BRB Modular Pty Ltd v AWX Constructions Pty Ltd & Ors [2015] QSC 218
SUPREME COURT OF QUEENSLAND
CITATION: BRB Modular Pty Ltd v AWX Constructions Pty Ltd & Ors
[2015] QSC 218
PARTIES: BRB MODULAR PTY LTD
ACN 114 678 349
(applicant)
v
AWX CONSTRUCTIONS PTY LTD
ABN 118 400 098
(first respondent)
THE REGISTRAR (QUEENSLAND BUILDING AND
CONSTRUCTION COMMISSION)
(second respondent)
JORAM (JOHN) MURRAY
(third respondent)
FILE NO/S: SC No 7073 of 2015
DIVISION: Trial Division
PROCEEDING: Originating application
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 31 July 2015
DELIVERED AT: Brisbane
HEARING DATE: 28 July 2015
JUDGE: Applegarth J
ORDERS: 1. The application be dismissed.
2. The Registrar pay by cheque payable to the first
respondent, AWX Constructions Pty Ltd, from the
amount paid into the Court Suitors Fund by the
applicant pursuant to an order made 22 July 2015:
a. the sum of $3,935,707.39; and
b. interest calculated at the daily rate of $833.95
from 24 July 2105 to the date on which the first
respondent has received the money referred to
in order 2(a) above.
3. The Registrar pay by cheque payable to the applicant,
BRB Modular Pty Ltd, the balance of the amount paid
into the Court Suitors Fund by the applicant pursuant
to an order made 22 July 2015, together with any
accretions due.
-- 1 of 18 --
2
4. The applicant pay the first respondent’s costs of and
incidental to the application on a standard basis,
excluding the costs of and incidental to the
interlocutory hearing on 22 July 2015 which remain
reserved.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT AND
RECOVERY OF PROGRESS PAYMENTS – where the
applicant seeks a declaration that an adjudication decision is
void by reason of jurisdictional error and an injunction
restraining a sub-contractor from giving effect to it – where
applicant submits that no reference date accrued pursuant to
Building and Construction Industry Payments Act 2004 (Qld)
– where contract required submission of a statutory
declaration before a payment claim could be made – where
contract required the sub-contractor to depose that, to the best
of its knowledge, all sub-contractors had been paid – where
sub-contractor delivered a payment claim together with a
statutory declaration in the prescribed form with the addition
“other than those owed variations, payable by the head
contractor” – where applicant submits that no reference date
for the making of a payment claim arose as the declaration
was not in the required form – whether the contractual
condition is effective to exclude the sub-contractor’s statutory
entitlement to make a progress claim under the Act
Building and Construction Industry Payments Act 2004
(Qld), ss 4, 16, 99
Building and Construction Industry Security of Payment Act
1999 (NSW), ss 13(7), 13 (9)
Subcontractors’ Charges Act 1974 (Qld), s 5
BHW Solutions Pty Ltd v Altitude Constructions Pty Ltd
[2012] QSC 214, cited
Capricorn Quarries Pty Ltd v Inline Communication
Construction Pty Ltd [2013] 2 Qd R 1; [2012] QSC 388, cited
De Neefe Signs Pty Ltd v Build1 (Qld) Pty Ltd; Traffic
Technologies Traffic Hire Pty Ltd v Build1 (Qld) Pty Ltd
[2010] QSC 279, cited
HM Hire Pty Ltd v National Plant and Equipment Pty Ltd
[2014] 2 Qd R 44; [2013] QSC 274, cited
John Goss Projects v Leighton Contractors (2006) 66
NSWLR 707; [2006] NSWSC 798, cited
John Holland Pty Ltd v Coastal Dredging & Construction
Pty Ltd [2012] 2 Qd R 435; [2012] QCA 150, cited
Lean Field Developments Pty Ltd v E & I Global Solutions
(Aust) Pty Ltd [2014] QSC 293, considered
-- 2 of 18 --
3
McConnell Dowell Constructors (Aust) Pty Ltd v Heavy Plant
Leasing Pty Ltd [2013] QSC 269, cited
Northbuild Construction Pty Ltd v Central Interior Linings
Pty Ltd [2012] 1 Qd R 525; [2011] QCA 022, cited
R J Neller Building Pty Ltd v Ainsworth [2009] 1 Qd R 390;
[2008] QCA 397, cited
State of Queensland v T & M Buckley Pty Ltd [2012] QSC
265, considered
COUNSEL: P R Franco QC and M H Martinez for the applicant
D P O’Brien QC and L M Campbell for the first respondent
SOLICITORS: Holding Redlich for the applicant
McInnes Wilson Lawyers for the first respondent
[1] The applicant (BRB) and the first respondent (AWX) are parties to a construction contract
by which AWX agreed to construct a camp and accommodation village at an LNG
processing facility. Subject to certain conditions, AWX is entitled to make a progress
claim on the 28th of each month. One of those conditions is compliance with cl 14.10
which provides that:
“The Subcontractor must deliver to the Contractor’s Representative a
completed and signed statutory declaration in the form set out in Schedule 3,
at least 2 working days prior to the time when, subject to the requirements of
clause 14.1(a) to (d), each claim for payment may be made pursuant to clause
14.1.”
[2] Paragraph 5 of the prescribed statutory declaration requires the deponent to declare that:
“To the best of my knowledge all sub-contractors and suppliers who have at
any time been employed by the Subcontractor for work under the Subcontract
have as at the date of this declaration been paid all moneys due and payable
to them in respect of their employment in relation to that work.”
[3] AWX delivered a payment claim together with a completed and signed statutory
declaration in the required form, but added the following notation at the end of
paragraph 5:
“other than those owed variations, payable by the head contractor.”
[4] BRB contested the payment claim, contending that it had not been made from a valid
reference date, and so was not a valid payment claim under the Act. The matter proceeded
to an adjudication. The adjudicator awarded AWX $3,706,601.88 including GST.
Relevantly, the adjudicator decided that the contract provided for the working out of a
reference date. By reason of s 99 of the Building and Construction Industry Payments
Act 2004 (Qld), the contractual precondition did not affect a reference date arising for the
purpose of making a payment claim under the Act.
-- 3 of 18 --
4
[5] BRB seeks a declaration that the adjudication determination is void for jurisdictional
error, and an injunction restraining AWX from giving effect to it. The essence of BRB’s
case about jurisdictional error is that no reference date for the making of a payment claim
under the Act had arisen. A contractual precondition to a reference date arising under the
contract, namely the provision of a statutory declaration in the form provided for under
the construction contract, was not complied with by AWX.
[6] BRB identifies the key issue as being whether the parties’ agreement that an entitlement
to make a progress claim only arises after delivery of the statutory declaration is contrary
to the Act.
The parties’ essential contentions
[7] AWX argues that the contractual precondition of providing a statutory declaration in the
form provided for under the construction contract unduly restricts the making of statutory
payment claims under the Act and cuts across, rather than furthers, the objects and
purpose of the Act. That precondition is said to lack utility and have a stifling effect on
the making of a payment claim under the Act.
[8] According to AWX, the basic purpose of the Act is to provide a statutory right to make a
progress payment under a construction contract and to provide a mechanism for the
prompt payment of an adjudicated amount. The purpose of the Act is to ensure on-going
cash-flow between the contractor claimant and the other party to the construction
contract. Creditors of the contractor, including sub-contractors, may incidentally benefit
from the ongoing cash-flow, however the Act is not directly concerned with the
relationships between a party to the relevant construction contract and third parties
(including parties up or down the construction claim).
[9] By contrast, BRB contends that the Act is concerned with protecting the position of third
parties down the construction chain, such as sub-contractors. It argues that it would
encourage payment to these sub-contractors if parties had freedom to agree that a
contractor had no entitlement to make a progress payment claim until it had paid
undisputed amounts due to its own sub-contractors.
[10] Next, AWX argues that the consequences of non-compliance with the statutory
declaration precondition are draconian. Unless a statutory declaration is provided in
exactly the form required under the contract, no statutory payment claim could ever be
made. A party in AWX’s position would be prevented from making a payment claim
under the Act if it owed any money to one of its sub-contractors, even a tiny amount.
[11] BRB responds that the contractual condition is not onerous. It only requires the contractor
to declare that, to the best of its knowledge, all sub-contractors have been paid as at the
date of the declaration all moneys due and payable to them. Paragraph 8 of the required
form provides a carve-out from this declaration in respect of certain matters in dispute.
As a result, the contractor is obliged to do no more than declare that sub-contractors have
been paid all undisputed amounts owing to them, to the best of the deponent’s knowledge.
BRB also argues that cl 14.10 does not, in terms, require strict or exact compliance with
the form because the contract should be given a pragmatic and commercial construction.
-- 4 of 18 --
5
A failure to dot an “i” would not mean that AWX had not “complied with clause 14.10”
within the meaning of the contract.
[12] Next, AWX argues that the requirement that a compliant statutory declaration be provided
in order for a reference date to arise is of no relevant utility. BRB has no contractual
relations with, or liability to, any of AWX’s sub-contractors. The status of relations
between AWX and the sub-contractors has no bearing upon BRB’s indebtedness to AWX
for the work AWX has undertaken under the construction contract or the assessment of
any payment claim made under the Act. The statements in the declaration do not facilitate
the statutory entitlement to a progress payment or the assessment of a payment claim by
BRB under the construction contract. This is not a case in which there is a direct nexus
between the required statements in the declaration and the contents of the payment claim.
[13] BRB contends, however, that the required declaration has utility in informing it about the
position of sub-contractors working on the project.
[14] In summary, AWX’s case is that the precondition of providing a statutory declaration:
impedes rather than further the objects of the Act;
is unduly onerous and the consequences of non-compliance are
disproportionate and extreme; and
has no utility or relevance to the payment claim or its assessment.
[15] BRB’s essential case is that whilst the contractual precondition may, in some situations,
impede essential cash-flow to a contractor, on balance, the practical requirement to pay
sub-contractors and to declare that they have been paid, encourages such third parties to
be paid and thereby facilitates an important objective of the Act. The Act is said to be
concerned with protecting the position of smaller sub-contractors down the contractual
chain. If a contractor is unable to pay undisputed amounts due to its sub-contractors, then
it would be insolvent, and BRB observes that it would not assist the sub-contractors for
the principal to pay an insolvent contractor. BRB argues that in such a situation, the sub-
contractors’ rights are best protected by serving on the principal a notice of charge under
the Subcontractors Charges Act 1974 (Qld).
Does the condition impede, rather than facilitate, the objects of the Act?
[16] The resolution of this question depends on the identification of the objects of the Act, and
an assessment of whether, on balance, the condition impedes them.
[17] BRB’s case is that the Act is largely concerned with protecting smaller sub-contractors
down the chain, and that a statutory declaration provision of the kind under scrutiny is a
“pragmatic and commercial way to achieve this end”. It provides a party in AWX’s
position with a strong incentive to pay sub-contractors undisputed amounts owing to
them.
-- 5 of 18 --
6
[18] Whilst conceding that the provision may be said to impede the operation of the Act by
stopping cash-flow in a case such as this, BRB argues that it also facilitates the operation
of the Act because, in practice, the provision requires more than a piece of paper. In
substance, it requires a party to pay undisputed amounts to sub-contractors in order to
provide the required statutory declaration, and the practical requirement to pay sub-
contractors is said to encourage contractors to keep cash flowing down the chain to sub-
contractors. On balance, the provision is said to do more to facilitate, than to impede, the
objects of the Act.
[19] The objects of the Act have been stated elsewhere.1 The Act provides a statutory
mechanism for the recovery of progress payments for the carrying out of “construction
work”. It gives a statutory entitlement to a provisional progress payment to a contractor
who qualifies for that entitlement. The right to such a payment and the valuation of that
right may become the subject of an adjudication process, and the adjudication decision
may be enforced as a court judgment. Commercially, that outcome has an important cash-
flow effect.2 The Act provides a speedy means of ensuring cash-flow to a party from the
party with which it contracts.3
[20] The Act confers an entitlement upon a party to a construction contract who qualifies for
that entitlement. The Act does not give any entitlement to third parties to be paid out of
a progress payment, or for the progress payment to be secured for their benefit.
[21] One of the incidental benefits of cash flowing to a contractor who has an entitlement
under the Act is that money will flow to that contractor’s creditors, including any sub-
contractors. But the Act does not address the position of third parties, and certainly does
not single out sub-contractors for special treatment over other creditors. The Act proceeds
on the basis that a contractor to whom a progress payment is made will deal with the
moneys it receives in accordance with its legal obligations.
[22] The interests of third parties are not irrelevant, in the sense that they may stand to gain
from the benefit that the Act gives in providing a cash-flow to a contractor who has an
entitlement under the Act. But those third parties are not the primary beneficiaries of the
Act’s provisions, and the Act does not purport to regulate relations between a contractor
and third parties. For example, the Act does not oblige a contractor to whom a progress
payment is made in accordance with the contractor’s statutory entitlement to pay its
creditors. The obligation to do so is left to the general law and commercial realities.
[23] BRB points to certain statements made by the responsible Minister in the Second Reading
Speech for the Bill which became the Act. The Minister rejected a proposed “pay when
paid provision”.4 In doing so, he referred to “developers, big builders and all of those
people who would use their might and power against the small sub-contractors” and stated
that the legislation was about “protecting the small sub-contractors”. These statements
recognise that small sub-contractors experience cash-flow problems and that the payment
1 Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2012] 1 Qd R 525 [52] at 546 – 550 [66];
John Holland Pty Ltd v Coastal Dredging & Construction Pty Ltd [2012] 2 Qd R 435 at 441 [15] – 442 [19]
(“John Holland”).
2 Capricorn Quarries Pty Ltd v Inline Communication Construction Pty Ltd [2013] 2 Qd R 1 at 9 [41].
3 HM Hire Pty Ltd v National Plant and Equipment Pty Ltd [2014] 2 Qd R 44 at 54 [28] – 55 [29].
4 Hansard, Queensland Legislative Assembly (18 March 2004), 863.
-- 6 of 18 --
7
to them of a progress payment in accordance with the legislation should not depend upon
a bigger builder being paid. As a result, the Act provides that a “pay when paid provision”
has no effect.5
[24] BRB submits that these Ministerial statements are supportive of the view that the statutory
declaration provision accords with the objects of the Act. I disagree. The Minister
identified a core concern in enacting the legislation, which justified the rejection of a
proposal from the Master Builders Association of Queensland for a “pay when paid
provision”. The concern was for sub-contractors to receive progress payment under the
Act. That concern might be said to extend to sub-contractors who are unable to pay some
of their sub-contractors.
[25] The Act does not condition the right to make a payment claim in accordance with its
provisions upon the contractor first paying its sub-contractors or other third parties to
whom it owes money. The Act does not qualify the obligation to make a progress
payment to which a contractor is entitled under the Act in circumstances in which the
other party to the construction contract reasonably believes the contractor is insolvent or
to be on the brink of insolvency, or reasonably believes the contractor is presently unable
to pay third parties. The Act provides a statutory entitlement despite these sort of
circumstances. It may be said that the Act provides the entitlement because in some cases
a contractor is unable to pay third parties, including sub-contractors, money that is owed
to them, and requires a progress payment to do so.
[26] The Act does not require a contractor to prove that all of its sub-contractors (or, for that
matter, other creditors) have been paid. Such a requirement might be said to undermine
the Act’s purpose of ensuring cash-flow to a party from the party with whom it contracts.
[27] The position may be illustrated by an example. Contractor X has two construction
contracts. One is at Mine A for Company A, and another is at Mine B for Company B.
X pays its creditors on time. It expects to receive a $1 million progress payment on 15
August from Company A, and to use that money to pay $100,000, which will become
owing to a sub-contractor on Project B on 25 August. X also expects Company B to pay
it $1 million for work which it has done on Project B, and is in a position to make a
payment claim so that it will receive the $1 million from Company B on 31 August.
[28] Company A unexpectedly goes into administration, or for some other reason fails to pay
the $1 million which is due to be paid on 15 August. Under a contractual provision of
the kind which BRB seeks to uphold, X would not be entitled to receive the $1 million
from Company B on 31 August. This is because X is unable to pay the sub-contractor on
Project B. It could not pay that sub-contractor because it did not receive the $1 million
from Company A. The contractual provision in question would prevent it receiving
$1 million from Company B and paying its sub-contractor out of that money. X’s cash-
flow would be disastrously affected, not only by not receiving the $1 million owed to it
by Company A, but also by the operation of the contractual provision which disentitles it
to a progress payment of $1 million from Company B.
5 The Act, s 16.
-- 7 of 18 --
8
[29] The purpose of the Act, and for that matter the interests of third parties such as the sub-
contractor in the example which I have given, would seem to be advanced by ensuring
the cash-flow to X of the progress payment which falls due on 31 August. Without it, X
may face insolvency, with catastrophic consequences for it, its workforce and its
creditors. A contractual provision of the kind under scrutiny in this case would have such
a consequence.
[30] The essential issue is whether the Act’s objects are advanced by confining its benefits to
those contractors who may be in the fortunate position of being able to pay all of its sub-
contractors. Expressed differently, are the objects of the Act advanced or impeded by
allowing parties to exclude what would otherwise be a statutory entitlement to a progress
payment in circumstances where the contractor is unable to declare that all of its sub-
contractors have been paid?
[31] In my view, they are impeded because such a provision halts the flow of cash to a
contractor who needs it, and the purpose of the Act is to ensure such a cash-flow.
[32] While it may be said that such a provision has the beneficial effect of encouraging
contractors to pay sub-contractors when they are able to do so, and thereby benefits
certain third parties, the payment of third parties is not the focus of the Act. The Act’s
focus is on the parties to a construction contract. The principal object of the Act of
ensuring cash-flow to a party which establishes a statutory entitlement to a progress
payment (including those who are on the brink of insolvency) is best advanced by not
enforcing contractual provisions which purport to exclude that statutory entitlement by
requiring a contractor to declare, when it is unable to do so, that all of its sub-contractors
have been paid.
[33] To the extent it is appropriate to take account of the interests of third parties, rather than
the parties to a construction contract, third parties who are owed money by a contractor
who is entitled to a statutory progress payment would seem to be better served by
facilitating cash-flow to the contractor, particularly a contractor who has fallen upon
temporary hard times, than by restricting such a cash-flow. The contractual requirement
to declare that, to the best of the contractor’s knowledge, all sub-contractors and suppliers
have been paid all moneys due and payable to them (a requirement which the legislature
has not seen fit to include as a condition upon the conferral of a statutory right) may
encourage contractors to pay undisputed amounts to its sub-contractors, and thereby
benefit third parties. However, on balance, that benefit to third parties is outweighed by
the benefit to contractors and their creditors (including sub-contractors) of the cash-flow
which the Act provides to contractors who require a cash-flow to pay their creditors, stay
in business and complete construction contracts.
[34] I conclude that the relevant condition impedes rather than facilitates the objects of the
Act.
-- 8 of 18 --
9
BRB’s reliance on the New South Wales Act
[35] I do not consider that this conclusion is altered by the fact that the New South Wales
Parliament enacted a provision that a “head contractor” which submits a payment claim
must accompany it with “a declaration to the effect that all subcontractors, if any, have
been paid all amounts that have become due and payable in relation to the construction
work concerned”.6 Whilst both the Queensland Act and the New South Wales Act have
similar objects, their provisions are not identical. The Queensland Parliament, despite
amending the Queensland Act in recent years, chose not to follow New South Wales in
enacting such a provision. Also, the New South Wales requirement applies to a “head
contractor”, and so the New South Wales Parliament did not apparently see any advantage
in imposing such a requirement upon an intermediate contractor or sub-contractor in
AWX’s position.
[36] BRB submits that the fact that the New South Wales legislature chose to mandate such
an approach for head contractors is a strong indication that the approach:
(a) is not inimical or contrary to legislation such as the Queensland Act; and
(b) serves a good purpose consistent with the objects of such legislation.
I consider that the New South Wales provision reflects the fact that the New South Wales
Parliament has made a different legislative judgment to that of the Queensland Parliament
about whether such a provision impedes or facilities the objects of the Act in the case of
contracts between a principal and head contractor. The legislative judgment reached by
the New South Wales Parliament in that context should not be taken as reflecting the
legislative judgment taken by the Queensland Parliament in enacting different legislation
and in not amending that legislation so as to adopt a provision similar to the New South
Wales provision, let alone one which would extend to all construction contracts.
[37] The Queensland Parliament may be taken to have made the legislative judgment that such
a provision is unnecessary to achieve the purposes of the Act, or that such a provision is
inconsistent with the purposes of the Act.
[38] The question remains whether the Queensland Parliament has accorded the freedom to
parties to a construction contract to impose such a restriction on the payment of a statutory
progress payment entitlement in circumstances in which the Parliament chose not to
impose such a condition as part of the statutory scheme. For the reasons already given,
and for the reasons which follow, I consider that the Queensland Act does not accord
parties such a freedom in respect of constraints on the payment of statutory progress
payments, as distinct from progress payments to which there is a contractual entitlement.
BRB’s insolvency argument
[39] BRB argues that if a contractor were unable to pay undisputed amounts due to its sub-
contractors, it would be insolvent.7 BRB contends that, as a general rule, it would not
assist the sub-contractors for the principal to pay an insolvency contractor. Rather, the
6 Building and Construction Industry Security of Payment Act 1999 (NSW), s 13(7) and (9).
7 It points to the fact that the statutory declaration addresses a point in time before any progress claim is made.
-- 9 of 18 --
10
sub-contractors’ rights would be best protected by serving on their principal a notice of
charge under the Subcontractors’ Charges Act 1974 (Qld).8 In general terms, s 4 of the
Building and Construction Industry Payments Act 2004 (Qld) permits a contractor to do
so, but not also to start or continue proceedings under part 3 of that Act. In simple terms,
a contractor may give a notice of claim of charge under the Subcontractors’ Charges Act
1974 (Qld) or pursue a payment claim under the Act, but not do both.
[40] The first limb of BRB’s argument is that if a contractor were unable to pay undisputed
amounts due to its sub-contractors, then it would be insolvent. In developing this
argument, BRB puts to one side the scenario of a contractor’s intransigent refusal to pay
undisputed amounts owing to its sub-contractors. Leaving aside the case of a contractor
who chooses not to pay sub-contractors undisputed amounts, BRB contends that if a
contractor is unable to pay sub-contractors, then it must be insolvent. I accept that a party
which has not paid all of its sub-contractors all of the money owed to them on a particular
date may be insolvent. The failure to pay a sub-contractor may be an indication of
insolvency. But it does not necessarily prove insolvency. In the example given above,
Company X may not have the immediate cash resources to pay the sub-contractor, but
may be able to pay the sub-contractor by immediately selling a vital piece of equipment
at a fire sale price. It would avoid insolvency and be able to pay its debt, but its future
would be bleak. This is the kind of situation which the Act seeks to avoid by ensuring
the cash-flow of a contractor who has a statutory entitlement under the Act.
[41] BRB’s argument is that a provision which withholds payment of a statutory progress
payment to a contractor, whose only outstanding debt may be a relatively small amount
due to one sub-contractor, is in the best interests of its sub-contractors. I suspect that
most sub-contractors would disagree and prefer to be paid out of the statutory progress
payment. A provision like cl 14.10 holds up what would otherwise be payment of a
statutory progress payment. This carries the risk of insolvency and the winding-up or
bankruptcy of the contractor, along with others below it in the contractual chain and other
creditors. It may be cold comfort to a sub-contractor in such a situation that the principal
is sitting on what would otherwise have been a substantial payment. Insolvency and
liquidation of the contractor, together with the termination of contracts as a result of an
insolvency event, are likely to mean that whatever money is eventually paid to the
contractor who is then in liquidation will be dissipated on lawyers and liquidators. I am
not persuaded that withholding payment to a contractor who is suffering a temporary
shortage of liquidity and who may be on the brink of insolvency is likely to assist sub-
contractors. Instead, they are more likely to be assisted by a developer or head contractor
paying a contractor a statutory progress payment to which it is entitled in the expectation
that it will then pay its creditors.
[42] I am also not persuaded that the sub-contractors’ rights would be best protected by a
payment not being made to the contractor, with the sub-contractor instead serving a notice
of charge under the 1974 Act. The contractual provision of the kind under consideration
means that a progress payment is not payable. Section 5 of the 1974 Act makes provision
for a charge “on the money payable to the contractor”. The contractual provision of the
kind under scrutiny would be an answer to any claimed charge, namely that there is no
8 Section 4 of the Building and Construction Industry Payments Act 2004 (Qld) contemplates that a contractor
may choose to give a notice of claim of charge under the Subcontractors’ Charges Act 1974 (Qld) in relation
to construction work or related goods and services, subject to that construction contract.
-- 10 of 18 --
11
money payable by the principal to the contractor. Rather than a sub-contractor being
embroiled in arguments about the effect of any notice given by it under the 1974 Act, the
interests of a sub-contractor would appear to be better served by the party with which it
has a contract and which owes it money being paid, leaving the sub-contractor to negotiate
suitable arrangements for payment and to pursue legal proceedings if they are not.
[43] Insofar as the purpose of the Act in ensuring the cash-flow of contractors incidentally
benefits third parties, the interests of those parties would seem to be best assisted by not
giving effect to contractual provisions which purport to allow a principal to withhold
payment of what would otherwise be a progress payment to which the contractor is
entitled under the Act. In the case of a contractor who experiences a temporary loss of
liquidity, and whose solvency may be in doubt, the Act seeks to avoid, if possible, such a
contractor being placed into liquidation, with potentially disastrous consequences for the
contractor, its employees and its creditors.
[44] I acknowledge the risk that a truly insolvent company which receives a progress payment
may not be able to satisfy the debts owed to all of its creditors, including sub-contractors.
The payment made by the principal or head contractor may end up in the hands of certain
creditors, including secured creditors, rather than sub-contractors. However, the risk of
insolvency is a risk which the legislation shifts to the principal.9 The risk that some
creditors, but not certain sub-contractors, will be paid out of a progress payment is a risk
which the legislature chose not to address. It left the regulation of a contractor’s relations
with third parties to other laws.
[45] It is not always obvious that a contractor suffering a temporary lack of liquidity is
insolvent and a sub-contractor may be in a poor position to make an informed judgment
about whether the contractor is in fact insolvent or not. In terms of comparative risk, a
sub-contractor may prefer to take its chances of being paid by a contractor who receives
a progress payment rather than take the chance of ever being paid out of the money which
the principal or head contractor withholds. Ultimately, if some creditors of a contractor
are unfairly paid over some sub-contractors, then laws governing insolvency address that
issue. Secured creditors are likely to be in a position of advantage under either scenario.
[46] If it is appropriate to take account of the interests of third parties, including sub-
contractors, in determining whether a contractual provision of the kind under scrutiny in
this case impedes rather than facilitates the objects of the Act, then the position of sub-
contractors is likely to be advanced by not permitting such a contractual position to
exclude what would otherwise be a statutory entitlement to a progress payment.
Facilitation of a contractor’s cash-flow through the payment of a statutory progress
payment is likely to enhance the prospects of sub-contractors being paid when they most
need it. The alternative of leaving the sum in question in the hands of a principal or head
contractor to await the resolution of claims (by which time the contractor may have been
wound up or made bankrupt) may be of little practical assistance to a sub-contractor.
9 R J Neller Building Pty Ltd v Ainsworth [2009] 1 Qd R 390 at 401 [40].
-- 11 of 18 --
12
The circumstances in which a contractual provision will be ineffective for the
purposes of the Act
[47] Section 99(1) states that the provisions of the Act “have effect despite any provision to
the contrary in any contract, agreement or arrangement”. In addition, s 99(2) provides
that a provision of any contract agreement or arrangement is void to the extent to which
it:
(a) is contrary to the Act; or
(b) purports to annul, exclude, modify, restrict or otherwise change the effect of a
provision of the Act, or would otherwise have the effect of excluding, modifying,
restricting or otherwise changing the effect or a provision of the Act.
[48] Provisions of this kind should be applied according to their terms and no more widely.10
In interpreting and applying the provisions of s 99, it is necessary to pay due regard to the
objects of and policy underlying the Act. That said, the Act does not require the Court to
“strain to find that a provision of a contract offends the Act”.11
[49] I had occasion to consider the operation of s 99 of the Act in Lean Field Developments
Pty Ltd v E & I Global Solutions (Aust) Pty Ltd12 and observed that in assessing the
validity of a condition, a useful inquiry is whether it facilitates or impedes the purpose of
the Act. That observation was not intended to place a gloss upon s 99 or to be a substitute
for the words of the statute. I accept BRB’s submission that a contractual provision could
not be contrary to the Act simply because it does not further the objects of the Act. In
considering whether a provision of a contract is contrary to the provisions of the Act or
otherwise is ineffective by reason of s 99, it is necessary to be specific about how the Act
and its operation are said to be affected by the contractual provision. As I observed in
Lean Field, the extent to which a particular condition is contrary to the Act, or purports
to change the effect of the Act, depends upon its content and practical consequences. A
provision which has the purpose of regulating contractual rights to progress payments
may not be appropriate to condition a statutory right to a progress payment. The condition
is likely to be contrary to the Act or unjustifiably change the effect of the Act’s provisions
“where it does not facilitate a statutory entitlement to progress payments or the resolution
of payment claims made under the Act”.13 This is likely to be the case where the condition
impedes the making of a payment claim with no corresponding benefit in achieving the
Act’s purpose.14
[50] If, absent a contractual provision, a contractor would have a statutory entitlement to make
a claim for a progress payment under the Act, then the provision will have the effect of
excluding, modifying, restricting or otherwise changing the effect of the Act. The
position is otherwise where, even absent the provision, there would be no entitlement
under the Act, for example, because no reference date will have arisen.
10 John Goss Projects v Leighton Contractors (2006) 66 NSWLR 707 at 722 [78], cited with approval in John
Holland at 441 [14] and 443 [23].
11 Ibid.
12 [2014] QSC 293 at [75] – [77] (“Lean Field”).
13 Lean Field at [75].
14 Ibid.
-- 12 of 18 --
13
Is the contractual provision onerous?
[51] AWX contends that the precondition of providing the required statutory declaration is
unduly onerous, and one reason for this is that the relevant statutory declaration must be
given strictly in the terms provided in the form contained in Schedule 3 to the contract.
Unless a statutory declaration is provided in exactly that form, then no statutory payment
claim could be made. As a result, a party in its position would be prevented from making
any statutory payment claim if it delivered a statutory declaration which did not use the
exact words stated in the contract (even if it had paid all of its sub-contractors). It will
also be prevented from making a claim under the construction contract if it owes any
money to its sub-contractors, even a trivial amount to only one sub-contractor.
[52] The clause does not, in its terms, require strict or exact compliance with the required form
and the contract should be given a commercial construction. It is unlikely that the parties
intended that cl 14.10 would not be complied with if there was some trivial non-
compliance, for example, by the accidental omission of an inconsequential word in the
preparation of the required statutory declaration. However, the clause does not expressly
permit only substantial compliance or contain any qualification upon the requirement to
provide a statutory declaration which includes paragraph 5 without any qualification.
Whilst paragraph 8 of the form of statutory declaration permits certain matters in dispute
to be excluded, the effect of the contract is to require a party in AWX’s position to declare
that amounts which are not in dispute have been paid. The declaration in the form
required could not be completed if, for example, to the knowledge of the contractor, a
sub-contractor had not been paid $10 but had been paid the remaining $999,990 that was
payable to it.
[53] An inability to make the required declaration may have draconian consequences.
However, it does not mean that the requirement to complete the form is particularly
onerous. That said, the consequences of making a false declaration are significant and
where a contractor has many sub-contractors, complex arrangements with them and
complicated accounting records, it is possible that a deponent may be reluctant to make a
solemn declaration that, to his or her knowledge, every last cent which is due and payable
to each and every sub-contractor has been paid. The declaration in paragraph 5 starts “To
the best of my knowledge …”. This makes the requirement to give such a declaration
less onerous than one which requires a declaration as to the actual state of matters. In
fact, it could be said that a declaration in this form places a premium upon ignorance and
would encourage a deponent to know as little as possible about the state of payments to
sub-contractors, thereby reducing its utility. However, in circumstances in which the
deponent might be expected to know about the contractor’s state of accounts, I do not
consider that the requirement to complete the statutory declaration is unduly onerous.
The consequences of non-compliance
[54] AWX is on stronger ground in submitting that the consequences of non-compliance are
disproportionate and extreme. For example, one can imagine a situation in which
paragraph 5 of the declaration cannot be completed in an unqualified form because there
is some minor amount owing to a sub-contractor. The principal may have requested that
some minor works be undertaken and a sub-contractor is conveniently engaged to perform
them on or about the date when the necessary statutory declaration must be delivered in
-- 13 of 18 --
14
order to make a payment claim under the construction contract. For some good reason,
the contractor has been unable to pay the amount in question, for example, because the
sub-contractor has left the site and cannot be reached or there is some administrative
reason why the $1,000 payment cannot be processed that day. In such a case, cl 14.10
could not be complied with and there would be a severe consequence. A payment claim
could not be made under the Act and the contractor would be deprived of a statutory
entitlement to make a payment claim for an amount which may be vital to its cash-flow
and the completion of the contract. The principal’s contractual right to withhold what
otherwise would have been a payment to which the contractor was entitled as a matter of
statutory right would have severe consequences for the contractor and its creditors,
including sub-contractors.
[55] Subject to paragraph 8 of the declaration in relation to certain disputed matters, the
relevant contractual provision requires the declaration about the payment of sub-
contractors to be made without qualification, even a qualification which explains that the
unpaid amount is trivial or which provides a compelling or justifiable reason as to why
the amount in question (however small) has not been paid. The practical consequences
of not complying with the condition are severe.
Lack of utility in terms of the Act
[56] This is not a case in which the subject matter of the relevant statutory declaration relates
directly to the proposed payment claim. It does not declare information in relation to the
work undertaken by the contractor and its value. It does not relate to a matter in respect
of which BRB has a liability, since BRB does not have contractual relations with, or
liability to, any of AWX’s sub-contractors. The status of relations between AWX and
one or more of its contractors does not directly bear on BRB’s indebtedness to AWX for
the work AWX has undertaken under the construction contract or the assessment of any
payment claim made under the Act.
[57] A party in BRB’s position may have an interest in receiving information about disputes
that exist between its contractor and sub-contractors, and in ascertaining whether its
contractor has paid sub-contractors all the money that is owed to them. These and similar
legitimate interests in receiving information cannot be equated, however, with
information which has utility in terms of the purposes of the Act. The receipt of a
statutory declaration that contained paragraph 5 in an unqualified form would not be of
any great utility to BRB in processing a payment claim in respect of AWX’s work under
the construction contract.
[58] Any utility which it has in that regard and in thereby facilitating the assessment of a
payment claim made under the Act and the valuation of the statutory right, and any benefit
which such a provision has in terms of encouraging parties in the position of AWX to pay
their sub-contractors if they are able to, are outweighed by the adverse consequences of
non-compliance with the condition to the cash-flow of a contractor who would, absent
the contractual provision, be entitled to a statutory progress payment.
-- 14 of 18 --
15
Clause 14.10 excludes what would otherwise be a statutory entitlement and is
contrary to the Act
[59] Without the inclusion of cl 14.10 in the contract (and assuming compliance with other
preconditions which are not in issue in this case or which would otherwise be ineffective
to prevent a statutory entitlement arising), AWX would have a statutory entitlement to a
progress payment. I accept AWX’s argument that the consequences of non-compliance
with cl 14.10 are severe. Those consequences will be disproportionate in a case in which
the relevant non-compliance is trivial or where there is a reasonable justification for not
being able to give a declaration in the form of paragraph 5 without qualification.
[60] The contractual provision has no real utility in advancing the purposes of the Act. Non-
compliance with the statutory declaration precondition thwarts the payment of a statutory
payment claim which otherwise would be payable on or after the reference date. The
withholding of such a payment affects cash flowing to a contractor and the contractor, in
turn, paying its creditors, including sub-contractors. The contractual provision enables a
party to withhold payment in a case in which a contractor experiences a temporary lack
of liquidity or otherwise has a good reason to not pay a sub-contractor.15 Depriving such
a contractor of the cash-flow required to carry on its business and complete the
construction contract is inconsistent with the objectives of the Act.
[61] The condition impedes rather than facilitates the purpose of the Act. It has little, if any,
practical utility in facilitating the payment of a statutory entitlement. Its practical
operation is to impede the payment of a statutory entitlement without any corresponding
benefit. Any utility which the condition has in terms of facilitating payment of a statutory
entitlement and advancing the objectives of the Act is outweighed by its effect in
excluding what would otherwise be an entitlement to a progress payment and thereby
ensuring cash-flow to the contractor.
[62] For the purpose of the present application, I proceed on the assumption that other
preconditions for the making of the relevant pay claim were satisfied or that any other
conditions were unenforceable for the purposes of the Act. On that assumption, the
inclusion of cl 14.10 in the contract had the effect of excluding, modifying, restricting or
otherwise changing the effect of the Act which, absent cl 14.10, would have conferred an
entitlement to a progress payment under the Act on the reference date that was stated or
worked out under the contract. Because cl 14.10 has this effect, it is void to the extent to
which it affects rights and liabilities under the Act. It may be effective in terms of
contractual entitlements as between the parties, but it is ineffective to deprive AWX of
what would have been a statutory entitlement to payment in the absence of cl 14.10. For
these reasons, the provision is contrary to the Act. The provisions of the Act which have
the effect of conferring a statutory entitlement to a progress payment have effect, despite
this provision.
15 For example, for fear that to do so would constitute a preferential payment over other creditors.
-- 15 of 18 --
16
AWX’s alternative argument
[63] BRB’s case before the adjudicator which relied upon non-compliance with cl 14.10 was
framed in terms of there being no available reference date. The thrust of the argument is
to the effect that provision of a compliant declaration in terms of cl 14.10 was one of the
matters which permitted a reference date to be worked out and until there was compliance
with, amongst other things, cl 14.10, a reference date did not arise on the 28th of each
month. I regard it as somewhat artificial to frame the issue as BRB did before the
adjudicator as involving a reference date issue. The matter might be better framed as one
involving the effectiveness, for the purposes of the Act, of a contractual precondition to
the making of a claim for a progress payment on the date stated in the contract. However,
this was the manner in which the argument was framed and I conclude that the adjudicator
was correct to find that the effect of the provision was to impede what would otherwise
be a statutory entitlement without providing any corresponding benefit in the context of
the Act.
[64] AWX advances an alternative argument, namely that this is not a case in which the
reference date fell to be “worked out”. There was a date stated in the contract for the
making of payment claims, namely the 28th of each month, and, properly construed, the
conditions in cl 14.1(b) and cl 14.10 did not affect the date nominated for making of a
progress claim. Rather, they were directed to the validity of any payment claim. On this
argument, there simply was a reference date stated in the contract and one does not have
to have regard to cl 14.1(b) and cl 14.10 in order to work it out. The competing argument
is that, adopting a broad view of the meaning of “worked out”, the reference date is
worked out according to the fulfilment of the various conditions. It is unnecessary for me
to resolve this contest. If AWX is correct in its alternative argument, then the same
substantial issue arises in a different context. Rather than the issue being framed in terms
of a reference date, the issue is whether the payment claim which was made was a valid
one or not for the purposes of the Act because of non-compliance with the provisions of
cl 14.10.
[65] The same issues which I have canvassed about the content and effect of the contractual
provision arise in this context. The result is the same. The contractual provision is
ineffective to prevent AWX from making a payment claim for a progress payment to
which it is entitled as a matter of statutory right.
[66] The result which I have reached is the same as that reached in State of Queensland v T &
M Buckley Pty Ltd,16 which involved broadly similar provisions. In that case the making
of a payment claim was subject to the prior receipt by the superintendent of certain
information required by a clause in the contract. Justice Margaret Wilson concluded that
the right to deliver a contractual claim on the date stated in the contract was conditional
upon the prior delivery of the statutory declaration. The condition affected the right to
deliver the contractual claim, but not the date on which it may be delivered once there is
an entitlement to do so. The accrual of the stated reference date was not conditional upon
the prior delivery of the statutory declaration. The conclusion that the entitlement to make
a claim under the Act was not affected by the requirement to deliver the statutory
declaration derived support from authorities such as John Holland. Her Honour found it
16 [2012] QSC 265.
-- 16 of 18 --
17
unnecessary to decide whether the precondition was void under s 99, considering that the
matter did not arise.
[67] The result in T & M Buckley is consistent with other authorities which are to the effect
that contractual preconditions on the entitlement to make a payment claim under a
construction contract, or the liability to make payment under a contract, do not constrain
the right to claim for payment under the Act.17 Whilst T & M Buckley does not rest that
conclusion on s 99, I consider that s 99 of the Act operates to render such contractual
preconditions ineffective for the purposes of the Act. While such provisions may be
effective for the purpose of a contractual entitlement, they are ineffective to exclude what
would otherwise be a statutory entitlement to a progress payment.
Other matters
[68] It is unnecessary to address another matter raised by AWX’s submissions to the effect
that the statutory declaration met the requirements of cl 14.10.
Conclusion
[69] The adjudicator had jurisdiction to determine AWX’s payment claim. BRB’s argument
about jurisdictional error, namely that no reference date for the making of a payment
claim under the Act had arisen because of non-compliance with cl 14.10, has not been
established. The contractual precondition relied upon by BRB to deny AWX a progress
payment under the Act was ineffective to prevent AWX from making its payment claim
dated 28 January 2015 and to rely upon the reference date stated or worked out in the
contract.
[70] The contractual provision has no real utility in advancing the purpose of the Act. Its
content and practical operation has the effect of depriving a contractor in AWX’s position
of a progress payment to which it would be entitled in the absence of that contractual
provision. Such a contractual provision has the effect of excluding, modifying, restricting
or otherwise changing the beneficial effect of the Act in conferring a statutory entitlement
to a progress payment upon a contractor. By depriving a contractor of such a progress
payment, the contractor (and, in turn, its creditors including sub-contractors) is deprived
of an important cash-flow.
[71] The purpose of the Act is to ensure cash-flow to a party which qualifies for a statutory
entitlement. The limited contractual freedom which the Act confers upon parties to agree
certain matters, including the working out of a reference date under the contract, does not
extend to the imposition of a contractual provision of the kind under consideration. Such
a condition purports to exclude what would otherwise be a statutory entitlement to a
progress payment. The practical operation of such a provision prevents cash flowing to
a contractor. Rather than having utility in facilitating the making, processing and
determination of claims made under the Act, the contractual provision impedes the
17 BHW Solutions Pty Ltd v Altitude Constructions Pty Ltd [2012] QSC 214; De Neefe Signs Pty Ltd v Build1
(Qld) Pty Ltd; Traffic Technologies Traffic Hire Pty Ltd v Build1 (Qld) Pty Ltd [2010] QSC 279; John Holland;
McConnell Dowell Constructors (Aust) Pty Ltd v Heavy Plant Leasing Pty Ltd [2013] QSC 269.
-- 17 of 18 --
18
objects of the Act. It is inconsistent with the purpose of the Act of ensuring cash-flow to
such a contractor.
[72] Any benefits such a clause may have in encouraging a contractor to pay sub-contractors
if it is able to do so before making a payment claim are outweighed by its draconian
consequences in depriving a contractor (and, in turn, the contractor’s creditors including
sub-contractors) of essential cash-flow.
[73] Encouraging a contractor to pay its sub-contractors, if it is able to do so, before itself
making a payment claim, is desirable. But contractors who experience a temporary
shortage of liquidity may be unable to pay their sub-contractors. The Act is intended to
assist them to do so by providing a cash-flow from developers and head contractors for
whom they have done work. A contractual provision which has the effect of stopping
that cash-flow pursuant to what otherwise would be a statutory right, is contrary to the
Act’s purpose. Whatever benefit such a provision has in the case of contractors who are
able to pay their sub-contractors is outweighed by the consequences for contractors who
are not able to do so. Depriving contractors of the cash-flow which the Act is intended
to ensure harms contractors. It has incidental consequences for sub-contractors, other
creditors and workers in the construction industry. To the extent the interests of those
third parties should be taken into account in a case such as this, their interests are better
served, in general, by the contractor being paid a progress payment, than by essential
cash-flow being blocked.
Orders
[74] The orders will be:
1. The application be dismissed.
2. The Registrar pay by cheque payable to the first respondent, AWX Constructions
Pty Ltd, from the amount paid into the Court Suitors Fund by the applicant pursuant
to an order made 22 July 2015:
a. the sum of $3,935,707.39; and
b. interest calculated at the daily rate of $833.95 from 24 July 2105 to the date
on which the first respondent has received the money referred to in order
2(a) above.
3. The Registrar pay by cheque payable to the applicant, BRB Modular Pty Ltd, the
balance of the amount paid into the Court Suitors Fund by the applicant pursuant to
an order made 22 July 2015, together with any accretions due.
4. The applicant pay the first respondent’s costs of and incidental to the application on
a standard basis, excluding the costs of and incidental to the interlocutory hearing on
22 July 2015 which remain reserved.
[75] I will hear the parties on the issue of the costs which were reserved by Bond J on 22 July
2015.
-- 18 of 18 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2015/218