David Cameron Mills t/as D C Mills Developments v Fitch [2015] QCAT 272
CITATION: David Cameron Mills t/as D C Mills
Developments v Fitch [2015] QCAT 272
PARTIES: David Cameron Mills t/as D C Mills
Developments
(Applicant)
v
Peter Fitch and Andrea Fitch
(Respondents)
APPLICATION NUMBER: BDL052-13
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Allen
DELIVERED ON: 14 July 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. David Cameron Mills must pay Peter Fitch
and Andrea Fitch costs of and incidental
to application BDL052-13 in an amount to
be agreed, or failing an agreement on a
standard basis with reference to the
District Court scale.
CATCHWORDS: BUILDING MATTERS – COSTS – where
respondents successful in defending claim and
obtained award under their counter application –
applicant failed to accept formal offer which was
not more favourable
Queensland Building and Construction
Commission Act 1991 (Qld) s 77(2)(h)
Lyons v Dreamstarter Pty Ltd [2011] QCATA
142
Better Homes Queensland Pty Ltd v
O’Reilly and Anor [2013] QCATA 122
-- 1 of 3 --
2
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
[1] Mr Mills constructed a dwelling for Mr and Mrs Fitch which resulted in an
application being made to the Tribunal by Mr Mills for the amount of
$206,794.04 for alleged unpaid monies due under the contract. Mr and Mrs
Fitch denied Mr Mills claim made a counter application in respect of defects
originally said not to be less than $200,000 and overcharging for labour in
the amount of $53,072.25.
[2] Ultimately, Mr Mills was unsuccessful in his claim and the Fitches were
successful in their counterclaim to the extent of being awarded $75,569.24
following a three and half day hearing with counsel on both sides.
[3] The Tribunal has a discretion in building matters to award costs1. Judge
Kingham noted that the section does not provide further guidance or
prescription about the occasions for or conditions of exercise of that power.
Further that, a jurisdiction given in general terms allows the Tribunal to make
an order as to costs that is justified in the circumstances. It a broad general
discretion which must be exercised judicially, not upon irrelevant or
extraneous considerations but upon facts connected with or leading up to
the litigation2.
[4] The Tribunal made a direction that the parties make submission in regard
to costs in its order of 24 March 2015. The Fitches have made submissions
requesting that they be awarded an amount of $103,256.17 in costs and
outlays. The outlays are in respect of experts who were required to give
evidence in regard to the defects and the costs of the building works.
[5] The Tribunal notes that an offer to settle the claim was made by Mr and Mrs
Fitch on 6 December 2013 in an amount considerably less that was
ultimately awarded to them and prior to the incurring of the bulk of their costs
in the amount of $60,163.17.
[6] While it is normal in the Tribunal that parties bear their own costs3 where an
offer which is not less favourable than the final decision has not been
accepted the Tribunal may award the reasonable costs of the party making
the offer4. This has a similar effect as a Calderbank offer. Clearly, Mr Mills
should have been able to obtain appropriate advice as to his prospects of
1 Queensland Building and Construction Commission Act 1991 (Qld), also see Lyons v
Dreamstarter Pty Ltd [2011] QCATA 142 per Kingham J.
2 Lyons v Dreamstarter Pty Ltd [2011] QCATA 142 Para 32 and 33.
3 Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 100.
4 Queensland Civil and Administrative Tribunal Rules 2009 (Qld) r 86.
-- 2 of 3 --
3
success in the application if it went to hearing in which case it would have
been in his interests to accept the offer.
[7] While the total amount of the costs is considerably more than was awarded
it must be noted that the Fitches were successful in defending Mr Mills’ claim
in the amount of $206,794.04 which puts the costs in proportion.
[8] This application was complicated both in terms of the legal issues and the
factual issues and having regard to the number of hearing days, it is clear
that legal representation was required. The material before the Tribunal only
indicates the amount of the costs and the Tribunal has been asked either to
seek further material as to the reasonable costs or have the costs assessed
on the District Court scale.
[9] That scale has been requested as the total amount of the claim was within
the jurisdiction of the District Court. The Tribunal notes that the jurisdiction
of the magistrate’s court extends to $150,000.00 and Mr Mills’ claim was as
mentioned in the amount of $206,794.04. It was submitted that a claim for
costs on the District Court scale had previously been granted by the
Appeals Tribunal in a building matter5.
[10] The Tribunal is satisfied that costs should be awarded to the Fitches in this
application as they were successful in defending the claim and also
successful in their counter application. These costs could also have been
limited if Mr Mills had accepted the offer to settle which was more favourable
to him than the final order of the Tribunal.
[11] The Tribunal orders that David Cameron Mills must pay Peter Fitch and
Andrea Fitch costs of and incidental to application BDL052-13 in an amount
to be agreed, or failing an agreement on a standard basis with reference to
the District Court scale.
5 Better Homes Queensland Pty Ltd v O’Reilly and Anor [2013] QCATA 122.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2015/272