Bradford v Queensland Building and Construction Commission [2015] QCAT 405
CITATION: Bradford v Queensland Building and
Construction Commission [2015] QCAT 405
PARTIES: Mark Antony Bradford
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: GAR408-13
MATTER TYPE: General administrative review matters.
HEARING DATE: 27 August 2015
HEARD AT: Brisbane
DECISION OF: Member Guthrie
DELIVERED ON: 13 October 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. The reviewable decision to refuse to
categorise Mr Bradford as a permitted
individual is confirmed.
CATCHWORDS: PERMITTED INDIVIDUAL – Whether applicant
took all reasonable steps to avoid the coming
into existence of the circumstances leading to
the relevant event – Queensland Building and
Construction Commission Act 1991 s 56AD
Building and Construction Industry Payments
Act 2004 (Qld)
Queensland Building and Construction
Commission Act 1991 (Qld), s 56AD
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 20, s 21
Subcontractors’ Charges Act 1974 (Qld)
Abigroup Contractors Pty Ltd v ABB Services
Pty Ltd [2004] NSWCA 181
Dellaway v QBSA [2007] QCCTB 181; cited
Delonga v QBSA [2004] QCCTB 26 (29 October
2004); cited
Hyde v QBSA [2003] QBT Q72-02; cited
-- 1 of 28 --
2
Laidlaw v QBSA [2010] QCAT 70
Queensland Building and Construction
Commission v Mudri [2015] QCATA 78
Sinclair Scott & Co v Naughton (1929) 43 CLR
310
Younan v Queensland Building Services
Authority [2010] QDC 158; cited
REPRESENTATIVES:
APPLICANT: Mr Mark Bradford represented by Mr Lindsay
Bowden of Counsel, instructed by QBM
Lawyers
RESPONDENT: Queensland Building and Construction
Commission represented by Ms Jodie Stroud,
solicitor Queensland Building and Construction
Commission
REASONS FOR DECISION
[1] The applicant was the sole director of BBC Concrete Pty Ltd (‘the company’
or ‘BBC’) when administrators were appointed on 6 September 2013. The
Queensland Building and Construction Commission (‘the QBCC’) notified
the applicant that it considered him an excluded individual for a ‘relevant
company event’.
[2] An excluded individual may apply to the QBCC to be categorised as a
permitted individual for the relevant event.1 Mr Bradford’s application to the
QBCC to be categorised as a permitted individual was refused on 17
October 2013. Mr Bradford applied to the Tribunal for review of the QBCC’s
decision.
[3] The decision of the QBCC is a reviewable decision for applying the
Queensland Civil and Administrative Tribunal Act 2009 (‘the QCAT Act’) to
the proceeding. The purpose of the review of a reviewable decision is to
produce the correct and preferable decision. The Tribunal must hear and
decide a review of a reviewable decision by way of a fresh hearing on the
merits.2
Applicable Law
[4] An individual may apply to the QBCC to be categorised as a permitted
individual for a relevant event under s 56AD(1) of the Queensland Building
and Construction Act 1991 (‘the QBCC Act’). An application must include
the reasons why the individual should be categorised as a permitted
1 Queensland Building and Construction Commission Act 1991 (Qld) s 56AD.
2 QCAT Act s 20.
-- 2 of 28 --
3
individual for the relevant event: s 56AD(3). The QBCC may categorise the
individual as a permitted individual by virtue of s 56AD(8):
…only if the authority is satisfied, on the basis of the application, that the
individual took all reasonable steps to avoid the coming into existence of the
circumstances that resulted in the happening of the relevant event.3
[5] In Younan v Queensland Building Services Authority,4 McGill DCJ said that,
in determining whether all ‘reasonable steps’ were taken, consideration
should be given to what action was taken at the relevant time and what was
reasonable in all the circumstances without the benefit of hindsight. McGill
DCJ said:
The section speaks about taking reasonable steps to avoid the coming into
existence of the circumstances that resulted in the happening of the relevant
event. The test in s 56AD(8) requires first, the identification of the relevant
event; second, the identification of the circumstances that resulted in the
happening of the relevant event; third, a consideration of whether the
relevant individual took all reasonable steps to avoid those circumstances
coming into existence; and, if satisfied of that, fourth, a decision whether to
categorise the individual as a permitted individual.
[6] All reasonable steps does not mean all possible steps.5 Relevant steps are
those taken to avoid the coming into existence of the circumstances that
resulted in the relevant event, but not the relevant event itself.6 The test of
reasonableness has been considered an objective one to be applied having
regard to the actual circumstances of the applicant.7 A wide enquiry is
appropriate which includes the manner in which the applicant conducted the
business.8 In Younan v Queensland Building Services Authority the court
confirmed that approach:
What were reasonable steps depended on what was reasonable for the
individual concerned in the circumstances in which he found himself, with
such information as he then had … It is not a question of whether he did
everything possible to prevent those circumstances from arising, or whether
they would not have arisen if he had acted differently. The reasonableness
of his behaviour must be assessed by reference to what was known by him
at the time, without the benefit of hindsight….9
[7] As the court observed, the focus of s 56AD is concerned with the prudent
management of a company as an ongoing business, or prevention rather
than dealing with problems after they have arisen.10
Matters to be considered
[8] Section 56AD(8A) sets out matters to which the QBCC and therefore the
Tribunal on review must have regard in deciding whether an individual took
‘all reasonable steps’. The matters set out in s 56AD(8A) are:
3 QBCC Act s 56AD(8).
4 [2010] QDC 158.
5 Hyde v QBSA [2003] QBT Q72-02 [52-53].
6 Ibid, [38-40].
7 Delonga v QBSA [2004] QCCTB 26 (29 October 2004) [33].
8 Dellaway v QBSA [2007] QCCTB 181 (12 December 2007) [7].
9 Ibid, [26].
10 Ibid at [23]-[25].
-- 3 of 28 --
4
(a) keeping proper books of account and financial records;
(b) seeking appropriate financial or legal advice before entering into financial
or business arrangements or conducting business;
(c) reporting fraud or theft to the police;
(d) ensuring guarantees provided were covered by sufficient assets to cover
the liability under the guarantees;
(e) putting in place appropriate credit management for amounts owing and
taking reasonable steps for recovery of the amounts;
(f) making appropriate provision for Commonwealth and State taxation debts.
[9] In essence, s 56AD(8B) provides that other matters can be considered for
deciding the question.
Information an Applicant must give the Tribunal
[10] While there is generally no onus of proof in the review jurisdiction11 in the
absence of sufficient information from an applicant a decision-maker will be
unable to make a decision to categorise the person as a permitted
individual.
Role of the QBCC in review proceedings
[11] Section 21(1) of the QCAT Act, provides that in a proceeding for the review
of a reviewable decision, the decision-maker must use his or her best
endeavours to help the Tribunal so that it can make its decision on the
review. The respondent adopts a model litigant role and does not adopt an
adversarial approach.
The issues
[12] Accordingly, the issues for consideration by the Tribunal are as follows:
(1) The identification of the relevant event;
(2) The identification of the circumstances that resulted in the happening
of the relevant event;
(3) A consideration of whether the applicant took all reasonable steps to
avoid those circumstances coming into existence including
identification of the steps taken by Mr Bradford and whether they were
reasonable;12
(4) And, if satisfied in relation to (3), a decision about whether to exercise
the discretion to categorise the individual as a permitted individual.
The evidence
[13] Mr Bradford provided four written statements to the Tribunal with annexures
and was cross-examined at the hearing. At all relevant times, Mr Tom Voyce
held the position of Contract Administrator with BBC. It was his role to
source projects, attend to contract negotiations and monitor the
11 See discussion in Laidlaw v QBSA [2010] QCAT 70.
12 Queensland Building and Construction Commission v Mudri [2015] QCATA 78.
-- 4 of 28 --
5
performance of all of BBC’s contracts. He was also responsible for issuing
payment claims under the contracts and for following up unpaid claims.13 At
all relevant times, Mr Philip Vanderburg held the position of Workplace,
Health and Safety Officer with BBC. Mr Voyce and Mr Vanderburg gave
evidence at the hearing and were available for cross-examination. Mr Voyce
and Mr Vanderburg gave their evidence in compliance with Notices to
Attend issued by the Tribunal.
[14] The respondent provided an Index of Documents and three affidavits of the
original decision-maker, Ms Natasha Dennis.
Identification of the relevant event
[15] There is no dispute that the relevant company event is the appointment of
administrators to BBC, which occurred on 6 September 2013 while Mr
Bradford was a director of the company, and the Tribunal so finds.
Identification of the circumstances that resulted in the happening of the
relevant event
[16] BBC was a sub-subcontractor on the Gladstone Liquefied Natural Gas Plant
project. BBC was subcontracted to McNab Constructions Australia Pty Ltd
(‘McNab’) to complete the concrete works (‘the McNab project’). The project
involved the construction of substantial buildings and facilities on Curtis
Island. The principal contractor was Bechtel Australia Pty Ltd (‘Bechtel’). Mr
Bowden, for the applicant, submitted that the failure of the McNab project
led to the lack of cash flow, which ultimately led to the appointment of the
administrators.14 Indeed, Mr Bowden submitted that this one contract was
the sole cause of the commercial failure of BBC.15
[17] In his application to the QBCC to be categorised as a permitted individual,
Mr Bradford indicated that the main cause of the relevant event was the
inability of the company to recover amounts owing to it. He also indicated
that he first became aware of the cause of the relevant event or, alternatively
the date it should reasonably have come to his attention was 3 September
2013. He indicated that other significant contributing causes of the event
were the debt owed to the Australian Taxation Office (‘the ATO’) and
insufficient working capital.16
Background and corporate history
[18] The applicant held and holds a licence in the class of concreting.
[19] Based on Mr Bradford’s written statement dated 2 February 201517 and the
ASIC Historical extract for the company as at 17 January 201418 and there
being no contradictory evidence before it, the Tribunal finds that:
13 Exhibit 1, paragraph [21].
14 Submission of the applicant at paragraph [56].
15 Submission of the applicant at paragraph [22].
16 Exhibit 8, at pp 25 to 29 (inclusive).
17 Exhibit 3, paragraphs [3], [4], [6], [7], [9], [10].
18 Exhibit 1, annexure “MB-1”.
-- 5 of 28 --
6
a) Bosform was a group of companies owned by the Bos family. Some of
the Bosform entities owned the office premises from which BBC
operated.
b) For approximately 16 years prior to the incorporation of BBC Mr
Bradford worked for the Bos family as senior site foreman of Clonmel
Pty Ltd trading as Remo Concrete Constructions. Mr Craig was a
senior manager and was intending to retire.
c) In about 2005, a succession plan would see a new entity BBC
incorporated which would trade as Remo Concrete Constructions with
Mr Bradford and Mr Craig to each hold 20% stakes and Mr and Mrs
Bos to hold the remaining 60%. Over the following five years the other
directors would retire and Mr Bradford would take over each of their
interests for $0.00.
d) BBC was incorporated on 11 July 2005.
e) By about mid 2010 Mr and Mrs Bos decided not to retire and required
some payment for their share of the company, which Mr Bradford
negotiated to $720,000.
f) In about 2011, Bosform put up bank guarantees to builders so that the
company could get cash retention monies returned which were used
to pay out Mr and Mrs Bos. Other money also had to be used. As part
of putting up those guarantees, Bosform required BBC to share their
premises and required rent and payment for shared services.
g) Mr and Mrs Bos ceased as directors on 25 June 2011. Mr Craig ceased
as a director on 30 June 2009. Mr Bos ceased as a secretary of the
company on 2 October 2012 when Mr Bradford was appointed.
h) As at 1 October 2012, Mark Bradford Investments Pty Ltd was the only
shareholder.
i) BBC shared some staff with Bosform including Mr Hennie du Preez,
Ms Hayley Banks and Ms Roberta Bright. Ms Banks was a full time
employed Accountant and Ms Bright worked in payroll/bookkeeping.
Mr du Preez had worked with Bosform for about seven or eight years.
j) BBC also had dealings with Ms Leis of Price Waterhouse Coopers
(‘PWC’).
k) In addition to Mr Bradford, the staff of BBC included Mr Voyce, Mr
Kane Norman, Operations Manager and Mr Vanderburg. Mr Blake
Bradford, Mr Bradford’s son was an estimator. BBC also employed
nine site foremen. Other staff were hired as and when needed for each
contract.
[20] Mr Bowden submits that the Tribunal must consider Mr Bradford’s 25 years
experience in the concreting industry and 16 years working with Remo
Concreting. Further, Mr Bowden submits that it is relevant to consider that
BBC had been trading for a lengthy period before the troubles which led to
its demise.
-- 6 of 28 --
7
[21] Mr Bradford was the sole director of BBC for a period of just over two years
before the administrators were appointed. Indeed, for reasons that follow,
the Tribunal considers the changes to the control of BBC from 2 October
2012 negatively impacted the financial position of BBC between October
2012 and 6 September 2013 (the relevant period).
[22] The Tribunal accepts that BBC had adequate staff and access to accounting
advice through Mr du Preez and his accounting staff and Ms Leis. The
Tribunal also accepts that the other staff were appropriately qualified for
their roles and Mr Bradford was entitled to rely on their expertise.
The ATO Liability
[23] In his first statement, Mr Bradford says that during 2012 and 2013, BBC
expected, having regard to the number and contractual value of the
contracts on foot at the time, that it would receive sufficient funds from the
payment of issued claims and released retention monies to be in a position
to pay its commonwealth and state taxation liabilities. In early 2013, with the
unusually large number of days affected by inclement weather causing
delays on the McNab project, the company had to pay wages for workmen
on site but had not been paid by McNab. Mr Bradford says that at about that
time, McNab owed BBC $405,000 and he arranged for Mr du Preez and Ms
Leis to contact the ATO and arrange a repayment arrangement.19
[24] In January 2013, Ms Leis negotiated a payment arrangement with the ATO
to commence from 28 February 2013. BBC paid the ATO as follows:
28/2/13 $50,000
27/3/13 $70,000
26/4/13 $70,000
27/5/13 $70,000
5/6/13 $160,000
[25] No other payments were made to the ATO in line with the repayment
arrangement before the administrators were appointed. The Tribunal makes
findings of fact accordingly.
[26] By letter dated 27 May 2013, the ATO notified BBC that it had been
classified as a large withholder of PAYG and so it was required to submit
weekly PAYG payments commencing from 1 July 2013.
[27] It is not disputed by Mr Bradford that he did not retain any amounts in order
to pay the ATO. The Tribunal finds accordingly.
[28] In cross-examination, Mr Bradford did not accept that he was using future
money to pay past payments of PAYG tax. Mr Bradford said that unless he
was a multimillionaire he could not pay the PAYG amounts until he received
payment from McNab.
19 Exhibit 1, paragraphs [77] to [80].
-- 7 of 28 --
8
[29] By letter dated 17 July 2013, the ATO notified BBC that its integrated
account had an overdue amount of $548,359.26 and BBC was warned of
intended debt collection action. The Tribunal finds accordingly.
[30] On 19 August 2013, the ATO issued a ‘Notice of Director’s Liability to pay a
Penalty’. The amounts detailed in the notice totalled $575,344 being the
total of the unpaid amount of each taxation liability of BBC for particular
withholding periods:
1 December 2012 to 31 December 2012 $ 3,657.00
1 March 2013 to 31 March 2013 $183,817.00
1 May 2013 to 31 May 2013 $220,414.00
1 June 2013 to 30 June 2013 $167,456.00
[31] Mr Bradford was unable to pay the outstanding taxation liability within the
period stipulated in the notice, i.e. by 9 September 2013. The Tribunal finds
accordingly.
[32] The records relied on by Mr Bradford reflect that BBC met its payroll tax
obligations up until June 2013. The Tribunal finds accordingly.
Working capital
[33] In the process of ‘paying out’ the retiring directors of BBC, the previous
National Australia Bank overdraft facility was refinanced with Bendigo Bank.
Bendigo Bank’s response to the application for finance dated 25 February
201320 sets out the details of the borrowers, facility and limits as follows:
a) Mark and Deborah Bradford – residential home loan - $566,000
b) Mark and Deborah Bradford – residential home loan - $190,000
c) BBC trading as Remo Concrete Construction – overdraft facility -
$250,000
[34] The general terms and conditions of the refinance offer from Bendigo
included that the home loan facility of $566,000 was to reduce by $200,000
by 30 September 2013 with payment reductions to be staged in line with
cash flow and return of retention as follows:
30/4/13 $75,000
30/6/13 $25,000
31/8/13 $50,000
30/9/13 $50,000
[35] While the Bendigo Bank offer states that Mr Bradford’s property at Biggera
Waters was valued at $850,000, Mr Bradford gave evidence that he had no
equity in either of his personally owned real estate assets. Bendigo Bank
also expected as security a guarantee in favour of BBC Concrete Pty Ltd
from Mr and Mrs Bradford and Mark Bradford Investments Pty Ltd.
20 Exhibit 4, annexure “MB-35”.
-- 8 of 28 --
9
[36] Emails from Bendigo Bank to Mr du Preez and Mr Bradford dated 6 March
and 28 May 2013 respectively state:
[On 6 March 2013] We need to be extremely confident in the fact that the
Cash Flow of the business can sustain the requirements of the Business in
addition to the agreed tax payment plan and the Home Loan reductions.
My understanding is that the scenario is that BBC is using the funds set aside
for the BAS payment to clear the extra $250K facility with NAB.
Scheduled ATO payments
Date Amount
28/02/2013 $50,000
28/03/2013 $70,000
28/04/2013 $70,000
28/05/2013 $70,000 + Normal March BAS
Payment
28/06/2013 $70,000
28/07/2013 $70,000
28/08/2013 $20,000 + Normal June BAS
Payment
$420,000
The ATO payments will be in addition to the Debt reductions on the Home
Loan of $200,000…
[On 28 May 2013] …As per my email [in March] I went over above my
authority level to allow the refinance without the tax due 28/02/2013 having
been paid, on the clear understanding that the Cash Flow of the business
was sufficient to allow you to meet the ATO payment schedule and the Home
Loan Reductions.
…
…have failed to follow you up to arrange the Principal Debt reduction of
$75,000 that was due as at 30/04/2013.
We need to make arrangements now to have funds transferred to make the
1st of the due reductions.21
[37] According to BBC’s bank account statements the amount of $246,625.69
was drawn down on 28 March 201322. Payments of $75,000 were made in
both May and June 2013.23
21 Exhibit 4, annexure “34”.
22 Exhibit 4, annexure “35”.
23 Exhibit 4 paragraph [58] and annexure “34”.
-- 9 of 28 --
10
[38] Mr Bradford’s evidence was that Mr and Mrs Bos had guaranteed an
overdraft of $500,000 to $650,000 but, once he alone controlled BBC, he
could only obtain an overdraft of $250,000.
[39] The Tribunal finds that, at all relevant times, BBC’s total overdraft facility
was $250,000, which was drawn down in late March 2013. The Tribunal
finds that, at all relevant times, Mr Bradford had no equity in any of his
personal assets. The Tribunal also finds that in 2013, BBC was required to
make repayments to Bendigo Bank as outlined in Bendigo Bank’s email set
out above. These payments were in addition to the payments BBC was to
make to the ATO. Mr Bradford was aware of these circumstances at the
relevant time/s.
The McNab project and its impact on BBC’s cash flow
[40] Mr Bradford says that BBC’s need to negotiate a repayment arrangement
with the ATO in January 2013 and its inability to pay any amounts to the
ATO after June 2013 was due to the company’s cash flow problems were
caused by McNab’s failure to pay BBC’s payment claims in full in 2013.
[41] The payment claims made by BBC to McNab for work they performed and
the amounts McNab approved can be gleaned from the documents at “MB-
9” of Exhibit 1.
Claim/approval Date Amount
Claim 1 15/12/12 $59,640.66
Approved As at
19/1/13
$33,996.60
Claim 2 25/1/13 $139,580.10
Approved As at
19/2/13
$156,715.90
Claim 3 25/2/13 $271,012.50
Approved As at
14/3/13
$250,830.93
Claim 4 25/3/13 $463,285.91 (including variations
totalling $167,935.50)
Approved As at
15/4/13
$263,211.25 (variations mostly
rejected by McNab)
Claim 5 30/4/13 $631,632.07
Approved As at
15/5/13
$383,711.65
Claim 6/7 30/5/13 $535,755.98
Approved As at
17/6/13
($495,612.19)
Payment Claim 9 1/7/13 $628,409.69
Claim 10 30/7/13 $1,171,939.37
Claim 10 30/7/13 $575,347.43
Payment Certificate 8
(McNab)
26/8/13 ($189,636.48)
-- 10 of 28 --
11
[42] In his statement, Mr Bradford states that McNab paid $80,000 on 3 March
2013, $125,000 on 18 March and $125,000 on 27 March 2013.24 He further
states that he was expecting to be paid $500,000 to $750,000 in April but in
May, BBC received $380,000 of which $75,000 was used to pay Bendigo
Bank. McNab did not pay BBC in June 2013.25
[43] The initial negotiations between BBC and McNab regarding the project
commenced in October 2012. Mr Voyce was dealing with McNab’s Mr Matt
Farmer with whom he had a good relationship. BBC had also worked with
McNab on another project, the Village, Coorparoo and hoped to work on
another stage of that project in the future.
[44] At that same time, BBC had a number of other contracts on foot and
significant sums of money tied up in retentions for those projects.26
[45] Originally, BBC provided a quote for three packages of work. On 23 October
2012, BBC quoted $1,825,000 plus GST to perform a revised package of
work27 which was accepted by McNab. In an email dated 23 October 2012,
Mr Farmer tells Mr Voyce:
As agreed over the phone earlier, McNab and Remo will go into contract for
the ‘Ground works’ and ‘Tilt panels’ on the GLNG – Curtis Island Project for
a sum of $1,825,000.
Obviously, there’s a bit of paperwork coming your way, but please accept this
email as a Letter of Intent. Initially, could you please start with the attached
two forms and get them to me tomorrow, which will then enable me to pass
onto the relevant people in McNab for their approval so I can then send you
your contract.28
…
[46] Mr Voyce said that after receipt of this email he was under the impression
that a contract would be forthcoming from McNab on that basis, that is, the
scope or works and letter of intent that had been discussed. An email on 19
November 2012 from Mr Farmer states that McNab is waiting on Bechtel,
to approve McNab’s subcontractors.29
[47] In an email dated 23 November 2012, Mr Farmer tells Mr Voyce that he has
received approval to get BBC underway with BBC’s workforce to start on
Temporary Work Permits.30
[48] On 4 December 2012, BBC mobilised four or five people to Curtis Island,
prior to a formal written contract (including the scope of works) being
completed between BBC and McNab. The Tribunal finds accordingly.
[49] Mr Bradford said that at that stage there was one building platform ready.
He said that all of BBC’s negotiations with McNab had been on the basis
that they would do work on one building at a time. He referred to the initial
mobilisation as a ‘soft start’ with a view to mobilising more workers in
24 Exhibit 4, paragraph [56].
25 Ibid, paragraphs [58] and [59].
26 Exhibit 1, paragraphs [24] and [25].
27 Ibid, annexure “MB-6”.
28 Ibid.
29 Ibid.
30 Ibid.
-- 11 of 28 --
12
January 2013. He said that the soft start ran from 7 December 2012 to 20
December 2012. Between 23 December 2012 and 8 or 10 January 2013
work on site ceased.
[50] BBC received the draft contract on 4 December 2012 which was also the
date stipulated in the contract as the anticipated date for commencement.
The date of practical completion was stated to be 12 April 2013. Claims
were to be paid within 25 business days. The draft scope of works was
dated 3 December 2012. Some handwritten amendments were made to the
draft documents.31 Mr Voyce said he made the changes.
[51] Mr Bradford said that while he mobilised his workers in the absence of a
formal contract, he felt the letter of intent, emails and discussions between
the parties meant there was an agreement in place.
[52] Mr Bradford said that on 7 December 2012 he and Mr Vanderburg travelled
to Curtis Island and met with Mr Farmer and Mr Brian Boyd of McNab. They
went through the draft contract documents and highlighted the changes
required to reflect the agreement that BBC considered had been reached in
November 2012.32 Mr Farmer agreed that changes had to be made but, due
to the number of changes, he said he would have to have them fixed up at
head office and then the final version would be sent to BBC for signing.33
[53] Mr Farmer had a motorbike accident which meant that he was not back on
site until about 24 January 2013.34 Mr Bradford said that Mr Kane Keefe,
who took on Mr Farmer’s role in his absence, was not aware of the agreed
changes to the scope of works. Mr Keefe wanted BBC to do work which
was outside the agreed scope of works. While BBC performed the work, Mr
Bradford said he believed BBC would be paid for any variations to the
agreed scope of works.
[54] Mr Voyce’s evidence regarding the impact of Mr Farmer’s absence was
consistent with that of Mr Bradford.
[55] A further meeting took place on 5 February 2013, attended by Mr Bradford,
Mr Voyce, Mr Vanderburg and Mr Norman. Again, the scope of works issues
were discussed.35
[56] On 13 February 2013, Mr Voyce signed the contract on BBC’s behalf, with
Mr Bradford witnessing his signature.
[57] Wet weather affected the site in January and February. Mr Bradford said
that there were only about four working days in February. However, Bechtel
acknowledged just two days of wet weather. That meant that BBC was not
given an extension of time to complete its work. BBC had to pay its full-time
employees despite them being unable to perform any work. Mr Bradford
agreed in cross-examination that the wet weather cost him about $120,000.
[58] Mr Voyce said that ‘at first McNab agreed to BBC doing one building at a
time but that changed when they got behind due to rain delays.’ He said that
31 Ibid, annexure “MB-6”..
32 Exhibit 4, paragraph [33].
33 Ibid, paragraph [34].
34 Ibid, paragraph [40].
35 Ibid, paragraph [45].
-- 12 of 28 --
13
McNab expected BBC to increase its labour above what was agreed pre-
tender, effectively doubling or tripling its labour on site, which was not easy.
He said that at the time of tender, mobilisation was clear. The temporary
work permits would get the men on site and they would transfer to full work
permits. He said that Bechtel decided that was no longer an option so the
process of mobilising labour became more difficult.
[59] Mr Bradford’s written statement reflects that in February/March 2013
McNab required seven buildings on site to be resourced regardless of the
agreement that BBC complete one building at a time and that BBC had
difficulty sourcing the necessary labour.36
[60] In cross-examination, Mr Bradford said he did not seek liquidated damages
at that time because he believed the wet weather and an extension of time
should have been allowed. He did not seek legal advice at that time.
[61] While it was Mr Voyce’s and Mr Bradford’s evidence that the agreement
with McNab was that BBC would complete work on one building at a time,
the Tribunal could not locate any documentary evidence of BBC and McNab
agreeing to that at any time before the contract was executed. The contract
documents also do not reflect this. In an email dated as early as 26 February
2013, Mr Farmer indicates that the project was under-resourced by BBC
from the start. He states: ‘the resource expectation was intended for 26 men
to be onsite from day one.’37
[62] The Tribunal considers that there was clear dispute regarding BBC’s
resourcing of the project prior to any formal contract being signed by McNab
as well as issues regarding BBC’s scope of works.
[63] Mr Bradford gave evidence that in March 2013 McNab wanted more and
more men on site and more and more buildings started. He agreed that BBC
tried to accommodate those demands. Mr Bradford’s evidence was that
McNab agreed to source additional workers through QMC labour hire for
BBC because McNab accepted that BBC had performed work outside its
scope of works.
[64] Mr Bradford’s evidence was that BBC verbally agreed to working on one or
two extra buildings but there was no formal notification to accelerate the
programme. The cost of the QMC labour hire arranged by McNab was
$250,000. Mr Bradford said that those workers were kept on for two or three
rotations and later, after the contract was terminated, McNab claimed the
QMC labour costs as a back charge against BBC.
[65] Mr Voyce’s evidence was essentially consistent with Mr Bradford’s evidence
regarding the backcharging to BBC. Mr Voyce considered McNab used
more men than required for the work and then charged BBC for it. He said
BBC agreed because they felt they had no option.
[66] Mr Bradford gave equivocal evidence about whether the contract at “MB-7”
of Exhibit 1 reflected the terms of the final contract. A contract signed by
both McNab and BBC is not before the Tribunal. Mr Bradford’s oral evidence
was also somewhat equivocal about whether BBC had ever received a copy
36 Exhibit 1, paragraph [41].
37 Exhibit 3, annexure “MB-18”.
-- 13 of 28 --
14
of the completed contract back from McNab. He said he might have
received it after threatening, in late March, to demobilise from Curtis Island.
In a letter to the QBCC Mr Bradford states that the contract arrived on 27
March for execution by BBC but it took a further two weeks to finalise and
clarify all scope issues and terms before signed copies were completed. He
further states that after the contract was signed, McNab claimed BBC was
in breach of the contract.38
[67] The Tribunal finds, based on the evidence, that both parties executed the
formal written contract no earlier than late March 2013.
[68] Mr Bradford said that the threat to demobilise was made around the time
that Mr Voyce spoke to a friend who was a lawyer. It was an informal
discussion. Mr Bradford described it as an ‘off the record’ meeting. BBC did
not pay for any legal advice. Mr Voyce could not recall when he spoke to a
solicitor or what advice he received. The Tribunal finds that BBC did not
seek formal legal advice on that occasion.
[69] Mr Bradford said that in March and April 2013, BBC’s relationship soured
with McNab. Mr Bradford said that he had a very heated discussion with the
site foreman regarding the acceleration of the programme of work and,
subsequently, he was told he could not contact the site foreman or the team
on site anymore.
[70] In late April 2013, McNab decided that BBC would not complete certain
work. Dowells completed the work. McNab back charged the costs
associated with the work to BBC. This caused considerable problems
between the parties. Mr Voyce continued to contact McNab seeking
clarification of those issues and copies of documentation relating to the work
done by QMC and Dowells.39
[71] Mr Bradford gave evidence that he felt his workers had caught up by that
stage and he believed BBC could get the work back.
[72] A letter from McNab to BBC dated 9 May 2013 states that the decision to
take part of the works out of BBC’s hands stands. The letter raises McNab’s
concern that BBC was not performing and that the resourcing and quality
issues were not satisfactory.40
[73] The Tribunal finds that resourcing of the project remained an area of
ongoing dispute after the contract was completed.
[74] Mr Bradford said that in May/June 2013, an employee at Dowells suggested
that BBC might have a claim under the Building and Construction Industry
Payments Act 2004 (Qld) (‘BCIPA’). Mr Bradford said that the employee told
him that if he took that step, the relationship with McNab would go ‘pear
shaped quickly’.
[75] Mr Bradford’s statement indicates that when McNab owed BBC around
$500,000 he considered issuing a sub-contractor’s charge. He had a
meeting with Bechtel on the understanding that Bechtel had not been
38 Exhibit 1, annexure “MB-3”.
39 Exhibit 3, paragraph [41].
40 Exhibit 1, annexure “MB-13”.
-- 14 of 28 --
15
paying McNab. However, at the meeting, Bechtel assured BBC that that
was not the case, so BBC did not issue a sub-contractor’s charge.41
[76] On 3 July 2013, McNab informed BBC that McNab and Bechtel were in
negotiations that were likely to end the subcontract on Curtis Island.42 Mr
Bradford said that BBC ceased work on site sometime in July. His written
statement says that in about August 2013 Bechtel advised BBC that it
should demobilise.43 He said there were about six men on site at the time.
[77] Meetings were held with McNab regarding the final payment to BBC. Mr
Voyce and Mr Vanderburg attended the meetings. Mr Bradford said he did
not attend those meetings because he hoped an amicable settlement could
be reached and felt that was more likely in his absence. He had been told
not to deal with Mr Boyd who would be attending those meetings.
[78] Mr Bradford’s statement indicates that in mid-August 2013 BBC was given
some of the QMC and Dowell’s time sheets and dockets which BBC had
been trying to obtain for months.44 Mr Bradford’s statement indicates that in
late August 2013, the company submitted an offer that McNab pay BBC
$630,000. He states that the offer of $155,000 from McNab was received in
September 2013.45
[79] Mr Bradford said, that following a meeting, Mr Voyce and Mr Vanderburg
told him that BBC could expect to receive about $650,000 from McNab.
[80] Mr Voyce said the meetings occurred over a six to eight week period and
required the consideration of 60 to 80 variations. After a meeting Mr Voyce
said he believed that McNab would pay a final payment to BBC $650,000
to $700,000. He and Mr Vanderburg were both confident of this and
informed Mr Bradford that that would likely occur. When the payment did
not come through at the end of the month, another meeting was held and
that was when McNab offered $155,000. Mr Voyce said that after the offer
from McNab, BBC started thinking about legal advice.
[81] Mr Vanderburg recalled three meetings with McNab. He said that at the first
meeting he and Mr Voyce mainly listened then went away and worked out
the spreadsheets and came back with a figure. Originally, BBC was looking
at claiming $1.1 million.
[82] After the second meeting, he and Mr Voyce felt they had been assured that
BBC would get $600,000. Their hopes were dashed at the final meeting. He
said that there had been a discussion between Mr Bradford and Mr Voyce
regarding a figure less than $600,000 that BBC would be prepared to accept
but $155,000 was not enough. Consistently with Mr Voyce’s evidence, he
said that the meetings occurred over a six to seven week period. Mr
Vanderburg said the last meeting was only weeks before administration.
[83] The Tribunal finds that Mr Bradford believed that McNab was likely to pay a
final payment claim of about $600,000 in approximately early August 2013.
41 Exhibit 3, paragraph [40].
42 Exhibit 1, annexure “MB-8”.
43 Exhibit 1, paragraph [53].
44 Exhibit 3, paragraph [41.]
45 Exhibit 1 paragraph [56].
-- 15 of 28 --
16
[84] Mr Bradford said that he was in contact with his financial team at PWC and
with Mr du Preez. He said that in June or July 2013, Mr du Preez advised
him to sue. He did not do so because BBC was engaged in negotiations
with McNab at that time and he was concerned that if he took steps to sue,
those negotiations would cease. In his statement, he says that he did not
want to sue, as he believed McNab had a counter-claim.46
[85] According to the payment schedules completed by McNab, the reasons for
the differences between the amount claimed by BBC and the amount paid
by McNab, included work McNab regarded as incomplete, the claimed
amount being too high for the work then completed or variations claimed by
BBC that were not accepted by McNab. Some of the variations included
back charges for labour performed by QMC and Dowells. In rejecting BBC’s
claims, McNab referred to clauses in the sub-subcontract including clauses
24 and 25 (variations) and 27 (site cleaning) as well as the scope of works.
[86] Documents before the Tribunal record that the back charges were $632,000
for Dowells, $267,000 for QMC and $45,000 for materials, a total of
$944,000.47 Mr Bradford said he never agreed to that figure and believed it
to be an extremely over inflated figure. He said he thought that about half
of that figure would be more accurate and he used that figure to arrive at
what he believed to be the amount owing to BBC by McNab at the
conclusion of the contract.
[87] Based on the payment claim documents, the Tribunal finds that from
February / March 2013, McNab was not paying BBC’s payment claims in
full. Further, there was dispute between BBC and McNab regarding BBC’s
claims.
[88] In his statement Mr Bradford says that, until the McNab project, BBC had
not encountered any significant problems during the negotiation or contract
management stages with other contractors that couldn’t be sorted out
amicably and in a reasonably quick time frame.48 BBC had always dealt with
‘Tier 1’ companies.
[89] Mr Bradford gave evidence that in 35 years in the industry he had never
obtained legal advice on a contract before signing it. He acknowledged that
a contract should reflect the agreement reached between the parties and
that it has to be accurate because the parties are bound by its terms. He
agreed that a number of changes were made to the agreement he felt had
been reached with McNab by the end of November/early December 2012.
[90] Mr Voyce said that he does a similar job for his current employer and no
legal advice is sought there either but said that the director is a solicitor.
[91] In cross-examination, Mr Bradford did not accept that it was reasonable for
him to obtain legal advice before he mobilised his workers. He said it would
probably have been reasonable to seek advice relating to McNab’s refusal
to extend time. He did not consider that it was reasonable for him to seek
legal advice regarding the acceleration of the programme of work or the
alleged breach by McNab involving the use of Dowells and then back
46 Exhibit 2, paragraph [6].
47 Exhibit 3, “MB-36”.
48 Exhibit 1, paragraph [64].
-- 16 of 28 --
17
charging BBC. Mr Bradford said that BBC and McNab were trying to work
this out and the back charge was just McNab’s verbally expressed view. He
agreed that in hindsight it would have been reasonable to seek advice about
recovering money owed to BBC by McNab. However, he said that he could
not have done so in April 2013 as he was trying to maintain a working
relationship with McNab. He was working on another project with McNab,
the Village at Coorparoo, and hoped to work on other projects with them.
Mr Bradford did not accept that his failure to seek legal advice contributed
to the failure of the company.
[92] In re-examination, Mr Bradford said that, at the time, he did not consider
that McNab had breached the contract by varying the contract in respect of
the back charges or the wet weather decision. He said he thought that it
was a dispute about the variations and that it would be settled at the end of
the project. He believed that if he instituted proceedings he would be ‘off the
project’. He said that he did not think he could sue. He knew that there were
processes and he had had the conversation with the employee from
Dowells about the BCIPA claim and ‘vaguely knew’ about the
Subcontractors’ Charges Act 1974 (Qld) ‘but did not really think about it’.
He was trying to come to an amicable arrangement and continue with other
projects. About four weeks out from administration, he was acting on the
assumption that BBC would receive approximately $700,000 from McNab.
[93] The Tribunal finds that at no time did Mr Bradford seek formal legal advice
regarding the McNab project. No advice was sought before entering into the
contract or during the project. Further, no legal advice was sought at any
time regarding recovery from McNab of amounts BBC considered to be
owing to it under the contract. BBC did not make any BCIPA claim, or
exercise its potential rights under the contract. BBC did not exercise any
rights under the Subcontractors’ Charges Act 1974.
The contract documents
[94] The Tribunal has examined the documents that formed the contract
between BBC and McNab:
Formal instrument of agreement
Exhibit A - General conditions
Exhibit B – Special conditions
Exhibit C – Quantities, pricing and data
Exhibit D – scope of work and technical specifications
Exhibit E – drawings
General conditions of sub-subcontract
General conditions of Sub-Subcontract Schedule 1 – Scope of Works
General conditions of Sub-subcontract Schedule 2 – Specifications
General conditions of Sub-Subcontract Schedule 3 – drawings.
-- 17 of 28 --
18
[95] The General conditions contain details of the scope of works.49 Clause 24
provides for variations. According to McNab’s response to the variations
claimed by BBC in April 2013, it rejected a number of claims due to BBC’s
failure to comply with clause 24. Clause 29 provides for delay and
extensions of time. It sets out the circumstances under which the sub-
subcontractor is entitled to an extension of time and the process for seeking
an extension of time. It is not apparent that BBC pursued its rights under
clause 29 when wet weather delayed its work in February 2013.
[96] Clause 30 provides that the subcontractor may direct the sub-subcontractor
to accelerate the execution of the sub-subcontract works or to recover any
delay in the execution of the sub-subcontract works but provides for the
process for making such a direction.
[97] Clause 52 covers default by the subcontractor and clause 53 deals with
default by the sub-subcontractor’s default. Dispute resolution is provided for
in clause 55, which provides for mediation and arbitration in the event of a
dispute.
[98] Based on clause 1.2 of the formal instrument of agreement the contractual
obligations between Bechtel and McNab could potentially affect BBC.
[99] It is arguable that clauses 3 and 4 of the formal instrument of agreement
prevented BBC relying on any verbal terms it says were negotiated pre-
tender or before the contract was executed. It seems to the Tribunal that
this is in fact what BBC sought to do throughout its dealings with McNab in
2013.
Financial advice and recovering monies
[100] In a written statement, Mr Bradford states that the company had appropriate
credit and debt recovery policies. Monthly profit and loss breakdowns were
compiled by Mr du Preez and in-house accounting and administration staff.
Meeting were held twice monthly between Mr Voyce, Mr du Preez and Mr
Bradford to go through breakdowns of jobs, profit percentage margins,
losses and how to streamline operations or areas where the company could
improve.50
[101] Mr Voyce said that he and Mr Bradford monitored cash flow weekly. Mr
Voyce said that he was always ringing and emailing McNab about
payments. He regarded some of McNab’s responses to BBC’s payment
claims to be unreasonable.
[102] Mr Voyce said that he would tell McNab that BBC was expecting money on
a particular date but only part of the payment would be paid and then, at
some point, the payments stopped all together. He was able to obtain
$100,000 from John Holland with whom BBC was working on another
project, which was nearing completion. Despite the payment not being due,
their good working relationship meant that John Holland was prepared to
pay the amount early. Mr Voyce said that things got to the point, around
July/August 2013, where they could not keep going back to John Holland
49 Exhibit 1, “MB-7”, General conditions, clause 2.
50 Exhibit 1, paragraphs [70] and [71].
-- 18 of 28 --
19
for money. Mr Bradford’s statement indicates that this was in early August
2013.51
[103] Mr Bradford states that meetings were held at least every two months with
Ms Leis of PWC in relation to profit and loss, taxation issues and accounting
in general. Numerous phone calls were made to Ms Leis in between these
meetings.52
[104] Mr Bradford’s evidence is that in early June 2013, he spoke with Mr du
Preez about BBC’s cash flow issues and they sought advice from Ms Leis
of PWC about raising working capital for the companies due to the ongoing
issues with McNab.53
[105] A meeting was held on 12 June. Over the next week or so documents were
put together as requested by PWC but in the end ‘the outcome was that we
were not in a position to raise enough capital due to no significant assets to
lend against.’54
[106] In mid-2013 Mr Bradford retrenched 50 to 60 employees. He states that this
was a the time that he was unable to inject any working capital as he did
not have sufficient personal funds and because the business loan with
Bendigo bank was fully drawn down.55 He further states that this was at a
time when a couple of contracts were nearing completion.56 Presumably,
the retrenched employees were those hired for those contracts.
[107] In early July 2013, Mr du Preez spoke with Rabo Bank in regards to
obtaining business finance but again that did not come to fruition.57
[108] In early August 2013, Mr du Preez who had been in regular contact with the
ATO and had disclosed the issues with the McNab contract, told Mr
Bradford that the ATO had suggested that it could issue garnishee notices
to McNab to recover the taxation debt. Mr Bradford states that he decided
that this was not in the interests of BBC as he considered that McNab had
a counter-claim against BBC.58
[109] As the ATO director’s penalty notice drew nearer Mr Bradford spoke to PWC
about engaging a good administrator to explore all options and discuss the
next course of action.59
[110] Mr Bradford says that he approached Korda Mentha and understood that
they would operate the company for a minimum of eight weeks as the work
on hand and money due in would satisfy the ATO debt but this did not occur
once Korda Mentha was engaged.
[111] The Tribunal finds that BBC sought advice regarding the raising of capital
in June 2013 but was unable to raise capital in July 2013. In the absence of
51 Exhibit 3, paragraph [45].
52 Exhibit 1, paragraph [72].
53 Exhibit 3, paragraph [54].
54 Exhibit 3, paragraph [55] and [56].
55 Exhibit 2, paragraph [11].
56 Exhibit 1, paragraphs [26] and [27].
57 Exhibit 3, paragraph [57].
58 Exhibit 1, paragraph [66].
59 Exhibit 3, paragraph [68].
-- 19 of 28 --
20
any evidence to the contrary, the Tribunal finds that Mr Bradford did not
seek any financial advice prior to BBC commencing the McNab project.
[112] The Tribunal finds that Mr Bradford and other members of BBC’s staff were
monitoring BBC’s cashflow week to week in 2013. The Tribunal accepts that
Mr Voyce was requesting payment from McNab and seeking payment from
other sources to assist with BBC’s cashflow.
[113] The Tribunal accepts Mr Bradford’s evidence that he continued throughout
2013 to source further work for BBC and manage other ongoing projects,
payment for which would have assisted with BBC’s cashflow.
The Report by Administrators dated 2 October 2013
[114] At paragraph 2.7 of the report by the administrators, Korda Mentha sets out
the events leading up to the administration:
The Director of the Company has advised us that the Company’s financial
position can be attributed to:
McNab Constructions Aust Pty Ltd (‘McNab’), who owed the Company
$1,195,786, not paying the outstanding monies. This amount has been due
since at least June 2013. The outstanding amounts related to the Curtis
Island LNG plant.
Additionally the Australian Taxation Office (‘ATO’) issued a Directors penalty
notice for $575,344 which required payment by 9 September 2013, in the
absence of which the Director would become personally liable for the debt.
The issuing of this notice led to the appointment of the Administrators.
Our investigations indicate the Company’s financial difficulties can also be
attributed to:
The Company not previously having managed its contractual position to
avoid the McNab debt being so significant and overdue for such a long
period.
Insufficient working capital to continue trading in the absence of the
McNab payment.
Historical trading results and cash flow being insufficient to meet
outstanding liabilities to the ATO.
[129] Korda Mentha’s report also states that the profit and loss statement
suggests that the company was trading strongly between 1 July 2013 and
5 September 2013 and that if the company had been able to collect
monies due by McNab ($1,195,786) and other debtors it may have been
solvent.60 It also states that the company had trade debtors in the amount
of $2,430,779.61
Conclusion regarding the circumstances that resulted in the happening of
the event.
[115] Mr Bowden argues that the failure of the McNab project was the one
circumstance that led to the happening of the event. The Tribunal does not
accept that submission. While the Tribunal accepts that the failure of McNab
60 Paragraph [2.10] of the Korda Mentha report at annexure “MB-3” of Exhibit 1.
61 Ibid, at paragraph [2.9.1] on p 7.
-- 20 of 28 --
21
to pay BBC its payment claims in full affected BBC’s cashflow, other
circumstances contributed to that lack of cashflow becoming a serious issue
for BBC. For example, had BBC had sufficient working capital McNab’s
failure to pay may not have so dramatically affected BBC.
[116] The Tribunal has accorded substantial weight to the report of Korda Mentha
in identifying the circumstances that resulted in the administration of BBC.
The Tribunal considers that the factors listed by Korda Mentha as the events
leading up to administration and the factors which contributed to BBC’s
financial difficulties are consistent with the evidence of Mr Bradford. Based
on the findings of fact already made by the Tribunal and the report of Korda
Mentha, the Tribunal identifies the following circumstances that resulted in
the happening of the event.
[117] The administrators were appointed because Mr Bradford was unable to
satisfy the Director’s Penalty notice issued by the ATO in August 2013.
[118] BBC’s tax liability was a relevant circumstance as was the inability of BBC
and Mr Bradford to meet that liability resulting in the need for a payment
arrangement with the ATO, which commenced from 28 February 2013.
Further, BBC’s failure to adhere to that arrangement was also a relevant
circumstance.
[119] Further, BBC’s lack of cash flow due in part to the non-payment of its
payment claims in relation to the McNab project was a relevant
circumstance.
[120] From BBC’s point of view, McNab owed it substantial monies. Its failure to
recover those monies was also a relevant circumstance.
[121] BBC’s inability to raise working capital when it experienced cash flow
problems was also a relevant circumstance as well as its insufficient
working capital to continue trading in the absence of any payments from
McNab.
Consideration of whether the applicant took all reasonable steps to avoid
those circumstances coming into existence including identification of the
steps Mr Bradford took.
Submissions
[122] The Tribunal has already dealt with the applicant’s submission regarding
BBC’s previous profitability62 and accepts Mr Bradford’s lengthy experience
in the concreting industry including 16 year working for Remo Concreting.
[123] It was submitted that as BBC only dealt with ‘Tier 1’ construction companies
there was ‘really no room to negotiate the terms of each contract and
therefore no need to instruct solicitors in relation to each contract.’
[124] It was further submitted that the failure of the McNab contract could not be
attributed to the lack of a contract being in place prior to mobilisation of
BBC’s workforce. It is argued that the email of 23 October 2012 was a ‘letter
62 [20], [21].
-- 21 of 28 --
22
of intent’ and at that stage the parties were bound. The applicant relies on
a number of cases for that proposition.63
[125] It is argued further that the steps taken up to and including the meeting on
7 December 2012 is clear evidence that the scope of works was settled by
that date at the latest and that thereafter the parties proceeded as if there
as a contract even if there was not and the subsequent conduct is
admissible.64
[126] Alternatively, the applicant argues that if there was no contract then BBC
may well have been better placed. It could have walked off the job and
pursued a quantum merit claim.
[127] The applicant further submits that there is no basis for concluding that the
absence of a contract made any difference to the result as none of the terms
of the contract would have assisted BBC to avoid the consequences that
occurred.
[128] By subsequently signing the contract the parties applied the terms of the
contract to their relationship retrospectively and it defined their rights. As
McNab did not change its position but continued to deny BBC’s claim, the
dispute did not relate to or arise out of the fact that there was no written
contract.
[129] The applicant acknowledges three disputes: (a) as to variations, (b) as to
certain back charges and (c) as to simple non-payment of some progress
claims.
[130] The applicant relies on a number of events which he says were beyond his
control which affected the manner in which the project was performed by
BBC and the profitability of the contract:
a) the motorcycle accident of Mr Farmer which prevented him being on
site.
b) From about the last week in January until about the first week of March
there was wet weather. This had the result of preventing work on the
site by BBC. McNab refused to give an extension of time.
c) Then McNab wanted to vary the scope of works. They wanted work to
be done on seven buildings simultaneously. This required much
additional staff and equipment on the part of BBC.
d) McNab then decided to remove critical parts of the work from BBC.
[131] Mr Bowden submitted that Mr Bradford was on top of the events as they
occurred and the difficulties that they created and was aware of his legal
options. He considered using his BCIPA rights when McNab owed
$400,000.00. When the debt was about $500,000, he considered a
subcontractor’s charge. However, mindful of the business aspect of what
was occurring and the healthy business relationship with McNab because
of the Village Coorparoo project, he decided to negotiate rather than to
63 Sinclair Scott & Co v Naughton (1929) 43 CLR310 at 317.
64 Abigroup Contractors Pty Ltd v ABB Services Pty Ltd [2004] NSWCA 181 at [63] per
Giles JA.
-- 22 of 28 --
23
litigate. Litigation would be a lengthy process and BBC did not have that
time.
[132] The attempt to refinance in mid-June 2013, demonstrates Mr Bradford’s
financial awareness, concern and responsibility and the repayment
arrangement negotiated with the ATO also supports that submission.
[133] In mid-August there was discussion of a possible compromise with McNab
and that was the appropriate approach. The administrators were appointed
when this was unavoidable. This was only two to three weeks after the final
attempt at negotiation.
[134] In terms of the general discretion, the applicant submits that there can be
no criticism of the applicant as to how he handled the McNab transaction
once the dispute had arisen. However, time ran out.
[135] The QBCC submits that the applicant has not demonstrated that he has
taken all reasonable steps to avoid the circumstances resulting in the
relevant event in particular that he:
did not seek appropriate legal advice before entering into financial
or business arrangements or conducting business
did not put in place appropriate credit management for amounts
owing and take reasonable steps for recovery of the amounts or
did not make appropriate provision for Commonwealth or State
Taxation debts and therefore the discretion should not be exercised.
[136] The QBCC made additional submissions related to the general exercise of
the discretion but given the conclusion reached by the Tribunal it is
unnecessary for the Tribunal to consider those submissions.
Consideration
[137] In deciding whether Mr Bradford took all reasonable steps to avoid the
coming into existence of the circumstances that resulted in the happening
of the relevant event, the Tribunal must have regard to the matters set out
in s 56AD(8A).
Keeping proper books of account and financial records
[138] The respondent does not take issue with the books of account. The report
of Korda Mentha states that from their investigation, at that point, they
considered that the company had maintained books and records in
accordance with the requirements of the relevant Act.65 The Tribunal is
satisfied that the applicant kept proper books of account and financial
records in respect of BBC.
Seeking appropriate financial and legal advice before entering into financial or
business arrangements or conducting business
[139] Mr Bowden submits that the problem confronting the applicant was not one
to be solved by any form of technical financial or legal advice and that Mr
Bradford’s problem was that McNab took a perverse view of its obligation to
make payments under the contract. BBC proceeded on the basis that it had
65 At paragraph [3.4.1].
-- 23 of 28 --
24
a good case and legal advice confirming that fact was not of any particular
use. The Tribunal does not accept that submission.
[140] That submission assumes that, had legal advice been obtained, it would
have been consistent with Mr Bradford’s views at all relevant times. The
Tribunal does not know what the advice would have been as no advice was
sought.
[141] Further, if indeed Mr Bradford considered BBC had a good case, then
McNab’s continuing failure to accede to BBC’s demands could well have
been dealt with in a timely manner by seeking and pursuing contractual
advice.
[142] Mr Bowden’s alterative argument is that if there was no contract in place
until late March 2013 BBC could have walked off the job up until that time.
Presumably then had BBC done so, the relevant event may have been
avoided. However, Mr Bradford did not seek advice about BBC’s options at
that time.
[143] Mr Bradford is not a lawyer. While it may not have been his practice to seek
legal advice before signing a contract, the McNab project was a large one,
governed by many legal documents not only between McNab and BBC but
also between Bechtel and McNab. Any dispute between Bechtel and
McNab could potentially affect BBC. During the negotiations with McNab,
Mr Bradford was aware of the other matters impacting BBC’s financial
position including the lack of working capital, its inability to raise further
working capital, the other contracts BBC had on foot, its ongoing taxation
liabilities and the impact non-payment by McNab would have on cashflow.
Further, it is not prudent to commence to perform a contract prior to its
execution.
[144] While Mr Bradford and Mr Voyce considered they had an agreement with
McNab, in December 2012, there was no completed contract in place before
BBC mobilised workers to Curtis Island and commenced work. No advice
was sought regarding BBC’s rights and obligations in the absence of a
formal written contract, for example, whether the parties were bound by a
‘letter of intent’ or otherwise.
[145] The applicant submits that once a dispute arose, negotiation was the best
option to resolve any dispute and there was no reason to consider that any
other legal avenue would have led to a better result. Mr Bradford’s evidence
was that BBC had never experienced such conflict on a project before and
that in other contracts any dispute was sorted out amicably and within a
reasonably quick time frame. That did not occur with the McNab project.
The ongoing disputes with McNab were outside Mr Bradford’s usual
experience yet he did not seek any legal advice about any options available
to BBC at any time.
[146] Further, the Tribunal does not consider that it can, or is required to,
determine that negotiation was the best option. Nor does the Tribunal
consider that the appropriate question for it to ask and determine is whether
any other legal avenue would have successfully avoided the relevant event
or whether Mr Bradford should have commenced legal proceedings or
whether any such proceedings would have been successful. It is also
-- 24 of 28 --
25
unnecessary for the Tribunal to speculate as to what legal advice would
have been given had it been sought.
[147] The Tribunal must ask whether the seeking of appropriate legal advice at
any particular stage was a reasonable step to avoid the coming into
existence of the circumstances that resulted in the administration given
what Mr Bradford knew at those points in time.
[148] The Tribunal has found that there were disagreements between BBC and
McNab regarding not only the scope of works but also site management of
the work including the impact of wet weather on site and the refusal of
McNab to grant BBC an extension of time to complete its work as well as
payment issues. Those disagreements arose as early as February 2013
prior to the contract being finalised and remained ongoing problems
thereafter. Mr Bradford did not seek legal advice about BBC’s rights or
remedies in respect of those issues. Mr Bradford conceded in cross-
examination that it was probably reasonable for him to have sought legal
advice about McNab’s refusal to grant an extension of time for BBC to
complete its work following the wet weather in January and February 2013.
[149] After the contract was made, there was dispute between McNab and BBC
over a number of issues including the scope of BBC’s works, ongoing issues
regarding the wet weather delays, the engagement by McNab of other
labour, the back charges that flowed from this, McNab’s withdrawal of
certain work from BBC and the non-payment of claims and variations. At no
time did Mr Bradford seek legal advice about BBC’s rights or remedies in
respect of any of those areas of dispute. All of those areas of dispute
negatively impacted BBC’s cash flow.
[150] Further, Mr Bradford did not seek legal advice on any options BBC might
have to recover monies he maintained were owed by McNab. He did not
pursue the dispute resolution processes under the contract.
[151] The Tribunal does not consider that Mr Bradford’s reason for failing to seek
advice in March/April 2013 was due to his desire to maintain a relationship
with McNab. He gave conflicting evidence that the relationship had soured
by March/April 2013. Rather, the Tribunal considers he simply held fast to
the position that BBC would be paid without any reasonable basis for
maintaining that position at that time. Further, and in any event, given Mr
Bradford’s knowledge of the financial circumstances impacting BBC, the
Tribunal considers his decision to prioritise the maintenance of a
relationship with one contractor, albeit a large company, over BBC’s future
viability to be unreasonable and imprudent.
[152] The Tribunal does not consider that Mr Bradford’s belief that BBC would be
paid $650,000 as late as early August 2013 prevents such a finding.
[153] Taking into account the matters known by Mr Bradford regarding the
financial position of BBC, at all relevant times, including its limited working
capital, its inability to quickly raise further working capital, and the effect any
non-payment by McNab would likely have on BBC’s cash flow, and for the
reasons already given, the Tribunal concludes that Mr Bradford did not seek
appropriate legal advice in either entering into business arrangements or in
-- 25 of 28 --
26
conducting business. Further, the Tribunal considers that the seeking of
such advice in those circumstances was reasonable.
[154] The Tribunal considers it open to find that Mr Bradford did not seek
appropriate financial advice before entering into the contract with McNab
and it was reasonable to do so. While PWC and Mr du Preez were consulted
and involved in negotiations with the ATO and Bendigo Bank and Mr du
Preez provided updates to Mr Bradford regarding BBC’s cash flow, neither
PWC nor Mr du Preez were engaged to advise whether BBC had sufficient
working capital to continue trading in the absence of payment by McNab.
Negotiations with the ATO commenced as early as January 2013 due to
concern regarding McNab’s non-payment of BBC’s claims. That was before
the contract documents were executed by BBC and McNab.
[155] The focus of s 56AD is concerned with the prudent management of a
company as an ongoing business, or prevention rather than dealing with
problems after they have arisen. The Tribunal does not consider that Mr
Bradford took any proactive steps by seeking relevant advice either before
entering into the contract with McNab or after its execution when it was clear
disputes had arisen.
Reporting fraud or theft to the police.
[156] This matter does not arise on the facts of this case.
Ensuring guarantees provided were covered by sufficient assets to cover the
liability under the guarantees
[157] The Tribunal has no evidence before it regarding any guarantees.
Putting in place appropriate credit management for amounts owing and taking
reasonable steps for recovery of the amounts
[158] At the time of administration, Mr Bradford informed Korda Mentha that BBC
was owed $1,195,786 by McNab. The company had recorded trade debtors
of $2,430,799.
[159] Mr Bowden submits that the McNab debt was probably not recoverable yet
also argues that McNab was intent on breaching the contract. The Tribunal
does not consider that it must determine whether the debt was recoverable
or whether McNab breached the contract.
[160] The Tribunal has found that Mr Voyce secured funds from another
contractor to assist BBC’s cash flow and cash flow was monitored
throughout 2013. Mr Voyce also demanded payment from McNab
throughout 2013. These were reasonable steps. Mr Bradford retrenched
some staff in June 2013. In the circumstances, this was also likely to be a
reasonable step.
[161] The Tribunal has found that Mr Bradford managed other ongoing projects
throughout 2013, payments for which may have assisted BBC’s cash flow
and Mr Bradford continued to source other projects for BBC.
[162] The Tribunal has already found that the non-payment of BBC’s claims in
connection with the McNab project negatively impacted BBC’s cash flow in
2013. McNab did not pay BBC the total amount of its monthly payment
claims from February/March 2013. Mr Bradford informed Korda Mentha that
-- 26 of 28 --
27
McNab had owed BBC $1,195,786 since at least June 2013. However, Mr
Bradford did not seek legal advice about recovery action against McNab or
take any formal steps to recover any unpaid payment claims from McNab.
He did not make a BCIPA claim, issue a sub-contractor’s charge or seek to
avail himself of the dispute resolution processes provided for in the contract.
[163] While the staff of BBC and Mr Bradford took some reasonable steps for
recovery of amounts owing to BBC, the Tribunal does not consider that Mr
Bradford took all reasonable steps for recovery of amounts owing to BBC.
Making appropriate provision for Commonwealth and State Taxation debts
[164] Korda Mentha’s investigations revealed that BBC’s historical trading results
and cash flow were insufficient to meet the outstanding liabilities of the ATO.
[165] BBC had not retained funds to pay the ATO. Mr Bowden submitted to the
Tribunal that he had never seen any commercial business keep PAYG tax
aside. What other businesses do about making provision to meet their
PAYG liabilities is not in evidence before the Tribunal. The Tribunal must
consider whether Mr Bradford as director of BBC made appropriate
provision for taxation debts.
[166] Mr Bowden also submitted that but for the McNab transaction, BBC could
have met its liability to the ATO. It is clear that the McNab project affected
cash flow. However, there were other circumstances, which contributed to
BBC’s financial difficulties including its inability to raise further working
capital after March 2013.
[167] While Mr Bradford, through Mr du Preez, arranged for Ms Leis to liaise with
the ATO and she negotiated a payment arrangement with the ATO, BBC
did not have sufficient funds to pay the instalments once the company
experienced problems with cash flow and it did not make any repayments
after June 2013.
[168] It was Mr Bradford’s inability to satisfy the Director’s Penalty Notice issued
in August 2013 by 9 September 2013, which led to Mr Bradford engaging
Korda Mentha. The amount sought by the ATO was $575,344. As the
Tribunal has found, Mr Bradford had no equity in any of his personal assets
and no ability to raise funds to pay the ATO.
[169] For the reasons given, the Tribunal finds that Mr Bradford did not make
appropriate provision for taxation debts.
Other matters taken into account
[170] The Tribunal is entitled to have regard to other factors in considering
whether the applicant took all reasonable steps to avoid the circumstances
coming into existence. The Tribunal is entitled to consider the manner in
which Mr Bradford conducted the business of BBC in a broad sense.
[171] BBC’s limited working capital, the repayment arrangement with the ATO,
BBC’s commitments to repay particular amounts to Bendigo and its inability
to raise further working capital are all relevant matters for the Tribunal to
consider under s 56(AD)(8B) of the QBCC Act. Mr Bradford was aware of
those matters when he engaged BBC in the McNab project and acted as he
did in the relevant period.
-- 27 of 28 --
28
[172] Further, Mr Bradford decided to mobilise his men to Curtis Island in the
absence of a completed written contract. Mr Bowden submitted that it is not
unusual for lessees to take possession of premises in the absence of an
executed lease. However, the Tribunal does not consider that in either case
such action could be considered prudent.
[173] Mr Bowden submits that events beyond Mr Bradford’s control affected the
profitability of the McNab project.66 The Tribunal accepts that Mr Bradford
could not predict the weather or Mr Farmer’s accident. However, the
Tribunal does not consider it unusual for businesses to experience
unexpected events, which impact their financial position. Prudent
management of a business includes having contingency plans or strategies
in place to deal with such events.
[174] Further, the unexpected events gave rise to disputes regarding the scope
of works and the programme of work which were contractual matters. The
Tribunal has already considered Mr Bradford’s actions in relation to
obtaining legal advice and pursuing BBC rights and remedies under the
contract.
[175] In the circumstances of this case, the Tribunal does not consider that Mr
Bradford’s actions were those of a prudent manager.
Conclusion
[176] In all of the circumstances, the Tribunal is not satisfied that Mr Bradford took
all reasonable steps to avoid the coming into existence of the
circumstances, which led to the administration.
[177] Given that the Tribunal is not satisfied as to the threshold issue, the Tribunal
is not required to consider whether to exercise the discretion to categorise
the individual as a permitted individual.
[178] The reviewable decision to refuse to categorise Mr Bradford as a permitted
individual is confirmed.
66 [128] above and [46] of the written ‘Submissions of the Applicant’.
-- 28 of 28 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2015/405