Board of Professional Engineers of Queensland v Hart [2015] QCAT 525
CITATION: Board of Professional Engineers of Queensland
v. Hart [2015] QCAT 525
PARTIES: Board of Professional Engineers of Queensland
(Applicant)
v
John Hart
(Respondent)
APPLICATION NUMBER: OCR240-14
MATTER TYPE: Occupational regulation matters
HEARING DATE: 2 December 2015
HEARD AT: Brisbane
DECISION OF: Member Hughes
DELIVERED ON: 4 December 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. John Hart is reprimanded.
2. The penalty of $17,000.00 is imposed
upon John Hart, payable in 25 equal
monthly instalments of $680.00, with
the first instalment payable by 15
January 2016 and monthly thereafter.
3. John Hart is to pay to the Board of
Professional Engineers of Queensland
the costs of the investigation
including the costs of preparing for
the proceeding fixed at $33,883.33
payable in 25 equal monthly
instalments of $1,355.33 with the first
instalment payable by 15 January
2016 and monthly thereafter.
4. If any instalment of penalty or costs
remains unpaid for ten days beyond
the date it is due (unless because of
some unforeseen event beyond John
Hart’s control, the onus of proof of
which will lie on John Hart, and which
he must raise and establish to the
-- 1 of 9 --
2
Board’s satisfaction within ten days
after the due date), John Hart’s
registration will be automatically
suspended for a period of three years
from that date.
CATCHWORDS: OCCUPATIONAL REGULATION -
DISCIPLINARY PROCEEDINGS –
REGISTERED PROFESSIONAL ENGINEER –
UNSATISFACTORY PROFESSIONAL
CONDUCT - PENALTY - whether
‘unsatisfactory professional conduct’ – whether
‘misconduct in a professional respect’ – where
recurrence and seriousness of conduct did not
escalate to ‘misconduct in a professional
respect’ - where engineer applied and relied
upon incorrect calculations – where engineer
failed to produce documents to investigator -
whether suspension appropriate – where
conduct not dishonest or intentional – where
public safety paramount - where offending
conduct overlapped period of conduct
previously sanctioned – where suspension
would mean no opportunity to learn from
previous sanctions – where conduct resulted in
catastrophic failure – where theme of certifying
substantially defective structural plans – where
great potential for harm - where significant
monetary penalty will achieve deterrence
without oppression – where failing to produce
documents undermines integrity of Act
COSTS – where Board incurred costs to
investigate – where investigator costs reduced
to allow for economies of scale had proceedings
not been separate - where Board reasonably
but unsuccessfully sought suspension - where
engineer did not agree to Statement of Agreed
Facts and acknowledge conduct until late in
proceedings
Professional Engineers Act 2002, ss 3, 36, 55,
56, 131, Schedule 2
Queensland Civil and Administrative Tribunal
Act, ss 100, 102, 107
Adamson v. Queensland Law Society
Incorporated [1990] 1 QdR 498
-- 2 of 9 --
3
Board of Professional Engineers of Queensland
v. Bartilomo [2006] CCT ED 008-05
Board of Professional Engineers of Queensland
v. Hart [2013] QCAT 689
Board of Professional Engineers of Queensland
v. Hart [2015] QCAT 368
Board of Professional Engineers of Queensland
v. Jutte [2004] CCTK005-03
Board of Professional Engineers v. Khatri t/as
Umesh C Khatri Civil and Structural Engineers
[2013] QCAT 106
Board of Professional Engineers of Queensland
v. Moodie [2015] QCAT 127
Board of Professional Engineers of Queensland
v. Narsey [2012] QCAT 32
Board of Professional Engineers of Queensland
v. Wu [2011] QCAT 330
Board of Professional Engineers of Queensland
v. Zaranis [2009] CCT D001-09
Donald Campbell & Co. v. Pollak [1927] AC 732
Qui v. Building Professionals Board [2013]
NSWADT 289
R v. Beattie; ex parte Attorney-General (Qld)
[2014] QCA 206
Ralacom Pty Ltd v. Body Corporate for Paradise
Island Apartments (No. 2) [2010] QCAT 412
Urguhart v. Partington [2013] QCAT 133
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Ms P. Morreau of Counsel instructed by ClarkeKann
Lawyers appeared for the Board of Professional
Engineers of Queensland
RESPONDENT: Mr P. Franco of Queen’s Counsel instructed by
Carter Newell appeared for John Hart
REASONS FOR DECISION
What is this Application about?
[1] John Hart is a professional engineer who accepts he engaged in
‘unsatisfactory professional conduct’, but does not accept he should be
suspended for this as proposed by the Board of Professional Engineers.
Are there grounds for disciplinary action?
-- 3 of 9 --
4
[2] Mr Hart accepts that he engaged in ‘unsatisfactory professional conduct’.
Both the Board and the Mr Hart filed a Statement of Agreed Facts.1 This
reveals three grounds of unsatisfactory professional conduct:
(a) In 2007, Mr Hart applied and relied upon incorrect calculations in
providing a Design Verification Statement for vehicle hoists;
(b) In 2010, Mr Hart applied and relied upon incorrect calculations in
providing a Cable Capacity Letter; and
(c) In 2012, Mr Hart failed to produce documents to the investigation of
his 2007 and 2010 conduct.
[3] The Board filed an Investigation Report finding that Mr Hart did not
request documents from the Australian importer or manufacturer to prove
that the hoist model’s specifications correspond with the relevant
certification, did not correctly calculate cable capacity, and did not provide
documents to the investigator.2
[4] I am not satisfied this constitutes ‘misconduct in a professional respect’.3
That would require conduct that violates or falls substantially short of
professional conduct observed or approved by professionals of good
repute and competency.4 Without defining the term, the finding appears to
be usually reserved for cases of the most serious kind: contumelious
conduct entailing dishonesty, lack of integrity or wanton recklessness.5
[5] Although this is the third instance that Mr Hart has been before the
Tribunal for deficient conduct, it occurred over a period of 10 years and did
not occur after previous sanctions. I am not satisfied the conduct
escalated to the extent that its recurrence or its seriousness distinguishes
it from other cases involving Mr Hart where the Tribunal made no finding
of ‘misconduct in a professional respect’.6
[6] I am, however, satisfied that Mr Hart engaged in ‘unsatisfactory
professional conduct’ in that his conduct was of a lesser standard than
might reasonably be expected by the public or his peers and
demonstrates incompetence, or a lack of adequate knowledge, skill,
judgement or care in the practice of engineering.7
1 Statement of Agreed Facts dated 18 September 2015. Although Mr Hart sought to
subsequently minimise some of the circumstances in his written submissions, during
the hearing, Counsel for Mr Hart accepted the findings in the Statutory Declaration of
Roderick McDonald sworn 27 November 2015 responding to those submissions.
2 Report of Roderick McDonald dated 6 June 2014 attached to Statutory Declaration of
Roderick McDonald sworn 13 July 2015. During the hearing, Counsel for Mr Hart also
accepted the findings in the Statutory Declaration of Roderick McDonald sworn 27
November 2015 responding to Mr Hart’s submissions.
3 Professional Engineers Act 2002, Schedule 2.
4 Adamson v. Queensland Law Society Incorporated [1990] 1 QdR 498 at 507.
5 Board of Professional Engineers of Queensland v. Wu [2011] QCAT 330; Board of
Professional Engineers of Queensland v. Narsey [2012] QCAT 32.
6 Board of Professional Engineers of Queensland v. Hart [2013] QCAT 689; Board of
Professional Engineers of Queensland v. Hart [2015] QCAT 368.
7 Professional Engineers Act 2002, Schedule 2.
-- 4 of 9 --
5
[7] Because Mr Hart engaged in this ‘unsatisfactory professional conduct’, I
am satisfied grounds for disciplinary action are established.8 The Tribunal
may therefore make appropriate Orders.9
What is the appropriate penalty?
[8] Both the Board and Mr Hart submitted that he be reprimanded for his
conduct and fined $5,000.00. However, the Board submitted that Mr Hart
should also be suspended for a period of three years to protect the public
due to concerns about the safety of his work.
[9] The Board was particularly concerned about the gravity of Mr Hart’s
conduct, given he has been previously sanctioned for certifying
significantly defective structural plans for a residence10 and steel sheds11.
The Board cited the decision of Bartilomo where the Tribunal noted that
repeated carelessness cannot be tolerated in a registered professional
engineer.12
[10] As a matter of law, I am satisfied that conduct that although lacking in
intent, can be sufficiently serious by its nature and extent, multiplicity, lack
of insight or consciousness and loss or damage caused, to warrant
suspension.13 However, previous decisions imposing a suspension all
involved dishonesty or at least conduct that “bordered on dishonesty”,14
suggesting a high threshold.
[11] In Bartilomo, the Tribunal refrained from suspending the Engineer’s
registration and instead imposed a reprimand and fine of $10,000.00. The
Tribunal specifically noted that while the errors were serious and in
duplicate, they were unintentional.
[12] There is no evidence or suggestion that Mr Hart’s conduct was dishonest
or intentional.
[13] The legislation regulating the conduct of professional engineers is
designed mainly to protect the public and maintain public confidence in the
standard of professional engineering services.15 When disciplining
professional engineers, a penalty should have a deterrent effect without
being oppressive.16
8 Professional Engineers Act 2002, s 36(a), (b).
9 Professional Engineers Act 2002, s 131.
10 Board of Professional Engineers of Queensland v. Hart [2013] QCAT 689.
11 Board of Professional Engineers of Queensland v. Hart [2015] QCAT 368.
12 Board of Professional Engineers of Queensland v. Bartilomo [2006] CCT ED 008-05 at
22.
13 Similar factors were considered in Qui v. Building Professionals Board [2013] NSWADT
289 at [98].
14 Board of Professional Engineers of Queensland v. Jutte [2004] CCTK005-03; Board of
Professional Engineers of Queensland v. Wu [2011] QCAT 330; Board of Professional
Engineers of Queensland v. Narsey [2012] QCAT 32.
15 Professional Engineers Act 2002, s 3.
16 Board of Professional Engineers of Queensland v. Bartilomo [2006] CCT ED008-05;
Board of Professional Engineers of Queensland v. Zaranis [2009] CCT D001-09.
-- 5 of 9 --
6
[14] Previous decisions involving inadequate or defective calculations have
imposed reprimands and fines. In Khatri,17 the Tribunal imposed a
reprimand and fine of $3,000.00. In Moodie,18 the Tribunal imposed a
reprimand and fine of $5,000.00.
[15] A key difference here is pattern of error: this is the third time that Mr Hart
has miscalculated design plans. Public safety is paramount19 and the
penalty must reflect the need to deter continuing carelessness:
The public is entitled to be able to rely upon engineering documentation
brought into existence and signed by a registered professional engineer with
confidence that the matters related to therein have been attended to, and that
appropriate care and skill is brought to bear upon those matters.20
[16] Mr Hart was reprimanded and fined $5,000 for his first erroneous
calculations21 and reprimanded and fined $15,000 for his second
erroneous calculations22. However, although the conduct is repeated, it did
not occur after previous sanctions. The earlier penalties are therefore not
a circumstance of aggravation, but they are relevant to forming an overall
view of the appropriate penalty.23
[17] Similar to the circumstances leading to his most recent sanction, Mr Hart’s
conduct created a clear and serious risk of safety to persons using the
building or in its vicinity. However, Mr Hart has continued to practice
without incident for five years since this most recent conduct.24 This
suggests that deterrence and the need to protect public safety25can be
achieved by a similarly significant monetary penalty. To increase the
penalty to a suspension for similar conduct overlapping that period,
without giving Mr Hart the opportunity to learn from previous sanctions
would be oppressive.
[18] I consider that Mr Hart’s conduct is considerably more serious than his
2009 conduct resulting in a penalty of $5,000.00 because of its greater
scope and potential to harm others.
[19] I also consider that Mr Hart’s conduct is at least as equally serious as his
conduct resulting in the most recent monetary penalty of $15,000.00.
Although that conduct occurred over a period and property was damaged,
the conduct here overlapped that conduct and reinforces a theme of
certifying substantially defective structural plans. The conduct here
resulted in instances of catastrophic failure. There was great potential for
harm. That no actual harm was caused here is more attributable to good
fortune than any preventative or remedial action by Mr Hart.
17 Board of Professional Engineers v. Khatri t/as Umesh C Khatri Civil and Structural
Engineers [2013] QCAT 106.
18 Board of Professional Engineers of Queensland v. Moodie [2015] QCAT 127.
19 Board of Professional Engineers v. Hart [2013] QCAT 689 at [46].
20 Board of Professional Engineers of Queensland v. Wu [2011] QCAT 330 at [23].
21 Board of Professional Engineers v. Hart [2013] QCAT 689.
22 Board of Professional Engineers of Queensland v. Hart [2015] QCAT 368.
23 R v. Beattie; ex parte Attorney-General (Qld) [2014] QCA 206 at [19]; Board of
Professional Engineers of Queensland v. Hart [2015] QCAT 368 at [60].
24 The 2012 conduct is incidental to the primary breaches in 2007 and 2010.
25 Board of Professional Engineers v. Hart [2013] QCAT 689 at [38].
-- 6 of 9 --
7
[20] Further, unlike his most recent sanction, Mr Hart’s unsatisfactory
professional conduct here also extends to not providing the investigator
with documents. Counsel for Mr Hart submitted that Mr Hart’s failure to
provide documents should merely detract from any discount for co-
operation. However, unlike criminal proceedings attracting this discount to
encourage co-operation where there is no obligation, these are
disciplinary proceedings that do not confer a right to remain silent upon
those being investigated. The Legislature has specifically imposed an
obligation on those being investigated to provide documents. 26 The
integrity of the Act and public safety require that obligation to be enforced.
[21] Mr Hart claims that he did not provide the documents because of work
commitments and he was unsure of the nature of the documents being
sought. However, Mr Hart did not seek clarification until after the deadline
to comply had fallen.
[22] The purpose of providing these documents is to assist the investigator to
fulfil the objects of the Act. Failing to produce relevant documents
undermines the integrity of the Act by curtailing the investigator’s ability to
make the most accurate findings and appropriate recommendations based
on all relevant information. Professional engineers must prioritise
investigator requests accordingly.
[23] The Act prescribes a maximum penalty of 50 penalty units for not
producing a document,27 equating to $5,500.00. Although not specifically
charged with an offence under this provision, I consider an additional
monetary penalty of $2,000.00 is warranted for Mr Hart’s failure to give
information to the investigator.
[24] Applying the totality principle and having regard to the Tribunal’s previous
sanctions totalling $20,000.00,28 I am satisfied that the whole of Mr Hart’s
conduct would attract a total monetary penalty of $37,000.00. I therefore
order that Mr Hart is reprimanded and fix the total penalty for the conduct
the subject of these proceedings at $17,000.00. This will achieve
deterrence without oppression.
[25] Given Mr Hart is in a difficult financial position and is considering selling
his home to pay wages and other commitments,29 I will allow him to pay by
25 monthly instalments. This helps obviate any oppression to Mr Hart.
Should Mr Hart pay the Board’s costs?
[26] The Board also sought an Order that Mr Hart pay its costs of $55,000.00,
comprising $22,550.00 for investigator reports, $4,125.00 for counsel’s
fees and $28,325.00 for solicitors’ costs.
[27] The Tribunal may require the engineer to pay an amount to the Board as
compensation for all, or a part of, the reasonable costs of any investigation
including the costs of preparing for the proceeding.30
26 Professional Engineers Act 2002, s 55.
27 Professional Engineers Act 2002, s 56.
28 R v. Beattie; ex parte Attorney-General (Qld) [2014] QCA 206 at [19].
29 Respondent’s Submissions dated 16 November 2015 at paragraph 37.
-- 7 of 9 --
8
[28] It is common for the Tribunal to order that the engineer pay the costs of
the investigation.31 The Board has been required to incur costs to
investigate Mr Hart. It should be reimbursed those costs. However, for
reasons not clear, the Board has conducted separate investigations with
separate proceedings despite all conduct occurring before 2012. I
therefore consider it reasonable to reduce its investigator costs
recoverable from Mr Hart to $15,000.00, to allow for the economies of
scale it would have achieved from consolidating its investigations and
proceedings.
[29] Other costs in the Tribunal are not awarded as a matter of course. Each
party must bear their own costs,32 unless the interests of justice require
the Tribunal to order a party to pay the costs of another party.33 There is
therefore a strong indicator against awarding costs.34 In deciding this, I
may regard prescribe circumstances. Importantly, they are not mandatory
and some of these may be more apposite in a particular case:
… although the applicant relies on s 102 and the matters to be taken into
account in that section, which are always helpful general principles to apply
with respect to costs any award of costs is discretionary.35
[30] The Tribunal is mandated to fix costs if possible.36
[31] The Board was ultimately unsuccessful in obtaining an order to suspend
Mr Hart. It was reasonable for the Board to seek this order given that it is
charged with maintaining standards within the profession. However, and
because it is in the interests of the public and the profession as a whole
that the Board pursued a suspension, it is appropriate that the costs
attributable to preparing and advocating for a sanction that ultimately did
not succeed is shared among the members as a whole through
registration fees.
[32] Nevertheless, it was not until 18 September 2015 – around three months
before the hearing and relatively late in the proceedings - that Mr Hart
agreed to filing a Statement of Agreed Facts and acknowledged his
conduct amounted to unsatisfactory professional conduct. Much of
preparation for the hearing was therefore necessitated by Mr Hart’s late
acknowledgement of his conduct – regardless of the Board pursuing a
suspension.
[33] In these circumstances, I consider it reasonable to order that Mr Hart pay
the Board two-thirds of its solicitors’ costs equating to $18,883.33, but not
its counsel’s fees.
30 Professional Engineers Act 2002, s 131(f).
31 Board of Professional Engineers of Queensland v. Hart [2015] QCAT 368 at [68]; Board
of Professional Engineers of Queensland v. Bartilomo [2006] CCT ED 008-05; Board of
Professional Engineers of Queensland v. Moodie [2015] QCAT 127; Board of
Professional Engineers of Queensland v. Wu [2011] QCAT 330.
32 Queensland Civil and Administrative Tribunal Act 2009, s 100.
33 Queensland Civil and Administrative Tribunal Act 2009, s 102.
34 Ralacom Pty Ltd v. Body Corporate for Paradise Island Apartments (No. 2) [2010]
QCAT 412 at [29].
35 Urguhart v. Partington [2013] QCAT 133 at [106].
36 Queensland Civil and Administrative Tribunal Act 2009, s 107(1).
-- 8 of 9 --
9
[34] The Tribunal therefore orders that Mr Hart pay to the Board its costs fixed
at $33,883.33. Because of Mr Hart’s difficult financial circumstances, I will
allow him to also pay this by 25 monthly instalments.
What if Mr Hart does not pay an instalment?
[35] To help ensure Mr Hart pays the instalments when due and the public is
protected, it is appropriate that Mr Hart’s registration be suspended for a
period of three years should Mr Hart not pay an instalment.37 So that the
order is not oppressive to Mr Hart, it will be subject to some unforeseen
event out of Mr Hart’s control preventing him paying a required
instalment.38
What are the appropriate Orders?
[36] Both Counsel assisted the Tribunal by acceding to appropriate wording
should the Tribunal impose a monetary penalty. Both Counsel’s
assistance to the Tribunal throughout the hearing was invaluable.
[37] Because of my above reasons, the appropriate Orders are:
1. John Hart is reprimanded.
2. The penalty of $17,000.00 is imposed upon John Hart, payable in 25
equal monthly instalments of $680, with the first instalment payable by
15 January 2016 and monthly thereafter.
3. John Hart is to pay to the Board of Professional Engineers of
Queensland the costs of the investigation including the costs of
preparing for the proceeding fixed at $33,883.33, payable in 25 equal
monthly instalments of $1,355.33, with the first instalment payable by
15 January 2016 and monthly thereafter.
4. If any instalment of penalty or costs remains unpaid for ten days
beyond the date it is due (unless because of some unforeseen event
beyond John Hart’s control, the onus of proof of which will lie on John
Hart, and which he must raise and establish to the Board’s
satisfaction within ten days after the due date), John Hart’s
registration will be automatically suspended for a period of three years
from that date.
37 The Tribunal imposed similar orders in its most recent sanction of Mr Hart in Board of
Professional Engineers of Queensland v. Hart [2015] QCAT 368.
38 The Tribunal imposed similar orders in its most recent sanction of Mr Hart in Board of
Professional Engineers of Queensland v. Hart [2015] QCAT 368.
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2015/525