Dunmoor Pty Ltd AFT Tiny Turtle Trust Fund v Queensland Building and Construction Commission & Mainz [2015] QCAT 449
CITATION: Dunmoor Pty Ltd AFT Tiny Turtle Trust Fund v
Queensland Building and Construction
Commission & Mainz [2015] QCAT 449
PARTIES: Dunmoor Pty Ltd ATF Tiny Turtle Trust Fund
(Applicant)
v
Queensland Building and Construction
Commission
Mainz Development Pty Ltd
(Respondents)
APPLICATION NUMBER: GAR371-13 / BDL073-14
MATTER TYPE: General administrative review matters
HEARING DATE: 23 June 2014; 24 June 2014
HEARD AT: Brisbane
DECISION OF: Dr Cullen, Member
DELIVERED ON: 5 February 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. That the Queensland Building and
Construction Commission’s decision of
26 September 2013, to not issue a
direction to rectify to pursuant to s 72(1)
of the Queensland Building and
Construction Commission Act 1991 to
Mainz Developments Pty Ltd be
confirmed.
2. Dunmoor Pty Ltd ATF Tiny Turtle Trust
Fund to pay Mainz Developments Pty Ltd
the sum of $40,981.34, inclusive of GST,
plus interest at the contractual rate of 15%
from the time of invoicing on 2 October
2008, until the date of decision.
CATCHWORDS: Queensland Building and Construction
Commission - review of refusal to issue builder
with a Direction to Rectify due to monies
outstanding on contract – corresponding
domestic building dispute commenced by builder
seeking payment of monies owed – dispute
between homeowner and builder in relation to
-- 1 of 8 --
2
nature of contract – whether cost-plus or fixed
price – Tribunal determines contract is cost-plus
Queensland Building and Construction
Commission Act 1991 (Qld), s 72
Briginshaw v Briginshaw (1938) 60 CLR 336
REPRESENTATIVES:
APPLICANT: Dunmoor Pty Ltd ATF Tiny Turtle Trust Fund
represented by Mr CM Tam, of Counsel,
instructed by Hickey Lawyers
RESPONDENTS: for the Queensland Building and Construction
Commission represented by Ms Emily Roberts,
in-house legal counsel
Mainz Development Pty Ltd represented by Mr
P Van Grinsven, M + K Lawyers
REASONS FOR DECISION
Background
[1] In late 2008, the Applicant, Dunmoor Pty Ltd ATF The Tiny Turtle Trust Fund
(‘Dunmoor’), entered into a contract with the Second Respondent, Mainz
Developments Pty Ltd, to carry out renovations and extensions to a home
on Selkirk Avenue in Benowa, Queensland (‘the property’). The contract
amount nominated at Item 6 of the Master Builders Residential Building
Contract was $215,000.00. Dunmoor operates as the family trust for Dr
Chris Leat, a cosmetic surgeon with a practice on the Gold Coast, and his
wife and children. Mainz Developments had undertaken work on Dr Leat’s
surgery prior to entering into the contract in relation to his home.
[2] In April of 2012, Dunmoor lodged a complaint with the Queensland Building
and Construction Commission regarding works carried out by Mainz
Developments at the Leat’s home. The QBCC investigated, and determined
that the complaint items were ‘Category 2’ defects within the QBCC policy,
and refused to issue Mainz Developments with a direction to rectify for the
reason that the QBCC determined that it was not notified in accordance with
the defects policy (i.e. within the prescribed period).
[3] Subsequently, on 8 April 2013, Dunmoor lodged a second complaint with
the QBCC in relation to the work performed by Mainz Developments at
Selkirk Avenue. On 2 September 2013, QBCC inspector BJ Luckan
attended the property to undertake an inspection.
-- 2 of 8 --
3
[4] Following his inspection, Mr Luckan determined that the following items
were Category 1 building defects, and the responsibility of Mainz
Developments to rectify:
Items 1 and 2: timber floor boards in the hallways adjacent to the sliding
windows and the living room adjacent to the sliding doors;
Item 3: timber floor near the rear right hand side corner of the living room
behind the tv cabinet; and
Item 7: cracking to the tiles on the rear external deck.
[5] However, because Mr Luckan concluded that Dunmoor owed Mainz
Developments approximately $45,000.00, and the costs to rectify the
defects would not exceed $34,000.00, Mr Luckan declined to issue Mainz
Developments with a direction to rectify.
[6] Dunmoor argues that Mr Luckan’s decision was infected by his mistaken
acceptance of Mainz Development’s assertion that the contract between the
parties was a ‘costs plus contract.’ Dunmoor asserts that the contract was
a ‘fixed price contract’ in the amount of $215,000.00. If the Tribunal accepts
this argument, there is no dispute that Dunmoor has paid this amount.
[7] Dunmoor now seeks an Order requiring the QBCC to direct Mainz
Development to rectify the defects identified by Mr Luckan. On 13 February
2014, Mainz Development was joined as a party to Dunmoor’s review
application.
[8] On 31 March 2014, Mainz Developments filed Application BDL073-12 in the
Tribunal, seeking that Dunmoor pay the $40,981.34 it alleged was owing
pursuant to what it says is a cost-plus contract, together with interest at the
contractual rate of 15%, as set out in the Master Builders contract signed
by the parties.
[9] As the issues arising in the review matter (GAR371-13) and domestic
building dispute matter (BDL073-14) both require determination by the
Tribunal of the issue surrounding the nature of the contract (whether it be
fixed price or cost-plus), on 27 May 2014, the Tribunal ordered that:
GAR371-13 and BDL073-14 will remain as separate proceedings, but be
heard and determined together.
Dunmoor’s submissions
[10] Dunmoor emphatically argues that the contract was for a fixed price. Dr
Chris Leat, the husband of Dunmoor’s sole director, alleges that the contract
was not signed until after work was commenced by Mainz Developments
and further claims that he was not provided with a copy of the contract after
it was signed.
-- 3 of 8 --
4
[11] Dr Leat says that Mainz Developments advised that (1) the contract would
be $215,000.00 in total, and (2) did not inform him that it was not possible
to calculate a price for a substantial amount of the works to be carried out.
[12] Dunmoor points to the scoping document it provided Mainz Developments
with, which it says set out the 22 items of work to be undertaken for the total
price of $215,000. This document, Dunmoor submits, is proof that the
nature and extent of work was known with sufficient precision, pointing to
the conclusion that the contract was indeed for a fixed price.
[13] Although Dr Leat conceded that some small changes had been made to the
contract, he initially claimed that the only ‘variation’ was the addition of a zip
tap in the kitchen. During his cross-examination, Dr Leat conceded that he
was not present when his wife selected the electrical fit-out with Ideal
electrical, and that there was a level of uncertainty in the kitchen plans. In
particular, the appliances had not been selected by the Leats. It was also
necessary to upgrade the power board one month after the contract was
signed.
[14] Since the conclusion of the contract, although the works were not complete,
Dr Leat alleges that there are a number of defects. In relation to the defects,
Dunmoor has obtained an expert report from Enviropest which states that
the damage to the floor boards located in the right hand corner of the living
room behind the TV unit was caused by termites. The Enviropest report
concludes that the work carried out by Mainz Developments in this area was
inadequate, which led to the termite infestation.
Mainz Development’s submissions
[15] Mr Craig Maindonald, the managing director of Mainz Developments, gave
evidence that he was unsure of the scope of the works and extent of
renovations required by Dunmoor, and further that no drawings or plans
were provided. For this reason, Mr Maindonald says that he informed Dr
Leat that he could not reasonably calculate the cost and could not
guarantee the works for $215,000.00.
[16] Mr Maindonald agrees that Dunmoor provided him with a scoping
document, but says this was to provide an indicative amount only. In direct
contradiction to Dr Leat’s evidence, Mr Maindonald says that he explained
to Dr Leat what a cost plus contract was, and then specifically included
handwritten notes in the contract to state its definition.
[17] A cost-plus contract, also termed a cost reimbursement contract, is a
contract whereby the contractor is paid for all of its allowed expenses to a
set limit, plus additional payment to allow for a profit. Section 55 of the
Domestic Buildings Contracts Act 2000 (Qld) prohibits cost-plus contracts,
save for in certain circumstances. One such circumstance is where, as
Mainz Developments says is the case here, is where a substantial portion
of the subject work cannot be calculated prior to the contract being entered
into.
-- 4 of 8 --
5
[18] In the absence of Mainz Developments having been provided with drawings
or plans, the Tribunal finds that entering into a cost-plus contract was
permissible. The scoping document was not adequate for anything more
than an indicative price.
[19] According to Mr Maindonald, Dunmoor continually changed the scope of
the works after works commenced. As a consequence, by the time that
works were completed, Mainz Development had incurred costs and
expenses in the sum of $255,981.34. Mr Maindonald agreed that Mainz
Developments had been paid $215,000.00 by Dunmoor.
[20] Mr Maindonald says that although he was owed money on completion of
the work at Selkirk Avenue, and told Dr Leat that it would need to be paid
prior to handover, Dr Leat assured him that he would be repaid once he
received his tax refund. Despite these assurances, upon presentation of the
invoices at the end of the job, around July of 2008, he claims Dr Leat told
him to call a lawyer.
[21] Mr Maindonald gave evidence that he received advice that it would not be
commercially sensible to chase the final monies outstanding by Dunmoor,
given the legal costs involved. As such, it was not until Dunmoor
commenced the review proceedings in this matter involving the QBCC that
Mainz Developments sought payment of the monies it says are outstanding.
The written contract in evidence
[22] Considering the nature of the dispute between the parties, one would think
that the parties had entered into an oral contract. That is not the case,
however. Mr Mainsdonald has provided his copy of the contract, which is
the only copy of the contract in evidence before the Tribunal.1
[23] The contract is the standard ‘Master Builders’ contract. On the face of it, at
‘Item 3 Description of Services’, the following words have been written in by
Mr Maindonald:
Renovation of House at 14 Selkirk Ave Benowa is a Cost Plus Contract
Because there are No Plans or specifications as owner Do Not want to Pay
Council fees.
[24] Dr Leat admits that his signature appears on the contract, but alleges that
a fraud has occurred in relation to the words contained at ‘Item 3’ as set out
above. Dr Leat claims that the words were inserted after he signed the
contract.
[25] At Item 11 of the contract, Dr Leat says he cannot recall whether he told Mr
Mainsdonald that the ‘Bank of Queensland’ was his financer. He has not
offered any explanation as to why Mr Mainsdonald would have entered this
information on the contract on his own volition. Rather, he argues that Mr
1 Statement of Reasons, 321-332.
-- 5 of 8 --
6
Mainsdonald filled the contract out before he arrived at Dr Leat’s office to
sign it. Mr Mainsdonald denies this.
[26] In relation to the signing of the contract, Dr Leat’s evidence was that it was
done hurriedly at his office. He claimed that the ticks which appear in the
boxes of the only copy of the contract before the Tribunal (at Items 22 and
26) must have been added later. Dr Leat told the Tribunal that he ‘doesn’t
do contracts’ and that these items were left blank on the contract at the time
of his signing.
[27] Mr Mainsdonald says that he gave Dr Leat a copy of the contract, which Dr
Leat denies. In line with his evidence in this respect, Dr Leat has been
unable to provide the Tribunal with his copy of the contract, which he says
does not include the words written at Item 3. Although there is a third copy
of the contract that would have been given to the lending institution (the pink
copy), neither party has obtained the pink copy by way of a Notice to
Produce.
Burden of Proof
[28] The Tribunal is not in a position where it is possible to tell which witness, Dr
Leat or Mr Mainsdonald, is telling the truth in relation to the nature of the
contract. On Dr Leat’s version of facts, the Tribunal would have to accept
that Mr Mainsdonald engaged in what Dr Leat referred to as ‘fraud’ in writing
in the term that the contract was cost-plus, following Dr Leat’s signature.
[29] An allegation of fraud is serious, and as such, the Tribunal considers that
the standard of proof required by Briginshaw v Briginshaw2 must be met,
should Dr Leat wish to rely upon this allegation as a defence to the debt
claim commenced by Mainz Development. In relation to Dr Leat’s review of
the decision made by the QBCC, it isn’t quite correct to refer to Dr Leat as
having a burden of proof in relation to those proceedings. However, it is
mighty difficult for the Tribunal to reach the conclusion that the QBCC has
not made the correct and preferable decision where there is no information
capable of satisfying the Tribunal that the contract was not a cost-plus
contract, save for Dr Leat’s own assertions.
[30] In Briginshaw, the High Court stated at pages 361–2 that the balance of
probabilities test required the Tribunal in that case to:
feel an actual persuasion of its occurrence or existence before it can be
found. It cannot be found as a result of a mere mechanical comparison of
probabilities independently of any belief in its reality … [A]t common law … it
is enough that the affirmative of an allegation is made out to the reasonable
satisfaction of the tribunal
[31] Dr Leat invites the Tribunal to find fraud on the part of Mr Mainsdonald, in
circumstances where the evidence establishes that he himself did not take
any reasonable care, nor devote any time to ensuring that the contract that
bears his signature was completed prior to being signed. Dr Leat is a
2 (1938) 60 CLR 336.
-- 6 of 8 --
7
sophisticated, well-educated man. Yet, his position is that he was too busy
to properly read and complete a contract worth in excess of $200,000.00.
The Tribunal does not accept that Dr Leat would not have understood the
potential legal importance of entering into a contract.
[32] The contract that is before the Tribunal is consistent with the evidence given
by Mr Mainsdonald in all respects. Faced with conflicting evidence, and Dr
Leat’s bare assertions that Mr Maindonald has behaved fraudulently, the
Tribunal prefers the evidence that is corroborated by the only copy of the
contract before it.
[33] With hindsight, Dr Leat should have insisted upon a copy of the contract,
and then filed it away, in order to protect himself down the track if something
went wrong. Had he done this, he would now be able to produce a copy of
the contract that corroborates his version of events.
Issues in a review of refusal to issue a direction to rectify
[34] In an administrative review by a homeowner in relation to a decision by the
QBCC to not issue a builder with a direction to rectify, the Tribunal must
consider 3 issues:
a) Was the work ‘building work’ and was it ‘defective’?
b) Was the Applicant responsible for the defective work? And
c) Was the Commission’s direction to direct the Applicant to rectify the
defective building work reasonable in the circumstances?
[35] There is no dispute amongst the parties that the work performed at Selkirk
Avenue was building work. Although some of the work was rectified by
another contractor following Mainz Development’s departure from the site,
there is no serious argument that the work was performed by Mainz
Developments.
[36] The real issue in these proceedings is whether it would have been
reasonable for the QBCC to issue Mainz Developments with a Direction to
Rectify. The Tribunal concludes that the QBCC correctly decided that
money was owed pursuant to the contract, which is a cost-plus contract.
[37] Mainz Developments has raised the question of timeliness in relation to the
timeframe within which Dunmoor complained. Under s 72(8) Queensland
Building and Construction Commission Act 1991 (Qld), Mainz
Developments is responsible for defective work for six years and three
months from the date the work is completed or left in an incomplete state,
where there is a Category 1 defect.
[38] This Tribunal has not addressed this argument for the reason that its finding
that the contract was cost plus, and not fixed price, is determinative of the
issues.
-- 7 of 8 --
8
[39] In all of the circumstances, the QBCC’s decision not to issue a direction to
rectify to Mainz Developments, due to the monies owing by Dunmoor under
the contract, was the correct and preferable decision.
[40] Having made this determination in relation to Dunmoor’s review application,
the Tribunal must now consider the application by Mainz Developments
seeking payment of the amounts it says are outstanding.
[41] The Tribunal considers it just in the circumstances that Mainz
Developments now be paid for the work it has performed. Mr Mainsdonald
has satisfied the Tribunal that the work invoiced for was performed for the
benefit of Dunmoor pursuant to the contract.
[42] Mainz Developments claims $40,981.34, inclusive of GST, plus interest at
the contractual rate of 15% from the time of invoicing on 2 October 2008,
until the time of decision. As there is no real dispute that the work was
performed, this is the amount that the Tribunal orders be paid by Dunmoor
to Mainz Developments.
Orders
[43] That the Queensland Building and Construction Commission’s decision of
26 September 2013, to not issue a direction to rectify to pursuant to s 72(1)
of the Queensland Building and Construction Commission Act 1991 (Qld)
to Mainz Developments Pty Ltd be confirmed.
[44] Dunmoor Pty Ltd ATF Tiny Turtle Trust Fund to pay Mainz Developments
Pty Ltd the sum of $40,981.34, inclusive of GST, plus interest at the
contractual rate of 15% from the time of invoicing on 2 October 2008, until
the date of decision.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2015/449