Barry Pitt Constructions Pty Ltd v Smith & Anor [2015] QCAT 526
CITATION: Barry Pitt Constructions Pty Ltd v Smith & Anor
[2015] QCAT 526
PARTIES: Barry Pitt Constructions Pty Ltd
(Applicant)
V
Shane Harold Smith
Agnieska Smith
(Respondent)
APPLICATION NUMBER: BDL037-13
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Hughes
DELIVERED ON: 23 December 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. Shane Harold Smith and Agnieska
Smith are to pay to Barry Pitt
Constructions Pty Ltd the sum of
$3,797.25 by way of interest by 27
January 2016.
2. Shane Harold Smith and Agnieska
Smith are to pay to Barry Pitt
Constructions Pty Ltd, within 28 days
of agreement or assessment as
applicable, its costs of:
(a) the application (including their
remission by the Appeal Tribunal by
its order dated 9 December 2014 in
APL085-14) on an indemnity basis
calculated on the District Court Scale,
to be agreed, or absent agreement to
be assessed by Hickey & Garrett Legal
Costs Assessors, Level 21, 141 Queen
Street, Brisbane; and
(b) any assessment.
-- 1 of 7 --
2
CATCHWORDS: BUILDING DISPUTE – INTEREST – where
liquidated claim for progress payments – where
Tribunal may award interest at rate specified by
contract – where no basis to award interest for
adjustments and variations - COSTS – where
general rule that successful party is entitled to
costs in building dispute – where essential
element of counter-claim not proven – where
counter-claim dismissed in entirety – where
Tribunal awarded applicant full amount of claim
– where applicant wholly successful - whether
indemnity costs to be awarded – where parties
contractually agreed on basis to recover costs
and therefore appropriate to enforce terms of
contract to recover costs on ‘solicitor and own
client’ or indemnity basis
Civil Proceedings Act 2011, ss 5, 58, 59
Domestic Building Contracts Act 2000, ss 30,
66, 92
Queensland Building Services Authority Act
1991, s 77
Queensland Building Services Authority
Regulation 2003 (Qld), s 34B
Queensland Civil and Administrative Tribunal
Act 2009, s 107
A L Builders Pty Ltd v. Fatseas (No. 2) [2014]
QCATA 319
Ascot v. Nursing & Midwifery Board of Australia
[2010] QCAT 364
Baque v. Rivergum Homes Pty Ltd [2013]
QCATA 200
Barry Pitt Constructions Pty Ltd v. Smith & Anor
[2014] QCATA 339
Barry Pitt Constructions Pty Ltd v. Smith & Anor
[2014] QCAT 025
Commonwealth v. Verwayen (1990) 170 CLR
394
Contrast Constructions Pty Ltd v. Bartlett [2014]
QCATA 262
Faulks v. New World Constructions Pty Ltd (No.
2) [2014] QCAT 329
Glamoren Pty Ltd v. Lee & Anor [2012] QCATA
176
Hughes v. Metropolitan Railway Co. (1877) 2
-- 2 of 7 --
3
App Cas 439
Lyons v. Dreamstarter Pty Ltd [2012] QCATA
71
Stuart Homes and Renovations v. Denton &
Anor [2012] QCAT 43
Tamawood Ltd v. Paans [2005] 2 QdR 101
APPEARANCES:
This matter was heard and determined on the papers pursuant to section 32 of
the Queensland Civil and Administrative Tribunal Act 2009.
REASONS FOR DECISION
What is this Application about?
[1] Barry Pitt Constructions Pty Ltd successfully recovered $74,431.50 for
building work done for Shane Harold Smith and Agnieska Smith. Mr and
Mrs Smith did not succeed in their counter-claim against Pitt for defective
works and delay.
[2] The Appeal Tribunal then set aside the Tribunal’s decision not to award
interest and costs to Pitt and remitted those issues to the Tribunal for
determination according to law.
[3] Having received submissions from the parties, the issue for the Tribunal to
decide now is whether to award interest and costs to Pitt.
Preliminary matters
[4] In their submissions, Mr and Mrs Smith challenged the Tribunal’s
jurisdiction to award costs on the basis that because the contract was not
signed, it was not a ‘regulated contract’ and therefore the application is not
a ‘building dispute’1. They also argued that the fixing stage amount of
$50,000.00 exceeded the allowable percentage of the contract price.2
However, the failure by a builder to sign a contract or otherwise comply
with a requirement of the Domestic Building Contracts Act 2000 (Qld) does
not make the contract illegal, void or unenforceable.3 The Tribunal
therefore has jurisdiction.
[5] Alternatively, Mr and Mrs Smith submitted that the evidence before the
Tribunal proves that the contract relied upon by Pitt does not exist. They
also claimed that no interest is payable because practical completion was
not attained and therefore the amounts awarded cannot be due under the
contract. However, Mr and Mrs Smith previously did not dispute that Pitt
1 Queensland Building Services Authority Act 1991 (Qld), definition of ‘domestic building
dispute’; Domestic Building Contracts Act 2000 (Qld), s 30.
2 Contrary to Domestic Building Contracts Act 2000, (Qld) s 66.
3 Domestic Building Contracts Act 2000 (Qld), s 92.
-- 3 of 7 --
4
was entitled to $70,000.00 for progress payments, subject to any set off
for compensation for the cost of any rectification work, cost to complete
and damages for delay. Mr and Mrs Smith also counter-claimed for
various defects, incomplete works and delay.
[6] In these circumstances, Mr and Mrs Smith are estopped from denying the
existence of a contract and the attaining of practical completion – the
basis of their claim for damages for delay - for the purposes of determining
interest and costs. Mr and Mrs Smith are unable to deny the existence of a
contract and completion of work not previously disputed.4
[7] Mr and Mrs Smith also filed additional late submissions5 contrary to the
Tribunal’s Directions, about the conduct of Pitt during these proceedings
and various items of evidence, after the decision of the learned Member.
These submissions were not relevant to the issues for me to determine:
interest and costs.
Should Mr and Mrs Smith pay interest to Pitt?
[8] As noted by the Appeal Tribunal, it is not clear from the learned Member’s
reasons whether the sum of $74,431.50 arises from a contractual or
statutory entitlement. The learned Member dismissed those claims.
[9] The contract provided for progress payments at various stages of the
works. As noted by the Appeal Tribunal, neither party asserted that the
contract had been terminated and there is no reason why the claim of
$70,000.00 for the two progress claims should not be characterised as
collection of debts under the contract: they are claims for liquidated
amounts and not for damages.6 The Tribunal may therefore award interest
at a rate specified under the contract.7
[10] If the parties enter a contract and a rate is specified under the contract,
then that is the interest payable.8 The contract specified a rate of five
percent plus the annual rate equal to the Commonwealth Bank overdraft
index rate quarterly charging rate.9 In the absence of evidence of the
applicable Commonwealth Bank rate during the relevant period, Pitt seeks
a rate of five percent. That is appropriate given that it is the minimum rate
specified in the contract.
[11] Interest is payable on and from the day after the day the amount became
payable until the amount is paid.10 Mr and Mrs Smith paid the full amount
of the claim of $74,431.50 on 29 January 2014. The fixing stage progress
4 Hughes v. Metropolitan Railway Co. (1877) 2 App Cas 439, per Lord Cairns at 448;
Commonwealth v. Verwayen (1990) 170 CLR 394, per Deane J at [19].
5 First & Second Respondents’ Submissions In Reply On Costs And Interest filed 2 April
2015.
6 Barry Pitt Constructions Pty Ltd v. Smith & Anor [2014] QCATA 339 at [31] to [32].
7 Queensland Building Services Authority Act 1991 (Qld), s 77(2)(c); Queensland
Building Services Authority Regulation 2003 (Qld), s 34B(1)(a).
8 Contrast Constructions Pty Ltd v. Bartlett [2014] QCATA 262 at [74].
9 General Conditions, clauses 4.7, 32.1 and 37.
10 Queensland Building Services Authority Regulation 2003 (Qld), s 34B(2).
-- 4 of 7 --
5
payment of $50,000.00 was due and payable under the Contract by 7
December 2012.11 Therefore interest is payable on $50,000.00 at 5% p.a.
for 416 days from 8 December 2012 to 29 January 2014, being $2,849.31.
The practical completion payment of $20,000.00 was due and payable
before 17 February 2013 at the latest.12 Therefore interest is payable on
$20,000.00 at 5% p.a. from 17 February 2013 for 346 days, being
$947.94. Total interest on the progress claims therefore equates to
$3,797.25.
[12] The balance of $4,431.50 was awarded for adjustments and variations.
These could have been based on a statutory right or a contractual right.13
If statutory and not considered an award of ‘damages’, unlike the Courts14
the Tribunal does not have a wide statutory discretion to award interest.15
If contractual, the Tribunal may again award interest at a rate specified
under the contract as above.
[13] In the absence of an express finding of fact by the learned Member of the
basis for the award of $4,431.50, I am unable to award interest on this
amount. Even if the $4,431.50 was considered ‘damages’, in the absence
of an express finding by the learned Member of when each adjustment
and variation was payable, I am unable to find the amount for each
adjustment and variation was payable earlier than the day they were
ordered to be paid by the Tribunal, being 14 February 2014. As the full
amount of $4,431.50 for each adjustment and variation was paid by then,
no interest is payable on this amount.
[14] The total interest payable is therefore $3,797.25.
Should Mr and Mrs Smith pay costs to Pitt?
[15] The Tribunal may award costs when deciding a building dispute.16 This
confers a broad and general discretion on the Tribunal to award costs,
displacing the usual ‘no costs position’.17 The general rule in building
11 Affidavit of Shane Harold Smith sworn 18 June 2013 at paragraph 12(u) noted the
Fixing Stage Invoice dated 30 November 2012 that was not paid. Under Clause 4.5 of
the General Conditions, payment was due and payable within five working days of this
date.
12 Mr and Mrs Smith calculated their claim for liquidated damages from 12 November
2012 to 11 February 2013 - thereby implicitly conceding a practical completion date of
11 February 2013 - while Pitt conceded in its submissions that payment for practical
completion only became payable on 17 February 2013 when proceedings were
commenced.
13 Pursuant to the provisions of the Domestic Building Contracts Act 2000.
14 Civil Proceedings Act 2011, ss 58, 59 and s 5 definition of ‘court’.
15 Glamoren Pty Ltd v. Lee & Anor [2012] QCATA 176 at [18], per Wilson J.
16 Queensland Building Services Authority Act 1991 (Qld), s 77(3)(h).
17 Lyons v. Dreamstarter Pty Ltd [2012] QCATA 71 at [3] and unlike Ascot v. Nursing &
Midwifery Board of Australia [2010] QCAT 364 at [6] and [28] where Kingham DCJ
specifically applied the usual ‘no costs’ position in the absence of other provisions in
the relevant enabling Act and further noted considerations peculiar to review
proceedings in refusing to award costs against the unsuccessful party.
-- 5 of 7 --
6
disputes is that a successful party is entitled to recover its costs from the
other party.18
[16] Although the learned Member dismissed Pitt’s claim for costs on the
grounds that Mr and Mrs Smith were able to prove their case “at least in
part”,19 most of Mr and Mrs Smith’s claim failed for lack of evidence on the
amounts claimed. Although quantum was only one element of their claim,
it was an essential element and to be successful, a party must prove all
elements of their claim. Because Mr and Mrs Smith did not prove all
elements of their claim, they were not successful.
[17] The Tribunal therefore dismissed Mr and Mrs Smith’s claim of
$238,700.00 in its entirety. Conversely, the Tribunal awarded Pitt the full
amount of its claim of $74,431.50. It is difficult to envisage how much
more successful Pitt could have been.
[18] Pitt had to spend money to succeed in its claim and successfully resist Mr
and Mrs Smith’s claim. It would not be fair that it should have to pay those
costs.20
[19] Mr and Mrs Smith must therefore pay Pitt’s costs.
What costs should Mr and Mrs Smith pay?
[20] As noted by the Appeal Tribunal, as a matter of law a contractual
entitlement to recover debt collection costs arose at least for the two
progress claims.21 Pitt’s application to recover those progress claims
wholly succeeded. The parties contractually agreed on the basis to
recover costs in these circumstances. It is therefore appropriate to enforce
the terms of the contract so that Pitt recovers its costs on a ‘solicitor and
own client’ basis.22 Consistent with the finding of the Appeal Tribunal when
it awarded the costs of the appeal, this is ‘virtually the same as indemnity
costs’.23
[21] Pitt’s successful recovery of the two progress claims totalling $70,000.00
was inextricably intertwined with its claim for adjustments and variations
and successful defence of Mr and Mrs Smith’s counter-claim: they arose
out of the same facts and circumstances and to wholly succeed in its
claim, it had to successfully defend Mr and Mrs Smith’s counter-claim. It is
therefore not viable to apportion these costs separately: all of Pitt’s costs
of the application and responding to Mr and Mrs Smith’s counter-claim are
to be paid on the indemnity basis.
18 Faulks v. New World Constructions Pty Ltd (No. 2) [2014] QCAT 329 at [17]; A L
Builders Pty Ltd v. Fatseas (No. 2) [2014] QCATA 319 at [4].
19 Barry Pitt Constructions Pty Ltd v. Smith & Anor [2014] QCAT 025 at [57].
20 Tamawood Ltd v. Paans [2005] 2 QdR 101 at [33], cited in Stuart Homes and
Renovations v. Denton & Anor [2012] QCAT 43 at [8].
21 Barry Pitt Constructions Pty Ltd v. Smith & Anor [2014] QCATA 339 at [32]; Clause 33
of the Contract.
22 Pursuant to Queensland Building Services Authority Act 1991 (Qld), s 77(3)(h) and
clause 33 of the Contract.
23 Baque v. Rivergum Homes Pty Ltd [2013] QCATA 200 at [9].
-- 6 of 7 --
7
What are the appropriate Orders?
[22] The Tribunal must fix costs if possible.24 Unfortunately, the current
evidence does not allow me to fix costs. However, as this was a complex
building dispute involving contractual work to a value of approximately
$220,000.00 that was contested all the way through hearing and beyond,
it was reasonable for Pitt to engage Counsel.
[23] The appropriate Orders are therefore that:
1. Shane Harold Smith and Agnieska Smith are to pay to Barry Pitt
Constructions Pty Ltd the sum of $3,797.25 by way of interest by 27
January 2016.
2. Shane Harold Smith and Agnieska Smith are to pay to Barry Pitt
Constructions Pty Ltd, within 28 days of agreement or assessment as
applicable, its costs of:
(a) the application (including their remission by the Appeal Tribunal
by its order dated 9 December 2014 in APL085-14) on an
indemnity basis calculated on the District Court Scale, to be
agreed, or absent agreement to be assessed by Hickey & Garrett
Legal Costs Assessors, Level 21, 141 Queen Street, Brisbane;
and
(b) any assessment.
24 Queensland Civil and Administrative Tribunal Act, s 107.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2015/526