Coleman v Prentice & Anor [2015] QSC 118
SUPREME COURT OF QUEENSLAND
CITATION: Coleman v Prentice & Anor [2015] QSC 118
PARTIES: JOHN W COLEMAN AND
DIANNE L COLEMAN
(Plaintiffs)
v
PETER PRENTICE
(First Defendant)
and
AGRIPOWER AUSTRALIA LIMITED
(ACN 132 823 226)
(Second Defendant)
FILE NO/S: SC 189 of 2010
DIVISION: Trial
PROCEEDING: Trial
ORIGINATING
COURT: Supreme Court at Cairns
DELIVERED ON: 5 May 2015
DELIVERED AT: Cairns
HEARING DATE: 17-18 November 2014 and 19-22 January 2015
JUDGE: Henry J
ORDERS: 1. Judgment for the plaintiff against the second defendant in
the amount of $265,531 and interest thereon to be
determined.
2. The counterclaim and the claim as against the first
defendant are dismissed.
3. I will hear the parties as to the quantification of interest
and as to costs.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
RECOVERY – where the plaintiff seeks recovery of unpaid
invoices – where the plaintiff claims agreement was for
payment of hours worked with payment terms of 7 days from
invoice – where the defendants claim payment was subject to
reconciliation of mined product – where the plaintiff claims
unclaimed rent on leased storage facility – where the
defendants deny entering lease for storage – where the
plaintiff exercised a lien over stored product for unpaid
-- 1 of 55 --
2
monies
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – CONSTRUCTION OF
PARTICULAR CONTRACTS AND IMPLIED
CONDITIONS – DISCHARGE OF CONTRACT ON
DEFAULT AND LIKE GROUNDS – where the plaintiff
terminated the contract on account of unpaid invoices –
where the defendant claims termination was unlawful –
where the defendant counterclaims an amount for damages
for loss of profit on mined product – whether the plaintiff was
liable for any loss on account of unsaleable mined product –
whether the plaintiff is liable for unaccounted for mined
product
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – PERFORMANCE OF WORK –
GENERAL – where the parties made an oral contract to
perform road and mining works – where the plaintiff worked
under the direction and supervision of a representative of the
second defendant – where the defendant claims for damages
for loss of profit caused by the plaintiff’s work
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – PARTIES – GENERALLY – where the first
defendant was the director of the second defendant – whether
the contract for works was made with the first defendant or
second defendant
Mining and Quarrying and Safety and Health Act 1999 (Qld)
s 23
Australian Energy Ltd v Lennard Oil NL [1986], cited
Winks v WH Heck & Sons Pty Ltd [1986] 1 Qd R 226, 238,
cited
Roluke Pty Ltd & Anor v Lamaro Consultants Pty Ltd & Anor
[2008] NSWCA 323, considered
COUNSEL: Dr MA Jonsson, with S Williams for the Plaintiffs
PJ Favell for the First and Second Defendants
SOLICITORS: Williams Graham Carman Solicitors for the Plaintiffs
TressCox Lawyers for the First and Second Defendants
-- 2 of 55 --
3
Index
Heading Page
A. Introduction 4
B. The dispute in summary 4
C. The issues 7
D. The facts 7
Mr Prentice and Agripower 7
The intended operation 8
Discussion/Contact pre first meeting 10
The first meeting 11
Was the agreement with Agripower or Mr Prentice as an
individual? 13
Initial laying of the road 14
Costs of road works 14
Records of work performed 15
The test dig 16
The broadening of the task to mining work 17
The role of Ivar Storronning 18
Mr Storroning’s diaries and presence on site 19
Payment arrangements for mining work subject to an end
reconciliation? 20
Top soil stripping and road re-sheeting 23
Progress of mining work 23
Arrangements for screening 24
Screening activity 26
Bagging arrangements 29
Mixing and bagging activity 29
Screening and bagging by Agripower personnel 31
Acknowledgment of managerial failure 32
Storage 34
Invoices 39
Reasonableness of rates 41
Slow down in payments 42
Non-payment of invoices 42
The end of the business relationship 43
-- 3 of 55 --
4
The retention of product at Uramo 46
Condition of the product at Uramo 47
Presence of oversize granules in processed product 48
Survey 49
E. Did Coleman Contracting terminate unlawfully 50
F. Does the unaccounted for mined earth evidence a
breach by Coleman Contracting? 51
G. Is Coleman Contracting responsible for loss
occasioned by the unsaleable quality of the bagged product? 52
H. Is Agripower liable to pay the whole of invoices 9 and 10? 53
I. What if any amount should Agripower pay for storage at Uramo? 54
J. Conclusion 55
K. Orders 55
A. Introduction
[1] Diatomaceous earth is a sedimentary rock consisting of the fossilised remains of
diatoms, a type of phytoplankton. Its potential commercial uses make it a profitable
product, but only if its mining and processing are managed properly.
[2] A large deposit of diatomaceous earth was identified on Wyandotte Station north of
Greenvale in North Queensland. Testing suggested it had potentially significant
commercial value as a fertiliser and soil conditioner because of its high levels of
plant available silica and the natural capacity of diatomaceous earth to absorb and
retain moisture.
[3] The second defendant, Agripower Australia Ltd (“Agripower”), secured a mining
lease over the deposit. It now mines the deposit successfully. However the
commencement of its mining operation in 2009 was an era of early learning,
involving a degree of trial and error.
[4] The genesis of the commercial dispute with which this case is concerned lies in how
the early stages of the mining operation were managed by Agripower, its managing
director the first defendant Mr Peter Prentice and its site supervisor Mr Ivar
Storronning. At trial the defendants attempted to attribute blame for the
consequences of that management upon the contracting business engaged to perform
work for them and so avoid responsibility for paying the outstanding invoices of that
business.
B. The dispute in summary
[5] To mine the deposit of diatomaceous earth at Wyandotte Station, Agripower needed
to build an access road via neighbouring Gilldale Station.
-- 4 of 55 --
5
[6] The proprietor of Gilldale Station, Henry Daniels, now deceased,1 put Mr Prentice in
touch with Coleman Contracting, a local machinery contracting business that had
previously done road building work for Mr Daniels.2 The partnership proprietors of
that business were the plaintiffs, John Coleman and his wife Dianne (“Coleman
Contracting”).
[7] It was agreed between Mr Coleman for Coleman Contracting and Mr Prentice for
Agripower that Coleman Contracting would build the road. That work commenced
on 1 August 2009.
[8] Mr Prentice and Mr Coleman subsequently broadened the oral contract, agreeing to
Coleman Contracting performing more works for Agripower, including stripping
some of the deposit’s topsoil, extracting ore, screening ore, mixing and bagging ore
and even storing some of the bagged product at a shed at the Coleman’s station at
Uramo. The works were performed under the supervision of Agripower’s site
supervisor Mr Storronning and, to a less frequent extent, Mr Prentice.
[9] This initial extraction and processing of the product in the latter months of 2009
appears to have been a small operation. It was similar to the scale of a pilot project
and much could be learnt from it before further operations were to be undertaken in
the New Year after the wet. It also provided Agripower with some bagged product
for testing in the agriculture marketplace.
[10] Despite the embryonic scale of the project the work involved was costly. Coleman
Contracting invoiced in accordance with hours worked, recorded in day dockets,
verified by the signature of Mr Storronning.
[11] It had been agreed that invoices would be paid within seven days. At first, during
August and September of 2009, Coleman Contracting was promptly paid for the
work it performed. However the speed with which Agripower paid Coleman
Contracting’s invoices slowed in late September of 2009 and it took much longer to
pay the Coleman’s invoices throughout October of 2009.
[12] The last of Agripower’s payments to Coleman Contracting was made on 10
November 2009. That involved payment of the remainder of Coleman Contracting’s
invoice 7 and the whole of Coleman Contracting’s invoice 8. Invoices issued by
Coleman Contracting after that time went unpaid.
[13] Invoice 9, issued on 10 November 2009, remained unpaid, allegedly in breach of the
contract. Consequently, on 1 December 2009, Coleman Contracting withdrew its
services. The defendants allege this constituted a wrongful termination of the
contract. Coleman Contracting thereafter issued invoices 10 and 11.
[14] Invoice 10, like invoice 9, was for the screening and bagging of product and its
transportation to the Coleman’s Uramo shed. Invoices 9 and 10 involve a combined
total of $238,031.00. They are said to be payable under the contract or as services
provided at reasonable rates on request.
[15] The defendants deny liability in respect of invoices 9 and 10, principally on the basis
that having regard to the amount of earth which was actually extracted and
1 T3-50 L28.
2 T3-41 L22.
-- 5 of 55 --
6
processed they were overcharged and had overpaid for the total services provided.
Mr Prentice alleges and Mr Coleman denies they agreed that on the completion of
works there would be a reconciliation of the volume of product mined as against
invoices rendered, in consequence of which, in the event of a shortfall in volume,
Coleman Contracting would have to refund money it had been paid in respect of
invoices rendered for work performed. The defendants allege such a shortfall.
[16] Invoice 11 was for three months advance payment on storage at the Coleman’s
Uramo shed from November 2015 in the amount of $27,500.00. It is said to be
payable pursuant to an agreement to lease or as compensation for use and occupation
of the shed. The defendants deny there was any such agreement and, even if there
was, allege it was breached because the storage afforded inadequate protection of the
bags.
[17] Mr Prentice sought to remove the bags of diatomaceous earth stored at the
Coleman’s Uramo shed but was prevented from doing so by Coleman Contracting,
which purported to exercise a lien over the goods pending payment.
[18] On 13 April 2010 Mr and Mrs Coleman filed the present claim, claiming
$293,031.00 comprised of the unpaid invoices 9, 10 and 11 and an additional
$27,500.00 storage charge for a second quarter commencing from 1 February 2010.
[19] The defendants counterclaimed on 11 June 2010 seeking damages, the breadth and
quantum of which increased in subsequent amendments to the counterclaim. The
total counterclaimed is more than $3M and far exceeds the quantum of any set off
against the plaintiff’s claim if successful.
[20] A significant component of the defendants’ loss of profits claim is an allegation that
the product screened by the plaintiffs was rendered unsalable because its granular
sizes were not consistent within the saleable range for fertiliser of two to six
millimetres. The defendants claim they consequently lost profits in the order of
$1.5M. They attribute blame for that outcome on the plaintiffs, notwithstanding
Agripower’s oversight of the process.
[21] The defendants’ loss of profits claim also alleges stockpiled diatomaceous earth,
which was not processed or bagged prior to the withdrawal of Coleman Contracting
services, became adversely affected by the weather and thus unusable and
unsaleable.
[22] A further component of the defendants’ claimed loss relates to a quantity of
diatomaceous earth that was allegedly mined by Coleman Contracting but remains
unaccounted for. This is said to have given rise to a further significant loss of
profits.
[23] As to the amounts claimed by the plaintiff for storage at the Uramo shed the
defendants deny there was any lease concluded. Moreover they purport to set off
any liability for storage costs against their loss of profits in respect of the stored bags
on the basis the bags were rendered unsaleable because the plaintiffs allegedly
stored them in such a way as to expose them to weather and vermin.
[24] The defendants counterclaim also pleaded deficiencies and the need for rectification
in respect of the road works but that was not pursued at trial.
-- 6 of 55 --
7
C. The issues
[25] The outcome of this case depends heavily upon fact finding.
[26] The issues for determination are not readily compartmentalised. They are inter-
related and turn to a large extent upon an analysis of the facts of what actually
transpired before, during and after the performance of the works by Coleman
Contracting. That analysis will culminate in five key questions for determination:
(i) Did Coleman Contracting terminate unlawfully?
(ii) Does the unaccounted for mined earth evidence a breach by
Coleman Contracting?
(iii) Is Coleman Contracting responsible for loss occasioned by
the unsaleable quality of the bagged product?
(iv) Is Agripower liable to pay the whole of invoices 9 and 10?
(v) What, if any, amount should Agripower pay for storage at
Uramo?
[27] In turning to the factual analysis it is helpful to flag two factual features of some
significance in considering what occurred between the parties.
[28] Firstly, there is Mr Prentice’s assertion that Mr Coleman agreed to work and be paid
subject to an end reconciliation of the volume of product mined as against invoices
rendered, leaving Coleman Contracting potentially liable to repay Agripower
money. It is a surprising and significant qualification to what otherwise appears to
have been a straightforward system of progressively invoicing for hours of work
performed and verified by Agripower’s site supervisor.
[29] Secondly, there is Mr Prentice’s distancing of Agripower from the extent and
consequences of it having directed and supervised the work of Coleman Contracting.
This bears upon Coleman Contracting’s liability for some of the problems
complained of in the counterclaim, particularly the problem with the granular size of
the screened and bagged product. This second factual issue also informs the
plausibility or otherwise of Mr Prentice’s evidence as to the first.
[30] As will become apparent, I did not find the evidence of Agripower’s Mr Prentice on
these matters to be reliable.
[31] My abiding impression of the evidence generally is that Mr Prentice shaped his
evidence to divert blame for the problems arising out of this embryonic mining
operation away from their obvious cause – the way in which the operation was
managed by Agripower.
D. The Facts
Mr Prentice and Agripower
[32] Mr Prentice has qualifications in mathematics, mining engineering and mineral bio-
availability.3 He has worked over many years in the mining industry as an operator
and as a mining engineer as well as designing and building mining projects.4 When
asked if he had ever mined diatomaceous earth commercially before the Wynadotte
3 T4-18 L40.
4 T4-18 L16.
-- 7 of 55 --
8
operation he responded that he had some experience in about 1984 in consulting for
about 18 months in respect of an operation in Nevada which mined and processed
diatomaceous earth for filtration purposes. That was obviously a different role than
he assumed in the present matter, establishing a mining operation from scratch.
[33] Mr Prentice was founding director of Agripower when it incorporated in 2008.5
Agripower was incorporated in consequence of a restructure of arrangements
between investors looking to advance a diatomaceous earth project.6 They had been
involved in exploring tenement holdings north of Greenvale since 2000.7 It appears
some of them also had an involvement with an earlier diatomaceous earth mining
venture at Barraba in New South Wales.8
The intended operation
[34] Mr Prentice wanted to build a road to the deposit of diatomaceous earth on
Wyandotte Station and initiate some mining of the deposit, about 15 to 20,000
tonnes,9 prior to the coming of the wet in the summer of 2009/2010. The product
mined was intended for distribution10 to test the market place.
[35] According to Mr Prentice the decision to commence operations in 2009 was on the
strength of a supply arrangement it was entering into with an entity known as Hortus
to sell Agripower’s product as fertilizer.11 Hortus is an agricultural group that offers
technical services to farmers as well as distributing fertilizers. Because most
fertilizer spreading equipment is configured to spread a product two to six
millimetres in granular size, Mr Prentice explained Hortus wanted Agripower to
produce diatomaceous earth sized within the two to six millimetre range and bag it
into bulk bags of approximately one cubic metre for Hortus to sell to clients.12
[36] When challenged, Mr Prentice could produce no documentary evidence of any
agreement having been formalised with Hortus as at 2009.13 In fact a distribution
agreement does not appear to have been entered into until about a year later when,
on 19 October 2010, Agripower entered into a distribution rights agreement with
Nutrifert Pty Ltd, the marketing arm of Hortus.14 Mr Austin Smith, managing
director of Nutrifert, testified that there had been earlier agreements with another
entity in connection with the venture at Barraba15 but that an agreement with
Agripower was not concluded until 2010.16
[37] When the 2009 operation was being planned it was actually intended that the
product would be distributed to a Far North Queensland entity known as Miriwinni
Lime. That fact was exposed in cross-examination when a plan of operations for the
5 T4-18 L8.
6 T4-18 L47.
7 T4-19 L5.
8 T6-29 L13.
9 T4-52 L1.
10 T4-52 L3.
11 T4-19 L12.
12 T4-19 L33, T4-51 L42.
13 T5-10 L44 – T5-11 L4.
14 T4-52 L12, Ex 30.
15 T6-29 L9.
16 T6-28 L42.
-- 8 of 55 --
9
intended operation was put to Mr Prentice. While that plan17 named a company
other than Agripower as the relevant holder of the environmental authority for the
operation, albeit a company of which Mr Prentice was also a director, Mr Prentice
agreed it was the plan for the intended operation and that he would have given a
copy of it to Mr Storronning. The plan, endorsed July 2009, said of the operation:
“As this is for testing purposes a limited quantity of DE will be
mined, in the order of 23,000 cubic metres. The mined DE will then
be carted by truck to the Miriwinni Lime operations at Mt Garnet
from where it will be transported and then spread by Miriwinni Lime
to parties trialling the DE in and around the Far North Queensland
area, this will be done in the same way that Miriwinni lime transport
and spread their lime to customers. …
Due to the simplicity of the equipment requirements and the mining
methods used, the operation will be put out to contractors under the
supervision of mine staff. Mining will be carried out on a single shift
basis. …
Stripping of topsoil will commence in the open pit area within the
first few days. In total some 23,000 cubic metres of DE and 2,000
cubic metres of topsoil will be removed during the six weeks mining
and rehabilitation period.”18
[38] The arrangement planned with Miriwinni Lime fell through and, as Mr Prentice put
it, “that’s why we decided to then screen the product ourselves at site”.19 By the
latter months of 2009 it appears Agripower was planning to supply its processed
product to Hortus, albeit without a concluded agreement, obviously hopeful of
testing and developing market demand.
[39] The initial operation was to be on a small scale. As Mr Prentice explained:
“[T]he mining operation we were talking about then was only to
extract a small quantity—sub—twenty thousand cubic metres of
diatomaceous earth—so … it was a very small operation that would
be completed within weeks so it wasn’t a … huge operation that you
would typically go and find a major contractor that’s worked on the
coal fields, for example, and, you know, come up with lots of
equipment. You only wanted a small—a smallish type but
experienced operator.”20
[40] As the events that followed demonstrate, the intended operation was not one in
which managerial responsibility for the efficacy of the mining and processing of the
product was to be delegated to a specialist mining operator. Rather, as the plan of
operations suggests, Agripower intended to manage the mining and processing of
the product itself, with its own mine staff supervising the work of contractors.
17 Ex 3 p 378.
18 Ex 3 pp383, 385.
19 T5-10 L36.
20 T4- 23 L15.
-- 9 of 55 --
10
Discussion/Contact pre first meeting
[41] Mr Prentice testified he asked Henry Daniels, the proprietor of Gilldale Station,
whether he would recommend any local contractor for “putting in the access road
and even possibly carrying out the mining operation”.21 Mr Daniels told him Mr
Coleman’s machinery contracting business had done road works on Mr Daniels’
property after heavy rains had harmed his roads and explained he was “very
comfortable with what Coleman had done”.22 Mr Prentice testified he asked Mr
Daniels to convey Mr Prentice’s contact details to Mr Coleman.23
[42] John Coleman testified that Henry Daniels rang him one night asking if he would be
keen to put in an access road for a fertilizer mine that was going to be opened up.
Mr Coleman said he was interested.24 He thereafter placed a telephone call to Mr
Prentice in which they agreed to an on-site meeting.25
[43] According to Mr Prentice, Mr Coleman said at the outset of that telephone
conversation that he was aware from Henry Daniels they were “looking for a
contractor to do some road works and some mining”.26 That likely overstates what
Mr Coleman had been told, at least in the sense it suggests Agripower was
necessarily seeking the same contractor to do both the road works and the mining
work. At this stage it is obvious that, at the highest, Mr Prentice wanted a local
contractor to perform the road work and merely had in mind the possibility, because
of the small scale and simplicity of the looming mining operation, that such a
contractor might be able to work on the subsequent mining operation.
[44] In cross-examination Mr Coleman was pressed to acknowledge that he had told Mr
Prentice in their initial telephone conversation he was “very conversant with mining
operations”. Mr Coleman’s response, “I told him what we had been doing, yes”,
was not in tone or substance an acknowledgement that he had told Mr Prentice he
was very conversant with mining operations. Rather it was an acknowledgement he
had informed Mr Prentice of the nature of the work his business had recently done
for Kagara Zinc, a large mining operation.27 The reality is that Coleman Contracting
had performed earth works for an array of variety of entities and was not a specialist
mining operator.
[45] In initially giving his account of what was said during the telephone conversation,
and also what was later said at the first meeting on site, Mr Prentice did not allege
that Mr Coleman had claimed to be very conversant with mining operations.28
However when he was specifically asked whether Mr Coleman had mentioned any
experience in mining at the site meeting Mr Prentice responded:
“He mentioned to me both in the phone call we had—he said to me
he’d been working at Kagara Zinc for some time and had recently—
that assignment or contract had come to an end. But he’d had many
21 T4-23 L13.
22 T4-23 L20.
23 T4-23 L24.
24 T3-4 LL32-38.
25 T3-42 L43, T3-42 L28.
26 T4-23 L26.
27 T3-41 L29, T3-42 L37.
28 T4-23 LL25-35.
-- 10 of 55 --
11
years of mining, extracting, quarrying, with his plant and
equipment.”29
At an even later stage of his evidence Mr Prentice claimed that Mr Coleman
“represented himself to be a very experienced mining contractor”.30 This was an
exaggeration of what Mr Coleman had told him.
[46] I accept Mr Coleman would have mentioned that his business had on occasion
performed work for mines, for example Kagara Zinc. However even allowing for
Mr Coleman being keen to secure work for his business, I do not accept that he
claimed he or his business had particular expertise in conducting mining operations
as distinct from occasionally providing earthmoving services to mining operations.
[47] This distinction is important. It is fanciful to imply as the defence case effectively
did that Mr Prentice had been led to believe by Mr Coleman that the experience of
Coleman Contracting in mining was such that it could be left to conduct the mining
operation rather than merely performing work under Agripower’s direction and
supervision.
[48] The probability is Mr Prentice did not think it essential to secure a contractor with
significant mining expertise because the task of extracting, moving and processing
the earth on a small scale could be done under the direction and supervision of
persons from Agripower, vis Mr Prentice and Mr Storronning, who purportedly had
mining expertise.31
The first meeting
[49] There followed a meeting at Gilldale Station around the end of July 2009.32
[50] John Coleman testified the persons present at the meeting were him, his friend Mike
Donald, Henry Daniels, Peter Prentice, Ivan Storronning and a geologist called
Mike.33
[51] John Coleman described meeting at the front gate of Gilldale Station.34 On his
account they all then drove past the Gilldale homestead to where the road was to
cross into Wyandotte Station35 and then they went back to the Gilldale grid.36 On
Mr Prentice’s account they travelled more extensively onto Wyandotte Station
looking at deposits of diatomaceous earth in creek banks37 and to the area of the
mining lease.38
[52] Mr Coleman recalled there was some ribbon and a couple of pegs near the
Wyandotte boundary which he noticed during the drive.39 Mr Prentice testified that
29 T4-30 L13.
30 T5-5 L41.
31 T1-68 L43.
32 T3-5 L5.
33 T3-4 L43—T3-5 L2.
34 T3-4 L41.
35 T3-5 L40, T3-6 L15.
36 T3-6 L18.
37 T4-24 L38.
38 T4-28 L9.
39 T3-49 L35.
-- 11 of 55 --
12
earlier in the year he and the geologist, Michael Leu, had used strands of coloured
tape and pegs on the ground or on trees to mark four or five different routes that
might suit for the road to be laid within the constraints of the mining lease access
road area.40
[53] On John Coleman’s account of what was said at the first meeting, Peter Prentice
asked if Mr Coleman would be interested in putting an access track to the mine
because there was no road to there. The area was part of a lava tube overflow.41
Peter Prentice said the mine was 12.5 kilometres south on Wyandotte Station. They
went for a drive and Peter Prentice and Henry Daniels showed where the road
should go, including where it would traverse fence lines.42 Mr Coleman told Mr
Prentice what type of material was needed to do the job, telling him the road was
very rocky and it would be difficult to foresee what problems that would give rise to
once work was underway.43
[54] On Mr Prentice’s account the conversation included discussion to some extent of Mr
Prentice’s intended mining methodology of removing top soil and then ripping out
and excavating the diatomaceous earth.44 I accept Mr Coleman’s evidence that the
potential performance of mining work by his business was not discussed at this
meeting.45 Even on Mr Prentice’s account the only engagement of Mr Coleman
discussed at that stage was for the installation of the access road:
“I said to John, look, I want to keep this very simple. It’s—we’re
talking here of a few weeks work to put the road in; let’s not over
complicate it. If you can give me a quote for putting the road in,
that’s great, but I do know, you know, the boulders are variables.”46
[55] In advance of the meeting Dianne Coleman had written prices for hourly work by
different categories of machine work on a sheet of paper, which John Coleman took
to the meeting.47 Copies of that document, with different additional notations,
obviously added by the respective parties, became exhibits eight and 25 in the trial.48
[56] Mr Coleman testified that he spoke to Mr Prentice about the content of the prices
sheet he had in his possession,49 telling him, “That’s what we charge” and that they
would charge an hourly rate.50 In contrast Mr Prentice testified the contents of the
price sheet were not discussed.51 I did not believe him. Mr Prentice acknowledged
he was handed a copy of the prices sheet.52 The exhibit 8 version of that document
was acknowledged by Mr Prentice to appear to have some handwriting of his on it,
referring to a rate of 1.5 to 3 kilometres per day.53 Mr Prentice obviously gave
consideration to the prices in the sheet. For instance Mr Storronning testified that he
40 T4-22 L42-T4-23 L5.
41 T3-5 L34.
42 T3-5 L45.
43 T3-6 L23.
44 T4-28 LL9-30.
45 T3-49 L26.
46 T4-28 L25.
47 T3-6 L30.
48 T3-6 L43, T3-46 L44, T3-48 L35.
49 Ex 8.
50 T3-7 LL5-8.
51 T4-28 L35.
52 T4-31 L44.
53 T4-32 L10.
-- 12 of 55 --
13
was handed Mr Coleman’s pricing sheet after the meeting by Mr Prentice who asked
him whether the prices were reasonable and Mr Storronning told him they were.54
[57] On Mr Prentice’s account he told Mr Coleman that they preferred a fixed price and
Mr Coleman indicated that he would get back to Mr Prentice.55 I accept Mr Prentice
may have asked for an estimate of the overall price and that Mr Coleman may have
agreed to provide it, but believe Mr Coleman’s evidence that Mr Prentice did agree
to pay the hourly rates quoted by him.
[58] Mr Coleman testified that he asked about timing of payment to put in the access
track and Mr Prentice said it would be payment every seven days, which Mr
Coleman said would be fine.56 Mr Prentice’s recollection was that the topic of
payment within seven days was actually discussed and agreed to in a subsequent
phone call with Mr Coleman but on any view he agreed to such a payment scheme:
“John flagged with me at that point payment terms, and we discussed
payment terms. And I said look, normally you do the work and at
the end of the month you’d send us a bill and we’ll pay it promptly.
John sort of—you know, it’s hard to sort of guess but in the phone
calls seemed to err and ahh a bit and I remember this because he
said, look, I’d like to get paid a lot quicker. We’ve just finished a
contract at Kagara. I’ve got to gear up for this. I’ve got to get all—
everything in for it to set it up and the men. Can’t we get paid a lot
quicker than that? And I said, well, look—I think I said something
along the lines of, well, we could pay a lot quicker—you know,
every 14 days. And John was still umming and aahing on the phone
and I think I then said, look, ok, we’ll pay every seven days. If you
give us the detailed invoice we’ll pay every seven days.”57 (emphasis
added)
Was the agreement with Agripower or Mr Prentice as an individual?
[59] It is clear that throughout his dealings with Coleman Contracting Mr Prentice acted
in his capacity as a director of Agripower. Mr Prentice testified that he told Mr
Coleman from the outset that he was a director of Agripower.58
[60] Further, throughout the ensuing period in which Mr Coleman’s business performed
the work sought by Mr Prentice it issued invoices nominating the “customer” in
each instance as “Agripower”. Each invoice was addressed to suite 2, level 10, 70
Castlereagh Street, Sydney, NSW, 2000, Agripower’s registered office.59 That
address was ascertained when Mrs Coleman emailed Mr Prentice the first invoice,
asking him to forward “the mailing address for your company”.60 Mr Coleman
acknowledged in cross-examination that the invoices nominated Agripower as the
customer because that is who Mr Coleman thought his business was dealing with.61
54 T1-34 L40 – T1-35 L5.
55 T4-30 L37.
56 T3-7 L11.
57 T4-30 L43-T4-31 L7.
58 T5-14 L43.
59 Ex 3 p369.
60 Ex 3 p3.
61 T3-59 L23.
-- 13 of 55 --
14
[61] Mr Prentice was clearly acting in his capacity as a director of and on behalf of the
second defendant company. Coleman Contracting obviously understood it was
contracting with the company, not with Mr Prentice as an individual. Mr Prentice
assumed no personal liability in connection with the contract, for instance as a
guarantor. There is no proper factual foundation for him to be held jointly liable
with the company for its apparent indebtedness to the plaintiff.
Initial laying of the road
[62] Mr Coleman moved his business’s earth moving equipment to the worksite from
where it was located at Etheridge Shire Council and at the Coleman’s Uramo
property.62
[63] Work for the installation of the access road commenced on 1 August 2009.63 Mr
Coleman and his employees lived on site in an accommodation truck and a number
of camping trailers.64 They would work a 12 hour day from 6.00am to 6.00pm
although on occasion on the direction of Agripower’s site supervisor Mr
Storronning, the water truck would commence operations from 4.00am to “beat the
heat”.65
[64] Mr Coleman testified that as they dozed the road Mr Storronning would walk in
front of the bulldozer “with his GPS and his markings and he would either tape it or
he would mark it with a peg”.66
[65] Mr Coleman explained that during the initial laying of the road the material they
sourced for sheeting over the surface was red volcanic topsoil dug from pits near the
roadside, so called borrow pits, and nearby dams. This was done under the direction
of Mr Storronning.67
Cost of road works
[66] Mr Coleman testified that from an early stage a lot of basalt boulders were
encountered, some of which they were able to pull out. He obtained permission to
re-sheet, that is, apply fill over the top, capping over the rock.68 This was mentioned
in an email of 4 August 2009 in which Mr Coleman wrote to Mr Prentice, saying
inter alia:
“The road we are building for you out at Gilldale has a lot of
unexpected rock and will need to be sheeted over the top, which is
going to slow things down slightly. I have brought this to Ivar’s
attention. I anticipate that we can get the works done in
approximately 15 days to do the approximate 12kms of road.
For all machinery, trucks and camp facilities $132,000.
For establishment and disestablishment of all machines and trucks $8,800.”69
62 T3-7 L24.
63 T3-69 L10, Ex 3 p 197.
64 T3-26 LL29-42.
65 T3-27 L5.
66 T3-7 L30.
67 T1-36 L6, T1-37 L44, T3-9 LL10-20.
68 T3-8 L41.
69 Ex 3 p 2.
-- 14 of 55 --
15
[67] Mr Coleman testified the reference to the above amounts related to the access road
work70 but denied the reference to $132,000 meant he had agreed to build the road
for a fixed price.71 He explained he had earlier provided hourly rates72 and the
amounts in the email were estimates.73 That is consistent with the “subject” title of
his email being “Estimated costings”.
[68] The effect of Mr Prentice’s evidence was that this email had been sent as a follow up
to the telephone conversation between the two men that had occurred after the initial
on site meeting. The implication of Mr Prentice’s testimony was that the email’s
reference to $132,000 was a compliance with Mr Prentice’s seeking of a fixed
price.74
[69] It is likely Mr Prentice did ask for an approximation of how much the road works
were likely to cost and that the email of 4 August 2009 provided that approximation.
However I accept Mr Coleman’s evidence that Mr Prentice agreed to an hourly rate.
I do not accept that Mr Coleman intended or Mr Prentice interpreted the reference to
$132,000 in the email as indicating that a fixed price would be charged. Mr
Coleman foreshadowed from the outset that he would charge at an hourly rate and in
due course that is what he did. Mr Prentice raised no complaint when that occurred,
doubtless because that is what Mr Prentice had agreed to.
Records of work performed
[70] The Coleman’s business entered the hours of work performed by their business in
proforma books of numbered day dockets, configured so there were duplicate copies
of each docket and the top copy could be removed and given to the customer.75 It
appears from the day dockets tendered at trial76 that there were apparently different
day docket books maintained in relation to the operation of different items of plant
and machinery. Most of the dockets recorded between three to five days work
although in some instances they recorded only one day. Against each date the nature
of the machine being operated, the job being performed and the number of hours
taken was recorded for each date entry. There would be corresponding initials
entered by the machine operator.
[71] Mr Coleman explained the day dockets were filled out every day and, after a number
of day’s work, would be given to Mr Storronning to sign.77 It appeared to Mr
Coleman that Mr Storronning had “a day diary that he was filling out” and when
given a docket book for signature would sit on site in his hire vehicle for a period of
time and thereafter return the docket books signed by him, taking the top duplicate
copy of each.78 Mr Coleman said it appeared Mr Storronning would look through
the dockets thoroughly.79
70 T3-44 L13.
71 T3-74 L27.
72 T3-74 LL4-23.
73 T3-74 L22.
74 T5-13 L36.
75 T3-14 L5.
76 Ex 3 pp 197-316.
77 T3-13 L46.
78 T3-14 LL1-5.
79 T3-72 L31.
-- 15 of 55 --
16
[72] Mr Storronning confirmed once the day dockets were handed to him he would
double-check them, referencing his own notes, and then sign off on the day dockets.
He explained he did so in his capacity as supervisor on site and that he was
responsible for checking hours worked.80 He found no problem with the hours
claimed and noted in some instances Mr Coleman did not bother claiming minor
times worked.81
[73] Importantly, Mr Storronning signed each docket against the proforma entry
“Foreman signature”. This was obviously intended to represent a verification by Mr
Storronning that the work recorded had been performed. I accept Mr Storronning
actually did verify the work had been performed before signing the day dockets.
[74] Mr Storronning would arrange for scanned copies of the dockets to be emailed to Mr
Prentice and also forward or deliver the hard copies thereof to him.82
[75] Mr Prentice acknowledged in cross-examination that he was aware of the above
procedure and that he received copies of the day dockets from Mr Storronning.83
The test dig
[76] Mr Coleman explained that at a time before completion of the access road,84 Mr
Prentice asked if he could use the Coleman’s excavator to dig test holes at the
proposed mine site and Mr Coleman agreed.85 On his account Mr Prentice said they
would hit “pure white” after digging down half a metre. He testified that initially he
dug down with a grader blade to one and a half metres but hit nothing. Then one of
his workers operated an excavator and dug deeper. After penetrating two and a half
to three metres the earth changed to calcrete – hardened coral – then for the next two
and a half to three metres it was coloured diatomaceous earth. Then at about a depth
of six metres it became white diatomaceous earth. Mr Coleman testified that Mr
Prentice and some geologists who were with him tested and measured the earth as
they went. On Mr Coleman’s account Mr Prentice’s face showed the result was not
as good as expected.86
[77] Mr Storronning recalled Mr Prentice was adamant white high grade diatomaceous
earth would be just one metre below the surface but instead they encountered a grey
clay like material beneath the calcrete layer and white material was not encountered
until they had dug about six metres down.87
[78] On Mr Prentice’s account, the first digging by Coleman Contracting represented the
commencement of mining work rather than a mere test dig.88 Mr Prentice arranged
for a director of Agripower to be present for this first dig.89 Mr Prentice’s
recollection was that the excavator dug through “a depth of about four, five metres
80 T1-38 LL13-26, T1-43 L24.
81 T1-38 L38.
82 T1-72 L13.
83 T5-14 L10.
84 T3-11 L34.
85 T3-9 L46.
86 T3-10 LL1-43.
87 T1-41 LL31-42.
88 T4-37 L25.
89 T4-54 L42.
-- 16 of 55 --
17
max” at the time the ground layers transitioned from over burden into diatomaceous
earth.90 He testified the pure white product was struck about five metres down.91
[79] An industrial minerals consultant, David Chadwick, was present for this initial
excavation and he testified that the white layer was reached at a depth of six or
seven metres.92
[80] The fact that the diatomaceous earth was actually lower down than apparently
expected for this area is relevant to the cogency of evidence relating to a survey of
the pit discussed below.
The broadening of the task to mining work
[81] The abovementioned email from Mr Coleman to Mr Prentice of 4 August 2009
provided prices for other work which, according to the letter, Mr Prentice had
“asked for”. That work was described in the letter as “top soil stripping” by a
bulldozer, “digging and loading of ore” by an excavator and “carting of ore” from
the mine site to a stockpile at the Gilldale grid. That such price requests had been
made by Mr Prentice demonstrates that by 4 August 2009,93 apparently in the early
stages of the building of the access road, Mr Prentice must have had in mind the
possibility of engaging the Coleman’s business for purposes beyond that task. This
is consistent with Agripower self managing the project.
[82] Mr Coleman accepted in cross-examination that by 4 August 2009 Mr Prentice had
asked him for prices to do mining work.94 Mr Coleman testified that he initially
raised the idea of his business doing more than the access road with Ivar
Storronning, saying:
“[A]s we were putting the road down, I had spoke to Ivar just very
informal, like after work sitting around camp having a beer, who’s
going to be doing the mining? And he didn’t know at this stage, and
I dropped the seed—the hint that, you know, we’ve just come from a
mine before that and we’ve still got plenty of mining gear. You
know, if you’re after anyone to do some mining, we’d be keen to
throw our hat in the ring. So he was talking—he told me he was
talking to Prentice and told him about that.”95
[83] Mr Prentice testified that as the road work was progressing Mr Prentice would give
subtle hints that he was interested in his business staying on for mining work.96
[84] Mr Coleman explained that Mr Prentice subsequently spoke to him when visiting the
site and engaged Mr Coleman’s business to strip the mine site down to the point
where the diatomaceous earth product was.97
[85] On Mr Prentice’s account when the nature of the mining work was discussed Mr
Coleman was comforted by Mr Prentice’s assurance he would be present on the
90 T4-41 L46-T4-42 L2.
91 T5-20 L22.
92 T5-61 L17.
93 Ex 3 p 2.
94 T3-44 L40.
95 T3-11 LL4-10.
96 T5-19 L13.
97 T3-11 LL10-17.
-- 17 of 55 --
18
occasion when mining started “to actually run through with him looking at the top
soil, the overburden and the layering” of the diatomaceous earth.98
The role of Ivar Storronning
[86] Mr Prentice testified Mr Storronning was initially employed part time in mid 2009
and then commenced full time work when Coleman Contracting was engaged.99 Mr
Storronning confirmed Mr Prentice had at the outset given him the plan of
operations and that his role was that of supervising mine staff referred to therein.100
[87] Mr Coleman testified that Mr Prentice had employed Ivar Storronning as a site
senior supervisor, “to supervise the whole project”.101 That role is consistent with
the plain meaning of the title by which Mr Prentice described Mr Storronning’s
position, namely “senior site executive”.102
[88] Mr Prentice unconvincingly implied that Mr Storronning’s role was essentially
confined to maintaining statutory records of all tonnes or cubic metres moved by
transport to be screened or processed.103 On Mr Prentice’s account Mr Storronning
knew that he had to take the information he received from Coleman Contracting’s
truck drivers and “write up those records on site to ensure that the daily diaries and
statutory records were all up to date”.104 Mr Prentice’s apparent premise for
believing Mr Storronning knew he had to maintain such information is that he
understood Mr Storronning had acted as a senior site executive in previous mining
roles and also because Mr Prentice personally went through with Mr Storronning the
sort of records he had to keep.105 Those records predominantly appear to have been
diaries, discussed further below, in which Mr Storronning recorded work site
activity as distinct from some more systemic or prescribed record keeping system.106
[89] The notion that Mr Storronning’s role was essentially confined to record keeping is
clearly contrary to the evidence of his giving of directions and supervising of work
from the very outset of the operation. Mr Storronning testified he started off as the
site supervisor surveying where the road was to go by GPS107 and was engaged in
supervising Coleman Contracting throughout its involvement.108 He explained he
would receive directions about what was to be done on site from Mr Prentice with
whom he spoke most evenings.109
[90] Mr Coleman explained that initially Mr Prentice gave directions and then Ivar
Storronning directed Mr Coleman and his employees every day, after a morning tool
box meeting.110 Mr Coleman testified that Mr Storronning was on the property
98 T4-37 L22.
99 T4-37 L3.
100 T1-33 L11.
101 T 3-8 L2.
102 A term which, for example, pursuant to s 23 of the Mining and Quarrying and Safety and Health Act
1999 (Qld), describes the most senior officer employed or otherwise engaged by the operator for the
mine who is located at or near the mine and has responsibility for the mine.
103 T4-35 L6.
104 T4-44 L47.
105 T4.45 L5.
106 T4-45 L18-T4-46 L25; Ex 14, 15.
107 T 1-32 L26.
108 T1-33 L14.
109 T1-33 L30.
110 T3-8 LL1-7.
-- 18 of 55 --
19
every day that the road was being built, overseeing the whole job, and making sure
of what was occurring, “the same as any overseer would”.111
[91] Mr Prentice was reluctant to make the reasonable concession in cross-examination
that as site senior executive Mr Storronning was responsible for supervision of mine
staff.112 He unconvincingly asserted that Mr Storronning was not qualified to
supervise, obviously intending to bolster a similarly unconvincing implication by
him that on his understanding Mr Coleman was so experienced in mining operations
that Agripower did not need its own supervisor of the mining related work his
business performed.113
[92] Such an implication by Mr Prentice was at odds with his earlier evidence that:
“John wanted to know how we wanted to run the operation because
it’s one thing doing the road, it’s another thing running a mine and
hauling. And I had told John that we’d put Ivar on to be our SSE.”114
[93] That testimony gave away the true position. Mr Prentice would hardly have told Mr
Coleman such a thing if Mr Storronning was merely engaged to maintain records.
Mr Prentice well knew Coleman Contracting was not highly experienced in mining
work and would need to be directed and supervised in carrying out mining work.
Mr Storronning’s diaries and presence on site
[94] A number of diaries or notebooks in Mr Storroning’s hand writing were tendered in
evidence. Despite the attention given to them in the course of Mr Storronning’s
evidence they are not helpful in resolving any major feature of this controversy.
[95] The defendants argued it was apparent from the diaries that Mr Storronning could
not always have been on site and that he therefore could not in fact have supervised
all of Coleman Contracting’s work. The diaries were not particularly clear on the
detail of this issue.
[96] There was reference in the evidence to two occasions when Mr Daniels banned Mr
Storronning from the site, one on 23 October 2009 and one about 21 December.115
At one point Mr Storronning suggested that he was only on site for about 30 per cent
of the time after being banned116 however it appears that after the earlier ban Mr
Storronning did not actually stay away from the site for a prolonged period and Mr
Daniels was apparently persuaded to let Mr Storronning continue to see the
operation through.117 Ultimately the evidence as to how long Mr Storronning was
away from site after the October ban was uncertain. However I infer it was not a
persistent or prolonged absence, for Mr Prentice did not replace him as senior site
executive and Mr Storronning continued to verify the day dockets, as the day
dockets show.
111 T3-69 L17.
112 Eg T5-12 L16
113 T5-12 L20.
114 T4-34 L45.
115 Ex 19, 16.
116 T2-12 L22.
117 T1-83 L4.
-- 19 of 55 --
20
[97] Mr Storronning’s absence from the site from time to time would have been
unremarkable. Further, it is obvious in any event that Mr Storronning could not
have witnessed the carrying out of all of Coleman Contracting’s work all of the
time, even when he was present on site. He could not be omnipresent. However he
would not have needed to be. Like any supervisor he would have been able to make
informed judgments, draw inferences from what he saw had been done when he was
not watching and develop a sense of which features of the operation warranted more
intense supervision than others.
[98] One diary written by Mr Storronning118 was said by him to have been fabricated
after the event at Mr Prentice’s request and direction as to its content, under threat of
not being paid money he was owed by Agripower.119 Mr Storronning eventually
claimed privilege on that topic and it is unnecessary to reach a concluded view about
his allegation. There certainly are features of the diary’s content, including some
criticism of Mr Coleman, of a kind that smack of being written in the aftermath to
please the author’s employer. However that does not of itself mean Mr Prentice put
Mr Storronning up to writing the entries. For instance a number of emails Mr
Storronning apparently wrote of his own volition, at a time when he knew there was
a dispute between his employer and Mr Coleman and he had been asked to scrutinise
records,120 bear a similar self-serving “siding with the employer” quality.121
[99] Mr Storronning either concocted a diary at the request of Mr Prentice or fabricated a
conspiracy allegation against Mr Prentice. I accordingly approached his evidence
with caution. In the upshot though his evidence on matters of significance seldom
stood alone and it was Mr Prentice’s doubtful reliability on issues of importance
which was more concerning.
Payment arrangements for mining work subject to an end reconciliation?
[100] On Mr Coleman’s account his discussions with Mr Prentice about the performance
by his business of mining work and processing did not involve any material change
to the existing payment arrangements by which Coleman Contracting would
progressively invoice and be paid for work performed. Mr Prentice also
acknowledged that when payment arrangements for the mining work were discussed
he continued to agree to Mr Coleman’s request that invoices be paid within seven
days.122
[101] I am satisfied that the oral contract between them for the performance of the ensuing
mining and processing works was that the works would be performed by Coleman
Contracting and paid for by Agripower on the same basis as agreed in respect of the
roadwork, with Coleman Contracting’s known hourly rates to be charged for various
plant and machinery work and payment to made within seven days of invoice.
[102] I am also satisfied it was agreed either expressly, by implication or by conduct, that
the system of submitting the day docket records of the hours worked for verification
by Agripower’s site supervisor would continue.
118 Ex 15.
119 T1-73 L7, T2-26 L14.
120 T4-47 L9, T4-72 L10.
121 He was uncertain in respect of one such email in his name, of 13 December 2009, whether he was
the author – T2-52 L14.
122 T4-36 LL20-25.
-- 20 of 55 --
21
[103] However, according to Mr Prentice, when mining work commenced he secured the
agreement of Mr Coleman to a quite radical variation on previous arrangements.
He claimed it was agreed that at the conclusion of the mining works a survey of the
mine site would calculate how much product had been mined and there would be a
reconciliation of that amount as against the amount of mined product for which
Coleman Contracting had invoiced and been paid. In the event of that exercise
evidencing overpayment, Coleman Contracting would repay money to Agripower.
[104] The pleading of this alleged reconciliation agreement did not expressly refer to a
comparison of amounts charged with volume extracted123 but Mr Prentice testified
that is what was to be reconciled under the agreement:
“I said this has got to be a very simple operation, It’s a short
operation, its small volumes you’re going to be moving and we don’t
want to be out there every day trying to work out what is going on.
So we agree that, you know, the better way to do it was just keep
everything on a cubic metre basis, what’s mine, what’s hauled on a
cubic metre basis and at the end of the day, as would be normal,
you’d just get a pit survey, reconcile the volume and reconcile it
back to the invoices and you’d always expect an over or an under.
That’s pretty normal. I mean, in bigger operations, they’d have
weigh bridges on site that you’re talking about and every truck
would have a weigh bridge docket and you’d tally it all up but there,
you’re talking about moving hundreds and hundreds of thousands of
tonnes and for this it’s just impracticable. So from my experience in
mining, they’re the two ways you do it and the—just a simple cubic
metre to keep it going and then reconcile it back to the pit and then
there can be no arguments.”124
[105] A third “way”, not acknowledged in that passage of testimony, but particularly apt
to a fledgling operation like this, is to simply pay contractors an hourly rate,
supervising them to ensure they work during the hours claimed.
[106] Mr Prentice’s account of when this alleged reconciliation agreement was struck
seemed to be that agreement was reached in a discussion between he and Mr
Coleman around 16-18 August 2009125 although the reconciliation concept had
allegedly been discussed back on 4 August 2009.126 In a subsequent email to
Coleman contracting of 9 September 2009 Mr Prentice did refer to conducting a
“reconciliation” but that was only a reconciliation of the contents of an invoice as
against day dockets.127 It is remarkable, if there was a reconciliation agreement of
the kind testified to by Mr Prentice, that it was not referred to at all in any emails or
other contemporaneous documents.
[107] When it was put to Mr Coleman that it was agreed there was to be “a reconciliation
at the end” Mr Coleman emphatically rejected the notion as totally false and
observed not only “that did not happen” but also “and it would not happen”.128
123 Second further amended defence (“Def”) [4(b)].
124 T4-35 LL14-27.
125 T4-38 L37.
126 T4-38 L43.
127 Ex 3 pp22, 34.
128 T3-75 L30, T3-58 L24.
-- 21 of 55 --
22
[108] The latter point is a powerful one. Mr Coleman’s business operation was premised
upon the charging of hourly rates in respect of the operation of his machinery. His
method of record keeping and invoicing throughout this mining project involved the
recording and invoicing of hours worked, verified by Agripower’s Mr Storronning.
Given that methodology and its progressive verification of work actually performed
it is inherently unlikely Mr Coleman would have exposed his business to the
financial risk inherent in an after the event reconciliation by reference to volumes
never recorded by his business.
[109] I believed Mr Coleman’s testimony that the first time he had ever heard mention of
this supposed reconciliation agreement was at the end of the business relationship
when Mr Prentice would not pay.129
[110] It was suggested in cross-examination to Mr Coleman that the email of 4 August
2009 pointed to the agreement made in relation to the mining being for mining to be
priced at a cubic metre rate but Mr Coleman rejected that suggestion.130 On Mr
Prentice’s account the email followed a request by him, in response to Mr
Coleman’s interest in performing mining and hauling work, for Mr Coleman to give
Mr Prentice some rates for doing the mining and hauling.131 However Mr Prentice
did not testify whether he asked for those rates to be priced per cubic metre, per hour
or otherwise.132 Further the relevant content of the email does little to support the
suggestion that mining work was to be priced per cubic metre:
“…Other prices you asked for:
Carting of ore to stockpile at Gilldale grid from mine site $5.15 per
cubic metre (11.0hr/day, one lad per hour, truck & dog and type 2
roadtrain, 75cbm per hour)
Digging and Loading of Ore by Excavator $154.00 per hour
(11.0hr/day, shift approx. 825 cubic metres a day, provided ore is
pliable) If ore needs extra digging dozer may have to be employed as
well
Topsoil stripping by D7E bulldozer $154.00 per hour (unknown
depth of topsoil). …”133
[111] Two of the three priced items expressly nominated prices per hour. Moreover the
email’s subject heading was “Estimated costings”. When the email’s reference to
$5.15 per cubic metre for carting ore is read in that context, the broader context of
the parties’ discussions and the fact that work of that kind was performed and
charged at an hourly rate, it is likely the price per cubic metre was included as an
estimate of what Agripower would in effect pay per cubic metre based on the likely
carriage and capacity rates of the machinery operation for which Agripower would
be invoiced.
[112] In short it is unremarkable that in discussing permanent arrangements for mining
work Mr Prentice would have given consideration to whether Coleman
129 T3-58 L27.
130 T3-74 L26.
131 T4-33 L14.
132 T4-33 L13.
133 Ex 3 p 2.
-- 22 of 55 --
23
Contracting’s hourly rates were reasonable by reference to the volume of ore that
was likely to be mined and processed. However, I simply did not believe Mr
Prentice’s evidence that Mr Coleman agreed to a payment arrangement involving a
post payment survey of the mine pit, a purported reconciliation of volume surveyed
as against volume charged for and a prospective repayment of money by Coleman
Contracting back to Agripower. To the extent any “reconciliation” was ever
discussed between Mr Prentice and Mr Coleman it would only have been in the
sense of Agripower double checking the invoices rendered by Coleman Contracting
as against the day dockets verified by Mr Storronning before in turn paying the
invoices.
Top soil stripping and road re-sheeting
[113] Mr Coleman testified that because the road was built as an access road, not an ore
road for carting thousands of tonnes of ore, he suggested they push the first bit of
top soil off the mine area, retaining it near the mine for rehabilitation, and use the
rest of the soil overlaying the diatomaceous earth to re-sheet the road to build it up
to a standard on which road trains could cart and Mr Prentice agreed.134 Mr Prentice
acknowledged in evidence that in the course of what he described as the initial
“blazing” of the road, it was necessary to do some dressing of the road and that for
the fine dressing Mr Coleman was using overburden taken from the mine site.135 Mr
Prentice thought the overburden would pack down quite well for that purpose and
approved its use.136
[114] Mr Storronning testified that there was a complaint from a neighbour about dust and
problems with dust suppression and Mr Prentice recommended they use some of the
calcrete layer that came out of the pit as it would compact down very well.
[115] Mr Coleman explained that in extracting the soil overlaying the diatomaceous earth
there was a transition level in which seams of top soil and dirty diatomaceous earth
were mixed so that some diatomaceous earth was amongst the top soil that was used
to re-sheet the road.137 Mr Prentice testified that when he learnt diatomaceous earth
was being used as road fill he directed that to cease because it was unsuitable for
that purpose by reason of its absorptive nature.138
Progress of mining work
[116] Once the top soil removal process arrived at the layer of calcrete Mr Coleman
recalled Mr Prentice instructed that it be stacked to an area to the side of the pit to be
worked at some future time with a crusher.139
[117] Mr Coleman described performing further tasks at the direction of Mr Prentice, Mr
Storronning, or both.140 This included the building of a silt trap and bund walls for
the safe guarding of an onsite fuel depot141 and the building of a hard stand near the
front entrance to Gilldale Station to which the dirty diatomaceous earth could be
134 T3-11 L17-29.
135 T4-34 L20, L40.
136 T5-16 LL41-46.
137 T3-15 LL23-45; also see T1-37 LL5-15.
138 T5-21 L22.
139 T3-16 L5.
140 T3-16 L34.
141 T3-16 L36-T3-17 L6.
-- 23 of 55 --
24
carted.142 The building of the hard stand or run of mine (“ROM”) pad required
clearing and removal of boulders and re-sheeting of the ground surface using a layer
of dirty diatomaceous earth at Mr Storronning’s direction.143 Mr Coleman testified
that Mr Prentice and Mr Storronning then directed that the dirty diatomaceous earth
be carted up and put on the ROM stack, with the dirtiest content to be kept aside in
big rows with enough room left for the cleaner layers when they arrived.144
[118] In addition to Mr Prentice attending the mine site from time to time there were also
regular telephone conversations between he and Mr Coleman. On Mr Prentice’s
own account Mr Coleman telephoned him daily during the first few weeks of the
project and thereafter every second day until mid to late October.145
[119] Mr Coleman testified that as the excavation descended at Mr Storronning’s direction
a decline was cut down into it to permit traffic access.146 He recalled this was done
pursuant to plans he saw Mr Storronning draw.147
[120] Mr Prentice testified that Mr Storronning took samples from the pit wall and sent
them away for analysis.148 Mr Coleman observed Mr Storronning sieving and
taking samples away for testing and also saw that when present, Mr Prentice would
also test the diatomaceous earth.149
[121] Mr Coleman testified that when they finally arrived at the white diatomaceous earth,
about six metres down, they also commenced excavating and carting it to the ROM
pad.150 The white diatomaceous earth was stacked in lines separately on the ROM
pad from the dirty white diatomaceous earth.151
Arrangements for screening
[122] Mr Coleman testified that as the mining process proceeded he enquired who was
going to process the extracted diatomaceous earth, telling both Mr Prentice and Mr
Storronning that his business had a screening plant which had been screening gravel
for RoadTek from the Main Roads Department.152
[123] Mr Storronning testified that Mr Prentice had him search for a screening plant:
“I was asked to do some research and try and locate a screening plant and I
did that, but every avenue I took, Peter Prentice said it was too
expensive, so… John was asked about his, because he mentioned he had
one at his place that he used for doing gravel and Peter Prentice seemed
okay with that one being on site and we just had to modify it and put
different screens on it.”153
142 T3-17 L20.
143 T3-17 L32, T5-21 L1.
144 T3-17 L43.
145 T4-36 LL38-46.
146 T3-18 LL25-33.
147 T3-18 L33, T3-88 L13.
148 T5-12 L34.
149 T3-19 LL5-11.
150 T3-18 L42.
151 T3-19 LL25-30.
152 T3-19 L43-T3-20 L6.
153 T1-47 L25
-- 24 of 55 --
25
[124] Mr Prentice acknowledged in evidence that Mr Coleman told him the screening
plant had only been used to screen gravel.154
[125] In a letter to Mr Coleman of 22 September 2009155 Mr Prentice wrote:
“[W]e would be interested in hiring your mobile screening unit in
order to screen product we currently have in stock pile, for the next
few months. In addition we would like to look at the hire of this
screening unit next year for similar processing of product. We
understand that the unit is available and could be delivered to site for
immediate processing.”
[126] Mr Coleman testified that both Mr Prentice and Mr Storronning inspected his
business’s screening plant at the Coleman’s Uramo station.156 When Mr Prentice
enquired about the cost Mr Coleman said he knew nothing about the diatomaceous
product but he explained it would be necessary to change screens and that while his
plant was putting through 600 metres a day of gravel he did not know at what rate it
would put the diatomaceous earth through.157 I accept he gave no assurance as to
the rate at which he could screen the diatomaceous earth.
[127] Mr Coleman said they would charge $220.00 an hour.158 Mr Coleman recalled that
some days later Mr Prentice indicated he wanted to engage Mr Coleman’s business
to screen the product and wanted him to arrange it to be set up as soon as possible.159
[128] On Mr Prentice’s account of the discussions culminating in the arrangement for
Coleman Contracting to screen product at $220 an hour, he agreed to trial Mr
Coleman’s screening plant and only learnt once screening was underway and the
next invoice was issued that Coleman Contracting was charging $220 an hour.160
On his account when he discussed that rate with Mr Coleman it was explained that
was not merely the hire rate of the screening plant but was an all-up cost inclusive of
other related activity.161 Mr Prentice testified he told Mr Coleman he could obtain
another screening plant inclusive of associated expenses for less, to which on his
account Mr Coleman responded:
“[Y]es, but you—it may be a number of weeks, if not a month before
you get that plant, you can have mine within a week and then think
of what it’s going to save you if the wet comes early that you haven’t
lost all this money on mining and carting of material to the gate and
that was the clincher for me to say to John, yes, let’s go with it.”162
[129] That testimony tends to confirm, as Mr Coleman had testified and as
I accept, that the screening price had been agreed to before the plant commenced
operations. On any view it confirms even on Mr Prentice’s account that he did
accept the rate of $220 an hour. That testimony also highlights Mr Prentice’s desire
to screen the product quickly because of the looming wet season.
154 T5-22 L10.
155 Ex3 p25.
156 T3-20 L4.
157 T3-20 LL10-21.
158 T3-20 L18.
159 T3-20 LL25-30.
160 T4-59 L15.
161 T4-59 L21.
162 T4-59 L27, also see T5-23 L14.
-- 25 of 55 --
26
[130] Mr Prentice testified that his agreement to the hourly rate was premised on a
discussion with Mr Coleman in which it was estimated there would be a likely
throughput of 60 cubic metres per hour.163 Yet as he eventually acknowledged, after
some evasive responses, at no point in the screening process did he require any
recording of volumes of product processed.164 I do not accept that the agreement as
to the hourly rate was conditioned on any particular rate of throughput.
[131] Mr Coleman testified he had modifications done to the screening plant by an
engineering firm and paid for the screens, which Mr Prentice wanted to be stainless
steel to safeguard the quality of the product.165 Mr Storronning testified that Mr
Prentice approved the screens.166 Mr Prentice reimbursed Mr Coleman for the
screens.167
[132] Mr Coleman testified that he took the screening plant to the area of the ROM pad
near the entrance of Gilldale Station in about October 2009.168
Screening activity
[133] Mr Coleman testified that Mr Prentice decided to seek a 2-6 millimetre size screened
product. This had the consequence that with the finer and oversized product not
included there was a low recovery rate in proportion to the totality of the product.169
[134] On Mr Coleman’s account after the screening plant was delivered it was calibrated
and its angles were tested by Mr Storronning so as to achieve the product size
desired by Mr Storronning and Mr Prentice.170
[135] Mr Coleman explained it was impossible for any overflow on the screening machine
to process into the screened product and rather it would be directed by the screening
machine into the rubbish pile.171 Thus if there was a problem with intrusion of
larger sized granules during screening it had to have been with the screen size
settings.
[136] Mr Storronning testified that he and Mr Prentice spent about four days sampling
product when the plant was being commissioned.172 Mr Storronning acknowledged
that after that, while he occasionally double-checked, there was no regular sampling
of product size because, “we knew the size was the same every single time it was
fed.”173 There is no evidence of any subsequent variation to the screen size settings,
which suggests that if there was a problem with the size of the product generated by
screening it was likely present and undetected from the outset when Mr Prentice and
Mr Storronning oversaw the plant’s set up and undertook sampling.
[137] On Mr Prentice’s account:
163 T5-23 L17.
164 T5-23 L11.
165 T3-21 LL17-44.
166 T1-48 L33.
167 T3-21 L29.
168 T3-21 L47.
169 T3-22 LL31-35.
170 T3-22 LL14-18.
171 T4-8 L30-T4-9 L6.
172 T1-87 L16.
173 T1-87 L26.
-- 26 of 55 --
27
“The screening plant had a number of problems initially and then it
seemed to screen quite ok. Still continued to have hiccups with it in
terms of operational ability. There’d be stoppages and then it would
be fixed and work again. I think the—my observation was it was a
very old plant and it may’ve been good for gravel but it was not
ideal, particularly with how quickly they were feeding material
through it all the diatomaceous earth.”174
[138] Mr Coleman was challenged in cross-examination about the alleged failure of the
screening to yield a higher recovery rate and to process more quickly. His responses
demonstrate where real responsibility for the process adopted lay:
“And you were made aware that the screening should produce
between two and six mil granules? - - - That’s what they wanted and
it’s impossible for it to have no fines for a start.
Well, it should have – if it was working properly … yielded 75
percent in that size and the 25 percent would be re-worked? - - - I can
only be as good a man as the directions I’ve been given. I was
given–told what to do. … I bought the screens. … They … did the
testing on it and they–right, ready to go. If someone gives me a
direction and they’re paying me, that’s what I do. I don’t go and do
the opposite.
You told Mr Prentice that your machine could process 60 cubic
metres per hour, didn’t you? - - - I told him–we put through 600
cubic metres of type 2.2 grade gravel for the Main Roads
Department. That’s what I told him it will do. How would I know
what it would do? I’ve never laid eyes on the stuff. I can’t tell you
what that screening plant will do until I–I’ve never dealt with this
type of gear.
See, I suggest to you that if, indeed, the plant could handle and put
through 60 cubic metres per hour it could do 100 cubic metres of
diatomaceous earth per hour? - - - Well, it was putting through 600
metres a day of 2.2 grade gravel. What I would have said to him and
what I did say to him was before the machine left site, so how would
I have known what it could do. …
But you–do you agree that you told him it would process 60 cubic - -
-? - - - No, I didn’t. I told him 600.
600 cubic metres? - - - Of 2.2 grade gravel a day. That’s what it will
do. …175
Did you ever have any discussion with Mr Prentice about what was
the expected percentage recovery of material that was in the range
two to six mils? - - - No.
174 T4-60 LL15-20.
175 T4-7 L27-T4-8 L12.
-- 27 of 55 --
28
Can I suggest to you that the–what was required was a minimum of
75 percent of product being recovered within that specification? - - -
He never talked to me about it, no.
Did you ever do any testing … to see whether or not the machine–the
screen machine was, in fact, producing 75 percent in that
specification? - - - I never did any testing. They did it.
Did you ever do any testing to check the rate of throughput with the
screening plant? - - - No. They–they did it.”176
[139] Mr Coleman explained that in addition to Mr Storronning taking samples and
sending them away Mr Prentice also attended at the mine and conducted tests,
telling Mr Coleman what to do.177 Mr Storronning testified that Mr Prentice was
present throughout the trialling of the screening.178 Some records relating to their
screen testing process were tendered in evidence.179 Mr Coleman did not do any
testing180, nor was it suggested it was his role to do so.
[140] Mr Coleman testified that they screened the white and off-white product separately
and put the screened form of each product in individual stock piles.181
[141] On 21 October Mr Prentice asked Mr Coleman to use a rotary hoe on the product
before screening in order to reduce clumps in the product so as to process more of it
within the 2-6 millimetre size range rather than big lumps being screened off as
oversize.182 Mr Coleman procured a rotary hoe and it was used on the product for
two days, on 24 and 25 October 2009.183 Mr Coleman testified that Mr Prentice then
decided that process was more time consuming than it was worth and ceased it.184
[142] Mr Coleman testified that because the product absorbed water so readily,
particularly overnight, it was progressively turned over in its lineal lines on the
ROM pad so as to “solar dry it” before screening.185 If this was not done the product
would clog the screens.186
[143] Mr Storronning explained the screening process was slow, with only between 50 to
120 cubic metres per day being screened, because the high moisture clayish content
of the off white earth clogged both the small and large grade screens and needed to
be wire brushed free after every hopper feed.187 He explained more tonnage would
have been processed if they were not putting through so much off-white clayish
material.188
176 T4-7 L27-T4-14 L11, T4-14 LL32-45.
177 T3-22 LL18-26, T3-69 L42.
178 T1-47 L35.
179 Ex16.
180 T3-80 L12.
181 T3-23 L15.
182 T1-47 L13, T3-26 L15, Ex3 p73.
183 Ex 3 p 302 day docket 470.
184 T3-26 L25.
185 T3-22 L42-T3-23 L2.
186 T3-23 L8.
187 T1-50 LL21-43.
188 T1-65 L18.
-- 28 of 55 --
29
[144] Mr Storronning testified that the system of him verifying hours recorded as worked
in the day dockets continued through the screening process and the mixing and
bagging process.189 So too did his role as supervisor, overseeing all aspects of the
process and giving directions.190 Mr Storronning confirmed that if he had seen any
departure from what was required he would have intervened.191
[145] Once screening was underway the Coleman’s loaders were used at an hourly rate.192
Bagging arrangements
[146] Mr Coleman testified that he enquired of Mr Storronning what was going to be done
with the separately stock piled screened product.193 On his account Mr Storronning
apparently spoke to Mr Prentice and Mr Prentice offered the work of bagging the
product to Mr Coleman as an alternative to having to get another contractor in to
perform the work.194
[147] Mr Coleman testified he agreed to perform the work considering, given Mr
Prentices’ representation about the 100 year life of the project, that it was worth his
while to build a bagging plant and simply charge an hourly rate for two of his
employees to do the bagging.195
Mixing and bagging activity
[148] A mixing bay with a clean diatomaceous earth floor was built by Mr Coleman’s
business on site as a platform upon which the screened white and off-white product
could be blended in proportions requested by Mr Prentice.196 The mixing bay had to
be spotless and a regularly cleaned loader was used solely to perform the mixing
task.197
[149] Mr Coleman testified that Mr Storronning supervised the mixing process and also
took samples of the mixed product.198 Sampled product was forwarded to Michael
Leu for testing.
[150] The bulk density of the product was a particular focus of Agripower’s attention
during testing. Mr Prentice explained clay is inevitably present in diatomaceous
earth because diatoms are tube shaped and in their sedimentary state clay embeds
within the tube.199 Off-white diatomaceous earth has a higher clay content than
white diatomaceous earth and thus a higher bulk density, that is, a higher weight per
the same volume.200 The proportion of white and off white mixed together
influences the bulk density of the product.
189 T1-50 L15, T1-52 L42.
190 T1-52 L42 – T1-53 L4.
191 T1-53 L7.
192 T3-22 L41.
193 T3-23 L42.
194 T3-23 L44.
195 T3-23 L45-T3-24 L9.
196 T3-24 LL17-23.
197 T3-24 L42.
198 T3-24 L43-T3-25 L2.
199 T5-36 L36.
200 T5-37 LL5-17.
-- 29 of 55 --
30
[151] In an email to Mr Prentice of 14 October Mr Leu noted of samples that the off-white
was wetter and denser than the white and suggested they mix a blend of two white to
one off-white.201 That did not occur. The volume of available screened off-white
product significantly exceeded the volume of screened white product.202 Mr
Prentice requested the product be blended in a proportion of two off-white to one
white,203 which is the reverse of the mix suggested by Michael Leu.204 Mr Prentice
testified that to achieve adequate plant available silicon for fertiliser use he needed a
product with more off-white than white.205
[152] In an email of 16 October 2009 to Mr Leu and Mr Storronning, Mr Prentice outlined
the need for quite significant testing of the bulk density of unmined and mined
diatomaceous earth, explaining Hortus were “now very concerned” with what the
product’s bulk density would be.206 The email said of the need to test and determine
weights and volumes:
“All of this is impacting on sales and production. There is no point
in screening and bagging until we know the answers. …[T]his is
extremely urgent and … until this is resolved there is no point to
have John or his team at site.”207
[153] Further emails between Mr Prentice and Mr Leu on 16, 17, 18, 19 and 22 October
confirm detailed attention was being given to the high bulk density of the product in
this era.208
[154] Mr Prentice considered other proportionate mixes of white to off-white. For
instance his summary of a meeting with Mr Storronning and Mr Coleman of 21
October contemplated blending a ratio of .8 of a cubic metre of white with 1 cubic
metre of off-white.209 Further, his notes of a meeting with Mr Coleman of 25
November noted that while they had been blending one third white and two thirds
off-white, they would “now blend 1 for 1”.210
[155] As these various records of communications illustrate, there was a degree of trial
and error involved in Agripower’s evolution of a processing methodology
appropriate to the site’s product and Mr Prentice was actively involved in directing
the methodology to be used. Mr Prentice accepted in cross-examination that Mr
Coleman and his team had nothing to do with the design or formulation of the
processing methodology.211
[156] Mr Coleman explained that as time wore on it was apparent they would run out of
the white product first but Mr Prentice did not want them to mine any more of it and,
201 Ex 3 p52.
202 T3-24 L23.
203 T3-24 LL23-30.
204 T5-37 L45.
205 T5-37 L38.
206 T5-39 L65.
207 Ex3 p66.
208 Ex 3 pp 67, 68, 71, 72, 74, 75,76; Ex 10A. Some attention was also given to Ex3 p106 and its
reference to a pit having high clay diatomaceous earth but it doubtful whether that is actually a
reference to the site in this case.
209 Ex 3 p79.
210 Ex 3 pp123, 124.
211 T5-39 L34.
-- 30 of 55 --
31
instead, altered the blend proportion to three off-white to one white.212 It will be
recalled it was the off-white product which caused the most significant repetitive
delays in screening. Mr Prentice did not dispute the blend was altered to three parts
off-white to one part white but denied he had approved the change and could not
explain why it occurred because in his view the amount of mined white
diatomaceous earth should not have run low.213
[157] The mixed product was loaded into a hopper which fed the product into one cubic
metre woven fertilizer bags which would be hooked up to the bagging plant.214 Mr
Coleman testified that Mr Prentice supplied the fertilizer bags.215
[158] Mr Coleman testified that Mr Prentice conducted measuring exercises using the
buckets of loaders and excavators and boxes, including a one cubic metre box Mr
Coleman had used in the past for gravel screening.216 Mr Prentice explained this
box was used to measure the product to be bagged because it was found the one
cubic metre bags stretched so that when filled to capacity they exceeded a volume of
one cubic metre.217 It was ascertained that a volume of one cubic metre was
achieved by filling the bags with product weighed at 830 kilograms.218 On 15
October 2009 Mr Prentice directed Mr Storronning by email that “all existing bags
must be redone to be .85 per bag.”219
[159] Mr Coleman testified that after the bags were filled they would be tied off and
analyst tags were put on them by Mr Storronning who also noted the number of bags
in his diary.220
[160] Mr Coleman testified that Mr Prentice arranged for the collection of pallets and the
bags were loaded onto pallets and stacked ready for transportation.221
Screening and bagging by Agripower personnel
[161] Mr Coleman testified that towards the end of operations Mr Prentice wanted to
accelerate production, working longer hours at the screening plant “to beat the
rain”.222 Mr Coleman did not agree to provide the staff for that purpose but did
provide his machinery, charging for its after hours use but not charging for the
labour to operate it after hours.223 Mr Prentice testified that Agripower employed
staff who worked about three or four night shifts, screening and bagging product.224
212 T3-24 LL32-39.
213 T5-38 LL1-20.
214 T3-25 LL3-11.
215 T3-25 LL10-15.
216 T3-22 LL29-37.
217 T5-38 L28.
218 T3-25 LL17-24.
219 Ex 3 p66.
220 T3-25 LL25-33.
221 T3-25 L37-T3-26 L7.
222 T3-27 L13.
223 T3-27 L28, Ex 3 p 304 invoice 10.
224 T5-32 L23 – T5-33 L10.
-- 31 of 55 --
32
Acknowledgment of managerial failure
[162] Communication after the event suggests the bulk density problem was not perceived
to have been the sole cause of difficulty with the end product.
[163] A candid account from Mr Prentice was given in an email by him to Mr Storronning
of 18 March 2010, in which he wrote:
“You remember the bagged granular product we sent down to Hortus
at Toowoomba. This had a bulky density of around 860.
A couple of weeks ago we decided to trial a few bags by fine
grinding to produce a product we could use for foliar spray. Dave
Chadwick, who you have met carried out the grinding trials and tests.
A number of issues have arisen which I will set out below:
1. The product trialled had a bulk density of 960 and was
running 19.6% moisture. …
3. What David noticed was that there was a lot of fist size
lumps of clay in the product which they took out. Fist size
is a concern in how it would have got there.
4. David’s major concern was that on his analysis 50% of the
product is in fact clay. This will be a disaster if we get this
out in the field.
Clearly we have had an absolute disaster with what has happened,
not so much with the mining but with the screening. For some
reasons, assuming David is right, half of the product or close to it, is
clay. As you know from the mining point of view there are clay
bands which you take out separately and not mix with the raw DE.
To have so much clay in the product can only mean that everything
was mined and mixed together and we must have mined substantial
clay bands for the finished product to be 50% clay, as there is just
not that much clay.
This probably means that all the bagged product is going to be
useless.
What concerns me clearly is that the whole operation is going to
show up as being a total disaster. …”225
[164] The defendants emphasise this letter referred to the use of product for foliar spray
but the problems it identified were obviously not confined to use in that context, vis
the references to all of the bagged product being useless and the whole operation
being a disaster. That there was such broad concern is also evident in an email sent
later that day by Mr Prentice to Mr Chadwick, in which he wrote:
“You mentioned to me the issue of clays in the DE product. This is a
major concern for a few reasons. As you are aware the clay largely
occurs in bands and thus it should be quite easy from a mining stand
point to mine the clay bands and place it separately from the raw DE,
and interspersed clay would be very minor however to be near 50%
clay just does not sound realistic. Secondly it raises with me
225 Ex 3 p165.
-- 32 of 55 --
33
concern, as you have also mentioned the large clay particles in the
product, as to whether our process i.e. Screening plant is even
appropriate, or not set up correctly or it is not run correctly. …226
[165] Mr Chadwick gave a first hand account of his observations of the product trial
saying:
“We noticed when the product was feeding out into the mill, you
know, there was significant lumps of clay coming out … And some
of them were, sort of, fist sized.227
He went onto explain that it was not very clean diatomaceous earth and did
not have a high percentage of diatomaceous earth in it.228 He expressed a
view that the product did not appear to be the “lower layer white product”
and appeared to have “a fair bit” of the upper two layers in it.229 Mr
Chadwick made the observation that from what was now known in hindsight
about the profiles at the Wynadotte Station site the top two layers gave rise
to “quite elevated clay levels”.230
[166] The fact that clay bands had been mixed with layers of diatomaceous earth bespeaks
an obvious failure by Agripower management to properly direct and supervise the
mining and screening of the product. As to the screening Mr Prentice acknowledged
in cross-examination that he had agreed to the use of Mr Coleman’s screening plant
and that he and Mr Storronning had overseen its establishment and the
commencement of the screening operation with it.231 When it was put to Mr
Prentice that he, and at his direction Mr Storronning, had thereafter overseen the
ongoing running of the screening operation, he responded:
“Well, for probably about eight or nine days, yes.”232
[167] It is unsurprising that on 1 March 2010 Mr Coleman acknowledged in an email to
Mr Storronning:
“I am under a lot of pressure as regards the operations going forward
because last year there were many problems and the management of
the mining, hauling to the screening plant, screening were to be
blunt, really bad… You and I need to develop a really good position
to move forward on because at this stage we are working from a low
credibility point as regards management. It is important that I am
blunt to you on this, and open.”233
[168] Mr Prentice’s evidence displayed considerably less candour about the bad
management when he gave evidence at trial. He asserted that the above email’s
reference to bad management was to Coleman Contracting’s management, but that
evidence was unconvincing.
226 Ex 10B p2.
227 T5-62 L36.
228 T5-62 LL40-48.
229 T5-63 LL27-33.
230 T5-68 L39.
231 T5-73 LL37-42.
232 T5-73 L44.
233 Ex 3 p163.
-- 33 of 55 --
34
Storage
[169] The Coleman’s had a large shed at their station at Uramo. The prospect of Mr
Coleman’s business storing some of the bagged product had been mentioned in Mr
Prentice’s letter to Mr Coleman of 22 September 2009, referred to above. That letter
concluded:
“Finally, there will be a requirement to store finished product, which
is being bagged into one cubic metre bulk bags for delivery to
customers. We have inspected your shedding complex and have
estimated that in the order of 800 bulk bags could be stored. We
would like to look at storing bulk bags in the immediate future
following screening and bagging to commence next week. Next year
we would like to look at the opportunity to use this shedding
complex as a holding facility during the year for product deliveries
into the far north Queensland markets for fertiliser.”234
[170] On 30 September 2009 Mr Prentice emailed Mr Storronning and Mr Coleman
asking them to give thought to warehousing possibilities some of which were
mentioned by Mr Prentice in the email.235 One possibility included was the storage
of around 800 bags at Mr Coleman’s shed although the email noted that would
necessitate trucking the bags north to the shed and then bringing them south again
later.
[171] While Mr Coleman had no recollection of the email of 30 September 2009 he did
recall that by this time Mr Prentice had been to the Coleman’s Uramo Station in
order to inspect the screening plant and on that visit had seen the large new shed
they had on their property.236 Mr Prentice’s recollection was that he had seen the
shed at Uramo after screening in about mid October,237 although he also
acknowledged having noticed the shed when he visited to inspect the screening
plant.238 It is apparent from the terms of Mr Prentice’s letter to Mr Coleman of 22
September 2009 and its words – “we have inspected your shedding complex” – that
the inspection must have occurred by the time of that letter.
[172] Mr Storronning was present for the inspection of the shed and considered it was well
positioned away from the prevailing direction of storms.239 Mr Coleman testified
that during the inspection they measured up the shed and Mr Coleman told Mr
Prentice the shed would be capable of storing approximately 1500 to 2000 bags of
Agripower’s DE product.240 When photographs of the shed with bags in situ were
put to Mr Coleman in cross-examination he pointed out the depicted layers of bags,
particularly the top layer did not fill the outer edges of storage capacity and there
were other areas undepicted where there were no bags.241 The reference in Mr
Prentice’s letter of 22 September 2009 and his email of 30 September 2009 to 800
bulk bags being stored suggest Mr Prentice did not intend to store as many bags as
Mr Coleman estimated his shed could take. This appears unlikely to have been for
234 Ex 3 p 25.
235 Ex 3 p 42.
236 T3-29 L19, T3-29 L35.
237 T4-66 L46-T4-67 L2.
238 T5-28 L15.
239 T1-54 L22.
240 T4-3 L10.
241 T4-3 L36-T4-4 L20.
-- 34 of 55 --
35
want of storage capacity and rather the undesirability of trucking bags north and then
south again later. On Mr Prentice’s account the added transportation costs involved
in using Mr Coleman’s shed at Uramo rather than potential storage further south at
Charters Towers meant he only intended that Mr Coleman’s shed would be used as a
temporary measure for the wet season in the event there was not enough storage at
Charters Towers.242
[173] Mr Coleman testified that at a time after Mr Prentice had apparently been procuring
quotes for transportation of the product Mr Coleman offered to lease his shed for
$100,000 a year.243 It ought be appreciated that Mr Coleman was unlikely to have
been interested in an informal occasional storage arrangement because of the
inconvenience involved in freeing up shed space. Mr Coleman testified he told Mr
Prentice:
“I said, well, I’ve got that big shed at home. It’s got some stuff of
ours in it but I would rent it out as long as it was going to be – I
would lease it out to you if it was going to be worth it to us. I would
take my stuff out and put it in other sheds.”244
[174] On Mr Coleman’s account Mr Prentice indicated the price of $100,000 per annum
was at the lower end of the scale compared to some of the prices he had obtained
and Mr Prentice indicated he was going to lease the shed.245 Mr Coleman testified
that Mr Prentice said he wanted to begin carting to warehouse the product as soon as
possible “to beat the weather” and agreed to Mr Coleman’s request that a contract be
“signed up”.246
[175] On Mr Coleman’s account the conversation between he and Mr Prentice on the one
hand involved Mr Prentice agreeing “that he was going to lease the shed” but on the
other it involved Mr Coleman asking for a contract to be signed up.247
[176] Mr Prentice testified Mr Coleman took product to the Uramo shed without
authority.248 He claimed the first time he was aware of a potential charge of
$100,000 plus GST was when he received an offer on 6 November 2009. That
evidence was plainly wrong. Earlier on 29 October 2009 Mr Prentice had written to
Coleman Contracting saying, inter alia:
“b. Warehousing
1. You have a shed which we looked at which you would like to
lease out at $100,000 per annum, paid quarterly. Based on your
estimates you think the shed would conservatively hold 1500 stacked
3 high and that you may be able to get this close to 2,000 bags.
2. If we assume $100,000 for a year and 2,000 bags constantly this
works out around $4.16 per bag per month. This amount is at the
lower end of what we have been quoted in Charters Towers, I guess
my only thought process will (sic) we always hold bags in your shed
and right throughout the year.
242 T4-66 L40.
243 T3-29 L40.
244 T3-29 L28.
245 T3-29 L48.
246 T3-29 L45.
247 T3-29 L45.
248 T5-29 L6.
-- 35 of 55 --
36
3. The above cost includes warehousing and fork lifting driver. …
I will do a letter of agreement re the warehousing and get it to
you.”249
That correspondence is at odds with Mr Prentice’s testimony that he had not
agreed to a period for storage any longer than the wet.250 Mr Prentice’s
reference to quarterly payments for the storage facility assumes significance
given the eventual absence of a concluded annual lease agreement.
[177] The transportation of product to Uramo had actually commenced by at least 3
November 2009.251 Moreover there was a site meeting of 21 October, after which,
Mr Prentice wrote an email to Mr Storronning and Mr Coleman on 22 October
saying, inter alia:
“We must lock in Charters Towers storage.
We have agreed storage with John.”252
[178] Further Mr Prentice’s written summary of the same site meeting, distributed on 29
October, said:
“I would recommend that from today John Cart’s (sic) bags to his
shed and that on Wednesday he will have pallets to start putting them
on in the shed and stacking them 3 high. John has indicated his shed
will hold in the order of 1,500 to 2,000 bags. My suggestion is that
we fill John’s shed first and then we cart to Charters Towers
storage…”253
[179] Mr Prentice conceded that was an instruction to commence storage of the bags.254
[180] In the light of this array of evidence Mr Prentice’s testimony that Mr Coleman had
taken product to his shed without authority was not credible.
[181] Mr Coleman explained he asked Ivar Storronning to inspect his shed at Uramo to
ensure it was clean and ready after which Mr Storronning told him it was ready for
carting to begin to it.255 When pressed in cross-examination Mr Coleman
maintained that Mr Storronning had instructed him to start taking the product to his
Uramo shed.256 Mr Coleman explained that Mr Prentice and Mr Storronning wanted
to put the product into a shed before the rains.257 When pressed as to who actually
gave the direction he explained it was Mr Storronning and that Mr Storronning had
said “Peter wants to go ahead and cart that into there and get into there, start carting
to beat the wet.”258
249 Ex 3 pp 82-83.
250 T5-85 L17.
251 Ex 3 p301.
252 Ex 3 p73.
253 Ex 3 p80.
254 T5-29 L21.
255 T3-30 L41.
256 T3-81 L27.
257 T3-81 L42.
258 T3-84 L8.
-- 36 of 55 --
37
[182] On Mr Coleman’s account he then embarked upon carting product to his shed on the
strength of Mr Prentice having indicated he would enter into a contract.259 Mr
Coleman testified:
“…I told him I wanted this—the agreement drawn up—the lease—
the contract. And he told me he was going to go back to Sydney, get
his legal team to draw up a contract. So, unfortunately, I started
carting it into there then just started putting it into there and I had
asked where is this contract. I had asked Peter Prentice himself. I’ve
rang him. I asked Ivar to get onto it. I need this contract.”260
[183] Mr Coleman candidly acknowledged his regret that he commenced this feature of
the work before a written contract was entered into,261 however he maintained he
only commenced it when instructed to by Mr Storronning.262 On Mr Coleman’s
account Mr Storronning said he would follow up Mr Prentice and get the contract to
Mr Coleman.263
[184] Mr Coleman acknowledged that at that time he was eager to get in as much money
as he could.264
[185] On 6 November 2009, after carting to Uramo had already started, Mr Coleman wrote
in an email to Mr Prentice:
“Further to discussions regarding the lease of our shed at Uramo
Station for storage purposes, here is what we can offer you:
Shed will hold approx. 2000 bags of product.
Value of lease will be $110 000 (including GST) per year
paid in advance quarterly starting from the 10 November
2009.
Period of lease will be for three years.
You and representatives from your company will have access
to the shed at any time with prior courtesy call to the
homestead (07 4097 0222).
There will be a forklift or loader at your disposal for the
unloading and loading of product from trucks. If John or one
of our employees is available they will assist in the loading
and unloading.
Should our property be sold in the future we will give you at
least two months notice to vacate.
These are the anticipated due dates for lease payment:
10-11-09 $27 500.00
10-2-10 $27 500.00
10-5-10 $27 500.00
10-8-10 $27 500.00
259 T3-30 L24.
260 T3-30 L25.
261 T3-30 L30.
262 T3-84 L44.
263 T3-30 L42.
264 T3-77 L41.
-- 37 of 55 --
38
We will forward you an invoice in the weeks leading up to the due
dates for lease payments and payment can be made by EFT as
happens now with the mining.”265
[186] While that document was on its express terms an “offer” only it will be recalled that
back on 29 October Mr Prentice had promised to provide Coleman Contracting with
a letter of agreement about warehousing.266
[187] On 19 November 2009 Mr Storronning sent Mr Coleman an email saying inter alia:
“Peter Prentice would like to start carting product to Charters Towers
as early as tomorrow, he is getting more worried of losing product to
rain. Peter will confirm that sheds are locked in late this afternoon.
… We only need to do an additional four hours bagging per day to
keep up and to load as much product as possible to Charters Towers
before any rain. We will then concentrate on filling your sheds with
product and Fines …”267
[188] When the priority given in this correspondence to implementing storage at Charters
Towers is compared with the earlier priority given to implementing storage at Mr
Coleman’s shed in Mr Prentice’s written summary distributed 29 October it
demonstrates an obvious change in Agripower’s preferred location for storage as
November progressed. The likely reality is that Mr Prentice was content to exploit
the availability of the Coleman’s storage shed at Uramo pending the availability of
the better located storage in Charters Towers. He was therefore content to delay in
ever tending to a lease agreement for an unnecessarily long term of storage at
Uramo.
[189] On Mr Coleman’s account Mr Prentice visited their Uramo property after they had
carted approximately half a dozen loads of the bagged up diatomaceous earth to his
shed and started stacking them.268 On Mr Prentice’s account this must have
occurred on 25 November 2009.269 Mr Coleman testified that Mr Prentice took
photographs of the shed and indicated he was happy with what had been done.270
[190] By this time on Mr Coleman’s account Mr Prentice’s payment of Mr Coleman’s
accounts was not up to date and Mr Coleman was also in the process of
reconsolidating his business’s finances and was seeking to do so with the ANZ bank.
On Mr Coleman’s account he told Mr Prentice he needed to have the accounts
finalised and needed the contract.271 Mr Coleman testified that Mr Prentice told him
“Woah, don’t go there”, claiming it would all be done when he returned to
Sydney.272 Mr Coleman testified it was not done and he lost a lot of faith in Mr
Prentice’s word.273 Mr Prentice denied having said at that meeting that he would
sort out the contract and accounts on his return to Sydney.274
265 Ex 3 p 87.
266 Ex 3 p83.
267 Ex 3 p 96.
268 T3-31 L18.
269 T4-69 L40.
270 T3-31 L3.
271 T3-31 L25.
272 T3-31 L31.
273 T3-31 L38.
274 T4-74 L29.
-- 38 of 55 --
39
[191] Even on 30 November Mr Prentice was continuing to try and string Mr Coleman
along, saying in an email to Mr Coleman:
“I will work on the Warehouse Agreement tonight and will forward
it to you tomorrow.”275
It will be recalled he had been promising to forward the written agreement
since 29 October 2009.
[192] It appears that even after 19 November there were further delays in the availability
of storage at Charters Towers. For instance in a summary of the meeting with Mr
Coleman of 25 November Mr Prentice referred to transporting all bags to Charters
Towers “and nowhere else” as soon as the Charters Towers facility became available
and said:
“I understand that we should be able to start carting to Charters
Towers effective Sunday 29th November”.276
[193] It is little wonder Mr Coleman decided the writing was on the wall as November
drew to a close without payment of the long overdue invoice 9, without Mr Prentice
honouring his indication that a written lease agreement would be entered into and
with Mr Prentice now talking of transporting all bags for storage to Charters Towers.
Invoices
[194] Mr Coleman’s business issued a total of 11 invoices to Agripower. The invoices
were not issued every seven days despite the agreement that payment would be
made every seven days. Mr Coleman explained it was not possible to issue invoices
every seven days because his wife Dianne generated the accounts from their home
office and he was away for prolonged periods on the job so that he did not go home
every seven days.277
[195] All bar the eleventh invoice listed the day dockets relied upon in support of the
amounts charged. All such day dockets had been signed by Mr Storronning in that
part of the docket endorsed “Foreman signature”. Their referencing in invoices one
to 10 inclusive demonstrates those invoices were calculated by reference to actual
hours worked as validated by Mr Storronning.
[196] Mr Prentice testified that accompanying the invoices received from Coleman
Contracting copies of the relevant day dockets would also be attached.278
[197] The eleven invoices are summarised in the below table. The nature of the work
referenced in the table is ascertainable from the contents of the day dockets
referenced in the invoices with the exception of invoice 11 for which there are no
day dockets.
Invoice
sequence
number
Amount Period invoiced Work Invoice
date
Payment date(s)
1.279 $49,428.50 1-8/8/09280 Road work 8/8/09 11/8/09
275 Ex 3 p119.
276 Ex 3 p124.
277 T3-71 L35.
278 T4-39 L26.
279 Ex 3 p 196.
-- 39 of 55 --
40
2.281 $324,74.00 9-13/8/09 Road work and
digging test
holes at mine
13/8/09 21/8/09
3.282 $69,314.50 14-25/8/09 Road work and
removal and
carting of mine
top soil to re-
sheet road
25/8/09 27/8/09 ($29314.50)
28/8/09 ($40000.00)
4.283 $83,240.50 21/8/09-6/9/09 Road work,
removal and
carting of top
soil and loading
of ore
6/9/09284 10/9/09 ($40622.50)
21/9/09 ($40000.00)285
5.286 $34,128.00 25/8/09-5/9/09 Carting ore to
hard stand
20/9/09 14/10/09
6.287 $62,706.00 14-20/9/09 Road work,
dozing pit and
carting and
stacking ore on
hard stand
24/9/09 1/10/09
7.288 $141,671.0
0
21/9/09-
11/10/09
Road and mine
pit work,
screening plant
loading and
drying ore for
screening.
12/10/09 23/10/09 ($60000.00)
29/10/09 ($30000.00)
10/11/09 ($51671.00)
8.289 $29,502.00 12-20/10/09 Screening and
bagging plant
testing and
loading
20/10/09 10/11/09
9.290 $82,348.00 24/10/09-
9/11/09
Screening and
bagging plant
loading,
transporting
product to
Uramo shed
10/11/09 Unpaid
10.291 $155,683.0
0
4/11/09292-
29/12/09
Screening and
bagging plant
loading,
transporting
product to
Uramo shed
3/12/09
293
Unpaid
280 Invoice 1. contains an entry “8/1/09” attributable to “establishment”. It is likely that date is
erroneous and should instead be “1/8/09”.
281 Ex 3 p 209.
282 Ex 3 p 226.
283 Ex 3 p 239.
284 This date is actually recorded as 9/6/09 but that is an obvious error and it should instead be 6/9/09
which is the last date in the relevant day dockets.
285 This invoice is endorsed by hand to indicate the amount of $2618.00 was still owed.
286 Ex 3 p 254.
287 Ex 3 p 260.
288 Ex 3 p 273.
289 Ex 3 p 285.
290 Ex 3 p 295.
291 Ex 3 p 304.
292 This date is actually 11/4/09 in the invoice which again appears likely to be an error and should have
read “4/11/09”, which is the earliest date identified by the day dockets mentioned in this invoice.
293 This date is actually 12/3/09 in the invoice which again appears to be an error and given the repeat
nature of this error should read “3/12/09”.
-- 40 of 55 --
41
11.294 $27,500.00 1/11/09-31/1/10 Advance
payment of
storage costs for
Uramo shed
1/11/09
295
Unpaid
[198] As the above table demonstrates, the invoices issued by the Coleman’s business
continued to be paid after the testing of the screening and bagging plant process and
during the operation of the screening and bagging plant work.
Reasonableness of rates
[199] The plaintiff tendered two uncontested reports by experienced operators of plant and
machinery businesses, John Harron and Gordon Meares. Each opined that the
hourly rates charged by Coleman Contracting for the various plant and machinery
operated were reasonable in comparison with rates ordinarily charged in the
industry.296 In the case of Mr Meares’s report it referred not merely to plant and
machinery but also to the shed storage charge, noting the comparative rate of charge
out for similar sheds within the vicinity of about $15,000 per month.
[200] The defendant’s expert, engineer Benjamin White was in general agreement with the
opinions of Mr Harron and Mr Meares.297 Significantly while he concluded the
plaintiff’s rate of $220 per hour was reasonable he qualified that opinion as being
based on an operational period of approximately 50 hours rather than the plaintiff’s
invoiced 434 hours.298 However he noted he was unaware of what constraints were
placed on the plaintiff in carrying out the exercise.299 He explained in evidence that
he regarded 50 hours screening plant operation as being appropriate for a “single
campaign”.300 By that he acknowledged he assumed such a campaign would
involve a stable and established processing regime in which the methodology to be
applied is well known and well settled.301 His report acknowledged:
“The optimum methodology can only be developed on site by trying
different methodologies and trialling (by screening and analysing
samples) each methodology to determine which provides the
optimum result.”302
[201] It is noteworthy that even Mr Prentice’s own estimates of screening time required, as
evidenced in his emails in this era, far exceed the modest 50 hours referred to by Mr
White.303
[202] In any event it is not suggested the hourly rates in fact charged for screening as with
the other works departed from the rates to which the defendants had agreed.
Slow down in payments
294 Ex 3 p 317.
295 Given the invoice sequence and the date of the email offering storage (6/11/09) it must be that this
date involves backdating. The invoice is unlikely to have been issued earlier than early December
2009.
296 Ex 5, 6.
297 Ex 1 pp 10, 12.
298 Ex 1 p 13.
299 Ibid.
300 T6-20 L47.
301 T6-21 LL1-6.
302 Ex 1 p 19.
303 Ex 3 pp83 (30 days), 84 (26 days).
-- 41 of 55 --
42
[203] The first three invoices were paid comfortably within seven days. Some delay in
payment of the invoices then commenced. Only part of invoice 4 was paid within
seven days. It took 24 days to pay invoice 5 although invoice 6 was issued and paid
in the intervening period. None of invoice 7 was paid within time and the final
payment of it occurred on 10 November 2009, almost a month after it had been
issued. Invoice 8 was also paid on 10 November 2009, which was a fortnight after it
was due for payment. It was the last of the invoices paid.
[204] In explaining the delay in the payment of invoice 7 Mr Prentice explained
Agripower was experiencing a cash flow problem. He said:
“We were just balancing some cash flow because the GST office of
the Tax Office had come in and just done an audit and it held up
three months—three or four months of payments back to us which I
think was about—in total, about $400,000 whilst they did the audit
and then, when the audit was completed, they found nothing wrong
and didn’t reimbursement us, as they would’ve normally done, all the
money.”304
Non-payment of invoices
[205] Invoices 9, 10 and 11 were not paid. It is beyond doubt that day dockets recording
hours worked were generated and that they were signed by Ivar Storronning in
respect of the work claimed in unpaid invoices 9 and 10. Invoice 11 falls into a
different category in that it sought advanced payment for storage at the Uramo shed,
which of its nature would not have generated supporting day dockets.
[206] The total number of working hours invoiced for invoice 9 was 486 hours. The total
number of hours invoiced in invoice number 10 was 883 hours.
[207] Consideration of some examples of the long hours of work described in the day
dockets giving rise to invoices nine and ten is instructive.
[208] Examples of the type of work described in the day dockets relevant to exhibit nine
are:
“load screen sought out over size”
“load screen off white and stack and test”
“load screen and stack ore”
“load screen and bagging blend”
“load bagging unit and screen”
“bag product”
“load and blend product”
“screening plant ore”
“screening plant/white ore”
“load screen and stack product”
“load screen off white”
“load screen white”
“screening plant and test mix”
“white and off white”
“take load of product to Uramo shed”
304 T4-41 L10.
-- 42 of 55 --
43
“load to Uramo”
“grade and dry ore”
“tractor/rotary hoe over size”
“grade out off white/over size”
[209] Examples of the type of work described in the day dockets relevant to exhibit ten
are:
“load Uramo w/house”
“grade/dry ore”
“bagging plant”
“screening and stacking ore”
“bagging and blending product”
“bagging plant blend and load truck”
“load and blend load truck”
“load screen shift over size and fines”
“blend/load bagging plant/load truck”
“bagging plant”
“load screening plant”
“load screen/bagging plant”
“screening plant ore”
“screening off white ore”
“grade out and dry ore”
“load of product w/house Uramo”
[210] The duration and nature of the work being performed at the defendant’s work site,
inclusive of the conveying of product away from that site for storage, strongly
supports the conclusion that the defendants were, at the time the work was being
performed, well aware of it being performed and satisfied with the nature of the
work being performed. That conclusion is further supported by the fact that the
defendants’ Mr Storronning, the supervisor of the work being performed, signed the
work dockets which recorded the performance of the work.
The end of the business relationship
[211] Mr Coleman testified that he raised the apparently late payment of invoice number
nine several times with Mr Prentice and Mr Storronning305 but kept working, on the
strength of the promise of being paid.306
[212] According to Mr Prentice he became concerned that for the number of invoiced
hours of screening insufficient product was being processed.307 Further he was
concerned that invoice 9 included charges for items of plant that he thought were
included within the screening fee.308 When asked if he took those matters up with
Mr Coleman he responded:
“I took it up with John in phone calls and then I said to John we’ve
got to get together on this and I flew up to meet John … I sat down
305 T3-34 L7.
306 T3-34 L8.
307 T4-62 L35.
308 T4-63 L5.
-- 43 of 55 --
44
with John the whole day and we went through many, many issues to
do with screening and bagging and his costs.”309
[213] He gave evidence that this get together occurred at Mr Coleman’s home on 25
November 2009 and that he took hand written notes that were later typed up and
emailed by Mr Prentice to Mr Coleman and Mr Storronning on 1 December 2009.310
Mr Prentice cannot locate those hand written notes.311 In the course of recounting
what was said at the meeting Mr Prentice testified:
“I think just before I left he said to me that can we get these
invoices—this invoice paid which is this one that was outstanding,
and I—that’s when I turned to him and I said, well, look, let’s work
it out and—with the numbers. I was expecting him to re-issue a new
invoice to delete the grader and the loader hires and to adjust the
screening plant, and he was to give me an explanation of what they
were doing with the screening plant because, at the meeting, he
couldn’t provide an explanation of why all the hours on the screening
plant—which were now in excess of 200 hours—and the costs were
just getting out of control to screen. And until we got that, I wasn’t
prepared to pay the invoice.”312
[214] This evidence presented as hindsight reconstruction. The effect of Mr Prentice’s
evidence was to represent there were such problems with the state of invoice number
9 that he arranged to meet with Mr Coleman about it. Yet Mr Prentice’s purported
record of the meeting, which he swore was a true reflection of what happened at the
meeting,313 makes no material reference to the supposed problems with the content
of the invoice as rendered.
[215] Mr Coleman explained that after the issue of invoice ten he had significant expenses
which had built up in the course of providing his business’s services to the
defendants.314 He told Mr Prentice and Mr Storronning that he needed to be paid
because he did not have sufficient funds to continue.315
[216] Mr Coleman secured an on-site meeting with Mr Storronning on about 1 December
2009. He informed Mr Storronning that, on account of the non-payment, his
business was withdrawing and he gave instructions for the removal of his business’s
machinery from the work site.316 Mr Prentice recalls receiving a telephone call from
Mr Storronning on 1 or 2 December 2009 and being informed that Mr Coleman was
packing up his plant and leaving.317
[217] On 2 December 2009 at 9.05am Mrs Coleman emailed Mr Prentice saying:
“So sorry to hear about the fallout with John, it’s a shame for
everybody.
309 T4-63 LL8-15.
310 T4-63 LL26-47, Ex 3 pp 121-127.
311 T4-64 L41.
312 T4-63 LL18-26.
313 T4-64 L7.
314 T3-34 L10.
315 T3-34 L13.
316 T3-34 L35.
317 T4-64 L17.
-- 44 of 55 --
45
I do need to ask about the shed and invoice 9 though do you still
want the product in the shed at Uramo, if so when will the agreement
be ready, if not when will the product be removed? Can I please get
invoice 9 paid today? I’ll have the final invoice ready for you later
on today.
I wish you luck with the whole project, you have a worthwhile
product that will come through for you.”318
[218] In his responding email of 3 December 2009 Mr Prentice wrote, inter alia:
“I think in view of the circumstances it is best we remove all the bags
from your shed and store them elsewhere, so there is no possible
issue arising in the future. My priority at the moment is to get all
those bags at site into storage, then we will collect bags from your
shed and thus we will need some time and weather on our side. As a
guide there are between 850 and 900 bags at your shed and this is
around 11 truck loads using triples. I hope to have it all out before
Christmas.
In view of the situation what I want to do is get a final account which
includes, say leaving the bags in storage until the end of December,
agree that final account and at payment we also execute a deed of
release. We agree it all, pay it, sign it, it’s all done.”319
[219] On Mr Coleman’s account he was present when his lawyers subsequently
telephoned Mr Prentice about the outstanding money and Mr Prentice responded
“you tell the bastard he’ll have to fight for it if he wants money”.320 It appears from
the content of an email to Mr Coleman by Mr Prentice referring to receiving a call
from Mr Coleman’s lawyer that the call must have happened on Friday 4 December
2009.321 On Mr Prentice’s account of this conversation he told Mr Coleman’s
solicitor that he was waiting for Mr Coleman to get back to him with a
“reconciliation” of the high costs in invoice 9.322
[220] I do not accept that at the time Mr Coleman withdrew his services Mr Prentice was
genuinely waiting for Mr Coleman to come back to him with a modification of
invoice 9. The likely true position is that by this time it had become obvious that the
operation was costing more than Agripower could immediately afford to pay for and
Mr Prentice had become emboldened by his knowledge of Coleman’s financial
pressures.
[221] On Mr Prentice’s account Mr Coleman had revealed in the very first phone call
between them that he was under financial pressure because he no longer had work
with Kagara Zinc.323 Mr Prentice testified Mr Coleman wanted to be paid “early and
quickly” so that “he would have a cash flow that could ensure that he continue with
everything”.324
318 Ex 3 p 133.
319 Ex 3 p 134.
320 T3-78 L28.
321 Ex 3 p 141.
322 T4-65 LL25-45.
323 T4-39 L5.
324 T4-39 L8.
-- 45 of 55 --
46
[222] Mr Coleman’s business had been financed with Landmark bank, but its lending
affairs were taken over by the ANZ bank. Mr Coleman wanted to use the ANZ bank
for his finances but could not do so because he could not sufficiently clear his debts
because he could not get paid.325 Mr Coleman’s business was eventually financed
with Elders.326
[223] Mr Coleman accepted in cross-examination that he had asked Mr Prentice to provide
him with a letter to show the bank about how long the mine business was going to
last for and what the Colemans could expect.327 Mr Prentice explained his letter of
22 September 2009328 was the “fairly bullish letter” he had prepared in response to
that request.329
[224] Mr Prentice explained that Dianne Coleman subsequently made arrangements for
him to talk to a person called Garry at Bankwest with whom Coleman Contracting
was apparently having discussions about finance.330 While Mr Coleman recalled
there was a need for them to utilise a bank broker he had little other relevant
recollection on this point.331 Mr Prentice recalled that he did indeed speak to a
person called Garry at Bankwest confirming the effect of what he had written in his
letter of 22 September 2009.332 He thereafter emailed Dianne Coleman on 16
October 2009, writing:
“I spoke to Garry from Bankwest last night and he would like me to
do a letter for you.
I would like to go through with you over weekend so just give me a
call.”333
[225] Mr Prentice received an email from Dianne Coleman on 18 October 2009 in which
she thanked him “for talking to Garry from Bankwest”.334
[226] Against this background it seems likely Mr Prentice judged Mr Coleman was
sufficiently desperate that Coleman Contracting would continue to provide their
services despite the long delay in payment for services rendered. He misjudged Mr
Coleman.
The retention of product at Uramo
[227] In an email of 3 December 2009 by Mr Prentice to Dianne Coleman, Mr Prentice
indicated that in that “in view of the circumstances” his business proposed to
remove all of the bags from the Coleman Uramo shed by Christmas.
[228] Mr Coleman refused Agripower access to the property to remove the bags stored
there, exercising a lien over them because he was owed money.335
325 T3-65 L15.
326 T3-65 L27.
327 T3-64 L22, T3-65 L10.
328 Ex 3 p 25.
329 T4-42 L21.
330 T4-42 L25, T4-43 L16.
331 T3-65 L35.
332 T4-42 L27.
333 Ex 28.
334 T4-44 L28, Ex 29.
335 T3-61 L19, T4-70 L13, T4-71 L1.
-- 46 of 55 --
47
Condition of the product at Uramo
[229] Mr Prentice testified that there were approximately 692 bags of product at Uramo.336
[230] Mr Coleman acknowledged that some bags delivered to Uramo had not been moved
into the storage shed and were left sitting outside when Coleman Contracting ceased
working because the business had not been paid.337 Mr Coleman acknowledged an
awareness of the adverse effect of weather exposure upon diatomaceous earth but
explained he was unconcerned by that when he was not being paid.338
[231] Mr Prentice explained it took a couple of years before Agripower could get access to
the bags stored at Mr Coleman’s property when arrangements were made for expert
David Chadwick to assess the product stored there.339 In the meantime the CHEP
pallets on which the product had been stored were bought by Agripower because it
had become too expensive to continue to lease them over that period of time.340
[232] Mr Prentice testified that when the product at Uramo was examined it had a lot more
lumps in it than the Charters Towers product did,341 although the examination of the
Uramo product occurred long after the examination of the Charters Towers product.
[233] An examination of the bags stored at Uramo Station was conducted by David
Chadwick, a consultant in industrial minerals, on 4 November 2011. He noted a
total of 660 bulk bags each stored on pallets within the shed in addition to 32 full
bags and two half full bags of product stored on pallets on the ground outside the
shed.342 He purported to conduct a representative sampling of the bags.
[234] He noted there was water damage to the row of bags stored towards the edge of the
shed with probable water damage to the top of bags extending back three or four
rows from there.343 It also appeared bags within the weather affected area had
probable UV degradation.344 About 5% of the bags had suffered rodent chew
holes.345 He noted the entire product stored unprotected outside the shed was
unusable because of water and UV damage.346
[235] Mr Chadwick noted where there had been water ingress into bags that had resulted
in the top 20 millimetres being cemented together.347 Mr Chadwick explained that
after digging through that layer of clumping there was very little clumping beyond
about 150-200 millimetres into the profile of the bag thus suggesting it was the
product of ingress of water.348 He accepted it would have been preferable to have
taken samples from the full depth of bags but that was not practicable.349
336 T5-3 L20.
337 T4-4 L37-T4-5 L3, L42.
338 T4-6 L5.
339 T4-71 LL1-10.
340 T4-71 L38-T4-72 L2.
341 T6-10 L10.
342 Ex 39 p 4.
343 Ex 39 p 14.
344 Ibid.
345 Ibid.
346 Ibid.
347 Ex 39 p 11.
348 T5-65 L32.
349 T5-58 L4.
-- 47 of 55 --
48
Presence of oversize granules in processed product
[236] Mr Prentice testified that a number of bags supplied to Hortus were found to be
deficient, apparently rejected by their customers because there was too much
oversize earth in the bags causing their fertilizer spreading equipment to jam.350
[237] That hearsay evidence was apparently based on the hearsay evidence of Mr Smith of
Nutrifert who gave evidence of what he had been told by customers who had used
Agripower’s product. Mr Smith deposed in an affidavit:
“I recall that at least two customers of Nutrifert (which to the best of
my recollection is likely to have been Elders Bundaberg and Hoy
Boys Gordonvale) advised that Agripower’s product contained larger
particles of 10mm-20mm and other foreign rock material, and that on
at least one occasion, as a result of these particles being out of
specification, the drive shaft of their spreading equipment had broken
and the customer would not use the product again.
I therefore contacted Peter Prentice of Agripower, advising him of
the issues faced by Nutrifert’s customers.”351
[238] According to Mr Smith’s affidavit’s tabular record of when the product was
supplied, the entry for Elders recorded only generally a supply of 22 bags during
“2009-2011” and the entry was qualified by the possibility that a proportion of those
sales included product from the Barraba New South Wales mine site. The same
table recorded in respect of Hoy Boys that 12 bags had been supplied on 17 June
2011.352 Mr Smith deposed that Nutrifert did not itself inspect the product supplied
to Nutrifert’s clients.353
[239] The above vagaries in evidence were rendered less troubling when, in advance of the
trial, Mr Smith extracted and photographed some larger granules from some old
bags of product he had received from Agripower.354 His photograph shows a
number of granules within the 10-20mm range.
[240] In a similar vein a sample of bagged product produced in the process with which this
trial is concerned was taken by current Agripower site senior executive Lee-Anne
Gossage and tendered in evidence. It is apparent from that sample that some
granules exceed 6 millmetres in size.355
[241] Mr Chadwick also examined a representative sample of the bags in the Uramo shed
for product clumping and consistency. He found only small volumes of oversized
materials, in the order of 20 noted lumps larger than 20 millimetre clay clods across
all bags inspected.356 He also found of the representative sample examined that it
had excessive fine content less than 2 millimetres.357 Mr Chadwick acknowledged
that in the testing process some of his personnel had stood upon some of the bags
but did not consider that would have tended to crush the underlying product.358
350 T4-19 L37, T4-73 L39.
351 Ex 41 [8, 9].
352 Ex 41 [6].
353 Ex 41 [5].
354 Ex 42.
355 Ex 44.
356 Ex 39 p 11.
357 Ex 39 p 14.
358 T5-57 L31.
-- 48 of 55 --
49
[242] Agricultural consultant John Kilpatrick examined samples of diatomaceous earth
taken from the bags stored at Uramo station on 9 September 2011. His examination
of the samples revealed that 73.2% of product was within the required size with
13.2% being oversized and 13.6% being fines. He expressed the unchallenged
opinion that fines are inevitable with the movement of any product of this kind. As
to the oversize samples detected by him he opined they were not aggregates of two
or more smaller pieces and had not formed since the bags were put in the shed at
Uramo. Rather he opined they were in the product when it left the grading and
bagging plant near the mine.359
[243] Benjamin White, an expert witness engineer, noted Mr Kilpatrick’s view that the
coarser oversized particles could not have formed past the screening operation. He
observed of Mr Kilpatrick’s photographs that the oversize material appeared to be of
a constant size rather than a range of sizes. This led Mr White to doubt that the
oversize product was a result of general contamination and observed, without being
able to make a definite conclusion, that the oversize product may have been the
result of the coarse screen on the screening plant letting through product greater than
6 millimetres and potentially in the order of 10-12 millimetres in size.360
[244] The evidence of Mr Smith affirmed the importance of granular size not being more
than 6 millimetres and explained why bagged product containing such oversize
grains was not fit for purpose and unsaleable. While it is to be doubted whether
such product is thus rendered valueless it is clear that it is not fit for sale for its
intended purpose.
Survey
[245] On Mr Prentice’s account of the reconciliation arrangement with Coleman
Contracting there was supposed to be a survey at the conclusion of the works by
Coleman Contracting. Mr Prentice explained the commissioning of the survey was
delayed because Agripower was caught up with the screening operation and then Mr
Coleman’s departure.361
[246] It appears the actual survey was not conducted until 6 and 7 October 2011.
Curiously there is little foundational evidence about that process before the Court.
[247] Mining engineer Daniel Chippendale examined data including a survey of the
mining pit and stock pile which had apparently been conducted by Lester Franks on
6 and 7 October 2011. The surveyor was not called. Mr Chippendale concluded
that the volume of earth mined from the pit below the indicated diatomaceous earth
horizon was 12,632 banked cubic metres.362 It is unfortunate that there is no
evidence as to where that horizon was identified as commencing. It will be recalled
the diatomaceous earth in the vicinity commenced considerably deeper than the two
metre depth referred to in the plan of operations.
[248] The report of the defence expert mining engineer Benjamin White made some
calculations based on the survey information and quantified mined diatomaceous
earth at 12,560 banked cubic metres. However Mr White appeared to rely upon a
359 Ex 7 p 6.
360 Ex 1 p 20.
361 T4-38 L4.
362 Ex 2.
-- 49 of 55 --
50
30% inflation of that figure to arrive at a calculation of mined diatomaceous earth in
loose cubic metres of 16,328. The premise for that inflation of the figure appears to
be data contained in a report by an entity called DHB which is also not in evidence.
Mr White also had regard to an assumed quantity of diatomaceous earth screened,
again based on an assumption in DHB’s report which is not in evidence.
[249] Assuming for the moment that those matters had been properly proved, Mr White
concludes that of a total mined quantity of diatomaceous earth of 16,328 loose cubic
metres some 7,006 loose cubic metres is unaccounted for once allowance is made
for what was processed and what remained stock piled.
[250] There is every real possibility that this alleged shortfall remains in various forms at
or near the mine. As Mr White acknowledged there is an ever present prospect of
product being wasted throughout the handling process. Further it will be recalled
the diatomaceous earth was used to top dress the lengthy road built by Coleman
Contracting. A final variable is that it is unknown whether what the survey assessed
to be the commencement of the layer of diatomaceous earth is the same point at
which those excavating the pit considered that they were removing diatomaceous
earth as distinct from overburden.
[251] I accept Mr Coleman had no knowledge of the fact or cause of any discrepancy in
the quantity of mined product compared to what has been accounted for.363
[252] The defendants have not proved on the balance of probabilities that there exists a
material quantity of unaccounted for product.
E. Did Coleman Contracting terminate unlawfully?
[253] I have found Mr Prentice and Mr Coleman agreed that Coleman Contracting’s
performance of the mining and processing works would be performed by Coleman
Contracting and paid for by Agripower on the same basis as agreed in respect of the
roadwork, namely with Coleman Contracting’s known hourly rates to be charged for
various plant and machinery used and payment to be made within seven days of
invoice. As to the controversy in this case as to the rate of screening throughput I
have accepted the hourly rate agreed to for screening was not conditioned upon any
particular rate of throughput.
[254] The system of submitting the day docket records of the hours worked for
verification by Agripower’s site supervisor also continued. That subsequent conduct
supports the inference that the conditions of the previous contractual arrangement
persisted under the agreement relating to mining and processing.364
[255] Coleman Contracting terminated the contract by withdrawing its services on or
about 1 December 2009. At that time invoice 9, issued on 10 November 2009 and
due for payment 17 November, remained unpaid. It was long overdue despite
repeated requests for its payment.
[256] Invoice 9 was calculated in accordance with the hours of work recorded in the day
dockets which had been verified by Agripower’s site supervisor.
363 T4-14 L22.
364 Australian Energy Ltd v Lennard Oil NL [1986] 2 Qd R 216, 237; Winks v WH Heck & Sons Pty Ltd
[1986] 1 Qd R 226, 238.
-- 50 of 55 --
51
[257] There existed no legitimate basis for Agripower to avoid its prima facie liability to
pay the invoice pursuant to its contract with Coleman Contracting. Agripower’s
failure to pay invoice 9 constituted a clear breach of a fundamental term of the
contract between it and Coleman Contracting.
[258] In consequence of that breach, Coleman Contracting was entitled to terminate. That
it did by withdrawing its services. I find Coleman Contracting’s termination of the
contract by withdrawal of its services was lawful and Coleman Contracting was not
in breach of the contract.
[259] It will be recalled the wrongful termination and breach alleged against Coleman
Contracting was the foundation for the loss of profits counterclaim in respect of the
subsequently weather ruined stockpiled quantity of diatomaceous earth at the site. It
follows that feature of the counterclaim must fail.
F. Does the unaccounted for mined earth evidence a breach by Coleman
Contracting?
[260] It will also be recalled the defendants claim a large amount of mined diatomaceous
earth has in effect gone missing. They allege the plaintiffs mined and removed that
earth, not stockpiling or processing it and it remains unaccounted for. This is said to
be a breach of contract.
[261] This component of the counterclaim fails in several ways.
[262] Firstly it has not been proved it was a condition of the contract that Coleman
Contracting had an obligation to account for the whereabouts of the entire product it
mined. Coleman Contracting was not in control of the site. Its work was performed
under the supervision of Agripower’s site supervisor. Under that supervision it
moved mined product to a variety of locations, depositing it in some instances,
namely road layering, in such a way that the volume deposited could not practicably
be determined after the event. It performed its work at an hourly, not volumetric
rate. Against that background it cannot reasonably be implied it had any obligation
to account for the volume of mined product.
[263] Secondly I am not satisfied on the balance of probabilities that mined product is in
fact unaccounted for. There are several reasons for this, beyond the improbability of
clandestine removal of product. As already discussed, the amount of product
allegedly surveyed as mined has not been properly proved. That is because of the
absence of foundational evidence as to the amount alleged, including of the survey,
of the starting depth at which diatomaceous earth was extracted and of the bulking
factor. However, even if these problems of proper proof are ignored, the alleged
amount is not so large that it cannot be plausibly accounted for by reason of spillage
and deposition in unsurveyed locations, particularly the lengthy road.
G. Is Coleman Contracting responsible for loss occasioned by the unsaleable
quality of the bagged product?
[264] A feature of the defendants’ case which I have accepted is that the bagged product
had oversized granules, with the consequence that all of the bagged product which
was distributed to market as well as the bagged product which remained stored at
Charters Towers and Uramo by Agripower was not fit for sale. Agripower alleges it
-- 51 of 55 --
52
was deprived of the profits it would have made if the bagged product did not have
oversized granules.
[265] In this context it can be seen the damage occasioned to some of the bagged product
stored at Uramo through exposure to the elements is irrelevant. The product was not
fit for sale in the first place because of the presence of over-sized granules. If that is
not the fault of the plaintiffs they can hardly be held liable to pay damages in respect
of that which on the defendants’ own case is valueless.
[266] It will be recalled that in the final rushed days when Mr Prentice wanted longer
hours worked some product was screened and bagged by staff employed by
Agripower. This introduces an obvious difficulty for the plaintiff in attributing sole
blame and thus full responsibility for loss associated with the presence of oversized
granules upon Coleman Contracting. However a more fundamental difficulty
confronts the defendants.
[267] If it is assumed for the sake of argument that Coleman Contracting’s staff had been
the sole workers carrying out screening and bagging the critical issue is whether the
presence of oversized granules was a result of the plaintiff’s failure to exercise due
care and skill in its processing, particularly its screening and bagging, of the
diatomaceous earth. I do not accept that it was.
[268] The oversized granules either entered the bagged mix because of contamination
from the way product was moved about at site or because the screening plant was
unintentionally configured to permit a larger granule range than 6 millimetres. The
latter is most likely, and is the cause I infer, given the apparent consistency of the
oversized granules found in samples of processed product. That is, the screening
plant was configured so as to allow a bigger size granule than desired.
[269] As my earlier fact finding demonstrates, the screening and bagging process was
settled upon at the direction of Mr Prentice and was supervised by him and Mr
Storronning. More importantly it was Mr Prentice and Mr Storronning who were
actively involved in supervising and testing in the early days of the screening
operation. It must be that they did not test granular size adequately or at all. It may
be they did not appreciate the low degree of tolerance in the market place for
granules exceeding 6 millimetres. Also much of the documentary evidence of
communication in this era suggests the probability that Mr Prentice was likely more
concerned to test in respect of bulk density. Had they tested grain size properly they
would have detected the difficulty and, assuming they knew the market would
tolerate no margin for error, it would have been addressed.
[270] On the evidence it was not Coleman Contracting but Agripower which assumed
responsibility for testing the screened product when the screening process was being
established. This bespeaks the true allocation of responsibility in the environment in
which Coleman Contracting was working.
[271] Coleman Contracting was working under the direction and supervision of a principal
that assumed for itself the responsibility of controlling and testing the adequacy of
the screening process that it wanted Coleman Contracting to carry out. Coleman
Contracting’s obligation was to exercise no more than the care and skill an ordinary,
competent contractor would be expected to apply or exercise in carrying out that
-- 52 of 55 --
53
process,365 set by its principal. There is no evidence that Coleman Contracting did
not carry out the process as settled by Agripower. The problem with grain size was a
product of the process settled by Agripower and not a failure of care and skill on the
part of Coleman Contracting.
[272] It follows this feature of the counterclaim must also fail.
H. Is Agripower liable to pay the whole of invoices 9 and 10?
[273] Invoices 9 and 10 were both rendered in accordance with the agreement with
Agripower. I have rejected Mr Prentice’s allegation the agreement was qualified by
a reconciliation agreement.
[274] The invoices charged the known rates for hours of work verified in the day dockets
as performed by Agripower’s site supervisor. There is no credible evidence that the
hours claimed were not actually worked.
[275] The defendant’s point of particular complaint related to the large number of hours
charged in respect of screening. The complaint in essence is that the hours charged
are excessive and unreasonable in proportion to the amount of product screened.
However I have found that the agreement was not conditioned upon any particular
rate of screening throughput being delivered.
[276] Coleman Contracting had screened gravel before but never diatomaceous earth, as
Mr Prentice well knew. As the evidence shows, diatomaceous earth has quite
different properties from gravel. As much was demonstrated when the moist clayish
off white product, which Mr Prentice wanted to screen and mix in dominant
proportion to the white product, caused particularly significant interruptions to the
screening process. Coleman Contracting was new to this endeavour. It would have
been surprising if Coleman Contracting did commit to a volumetric throughput.
[277] The agreement was process not outcome oriented. That is, it was premised on the
performance of screening work at an hourly rate with the process being supervised
by and subject to the direction of Agripower.
[278] That in the end result there was a large number of hours worked for screening is a
product of the trial and error nature of Mr Prentice’s management of this infant
operation. It is not to the point that less screening hours, perhaps significantly less
hours, may have been required had Agripower chosen from the outset to expend
more money on expert services and plant and be in less of a rush to trial a
substantive production run before the wet.
[279] The amounts claimed in invoices 9 and 10, a total of $238,031, were debts properly
claimed and should be paid, plus interest, by Agripower.
I. What if any amount should Agripower pay for storage at Uramo?
[280] The plaintiffs claim for payment for payment in respect of the Uramo shed confronts
the obstacle that a lease agreement was not entered into. As Mr Coleman candidly
365 In contrast to an obligation to produce a result, a contrast discussed in Roluke Pty Ltd & Anor v
Lamaro Consultants Pty Ltd & Anor [2008] NSWCA 323 [77].
-- 53 of 55 --
54
acknowledged he agreed to move bagged product into his shed without ever
securing the agreement Mr Prentice repeatedly promised but did not deliver.
[281] Nonetheless I have found the defendants did request that Coleman Contracting move
bagged product into its Uramo shed and bagged product was undoubtedly moved
and stored there. Even Mr Prentice accepted it was not intended the bags be stored
there without charge.
[282] In the circumstances it is unnecessary to determine whether Agripower took
possession of the shed under a tenancy at will or stored its product there under a
licence. Under either it is the rate and period of remuneration for either benefit
which is the important determination to make.
[283] As to rate, the defendants well knew in electing to store product at the Coleman’s
shed that a rate of $110,000 including GST per annum had been quoted. They were
aware of the size of the facility and implicitly its worth to them. They had not at any
stage suggested a different rate. However there had been no agreement reached as to
the duration of the lease or licence.
[284] It will be recalled the plaintiffs prevented the defendants from recovering their
product, exercising a lien because of the non-payment of invoices.
[285] The plaintiffs accept that their remuneration should be limited to one quarter of a
year, $27,500, the amount of invoice 11. That is they do not press their claim for a
second quarter’s worth of remuneration. That is because they accept they are not
entitled to charge for remuneration for storage while the lien was being asserted.366
[286] There was no concluded agreement as to the duration of the storage period but, as I
have found, the defendants embarked upon the storage acknowledging payment
would be made quarterly.
[287] While the defendants sought to recover their stored bags prior to the conclusion of
the quarter, I find there was agreement between the parties that the payment for
storage when it commenced was at a minimum to be payment calculated at one
quarter of $110,000, that is $27,500.
[288] The second defendant is liable for that amount, plus interest.
[289] As to the due date of the payment for assessment of interest purposes, I am not able
to infer there was any agreement that the quarterly payment ought, as the plaintiffs
sought, be paid in advance. At the latest though the amount was due by 1 February
2010.
J. Conclusion
366 Plaintiff’s outline [219].
-- 54 of 55 --
55
[290] There should be judgment for the plaintiff against the second defendant in the
amount of $265,531 plus interest. It is desirable that the parties be heard as to the
quantification of interest on that amount.
[291] In light of my findings the plaintiffs’ claim as against the first defendant and the
counter claim should be dismissed.
[292] The parties should be heard as to costs.
K. Orders:
[293] My Orders are:
1. Judgment for the plaintiff against the second defendant in the amount of
$265,531 and interest thereon to be determined.
2. The counterclaim and the claim as against the first defendant are
dismissed.
3. I will hear the parties as to the quantification of interest and as to costs.
-- 55 of 55 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2015/118