Engapadalil v Steve Parcell Building Services [2015] QCAT 54
CITATION: Engapadalil v Steve Parcell Building Services
Pty Ltd [2015] QCAT 54
PARTIES: Fageer Engapadalil
(Applicant)
v
Steve Parcell Building Services Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL253-14
MATTER TYPE: Building matters
HEARING DATE: 5 February 2015
HEARD AT: Brisbane
DECISION OF: Member Favell
DELIVERED ON: 18 February 2015
DELIVERED AT: Brisbane
ORDERS MADE: The applications are dismissed.
CATCHWORDS: BUILDING MATTERS - where contract to build
new residence - whether contract required brick
work to be rendered - effect of variation
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Fageer Engapadalil
RESPONDENT: Steve Parcell Building Services Pty Ltd
REASONS FOR DECISION
[1] Fageer Engapadalil and Venitha Crispin contracted with Steve Parcell
Building Services Pty Ltd for a new domestic dwelling to be built at the
Promenade, Springfield Lakes on 19 June 2013. The contract was a
master builder’s residential building contract made up of 28 pages.
[2] This application was listed as a hybrid hearing however the parties agreed
that it was unlikely there would be compromise. The application was then
heard.
-- 1 of 6 --
2
[3] The building contract in the special conditions had the wording “as per
building specification and quote #1683/3 dated 17 June 2013”. That quote
relevantly described the exterior under the heading “building
specifications” as:
“Exterior cladding –
Boral single height bricks, from builders range, with natural
mortar
Rendered brick to front façade and
Linear to remainder.”
[4] Mr Engapadalil complains that the builder did not render the brick work on
the house and seeks an order that the builder render the brick work or pay
the owner the cost of rendering. He contends that the rendering was
required by the contract and was based on a covenant requirement
applicable to the area. His claim is for approximately $5,000.00 -
$6,000.00.
[5] He also seeks an order that the builder pay the owner the cost of variation
of $400.00 which was chosen by the owner to upgrade to double height
brick.
[6] The whole of the claim made depends on whether there was an obligation
in the contract to render the house.
[7] Mr Engapadalil contends that because the plans which were drawn by
William H Wilson and Associates had on drawing sheet 4 of 11 the words
“rendered B’work” on the front elevation and the right side elevation it was
a term of the contract that the brick work would be rendered.
[8] Mr Parcell contends that there was no such obligation agreed to in the
contract and points to the wording used under the heading “exterior” and
the 2 pages of drawings attached to the quote which made no reference
to rendered brick work except for a portion on the front elevation. Those
drawings have on them a statement that the drawing remains the property
of Steve Parcell Building Services and it has the notation “proposed
dwelling at lot 396 the Promenade Springfield Lakes for Fageer and
Vinitha.”
[9] In clause 10 of the contract the builder warrantied that it would carry out
the works in an appropriate and skilful way with reasonable care and skill
in accordance with the plans and specifications and in accordance with all
relevant laws and legal requirements.
[10] At the time of the signing of the contract the only plans in existence were
the 2 plans signed and dated the 19 June 2013. The only specifications
were those that were contained in the quotation also signed on 19 June
2013.
-- 2 of 6 --
3
[11] Mr Engapadalil relies on the plans drawn by W H Wilson made up of 12
pages. Whilst on page 4 of 11 there appears the words “rendered B’work”
on the front elevation and the right side elevation there is no such notation
on the left side elevation or the rear elevation.
[12] The words “rendered B’work” are said by Mr Parcell not to be a term of
the contract requiring brickwork to be rendered. He contends that on the
front elevation the rendered brickwork was to be confined to an area on
the side of the garage and on the right side it was to be rendered so as to
be able to finish the render on the front elevation by taking it around a
corner.
[13] The William H Wilson plans were drawn on the 5 July 2013 after the
contract was signed.
[14] Mr Engapadalil in part relies on a covenant approval for his lot from
Lendlease dated the 29 July 2013. It includes a stamp signifying approval
by Lendlease on the 6 pages of the Wilson plans included with the
covering letter.
[15] The difficulty with that is there is no evidence that the builder was in
anyway involved with the obtaining of covenant approval or agreed to the
rendering of brick work as claimed by Mr Engapadalil.
[16] Mr Engapadalil also relies on clause 16 in the building covenant. Clause
16 provides:
“External building materials
A selection of external building materials and colours which add variety and
complement the style of architecture must be used. All homes within the
Promenade must have a rendered finish to all external walls, and may
incorporate the following materials as a feature element:
one colour block, split, honed or polished;
feature stone;
prefinished metal feature panelling with light weight battens;
light weight cladding suitably painted or stained (e.g. weatherboard,
plywood);
Alternative materials may be permitted and will be considered on
within the Promenade. Galvanised iron, zinc or aluminium coated steel,
corrugated or unpainted fibre cement sheeting and bare, painted or pre
coloured concrete bog work are also not permitted for any external building
works.”
[17] “Render” is defined in the glossary of terms as “a finish applied to walls to
cover the bricks and mortar joints. The finish of render is commonly
smooth, but may be textured if desired as long as mortar joints and the
brick or masonry profile is not visible.”
-- 3 of 6 --
4
[18] Although the covenant asked for a site plan, floor plans, elevations and
sections with natural surface level and a schedule of external building
materials and colours, no such schedule was provided and the only
mention of render was on the front elevation and the right side elevation
on one wall of the garage.
[19] Again there is no evidence that the builder was a party to the covenants.
[20] The building contract allowed for variations by agreement. In clause 12
either party could give the other written notice requesting a variation and
the parties could agree to vary the works by adding or omitting work from
the works.
[21] In an email of 16 January 2013 from Mr Parcell to the owners there
appeared the following “firstly we are working on the understanding that
your home will include the following inclusions…render to front garage…”
On the 4 April 2013 a further email confirmed a further inclusion as
“rendered mail box”.
[22] An email on the 19 August 2013 Mr Parcell, in response to a question
from the owners said “to change the linear to the front of the family room
to render would be an extra $482.” In an email of the 29 August to Mr
Parcell from Mr Engapadalil a variation form with render to the front family
room was requested.
[23] On the 2 September 2013 Julie Dayes sent an email to the respondent
which included the words “also he wants the cost to render the bricks on
the top side of home so all brick rendered from end of garage to bed 3
please.” By an email 5 December Mr Parcell noted the bricks specified
which only included rendered brick to the front area. At that time he asked
the owners to confirm their brick selection and told them that he was
happy to render 1.2 meters down the side of the garage for them.
[24] A variation signed by the owners on 24 September 2013 said: “to change
the linear to the front of the family room to render would be an extra
$482.00.”
[25] On 18 October 2013 the owners signed a variation with the following
description: “change for single height bricks with natural mortar to
Haymarket double height bricks with natural mortar as marked in black on
an attached plan.” The portion was that marked in black was on sheet 3 of
11 of the Wilson plans. That change had been made to all of the right
side. The variation change was to cost a further $400.00. The variation
noted that the owners understood and accepted the conditions detailed in
the variation and certified that the variations were made at their choice.
[26] In an email 5 December 2013 to Mr Parcell, Mr Engapadalil, under the
heading “Issue” said “during one of the colour selection meeting we were
told that the rendered brick stopped at the side of the garage and the rest
was unrendered.” – “Later Darleen clarified the render was only at the
front”.
-- 4 of 6 --
5
[27] Darleen Keats gave evidence1 that on or around 18 October 2013 she
received a request from Mr Engapadalil to prepare a variation to change
the side of the garage from single height bricks to rendered brick. She
emailed a plan hatching in black the area to be changed to render brick
and also emailed the variation with the additional charge.
[28] The email 18 October 2013 which enclosed the hatched area had the
words “attached is a variation and plan showing the area to be changed to
rendered brick.” The variation which was sent at that stage described the
work as: “change side of garage as hatched on the attached plan from
single height bricks of natural mortar to rendered brick.” That area was the
right hand side of the building.
[29] After that quote was supplied for the variation to render Mr Engapadalil
asked for a variation changing all brick to double height. Darleen Keats
returned a variation and a plan showing the area to be changed to double
height brick and later that day Mr Engapadalil replied “If upgrading to
double brick we won’t be rendering side of garage so please do variation
form for all the brick area.” That was then done and the variation was
signed.
[30] Ms Keats, and Mr Parcell2 gave oral evidence as well as their affidavits
and were subject to cross examination. The effect of the evidence was
that it was not a term of the agreement that brick work be rendered.
[31] In my view the emails and discussions prior to the contract being signed
and the emails and variations after the contract was signed corroborate
the claim that rendering was not part of the contract.
[32] In any event even if it were, the subsequent variation removed any
requirement for rendered brick with the exception of the front elevation,
where it was provided.
[23] Julie Dayes also gave evidence and was cross examined.3 Contrary to the
allegation of the owners she said that she did not advise the owners that
their house was fully rendered. The emails that she refers to in her
affidavit, in my view support the contention that it is unlikely there was to
be rendering of brick apart from the front elevation. A photograph
tendered by the applicants showing double height brick on the right hand
side of the house also shows the render that has been returned from the
front of the house around to a portion down the side.4
[24] The available evidence does not support the contention that it was a term
of the contract that all of the brick work was required to be rendered.
Many of the statements in the emails referred to above are contrary to
there being a requirement to render all the brick work. There is nothing in
the written contract that requires the brickwork to be rendered. The
1 Exhibit 6.
2 Exhibit 3.
3 Exhibit 5.
4 See exhibit 1.
-- 5 of 6 --
6
reference to “rendered B’work” on the Wilson plans was created after the
contract was agreed and signed.
[25] I am not satisfied that it was a term of the contract that brick work was to
be rendered. Even if it was however, there was a variation that changed
any such obligation if it existed.
[26] The application for an order requiring the builder to render the brick is
dismissed. The alternate claim for compensation to render the building is
also dismissed. I further note there was no evidence of the cost of any
rendering to support the alternate claim.
[27] The claim for the cost of the variation is dismissed. There is no basis to
make such a claim and the material demonstrates that the variation was
made in writing and agreed to by the applicants.
-- 6 of 6 --