Duke Building Pty Ltd v Queensland Building and Construction Commission & Ors [2015] QCAT 397
CITATION: Duke Building Pty Ltd v Queensland Building
and Construction Commission & Ors [2015]
QCAT 397
PARTIES: Duke Building Pty Ltd
(Applicant)
v
Queensland Building and Construction
Commission
(First Respondent)
Randall and Sharna Wright
(Second Respondents)
APPLICATION NUMBER: GAR187-14
MATTER TYPE: General administrative review matters
HEARING DATE: 31 August 2015
HEARD AT: Brisbane
DECISION OF: Member Hughes
DELIVERED ON: 6 October 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Decision of the Queensland Building
and Construction Commission to issue
Direction to Rectify No. 40067 dated 9
May 2014 is set aside.
CATCHWORDS: DIRECTION TO RECTIFY – DELAY - whether
fair – where home owners did not properly
check whether builder licensed – where home
owners entered agreement without written
conditions – where home owners proceeded
with plans that were not certified or approved
by Council - where home owners aware of
importance of certification and approval –
where home owners failed to act in own
interests and as reasonable consumer by
delaying approved plans for over two years –
where Commission did not advise owners to
obtain approved plans when home owners
made first complaint in 2011 – where
substantial delay meant home owners failed to
mitigate and deprived builder of opportunity to
-- 1 of 7 --
2
rectify in timely manner – where giving
Direction To Rectify after prolonged delay
contrary to interests of building industry and
consumers as a whole - where
blameworthiness of home owners outweighed
disadvantage from items to rectify
Queensland Building and Construction
Commission Act 1991, ss 3, 72
Queensland Civil and Administrative Tribunal
Act, s 20
Brisbane South Regional Health Authority v.
Taylor (1996) 186 CLR 541
Dixon Projects Pty Ltd v. Queensland Building
Services Authority [2009] QCCTB 2
Duke Building Pty Ltd v. Queensland Building
Services Authority, 02/09/13, unreported
Duke Building Pty Ltd v. Queensland Building
and Construction Commission [2014] QCAT
190
Fontain v. Queensland Building Services
Authority [2004] QCCTB 163
Gary Norwood Homes Pty Ltd v. Queensland
Building Services Authority [1997] QBT 193
Glen Williams Pty Ltd v. Queensland Building
Services Authority [2012] QCAT 127
Ireland v. Queensland Building Services
Authority [1999] QBT 180
Taouk v. Queensland Building Services
Authority [2013] QCAT 508
APPEARANCES:
APPLICANT: Mrs Vivienne Hughes, Director appeared for
Duke Building Pty Ltd
FIRST RESPONDENT:
SECOND RESPONDENTS:
Mr Michael Stretton of Holding Redlich,
Solicitors appeared for the Queensland Building
and Construction Commission
Mr Randall Wright and Mrs Sharna Wright
appeared in person
-- 2 of 7 --
3
REASONS FOR DECISION
What is this application about?
[1] Issuing a ‘Direction To Rectify’ to a builder after a delay caused by Home
Owners raises issues of fairness. The Queensland Building and
Construction Commission issued a Direction to Duke Building Pty Ltd
almost three years after Duke stopped work.
[2] The delay was because the home owners, Mr Randall Wright and Mrs
Sharna Wright did not make their complaint until they day after they had
obtained certified plans, some two years and five months after Duke
stopped work.
[3] Duke has therefore applied to the Tribunal to set aside the Direction.
What is the background to the application?
[4] Renovating a home without certified plans, essential conditions in the
agreement and properly checking the builder is fraught with risk.
Unfortunately for Mr and Mrs Wright, this is what they did when they
engaged Duke to renovate their home in February 2011 for $145,500.00.
[5] Duke stopped work in June 2011 because of a payment dispute and
before completion.1 Mr and Mrs Wright then made a complaint to the
Commission in December 2011 about the work. The Commission issued a
‘Direction To Rectify’ that was set aside by the Tribunal, because Mr and
Mrs Wright’s delay in producing certified plans deprived Duke of an
opportunity to comply timeously.2
[6] Mr and Mrs Wright had not obtained certified plans until November 2013.
However, the very next day they made a further complaint to the
Commission - over two years since Duke stopped work. Based on this
complaint, the Commission gave Duke another ‘Direction To Rectify’ on 9
May 2014.3
[7] The issue for me to decide is whether giving this further Direction is fair.
Is the ‘Direction To Rectify’ fair?
What does the Tribunal consider?
[8] A ‘Direction To Rectify’ may not be given if, in the circumstances, it would
be unfair.4 The Commission – and the Tribunal5 - may consider all
1 In Duke Building Pty Ltd v. Queensland Building Services Authority, 02/09/13,
unreported, the Tribunal determined that because Duke was unlicensed, it had no right
to suspend works for non-payment.
2 Duke Building Pty Ltd v. Queensland Building and Construction Commission [2014]
QCAT 190.
3 Direction To Rectify No. 40067 dated 9 May 2014.
4 Queensland Building and Construction Commission Act 1991 (Qld) s 72(5).
-- 3 of 7 --
4
circumstances that are reasonably relevant to decide whether to give a
Direction, and is not limited to the terms of the contract.6
[9] The discretion to issue a Direction is seamless and involves weighing up
factors, both for and against, its exercise.7 The Tribunal must consider the
competing interests of the parties: blameworthiness of the home owners
and the cause of the defective building work are relevant.8
What is the ‘blameworthiness’ of the home owners?
[10] The relevant circumstances suggest culpability or at least an acceptance
of risk by the home owners in not properly checking whether their builder
was licensed,9 entering into an agreement without written conditions (apart
from an overview of work and payments), proceeding with plans that were
not certified or approved by Council, and not obtaining certified plans and
making their current complaint to the Commission until a substantial delay
of some two years and five months after the builder stopped work.
[11] Although plans were approved by the time the Commission gave the
Direction, the delay between Duke stopping work, and Mr and Mrs Wright
obtaining approval and making the current complaint is still two years and
five months. A home owner should not delay their application for a
Direction if the delay would result in the Direction being unfair or
unreasonable in the circumstances.10
[12] All but one of the items in the Direction are ‘Category 1’. For these items, it
means that it may be unfair or unreasonable to give a Direction if the delay
exceeds 3 months after the defective work became apparent.11 For the
‘Category 2’ item, it may be unfair or unreasonable if the delay exceeds
six months after the work was left incomplete or seven months, if the
home owner notified the builder within six months after the work was left
incomplete.12
[13] Mr and Mrs Wright lived in the house for a period of two years and five
months before obtaining certification and approval of the plans on 21
November 2013. They complained to the Commission about the items in
the Direction the next day on 22 November 2013. This suggests that
although Mr and Mrs Wright did not delay once they obtained approval,
the items were apparent well before then and the delay between work
5 The Tribunal’s role is to produce the correct and preferable decision by way of a fresh
hearing on the merits: Queensland Civil and Administrative Tribunal Act 2009 (Qld) s
20.
6 Queensland Building and Construction Commission Act 1991 (Qld) s 72(3).
7 Ireland v. Queensland Building Services Authority [1999] QBT 180 at 29.
8 Dixon Projects Pty Ltd v. Queensland Building Services Authority [2009] QCCTB 2.
9 A search was done on the Builder Licence Number but not Duke. No enquiries were
made about why the name revealed by the search did not match the name of the
Builder in the contract.
10 QBCC Rectification Of Building Work Policy.
11 QBCC Rectification Of Building Work Policy.
12 QBCC Rectification Of Building Work Policy.
-- 4 of 7 --
5
ceasing and Mr and Mrs Wright complaining to the Commission was
because they did not obtain certification earlier.
[14] Mr and Mrs Wright say they were not aware they needed to obtain
certification until the Commission advised them in September 2013.
However, it is reasonable to expect that the Commission should have
advised them of this when they made their initial complaint on 16
December 2011.
[15] Moreover, Mrs Wright knew the importance of getting approvals for the
building work during negotiations in early 2011, because Mrs Wright’s
business partner had been through an ordeal with builders who had
performed defective work.13 Their financier had also warned them to
obtain approvals to protect their asset and loan.14
[16] Therefore, despite knowing the importance of getting approvals, Mr and
Mrs Wright instructed Duke to proceed without certification and approval,15
because they wanted the work done quickly and were even willing to pay
an extra $3,000.00 for ‘as built’ approval (after completion) to ensure
this.16
[17] Mr and Mrs Wright claim that the builder advised them to defer approval
until completion to save time. However, it was Mr and Mrs Wright who
sought advice on how to expedite the building process. Regardless of
whether the builder advised them of how to proceed without certification of
approval, it was at their behest and for their benefit.
[18] The entire transaction is characterised by ‘cutting corners’ beyond that of
a reasonable consumer. Mr and Mrs Wright entered an agreement for
over $100,000.00 primarily without written terms and conditions. Mr and
Mrs Wright claim to have paid $8,000.00 in cash, but had no receipt to
show for it. Mr and Mrs Wright did not properly check whether Duke was
licensed. Mr and Mrs Wright did not specify in their agreement who would
be responsible for certifying plans and who is responsible for obtaining
and paying for them. Although they had been informed of at least some
degree of risk, Mr and Mrs Wright chose to proceed with plans that were
not certified or approved. Instead, Mr and Mrs Wright chose to seek
approval after completion to save time.
[19] Instructing a builder to proceed without plans that were certified or
approved, means Mr and Mrs Wright accepted or at least understood the
risk that the works might not comply with appropriate standards.
Moreover, while Mr and Mrs Wright may have had personal reasons for
proceeding with plans that were not certified or approved, it does not
justify a lengthy delay of over two years between their first complaint to the
Commission and actually obtaining certification to make a further
complaint, resulting in another Direction to the builder.
13 Statement of Sharna Wright dated 25 July 2013 at paragraph 15.
14 Statement of Sharna Wright dated 25 July 2013 at paragraph 19.
15 Statement of Sharna Wright dated 25 July 2013 at paragraph 20.
16 Statement of Sharna Wright dated 25 July 2013 at paragraph 14.
-- 5 of 7 --
6
[20] Plans can be certified any time. The delay in issuing the Direction can only
be due to Mr and Mrs Wright failing to act in their own interests by
obtaining certification at a time when a reasonable consumer would have,
or by the Commission’s failure to advise Mr and Mrs Wright of the need to
obtain certification when they made their first complaint, in December
2011.
[21] The evidence therefore suggests that Mr and Mrs Wright delayed
complaining to the Commission about the items forming the current
Direction not because they were not aware of the defects,17 but because
they had not had the plans certified. I am satisfied that Mr and Mrs Wright
should reasonably have been aware of the need to obtain certification
certainly by the time they made their first complaint to the Commission in
December 2011.
[22] Despite this, they did not obtain certification until November 2013. Their
further complaint was made the day after they finally obtained certification.
It is therefore reasonable to infer the delay arose because of their failure
to certify until November 2013 – well outside the prescribed periods for
when it is fair for the Commission to issue a Direction.18
[23] An important premise of regulatory time limits is that people should be
entitled to move on with their lives without an ongoing and indefinite threat
of complaints or legal action.19 The delay in obtaining certification has
deprived Duke the opportunity to address the issues in a timely way.
[24] Awaiting the outcome of other Tribunal proceedings also does not explain
the delay in certification. Regardless of whether Duke or Mr and Mrs
Wright were contractually responsible to obtain certification and approval,
or the outcome of the review of the previous Direction, Mr and Mrs Wright
have a duty to mitigate their loss and obtain certification and approval of
their plans in a timely manner to ensure any Direction is issued in a timely
manner, so the Builder can comply in a timely manner. They did not and
have therefore not acted reasonably.
[25] The Commission submitted that consumer protection is the primary
purpose of the Act and Parliament’s intent is to clearly lay responsibility for
defective building works with the builder.20 However, a Direction is not
given solely to benefit the individual home owner, but to discharge the
Commission’s statutory responsibilities to ensure proper industry
standards21 and achieve a reasonable balance between the interests of
builders and consumers.22
17 Paragraph [10].
18 Paragraph [12].
19 Review of the Limitation Of Actions Act 1974 (Qld), Report No. 53, Queensland Law
Reform Commission September 1998, p 6.
20 Glen Williams Pty Ltd v. Queensland Building Services Authority [2012] QCAT 127 at
[16].
21 Taouk v. Queensland Building Services Authority [2013] QCAT 508 at [39].
22 Queensland Building and Construction Commission Act 1991, s 3(a)(ii).
-- 6 of 7 --
7
[26] Giving a Direction after a prolonged delay for which the builder is not
responsible is contrary to the interests of the industry and consumers as a
whole. This is because it means the burden of insuring against and
responding to ongoing and indefinite complaints is inevitably passed on to
other builders and home owners through higher insurance premiums and
increased building costs.23
[27] While the belated acquisition of certified and approved plans means the
Direction is valid, it does not mean it is fair.
Does this blameworthiness outweigh the cause of the defects?
[28] In circumstances where Duke did not comply with the Code, the
Commission considered that it was not unfair to give the Direction.
Certainly as builder, Duke was responsible to ensure the building work
complied with the Building Code of Australia.24 However, fault or no fault
will not necessarily be the decisive factor on whether to issue a
Direction.25
[29] Mrs Vivienne Hughes for Duke considered the cost to fix the items would
be minimal, while the Commission was unable to quantify the cost to fix
the items. In these circumstances, I consider any disadvantage to Mr and
Mrs Wright from the items to rectify is not sufficient to outweigh the
countervailing factors against warranting a Direction in this case.
[30] It is therefore not ‘fair’ to give Duke the Direction.
What is the ‘correct and preferable’ decision?
[31] Because it is not fair to give Duke the Direction, the ‘correct and
preferable’ decision is that the Decision of the Queensland Building and
Construction Commission to issue Direction To Rectify No. 40067 dated 9
May 2014 is set aside.
23 Review of the Limitation Of Actions Act 1974 (Qld), Report No. 53, Queensland Law
Reform Commission September 1998, p 8, citing Brisbane South Regional Health
Authority v. Taylor (1996) 186 CLR 541 per McHugh J at 553.
24 Fontain v. Queensland Building Services Authority [2004] QCCTB 163.
25 Glen Williams Pty Ltd v. Queensland Building Services Authority [2012] QCAT 127 at
[16[, citing Gary Norwood Homes Pty Ltd v. Queensland Building Services Authority
[1997] QBT 193.
-- 7 of 7 --