakumaren, principal
hydrological modelling engineer. The report, provided to Mr Winders, modelled
the effectiveness of the proposed water management system. It notes that the
suspended solids are usually reddish brown in colour at low concentration and
blackish at high concentrations. The Court notes that the clarity of a liquid is
referred to as its turbidity. Exhibit 124 illustrates that. Exhibit 126 shows that Mr
19 T 3-16, lines 26-27.
20 T 3-32, line 41 to T 3-33, line 2.
21 T 3-29, lines 35-37.
22 T 3-25, lines 20-21.
23 T 3-31, line 35 to T 3-32, line 6.
-- 27 of 46 --
28
Winders is a mechanical engineer and that his registration with the Board of
Professional Engineers Queensland lapsed on 30 June 2016. Mr Winders is a very
experienced engineer and the Court draws no adverse inference from the lapse of
his registration, which he said was a “complete surprise” to him.24 In submissions,
the Court was informed that the registration of Mr Winders has been restored.
[46] Mr Winders was of the opinion that:
“… the draft EA is deficient in not specifying total suspended solids to be
equivalent to that which applies to the middle estuary.”25
[47] Mr Winders describes himself as an environmental engineer.26 He took part in
three expert conclaves, meeting with Dr Andrew McCowan, Dr Thorogood and
Mr Batchelor. Dr McCowan, an expert on water flow and mixing, was, by
agreement of the parties, not called. There are no issues regarding his opinions. Mr
Winders claimed that he was expert in the same areas as the opposing experts. His
curriculum vitae begins at page 38 of exhibit 49. He is, as has been noted, a
mechanical engineer by training.27
[48] Mr Winders is of the opinion that the proposed dams should be constructed to
meet the applicable requirements where their failure would have a high
consequence.28 He is of the view that this Court should decide on the applicability
of this standard to the proposed dams.29 He does however agree that a registered
engineer will need to be involved in the design process and will have to assess the
relevant consequence category at that time.30
[49] Mr Winders is of the opinion that turbidity limits on the discharge water do not
adequately deal with the issue of sedimentation, a matter on which he and Dr
McCowan did not reach any agreement.31 He did not raise the issue of sediment
with Dr McCowan32 and it was suggested in cross-examination that it is actually
not an issue at all.33 Mr Winders said that the matter was not about science but
24 T 4-33, line 35.
25 T 3-44, lines 13-14.
26 T 3-47, line 17.
27 T 3-47, lines 29-30
28 T 3-52, lines 23-25.
29 T 3-54, lines 14-15.
30 T 3-53, lines 23-25.
31 T 3-58, lines 8-9.
32 T 3-62, lines 27-28.
33 T 3-62, line 30 to T 3-63, line 2.
-- 28 of 46 --
29
about satisfying community values.34 When cross-examined about suspended
sediment and sedimentation, Mr Winders was unable to point to anywhere in his
reports where he expressed the concerns which he put to the Court in his
evidence.35
[50] Mr Winders agreed that turbidity is easy to measure.36 The unit of measurement is
Nephelometric Turbidity Units (NTU) and measurement can be done on-site.37
Measuring total suspended solids is more complicated and usually has to be done
off site.38 He agreed that he failed to raise this in the joint expert report process
with Dr Thorogood.39
[51] Mr Winders agreed that total suspended solids is unlikely to be a concern in
assessing whether or not water could be released.40 He was of the view that
compliance with the 50 NTU limit would not exclude a concern of potential
environmental harm.41 He was of the opinion that the impact of the mine is going
to be on total suspended solids but could not point to any data actually supporting
that.42
[52] As well as agreeing that sedimentation had not been brought up until he came to
the witness box,43 Mr Winders introduced another point which he described as
“critical”, well into his cross-examination.44 He said that the river flow limits for
water release are not appropriate.45 Mr Winders is an experienced expert witness
and was questioned about why he had not raised these matters earlier.46 He was
squarely challenged on the basis that his evidence was false.47
[53] Mr Winders acknowledged that in exhibit 107 at page 2, item (x) he had agreed
with Dr Thorogood that the draft EA provides that minewater may only be
34 T 3-64, lines 17 to T 3-65, line 11.
35 T 3-68, lines 35-36.
36 T 4-3, lines 45-46.
37 T 4-5, lines 3-5.
38 T 4-5, lines 11-12.
39 T 4-13, lines 18-36.
40 T 4-15, lines 19-46.
41 T 4-16, lines 4-8.
42 T 4-17, lines 38-46.
43 T 4-23, lines 14-16.
44 T 4-23, lines 30-44.
45 T 4-23, lines 38-39.
46 T 4-23, line 46 to T 4-25, line 22.
47 T 4-25, line 18.
-- 29 of 46 --
30
released during periods of “significant natural flow” in the river. He accepted that
this was directly contrary to the evidence he had just given in Court.48
[54] Mr Winders pointed out that he had to address three opposing experts.49 This is so,
although producing the expert reports took place over time and he had the choice
of whether or not to seek to cover the range of expertise required. Mr Winders is
experienced as an expert witness50 so it is hard to believe that matters which he
might regard as important would be likely to first enter his head when he is in the
witness box.
[55] In the same category of late changes of opinion is Mr Winders’ view that the
outfall into the Mary River is “completely unnecessary”.51 This was initially raised
on the second day of his cross-examination. It sits alongside his statement, made
only seconds before, that the need for a condition that the minewater dam be “high
consequence”, which he did raise in exhibit 111, was “… the nub of – everything
I’m involved with here is concerned with that …”52 If a river outfall was
completely unnecessary, it is impossible to believe that it would not have been
raised in the reporting process in which the experts engaged. The Court cannot
accept this evidence, for the reasons which have been given.
[56] Mr Winders did not find any seagrass in the middle estuary area that he
inspected.53 As a result of his inspection, he does not assert that the discharge
point, mapped as in the mid-estuary, has the water quality characteristics of the
lower estuary.54 He was of the opinion that the water quality objectives for the
lower estuary should be applied to the mid-estuary location at the point of the
proposed discharge from the mine55 “because the fish move up and down”.56 Mr
Winders eventually agreed that the water characteristics at the discharge point
reflect the mid-estuary characteristics of the Mary River, not those of the lower
estuary.57 The exchange in this cross-examination illustrates an argumentative
approach by Mr Winders rather than the approach of an expert. Additionally, the
48 T 4-26, lines 30-36.
49 T 4-24, lines 20-21.
50 T 4-23, line 46 to T 4-24, line 2 to T 3-70, lines 23-24.
51 T 4-31, lines 40-43.
52 T 4-31, lines 37-38.
53 T 4-44, lines 1-2 to T 4-44, lines 30-33.
54 T 4-46, lines 32-37.
55 T 4-47, lines 7-11.
56 T 4-47, lines 13-14.
57 T 4-47, line 7 to T 4-49, line 5 to T 4-50 lines 3-13.
-- 30 of 46 --
31
argument advanced was without any merit. Mr Winders was under no illusions
about being argumentative and he said:
“That’s the whole thrust of the argument I’m trying to … put to the
court.”58
[57] Mr Winders did not support using reverse osmosis water treatment as part of the
proposed project.59
[58] The Court had the advantage of carefully observing this witness when he gave
evidence. The Court formed the view that he failed to be convincing in raising
matters in Court and attaching importance to them when they had not been
prominent in the substantial process prior to the hearing. The witness’ manner was
defensive in cross-examination and he was unable to give a convincing
explanation why matters raised in Court for the first time were not expressed
earlier if they were significant. The Court is unable to be satisfied that the
concerns first raised in Court are actually matters of importance, for the reasons
which have been given.
The statutory party’s case
[59] The statutory party called one witness, Mr Timothy Mervyn Brain. He is a
manager with the Department of Environment and Heritage Protection. He was the
delegate of the administering authority who had the authority to decide
applications made to it. His affidavit material became exhibits 86 to 104.
[60] In cross-examination by Mr O’Brien QC, Mr Brain was shown exhibit 110, the
joint expert report by the mechanical engineers, Mr Elkin and Mr King, in relation
to noise.
[61] Mr Brain agreed that these experts’ jointly proposed revised noise conditions for
the EA should be adopted in place of those in the draft EA.
[62] The Court accepts that this is appropriate and recommends that the draft EA be
amended accordingly. The revised table, which appears on page 4 of exhibit 110,
is in the following form:
58 T 4-53, lines 1-3.
59 T 4-57, lines 37-40.
-- 31 of 46 --
32
Table 1 – Revised EA Noise Conditions: Table D1 – Noise Limits
[63] When cross-examined by Mr Houen, Mr Brain explained that the limits that are
used in the draft EA for water discharges are all limits that can be measured with a
meter “so that you can get an immediate result”.60 Turbidity is included to enable a
quick measurement and a quick decision about whether the water is compliant
with release criteria or not.61 Turbidity criteria was chosen on the advice from “our
scientific advisers”.62 Mr Brain said that the current version of the model mining
conditions “might include total suspended solids”.63 This matter was not pursued
before the Court. Submissions not seen by Mr Brain when he made his decision
were provided to the Court and became exhibit 72.
[64] Mr Brain said that, in respect of noise and dust at mines, the department would
typically respond to complaints and would not proactively set up noise monitoring
equipment itself, although it could do so.64 The monitoring required by the draft
EA is not required to be routinely sent to the department but is commonly viewed
when inspections are carried out.65 The submission that the statutory party’s
Assessment Report, exhibit 82, should have been made publicly available, as it
60 T 4-75, line 47 to T 4-76, line 2.
61 T 4-76, lines 4-14.
62 T 4-76, line 23.
63 T 4-76, lines 20-21.
64 T 4-76, lines 35-46.
65 T 4-77, lines 1-11.
-- 32 of 46 --
33
might have resulted in more objections, is not a matter upon which this Court can
take any action.
[65] The draft EA, exhibit 9, sets out requirements for dust and particulate monitoring.
The respondent is asking for continuous air quality monitoring.66 Mr Brain stated
that there is dust deposition monitoring. Exhibit 9 page 5, condition B2, requires
compliance with AS 3580.10.1, Methods for sampling and analysis of ambient air.
Condition B3 requires monitoring in accordance with one or other Australian
Standard Methods set out in B3, with sampling once every 6 days with a 24 hour
sampling period. The sampling locations are specified. The modelling done for
this project indicated that dust should not be a problem.67
[66] Concerning dust contaminating rainwater tanks, that was a matter considered in
relation to dust and there are requirements for dust deposition and air monitoring.68
The Land Court’s recommendation under s 269 of the MRA
[67] Section 269(4) of the MRA requires that when making a recommendation to the
Minister that an application for a mining lease be granted in whole or in part, the
Court shall take into account and consider a number of specified matters. These
will be dealt with seriatim, taking into account all of the material before the Court
and the preceding consideration herein. Exhibit 29, the affidavit of Mr Eames,
makes detailed reference to these matters.
Section 269(4)(a) – Whether the provisions of the MRA have been complied with
[68] An examination of the material before the Court demonstrates that all of the
provisions of the MRA have been complied with. There was no submission to the
contrary.
Section 269(4)(b) – Whether the areas of land applied for are mineralised or the other
purposes for which the leases are sought are appropriate
[69] There is coal in this area and the parent company of the applicant is a coal mining
company. It was not suggested that there is no coal here. The Court is satisfied that
the land applied for is mineralised. In exhibit 29, Mr Eames, a mining engineer,
explains in paragraph 42 that over 100 core samples have been drilled in and
around the mining lease areas, which are located in the Burrum coalfields.
66 T 4-80, lines 40-42.
67 T 4-81, lines 44-45 to T 4-82, lines 12-13 to T 4-83, lines 6-14.
68 T 4-83, lines 9-14.
-- 33 of 46 --
34
Historically, small scale coal mining was carried out in numerous places in this
area of coalfields, Mr Eames states. Where the lease area is sought for
infrastructure such as the rail link and coal preparation plant, these are appropriate
purposes for the proposed project.
Section 269(4)(c) – Whether there will be an acceptable level of development and
utilisation of the mineral resources within the areas applied for
[70] Exhibit 29, paragraph 50 shows that there is an anticipated 5 million tons of
product coal to be extracted at a rate of half a million tons per annum by open-cut
mining. The planned operation, with coal preparation and rail facilities, would be
an acceptable level of development and utilisation.
Section 269(4)(d) – Whether the land and the surface area of the land in respect of
which the mining leases are sought are of an appropriate size and
shape in relation to –
(i) the matters mentioned in paragraphs (b) and (c); and
(ii) the type and location of the activities proposed to be carried out
under the leases and their likely impact on the surface of the land
[71] The evidence before the Court shows that the land is a sufficiently regular shape
and size in relation to the specified matters and the type and location of the
proposed activities and their likely impact on the surface. There was no suggestion
to the contrary at the hearing.
Section 269(4)(e) – Whether the term sought is appropriate
[72] There was no suggestion to the contrary. The 20 year term sought for Colton A, B
and C is appropriate for the preparation, mining and rehabilitation which would be
required to be carried out.
Section 269(4)(f) – Whether the applicant has the necessary financial and technical
capabilities to carry on mining operations under the proposed
mining leases
[73] Exhibit 29, the affidavit of Mr Eames, indicates that the applicant has the
necessary means. There was no challenge to this at the hearing.
Section 269(4)(g) – Whether the past performance of the applicant has been
satisfactory
-- 34 of 46 --
35
[74] Exhibit 29, paragraphs 116 and 117, explain that the applicant does not have a
history of performance. The applicant was incorporated for the purpose of the
proposed project.
Section 269(4)(h) – Whether any disadvantage may result to the rights of—
(i) holders of existing exploration permits or mineral development
licences; or
(ii) existing applicants for exploration permits or mineral
development licences
[75] Exhibit 29, paragraphs 118 and 119 explain that the only affected tenure holder,
Blue Energy, has consented to the grant of the tenures sought.
Section 269(4)(i) – Whether the operations to be carried on under the authority of the
proposed mining leases will conform with sound land use
management
[76] The terms of the proposed mining lease and EA will have to be complied with.
The operations to be carried on would conform with sound land use management
if the conditions imposed are adhered to. It is noted that in cross-examination Mr
Eames said:
“At this stage I can just reaffirm we have no plans for another application at
this point in time.”69
[77] What is being considered by the Court is the proposal before it. Exhibit 29,
paragraphs 70 to 74 under the hearing “Possible future expansion”, set out possible
future applications. What distinction there may be between plans and these
possibilities was not explored with Mr Eames by any party.
Section 269(4)(j) – Whether there will be any adverse environmental impact caused by
those operations and, if so, the extent thereof
[78] There will be an adverse environmental impact caused by a coal mine. The extent
will be managed and minimised by the EA. The objections decision relating to
environmental matters which is below should be read in this regard.
Section 269(4)(k) – Whether the public right and interest will be prejudiced
[79] Exhibit 29, paragraph 123, states that the value of coal production from this
project is estimated to be in the order of $80 million per annum for total coal
production valued in the order of $800 million over the life of the project. Up to
120 employees would be required for construction and up to 120 full-time staff at
69 T 2-76, lines 45-46.
-- 35 of 46 --
36
full production. Recruitment is expected to be from the local area. Wages cost
during construction is estimated to be $32 million. Annual royalty to the State is
projected to be approximately $6.7 million, on average, from 2019. Annual payroll
tax is estimated to be $600,000. Taxes and charges paid to Federal, State and
Local Governments are estimated to be in excess of $17.5 million per annum on
average. Direct investment in construction and mining equipment is estimated to
be up to $250 million. Fixed infrastructure will be about 60% of this. Up to $100
million of construction expenditures is expected to be sourced from domestic
suppliers. Rail and port services expenditure are expected to exceed $13 million
per annum on average. There was no challenge made at the hearing to any of this.
It does not appear that the public right and interest will be prejudiced. Significant
public benefit is in prospect.
Section 269(4)(l) – Whether any good reason has been shown for a refusal to grant the
mining leases
[80] The consideration of the material put before the Court by the parties at the hearing
does not indicate the presence of any good reason for a refusal to grant the mining
leases.
Section 269(4)(m) – Whether, taking into consideration the current and prospective
uses of that land, the proposed mining operation is an appropriate
land use
[81] Exhibit 29 sets out that the land is unallocated state land, a road reserve without a
constructed road and a railway reserve without a rail line. This was not
contradicted. The prospective uses of the land would be likely to be unchanged
from current uses were it not for the proposed mining operation. The Court is
satisfied that the proposed mining operation is an appropriate land use. No other
use was supported in the evidence put before the Court. Historically, the area has
supported logging and coal mining.
Conclusion
[82] The Court recommends to the Minister that the applications be granted in whole.
Objections decision under the EP Act
[83] The Court has considered the matters set out in s 223 of the EP Act, which is
applicable due to s 683 of that Act. It is noted that no activities are contemplated in
-- 36 of 46 --
37
a wild river area and the status of the applications under the MRA has already
been considered: they are the subject of the recommendation that they be granted
in whole. The application documents and objections are before the Court, as are
the reports and evidence of the witnesses. The regulatory requirements were
considered in the evidence heard over four days and have been referred to in the
consideration above of the evidence produced at the hearing. What was put before
the Court at the hearing was not compartmentalised as the MRA and EP Act
hearings were conducted together, which provided efficiencies. The Court has
considered the Environmental Protection (Water) Policy 2009, the Mary River
environmental values and water quality objectives for basin no 138, including all
tributaries of the Mary River, exhibit 125. Also considered were the Model Mining
Conditions, version 5, exhibit 105. The Court also had the benefit of a comparison
of the Colton Coal Environmental Authority Conditions for Water with the Model
Mining Conditions and the Model Water Conditions for Coal Mines in the Fitzroy
Basin, exhibit 119.
The standard criteria
[84] The Court is required to consider the standard criteria. Before turning to this, it is
useful to refer to section 3 of the EP Act, which sets out the objective of the Act
and section 4, which states how that objective is to be achieved. Those sections
state:
3 Object
The object of this Act is to protect Queensland’s environment while
allowing for development that improves the total quality of life, both
now and in the future, in a way that maintains the ecological processes
on which life depends (ecologically sustainable development).
4 How object of Act is to be achieved
(1) The protection of Queensland’s environment is to be achieved by
an integrated management program that is consistent with
ecologically sustainable development.
(2) The program is cyclical and involves the following phases—
(a) phase 1 — establishing the state of the environment and defining
environmental objectives;
(b) phase 2 — developing effective environmental strategies;
(c) phase 3 — implementing environmental strategies and integrating
them into efficient resource management;
(d) phase 4 — ensuring accountability of environmental strategies.
[85] The standard criteria are defined in Schedule 4 in the following way:
standard criteria means—
-- 37 of 46 --
38
(a) the principles of ecologically sustainable development as set
out in the ‘National Strategy for Ecologically Sustainable
Development’; and
(b) any applicable environmental protection policy; and
(c) any applicable Commonwealth, State or local government plans,
standards, agreements or requirements; and
(d) any applicable environmental impact study, assessment or report;
and
(e) the character, resilience and values of the receiving environment;
and
(f) all submissions made by the applicant and submitters; and
(g) the best practice environmental management for activities under
any relevant instrument, or proposed instrument, as follows—
(i) an environmental authority;
(ii) a transitional environmental program;
(iii) an environmental protection order;
(iv) a disposal permit;
(v) a development approval; and
(h) the financial implications of the requirements under an
instrument, or proposed instrument, mentioned in paragraph (g) as
they would relate to the type of activity or industry carried out, or
proposed to be carried out, under the instrument; and
(i) the public interest; and
(j) any applicable site management plan; and
(k) any relevant integrated environmental management system or
proposed integrated environmental management system; and
(l) any other matter prescribed under a regulation.
[86] The National Strategy for Ecologically Sustainable Development is defined in
Schedule 4 as follows:
National Strategy for Ecologically Sustainable Development means the
‘National Strategy for Ecologically Sustainable Development’ endorsed by
the Council of Australian Governments on 7 December 1992.
[87] In Endocoal Limited v Glencore Coal Queensland Pty Ltd and Department of
Environment and Heritage Protection70 at [42], Member Smith, referring to his
decision in De Lacey & Anor v Kagara Pty Ltd71 said:
“The National Strategy for Ecologically Sustainable Development of
December 1992 contains the following statement of Australia’s goal, core
objectives and guiding principles for the Strategy:
‘The Goal is:
Development that improves the total quality of life, both now
and in the future, in a way that maintains the ecological
processes on which life depends.
70 [2014] QLC 54.
71 (2009) 30 QLCR 57.
-- 38 of 46 --
39
The Core Objectives are:
• to enhance individual and community well-being and
welfare by following a path of economic development that
safeguards the welfare of future generations
• to provide for equity within and between generations
• to protect biological diversity and maintain essential
ecological processes and life-support systems
The Guiding Principles are:
• decision making processes should effectively integrate
both long and short-term economic, environmental,
social and equity considerations
• where there are threats of serious or irreversible
environmental damage, lack of full scientific certainty
should not be used as a reason for postponing measures to
prevent environmental degradation
• the global dimension of environmental impacts of actions
and policies should be recognised and considered
• the need to develop a strong, growing and diversified
economy which can enhance the capacity for
environmental protection should be recognised
• the need to maintain and enhance international
competitiveness in an environmentally sound manner
should be recognised
• cost effective and flexible policy instruments should be
adopted, such as improved valuation, pricing and incentive
mechanisms
• decisions and actions should provide for broad community
involvement on issues which affect them
These guiding principles and core objectives need to be
considered as a package. No objective or principle should
predominate over the others. A balanced approach is required
that takes into account all these objectives and principles to
pursue the goal of ESD.’
From the precautionary principle perspective, the key is the
second bullet point to the guiding principles in the paragraph
above, which sets out in a lengthened form what is currently
referred to as the precautionary principle – that is, ‘where there
are threats of serious or irreversible environmental damage,
lack of full scientific certainty should not be used as a reason
for postponing measures to prevent environmental
degradation.”
[88] In Xstrata Coal Queensland Pty Ltd & Ors v Friends of the Earth - Brisbane Co-
Op Ltd & Ors72 President MacDonald considered the Goal, Core Objectives and
Guiding Principles and said, at [256]:
“The precautionary principle is encapsulated in the second principle above.
That is, where there are threats of serious or irreversible environmental
72 (2012) 33 QLCR 79 at [255].
-- 39 of 46 --
40
damage, lack of full scientific certainty should not be used as a reason for
postponing measures to prevent environmental degradation.”
[89] In Adani Mining Pty Ltd v Land Services of Coast and Country Inc & Ors73
President MacDonald said:
“Precautionary principle
[36] The first respondent submitted that the precautionary principle was
engaged in this case in relation to the DSC, the black-throated finch
and the waxy cabbage palm. The application of the precautionary
principle was discussed in detail in Telstra Corporation Ltd v
Hornsby Shire Council, where Preston CJ said:
“The application of the precautionary principle and the
concomitant need to take precautionary measures is triggered
by the satisfaction of two conditions precedent or thresholds: a
threat of serious or irreversible environmental damage and
scientific uncertainty as to the environmental damage. These
conditions or thresholds are cumulative. Once both of these
conditions or thresholds are satisfied, a precautionary measure
may be taken to avert the anticipated threat of environmental
damage, but it should be proportionate.”
[37] His Honour went on to say that
determining the existence of a threat of serious
irreversible environmental damage does not involve,
at the stage of assessing the first condition precedent,
any evaluation of the scientific uncertainty of the
threat. If there is not a threat of serious or irreversible
environmental damage, there is no basis upon which
the precautionary principle can operate.
The second condition precedent required to trigger the
application of the principle is that there be a “lack of
full scientific certainty”. The uncertainty is as to the
nature and scope of the threat of environmental
damage. Full scientific certainty is not required. If
there is no, or not considerable scientific uncertainty,
the second condition precedent is not satisfied and
even though there is a threat of serious or irreversible
environmental damage (that is, the first condition
precedent is satisfied) the precautionary principle will
not apply. The threat of serious irreversible
environmental damage can be classified as relatively
certain because it is possible to establish a causal link
between an action or event and environmental
damage, to calculate the probability of their
occurrence, and to insure against them. Measures will
still need to be taken but these will be preventative
measures to control or regulate the relatively certain
threat of serious or irreversible environmental damage,
73 [2015] QLC 48.
-- 40 of 46 --
41
rather than precautionary measures which are
appropriate in relation to uncertain threats.
If each of the two conditions precedent is satisfied the
precautionary principle will be activated. At this point
the evidentiary burden of proof shifts. A decision–
maker must assume that the threat of serious or
irreversible environmental damage is no longer
uncertain but is a reality. The burden of showing that
the threat does not exist or is negligible reverts to the
proponent of the development. The rationale for
requiring this shift of the burden of proof is to ensure
preventative anticipation; to act before scientific
certainty of cause and effect is established. The
preference is to prevent environmental damage rather
than to remediate it.
The function of the precautionary principle is,
therefore to require the decision-maker to assume that
there is or there will be a serious or irreversible threat
of environmental damage and to take this into account,
notwithstanding that there is a degree of scientific
uncertainty about whether the threat exists.
There is nothing in the formulation of the
precautionary principle which requires the decision-
maker to give the assumed factor (the serious or
irreversible environmental damage) overriding weight
compared to the other factors required to be
considered, such as social and economic factors, when
deciding how to proceed. The effect of the shift in the
evidentiary burden of proof simply means that, in
making the final decision, the decision-maker must
assume that there will be serious or irreversible
environmental damage. That factor must be taken into
account in the calculus which decision-makers are
instructed to apply under environmental legislation.
The precautionary principle should not be used to try
to avoid all risks. Rationality also dictates that the
precautionary principle and any preventative measure
cannot be based on a purely hypothetical approach to
the risk, founded on mere conjecture which has not
been scientifically verified.
The type and level of precautionary measures that will
be appropriate will depend on the combined effect of
the degree of seriousness and the irreversibility of the
threat and the degree of uncertainty. This involves
assessment of risk, namely the probability of the event
occurring and the seriousness of the consequences
should it occur. The more significant and more
uncertain the threat, the greater the degree of caution
required.
-- 41 of 46 --
42
Prudence also suggests that some margin for error
should be retained until all the consequences of the
decision to proceed with the development are known.
One means of retaining a margin for error is to
implement a step-wise or adaptive management
approach, whereby uncertainties are acknowledged
and the area affected by the development plan,
program or project is expanded as the extent of
uncertainty is reduced. An adaptive management
approach might involve the following core elements:
monitoring impacts of management or
decisions based on agreed indicators;
promoting research, to reduce key
uncertainties;
ensuring periodic evaluation of the
outcomes of implementation, drawing
lessons, and review or adjustment, as
necessary, of the measures or decisions
adopted;
establishing an efficient and effective
compliance system.
The precautionary principle embraces the concept of
proportionality, that is that measures should not go
beyond what is appropriate and necessary in order to
achieve the objectives in question. A reasonable
balance must be struck between the stringency of the
precautionary measures, which may have associated
costs, such as financial, livelihood and opportunity
costs and the seriousness and irreversibility of the
potential threat.
The precautionary principle, where triggered, does
not necessarily prohibit carrying out the development
plan, program or project until full scientific certainty
is attained. The solution is to assess the risk-
weighted consequences of various options and select
the option that affords the appropriate degree of
precaution for the set of risks associated with the
option.
The precautionary principle is but one of the sets of
principles of ecologically sustainable development. It
should not be viewed in isolation, but rather as part
of the package. This means that the precautionary
measures that should be selected must not only be
appropriate having regard to the precautionary
principle itself, but also in the context of the other
principles of ecologically sustainable development,
including inter-generational and intra-generational
equity and the conservation of biological diversity
and ecological integrity.
Intergenerational equity
-- 42 of 46 --
43
[38] In relation to the principles of equity, Preston CJ said that there is a
need for inter-generational equity and intra-generational equity. He
explained that inter-generational equity means that the present
generation should ensure that the health, diversity and productivity
of the environment are maintained or enhanced for future
generations. This is the definition contained in s.3.5.2 in the
Schedule to the IGAE. Preston CJ said that intra-generational equity
involves considerations of equity within the present generation,
such as uses of natural resources by one nation-state (or sectors or
classes within a nation-state) needing to take account of the needs
of other nation-states (or sectors or classes within a nation-state).
Conservation of biological diversity and ecological integrity
[39] In Bentley v BGP Properties Pty Ltd Preston CJ said:
“Maintaining ecological integrity involves maintaining
ecosystem health. Ecosystems become unhealthy if their
community structure (species richness, species
composition or food web architecture) or ecosystem
functioning (productivity, nutrient dynamics,
decomposition) has been fundamentally upset by human
pressures …
The conservation of threatened species is an essential
action in the conservation of species diversity, and hence
of biological diversity and ecological integrity.” (citations
omitted)
[90] In the present case, the evidence which has been provided to the Court establishes
that the quality requirements imposed for the discharge of water into the Mary
River are such that the release does not pose a threat of serious or irreversible
environmental damage. There is therefore no basis upon which the precautionary
principle could operate in this case. The Court has not accepted the evidence of Mr
Winders in relation to the matters already referred to so this conclusion is
inevitable on the basis of the remaining evidence. No evidence was led in regard to
inter or intra-generational equity beyond the concerns already addressed. The
reference to fisheries resources by Mr Winders was based on exhibit 58, the letter
dated 13 December 2015 from the Queensland Seafood Industry Association. It
states that the mining operation would put the fisheries resource at risk. It does not
contain scientific evidence to advance the claim made. Matters of biological
diversity and ecological integrity, also first raised by Mr Winders in Court, are not
accepted for the same reasons as his other items of oral evidence, first raised in
Court.
-- 43 of 46 --
44
[91] The matters set out in (b), (c), and (e) of the standard criteria have been considered
in the evidence given at the hearing to the extent to which the parties directed
attention to them. This may be found principally in the oral evidence and the
implications of these matters were explored in that evidence. There was no
environmental impact study in this case.
[92] The character, resilience and values of the receiving environment were considered
in the evidence which has been referred to above. All of the submissions have
been taken into account and best practice environmental management is
incorporated into the draft EA.
[93] In Adani Mining Pty Ltd v Land Services of Coast and Country Inc. & Ors,74
President MacDonald considered the adaptive management approach. That
approach is incorporated into the draft EA. The learned President considered that
approach warranted in the case before her. The learned President said:75
“Preston CJ said, in Telstra, such an approach might involve the following
core elements:
monitoring impacts of management or decisions based on agreed
indicators;
promoting research to reduce any uncertainties;
ensuring periodic evaluation of the outcomes of implementation,
drawing lessons and review or adjustments of the measures or
decisions adopted;
establishing an efficient and effective compliance system.”
[94] The monitoring of management decisions will be based on compliance with the
draft EA conditions. There is a compliance system which, if operated efficiently
and effectively, is capable of properly supervising compliance. ADAAM
submitted that there ought to be a condition that the applicant provides reports that
it may have from time to time to the statutory party, and that the statutory party
approve designs. This differs from the regulatory regime that has been adopted by
the statutory party. The Court is not able to be satisfied by evidence that this is
likely to lead to any improved outcomes so is not satisfied that such a condition
should be recommended. ADAAM has, in submissions, provided a number of
amendments that it suggests be included in the EA in the event that the proposed
project is to proceed. The proposed amendments reflect the areas of concern dealt
with at the hearing. They are not supported by the other parties. In no case was a
74 [2015] QLC 48.
75 Ibid, [268].
-- 44 of 46 --
45
proposed condition, when foreshadowed to a witness whose evidence the Court
has accepted, agreed to by the witness as being necessary. Since the evidence
before the Court did not demonstrate that the draft EA is deficient, except in
relation to the need for some revised noise conditions, the Court is not satisfied
that there is a need for any other amendments to the draft EA. The Court is
accordingly unable, on the basis of the evidence, to recommend any of these
amendments.
[95] The evidence is that the financial implications of the regulatory regime would not
be beyond the resources of the proponent of the project, in view of its position in
its corporate structure.
[96] The public interest, as the learned President pointed out in Adani Mining Pty Ltd v
Land Services of Coast and Country Inc. & Ors:
“… involves a discretionary balancing exercise of the widest import
confined only so far as the subject matter and the scope and purpose of the
statute may enable.”76 (citations omitted)
[97] The economic benefits of the proposed mine have been referred to, and they are
considerable. Weighing against this is the evidence presented to the Court by the
experts. The evaluation of that evidence shows that the precautionary principle
does not apply and there is no acceptable evidence upon which to base a rational
concern that would weigh against the benefits of the proposed project when
properly regulated.
[98] The planned development and management of the project site and the
environmental management system reflected in the draft EA have been taken into
account. The Court has not been referred to any other matter prescribed under a
regulation which would call for consideration beyond the examination which has
been conducted. The evidence does not support a need for sampling and testing of
rainwater tanks or for real-time noise monitoring.
Conclusion
76 [2015] QLC 48, [43].
-- 45 of 46 --
46
[99] As has already been referred to, the noise limits in Table D1 of the draft EA need
to be revised. They should follow Table 1 on page 4 of exhibit 110, which was set
out in [62] above.
[100] In accordance with section 222(1)(b) of the EP Act, the Court recommends to the
EPA Minister that the application be granted, but on stated conditions that are
different to the conditions in the draft.
ORDERS:
1. In accordance with s 269 of the Mineral Resources Act 1989, the Court
recommends to the Honourable the Minister administering the Mineral
Resources Act 1989 that the applications be granted in whole.
2. In accordance with s 222(1)(b) of the Environmental Protection Act 1994,
the Court recommends to the Honourable the Minister administering the
Environmental Protection Act 1994 that the application be granted, but on
stated conditions that are different to the conditions in the draft
environmental authority issued on 1 September 2014 to the extent that
Table D1 – Noise limits referred to in Condition D1 be replaced with the
following revised table:
Table D1 – Noise limits
WA ISDALE
MEMBER OF THE LAND COURT
-- 46 of 46 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2016/073