Castle Constructions (Qld) Pty Ltd v Pourasad [2015] QCAT 17
CITATION: Castle Constructions (Qld) Pty Ltd v Pourasad
[2015] QCAT 17
PARTIES: Castle Constructions (Qld) Pty Ltd
(Applicant)
v
Kaveh Pourasad
(Respondent)
APPLICATION NUMBER: BDL199-13
MATTER TYPE: Building matters
HEARING DATE: 21 – 22 August 2014, 25 September 2014 and
2 October 2014
HEARD AT: Brisbane
DECISION OF: Acting Senior Member Howard
DELIVERED ON: 21 January 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. Kaveh Pourasad must pay to Castle
Constructions Pty Ltd the sum of
$7499.33 by 4:00pm on 19 February 2015
in exchange for the certificates set out in
order 2.
2. Castle Constructions Pty Ltd must give to
Kaveh Pourasad the form 21 final
certificate and all associated certificates
for the house at 57 Messara Circuit,
Durack by 4:00pm on 19 February 2015 in
exchange for the payment of the amount
in order 1.
3. Either party may file submissions in
support of any claim for legal costs
including a detailed breakdown of the
costs claimed by 4:00pm on 19 February
2015.
4. If either party files submissions in
accordance with order 3 above, the other
party must file its submissions in
response by 4:00pm on 12 March 2015.
5. Any claim/s for costs will be determined
on the papers without an oral hearing not
before 12 March 2015.
-- 1 of 64 --
2
6. If no submissions are received from a
party concerning their claim for costs in
accordance with order 3 above, then the
application for costs will be dismissed.
CATCHWORDS: DOMESTIC BUILDING DISPUTE – where
builder claim final payment and for costs of
variations, as well as interest and costs under
the contract – where homeowner counter-claims
for damages for rectification and incomplete
works – whether homeowner took possession
before practical completion – whether contract
terminated by builder or homeowner – whether
termination under contract or at common law –
whether substantial compliance with practical
completion – whether variations instructed –
whether variations should be approved by
Tribunal under Domestic Building Contracts Act
1999 – whether defective or incomplete building
works
Domestic Building Contracts Act 1999 (Qld),
s 44
Bellgrove v Eldridge (1954) 90 CLR 613
Bettini v Gye (1876) 1 QBD 183
Bolton v Mahadeva [1972] 1 WLR 1009
Cooper v Ungar (1958) 100 CLR 510
D Galambos & Son Pty Ltd v McIntyre (1974)
ACTR 10
Hoenig v Isaacs [1952] All ER 176
Holland v Wiltshire (1954) 90 CLR 409
Kelly v Desnoe [1985] 2 Qd R 477
McDonald v Dennys Lascelles Ltd (1933) 48
CLR 457
Nina’s Bar & Bistro v MBE Corporation [1984] 3
NSWLR 613
Quinn Villages Pty Ltd v Mulherin [2006] QCA
433
Shevill v Builders Licensing Board (1982) 149
CLR 620
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Kava Piran, director, Castle Constructions
(Qld) Pty Ltd represented Castle Constructions
(Qld) Pty Ltd.
RESPONDENT: Mr Kaveh Pourasad represented himself.
-- 2 of 64 --
3
REASONS FOR DECISION
[1] This proceeding concerns a domestic building dispute. Essentially, Castle
Constructions Pty Ltd (the builder) claims its final payment under a
domestic building contract, the costs of variations together with costs of
debt collection and interest under the contract. The homeowner,
Mr Pourasad, counter-claims for damages for defective and incomplete
building work, together with interest and costs under the Queensland
Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’).
Background
[2] On 11 November 2012, Castle Constructions (Qld) Pty Ltd entered into a
domestic building contract with Mr Pourasad to construct a single storey
brick veneer house at 57 Messara Circuit, Durack. The contract price was
$205,300. The contract is a standard form HIA New Home Construction
Contract Version QC1 2010.
[3] Mr Piran, director of Castle Constructions, says that under the agreement,
the house was built by Castle Constructions at cost with no margin for the
builder. He says he agreed to construct on this basis for Mr Pourasad
because of their friendship, shared heritage and values, and his
knowledge that Mr Pourasad did not have significant financial resources
and was ‘proudly managing’ in difficult circumstances with a child with a
serious medical condition.
[4] The contract specified that the contract documents included the
architectural plans number NCRT1012 signed by the owner,1 and the
tender.2 There is a dispute about which set of architectural plans form part
of the contract (and this is relevant to whether some items are
incomplete). There is also a dispute about Schedule 6 of the tender,
specifically whether it was later amended by agreement.
[5] The building period provided for in the contract is ‘14 week (sic) plus rain
days’ after commencement, subject to clause 16. The commencement
date as specified in clause 6 of Schedule 1 is ‘ASAP’ in accordance with
clauses 2 and 16 of the contract. It is uncontroversial that the actual
commencement date was 17 December 2012.3
[6] Calculable delays are specified. The building period includes the following
allowances:
(a) For inclement weather and the effects of inclement weather, 10 days
in December, 10 days in January, and 14 days in February;
(b) For weekends public holidays rostered days off and other days not
generally available for the carrying out of works the contract, 5 days
December and January; and
1 Schedule 1, Clause 12.
2 Schedule 3 Excluded Items for Clause 21 are ‘as per tender’.
3 This is the date nominated for commencement by Mr Piran. Mr Pourasad advised at
hearing that he was unsure, but did not dispute the date.
-- 3 of 64 --
4
(c) For any other matter that is reasonably likely to delay the carrying out
of the works, ‘non’ (sic).4
[7] An allowance was not included for the industry shutdown period (which
commences on about 22 December for three weeks each year) which is
referred to in the general conditions to the contract,5 notwithstanding that
construction spanning the Christmas period was reasonably foreseeable.
[8] No incalculable delays were specified.
[9] The tender also refers to and explains the building period.6 For a house of
the size of the one concerned, it specifies, consistently with the contract, a
building period of ‘14 weeks plus rain days’. It then goes into an
explanation of calculating rain days. The number of days nominated for
the months of December, January and February are 11.5, 13 and 14.2
respectively (these are said to be as nominated by the Master Builders
Association from Bureau of Meteorology Records). It also says
Plus a reasonable estimate of the follow-on effects due to wet sites we
allow an additional 4 days per month due to the sites being inaccessible
until they dry out.
[10] Various prime cost and provisional sum items and allowances are
specified for the contract.7 The prime cost items include kitchen cabinets
at $6,000. Provisional sums specified include $5,000 for concreting the
driveway and porch; as well as $2,000 for front landscaping.
[11] From 5 February 2013 until some time in April 2013, Mr Pourasad and his
wife were overseas visiting family, after the tragic loss of their child in late
January 2013. Mr Piran says that immediately before they went,
Mr Pourasad visited Mr Piran and gave instructions concerning the works
and instructed a number of variations to the contract in respect of items: a
solar hot water system, prestige flat tile roof, a quiet motor for the garage
door, glass splashback in the kitchen and NBN. Variation documents were
not prepared at that time.
[12] Mr Pourasad acknowledges visiting to inform Mr Piran that he was going
away for an extended period. However, he denies giving any instructions
or instructing any variations at this, or any other time, other than in respect
of security screens (which are not at issue because they were paid in full),
some external concreting (also paid in full and not in issue) and ducted air-
conditioning (which was part of contract price rather than a variation).
[13] Mr Piran confirms that additional external concreting was instructed, but
says that due to delays between the quote being provided to Mr Pourasad
and instructions for the concreting to proceed, a delay of some 21 days
was occasioned in the building works (because certain plumbing and
4 Schedule 1, Clause 10(a).
5 General Conditions clause 16, especially 16.2(l).
6 Exhibit 11, attachment B, page 61.
7 Schedule 4.
-- 4 of 64 --
5
electrical works could not be completed until it was done).8 A number of
other extension of time claims are also made by Castle Constructions
relating to the alleged variations. These include 21 days to re-order a
stone top for a vanity unit stolen while the instructions regarding the extra
concreting were awaited9 and five days delay in the owner having the
power connected to the site.10 Mr Pourasad says that the latter delay was
caused by Mr Piran failing to provide him with information sooner.
[14] Mr Piran asserts that Mr Pourasad unilaterally and without his permission
took possession of the works on about 15 May 2013 before practical
completion was reached. Mr Piran says that Mr Pourasad was demanding
to take possession because he wanted to lay timber flooring (which was
not part of the contracted works) and that he did not want to wait until the
house was finished. Mr Piran says that he did not agree to this. He says
he told Mr Pourasad to extend his lease on his rental premises because
the house was not ready. He said that he was concerned that the flooring
may be damaged while the house was being finished: he did not want to
take responsibility for this possibility. However, he asserts that the
homeowner took the (hidden) laundry key from the metre box, and by
about a week later, on 15 May 2013, that Mr Pourasad was storing
flooring materials in the garage and had started laying the floor. On 16
May 2013, Mr Pourasad told him that he had opened the packets of
flooring and commenced laying the floor.
[15] Mr Piran says he had been in the process of preparing a defects
document listing minor defects and omissions under clause 24 of the
contract. He says that when he realised Mr Pourasad had taken
possession of the premises, Castle Constructions gave its claim for
practical completion (which was dated 16 May 2013) on 17 May 2013.
[16] Mr Pourasad says he received the final claim before he moved in.
He asserts that he moved in by agreement on 21 May 2013. He produced
documents from a removalist showing that his furniture and personal
effects were moved on 21 May 2013; and from a real estate agency about
the dates he tenanted rental premises, that is, until 21 May 2013. He says
that after he received the final claim on 17 May 2013, he telephoned Mr
Piran to ask whether he could move in. He says Mr Piran agreed that he
could and that he would come back to complete the remaining ‘bits and
pieces’. He acknowledges having possession of the front door key from 19
May 2013, when he says Castle Constructions’ subcontractor,
Paul Simpson, gave it to him in the presence of a Castle Constructions
representative, whom he revealed under cross-examination was Masoud
Piran, Mr Piran’s brother. He denies having obtained the laundry key
earlier, storing flooring materials and laying flooring in the house until 20
or 21 May 2013.
[17] On 7 June 2013, Mr Piran and Mr Pourasad jointly inspected the house for
8 Exhibit 2, [26] – [28], attachment KP 21.
9 Exhibit 2, attachment KP 24.
10 Exhibit 2, attachment KP 13.
-- 5 of 64 --
6
purposes of compiling (and signing) a minor defects list.11 Ultimately at
hearing Mr Pourasad accepted that they met, compiled the list and that he
signed the list (initially he contended that Mr Piran would not acknowledge
any defects), although he now says that Mr Piran ‘took advantage’ of him
by including only minor defect items on the list. According to Mr Piran, a
typed copy of the list was subsequently left at the house for Mr Pourasad.
Mr Pourasad denies having been provided with a typed copy of the list by
Castle Constructions.
[18] Although it is common ground that Mr Piran and Mr Pourasad had known
one another from at least 2000, the relationship between the parties broke
down after Mr Pourasad and his family moved into the home. The final
claim was not paid, despite Mr Pourasad requesting that his bank pay it.
Mr Pourasad’s bank records that it inspected the house but declined to
release the final payment because ‘a number of items including cupboard
doors, plastering, painting and a manhole were yet to be completed’.12
Mr Pourasad says that the inspection by the bank was done on 24 May
2013.
[19] Mr Pourasad and persons at his direction and unrelated to Castle
Constructions laid the flooring. Mr Pourasad eventually acknowledged that
the skirting boards were removed by them; that they cut or broke some of
the skirting boards in the process; and that they also made (and did not
repair) holes in some walls during this process.
[20] Castle Constructions did some further work in June and early July.
Mr Piran says, that is, when it could gain access to the premises from the
homeowners who were uncooperative. It is uncontroversial that the work
included mending some of the holes made in the walls and repainting the
walls and skirting (despite Mr Pourasad and his agents being responsible
for the damage), installing an antennae and a letterbox. Mr Piran says that
by 11 July 2013, all of the defects listed on Exhibit 5, had been completed.
[21] A final certificate was obtained by Castle Constructions after Mr Pourasad
had moved into the house.
[22] The bank was not at any time requested by Mr Pourasad to reinspect and
release the final payment. Mr Pourasad says this is because the work was
not finished.
[23] In late June 2013, Mr Pourasad obtained a building report from Pro-Check
which detailed some 96 alleged defects or incomplete items. Through his
lawyers, on 11 July 2013 he issued a notice to remedy breach to Castle
Constructions, alleging it was in substantial breach for failure to complete
the works within the building period and breach of the contractual and
statutory warranty to carry out the work in an appropriate and skilful way
as evidenced by the building report. The correspondence advised that
unless the breaches were remedied within 10 working days, Mr Pourasad
11 Exhibit 5.
12 Exhibit 11, attachment Q, letter from Westpac Bank dated 11 September 2013.
-- 6 of 64 --
7
intended to terminate the contract. The correspondence indicated that the
breaches could be remedied by attending to the 96 items of allegedly
defective or incomplete work.
[24] In reply, Castle Constructions, through its lawyers, advised that
Mr Pourasad had entered into possession of the works in breach of
clause 25.1 without the written consent of the builder, and before being
issued with a notice that practical completion had been reached.
Therefore, it asserted, the consequences in clause 25.3(c) followed.
Thereby, it alleged that Mr Pourasad was in substantial breach of the
contract and unable to issue a notice to remedy breach. Further, Castle
Constructions lawyers asserted that it was thereby released from further
completing the works. It also denied any substantial breach of the
contract.
[25] Castle Constructions did however provide extension of time claim forms,
and indicated that it was prepared to perform further work if it received the
final payment under the contract, in the sum of $20,530. It also provided
various variation documents. It asserted that any alleged defects and
incomplete works would have been completed or remedied in the
maintenance period had the proper course been followed. That said, if the
final payment was made, it offered to discuss completing remedial works.
Otherwise it indicated its intention to process a variation and notice of
practical completion and commence proceedings against Mr Pourasad.
[26] Mr Pourasad responded by purporting to terminate the contract.
[27] Castle Constructions then, alleging that the purported termination was
invalid and amounted to a repudiation, purported to make an election to
accept it and terminate the contract.
The claim and counter-claim
[28] Castle Constructions commenced proceedings in the Tribunal. It seeks
orders for the payment of its final claim under the building contract in the
sum of $20,530 together with the further sum of $14,437.83 for variations,
as well as interest under the contract and debt recovery costs under the
contract.
[29] The variation items claimed are set out in the table below. All of the
alleged variations themselves are set out in Exhibit 2 at attachments
KP 15, 27, 29, 32 and 35, although there appears to be some double-up.
For ease of reference, I have indicated the attachments to Exhibit 2 in
which each of them is claimed.
List of Variations Cost GST Total
1 Garage door Quiet Motor (KP 15) $100.00 $10.00 $110.00
2 Prestige Flat Roof Tiles (KP 35) $2,505.30 $250.53 $2,755.83
-- 7 of 64 --
8
List of Variations Cost GST Total
3 Upgrading Heat pump to solar HWS
(KP 15)
$850.00 $85.00 $935.00
4 Kitchen upgrading to: All Draw (10
Draws) soft close, handle less,
50mm Benchtop 900mm instead of
600mm Island+ Waterfall Glass
splashback. Cost excessive to
$5,000 (KP 35)
$4,000.00 $400.00 $4,400.00
5 Second Showerhead to Ensuite.
Square Ceiling Drop + Mixer +
plumbing (KP 15)
$650.00 $65.00 $715.00
6 Upgrade Internal Doors and
Architraves From hollow to Solid,
and laminated finish (KP 15)
$800.00 $80.00 $880.00
7 Cloths line (KP 32) $285.00 $28.50 $313.50
8 Driveway extra to provisional sum
(KP 32)
$1,265.00 $126.50 $1,391.50
9 Upgrading Mirrors to Frameless
(KP 15)
$220.00 $22.00 $242.00
10 Upgrading shower screen to semi
frameless and (IN/OUT) Pivot door
(KP 27)
$150.00 $15.00 $165.00
11 Custom-made Laundry Door
2400mm Height to match int. And
Toughen Glass (KP 27)
$470.00 $47.00 $517.00
12 Four Extra, External Lights LED
(KP 27)
$360.00 $36.00 $396.00
13 NBN (KP 27) $650.00 $65.00 $715.00
14 Extra Retaining wall at Front
Landscape (KP 32)
$300.00 $30.00 $330.00
15 Neighbourhood Rubbish Removal
(KP 32)
$520.00 $52.00 $572.00
Total $14,437.83
[30] Mr Pourasad opposes the application. He seeks a declaration that he
validly terminated the contract. He also seeks orders requiring the delivery
up of the Form 21 final certificate and all related certificates of inspection,
as well as damages for completion of the works and rectification of the
-- 8 of 64 --
9
alleged defects items (identified by Mr Fry) in the sum (which he clarified
at hearing) of $150,700, although his final submissions suggest it is
$153,700. He also seeks interest under the QBCC Act, as well as legal
costs.
Areas of Agreement
[31] There is very little agreement between the parties. Indeed, before the
hearing commenced, Mr Piran and Mr Pourasad did not agree on the date
of the contract, despite it being dated, or the date of commencement of
the works.
[32] However, at the commencement of the hearing the parties agreed that
(in the event that the homeowner is able to successfully claim damages),
about a small number of defect items and, in some cases, the reasonable
cost of same.13 The agreement reflects the outcomes of the expert
conclave, as follows:
Item No. Brief Description Cost
3.1 Small woodwork items including architrave refitting $650
3.14 Replace vanity unit (although the cost of the
rectification is not agreed and the estimates range
from $1,500 and $500)
Not agreed
5.0 Kitchen door $1,000
5.2(9) Kitchen : Gaps between the kickboards to be
rectified
Not agreed
8.1 Render garage wall $1,900
8.4 Storm moulds front door to be refitted $250
8.6 Render ensuite windows Not agreed
8.9 External control joints require mastic jointing $1,200
Issues concerning the evidence and credit of the witnesses
[33] Mr Piran and his wife, Ms Abdi Puya, who is a designer for Castle
Constructions, provided witness statements to the Tribunal. They were
cross-examined at the hearing. I found them to be impressive witnesses.
They gave straight-forward answers and the evidence each of them gave
was consistent with their own other evidence, as well as the
documentation before the Tribunal.
13 The item numbers and cost are drawn from Exhibit 21 and are reflected in Annexure A
to these reasons.
-- 9 of 64 --
10
[34] During the hearing, Mr Piran tendered an email trail and attached
unsigned statement of Paul Simpson,14 carpenter, whom he said was
overseas. The emailed unsigned statement tends to support Mr Piran’s
claims that Mr Simpson did not give the front door key to Mr Pourasad at
the request of the builder. Rather, he handed it over on Mr Pourasad’s
request because he saw that Mr Pourasad already had access to the site
through the laundry door and therefore, he thought it was not a concern.
However, Mr Simpson was not available for his evidence to be tested and,
in the covering email Mr Piran suggests a need to ‘say the same story’,
although he says Mr Simpson should add anything else he thinks is
relevant. These factors affect the weight which I consider Mr Simpson’s
‘statement’ should be given. In the circumstances, I have given it no
weight.
[35] I found Mr Pourasad was generally not an impressive witness. He
recanted on his own earlier evidence on a number of issues. Initially, he
accused Mr Piran of ‘fraud’ for providing a different set of plans (Exhibit 3)
than the set he had (Exhibit 12). However, subsequently when Mr Piran
produced an email from the certifier (Exhibit 17) to the effect (although in
rather vague terms) that copies of all documents were forwarded by it to
Mr Pourasad, he then said essentially that he did not know what
documents he had received. He did ultimately acknowledge that he may
also have received other documents from the certifier, including the
geotechnical report at Exhibit 16.
[36] Also, he asserted at some stage that the builder had denied that there
were any defects and just wanted his final payment. He subsequently
admitted that his signature appeared on Exhibit 5 dated 7 June 2013,
being the list of defects prepared by Castle Constructions but asserted he
had not seen it or been given a copy until the first day of the hearing. I do
not accept this. As he signed it, he must have been aware of its existence
at 7 June 2013.
[37] He denied requesting any variations other than those already paid for.
He says if he had, he would have paid for them immediately, as he did
with those items conceded. Yet during the hearing, he conceded that
NBN, solar HWS, a prestige flat tile roof and a special quiet motor for the
garage were provided although not part of the contract. In respect of the
NBN, he simply said he did not know why it was done and requested ‘the
proof’ that it was requested. Because I accept Mr Piran’s evidence
generally in preference to Mr Pourasad’s evidence and given that he had
agreed to build the house under the contract for Mr Pourasad without a
profit margin, I am satisfied that it is highly improbable that Mr Piran
decided without instruction to include those more expensive items. With
the exception of the clothesline and the rubbish removal (which is
discussed later), I accept that Mr Pourasad did request the variations
which Mr Piran and Ms Abdi Puya attest to.
[38] Further, as Mr Pourasad’s evidence progressed, it was revealed that the
14 Exhibit 4.
-- 10 of 64 --
11
Castle Construction representative whom he claimed was present when
Paul Simpson allowed him to have the front door key on 19 May 2013 was
Masoud Piran, Mr Kava Piran’s brother. Masoud was a personal friend of
Mr Pourasad, with whom he had shared rental accommodation many
years ago and who (to Mr Pourasad’s knowledge) worked as a taxi driver.
Masoud Piran had apparently done some painting as a labourer for Castle
Constructions in January 2013. Otherwise, he had no connection to Castle
Constructions. Mr Pourasad was well aware of this: when Masoud
attended on 19 May 2013, he attended as a friend to Mr Pourasad, not a
representative of Castle Constructions. I consider that Mr Pourasad was
disingenuous in stating that a representative of Castle Constructions was
present and that he intended to mislead by describing Masoud Piran as a
representative of Castle Constructions.
[39] His evidence about how damage to the skirting boards and paintwork
occurred was also revealing. He initially denied sending photographs to
Mr Piran of damage done (by him and his agents) during laying of the floor
when removing and replacing the skirting. Mr Piran produced a text
message to himself, which Mr Pourasad subsequently acknowledged he
had sent, which included the photographs (Exhibit 15). Mr Pourasad also
initially said that he personally had not done any of the work, that he had
hired a handyman to do it. Later, he acknowledged having personally
done some of it, although he said only in the second bedroom.
[40] Ultimately, he acknowledged that some of the skirting boards had been
cut during the process of removing it to lay the floor or refitting it, and that
holes in the plaster and damage to the paint caused in the process, had
not been fixed by him or the other persons involved. He suggested
(inconsistently with his earlier assertions that if he had instructed
variations, he would have paid cash up front for them) that this was
because he could not afford to pay the other persons any more, so he
finished it. He asserted that he did some painting and later said also that
the only damage caused by the floor laying was in the photographs,
nowhere else in the house.
[41] However, the expert reports suggest damage and other problems with the
skirting boards in a variety of rooms. It seems more probable than not that
the rather inexpert floor-laying done by Mr Pourasad and his agents was
the cause of the damage of this similar type in each of the rooms in which
it is an issue. As discussed earlier, the skirting boards are also included in
the Exhibit 5, as items to be attended to by Castle Constructions, as
Mr Piran says.
[42] At one stage, Mr Pourasad denied that Castle Constructions did any
further works after the Pro-Check report was obtained, but later agreed in
cross-examination that it had. He acknowledged that the letterbox and
antennae installation had been subsequently done. At this point, he said
that it was only after the Pro-Check report was sent to Castle
Constructions that no further work was undertaken by them.
[43] Because of the inconsistencies in Mr Pourasad’s evidence and the
-- 11 of 64 --
12
misleading evidence revealed by cross-examination, I concluded that he is
an unreliable witness. Wherever his evidence is inconsistent with
Mr Piran’s and Ms Abdi Puya’s evidence, I accept Mr Piran’s and Ms Abdi
Puya’s evidence.
[44] On the final day of the hearing, Mr Pourasad tendered a witness
statement (Exhibit 66) of Nivin Nader, his wife. She had not provided any
earlier witness statement. Ms Nader was not made available for cross-
examination. It was dated 23 September 2014, and addressed one issue
only which had been the subject of disagreement amongst the expert
witnesses. Because of its lateness and because it was unable to be
tested, I have given it no weight although in any event it would not have
affected the outcome.
[45] The expert witnesses, Bruce Moore and Michael Fry, are both builders of
a significant number of years (43 and 25 years respectively) experience.
Mr Moore also has qualifications as a quantity surveyor. Mr Fry is also a
licensed pest inspector. Mr Fry’s experience, as described at hearing,
appears to have been more in commercial rather than domestic building
construction until about 2008, when he commenced business as a building
and pest inspector. Since 2008, the bulk of his work appears to have been
residential. He was previously a carpenter until obtaining registration as a
builder. Mr Moore commenced trading as Building Surveys Australia in
1994, and has conducted work as a building inspector and quantity
surveyor in that entity. His says that residential work comprises the
majority of his work. He is not a registered pest inspector.
[46] Both Mr Moore and Mr Fry provided reports to the Tribunal. They were
directed to attend an expert conclave prior to the hearing, and required
pursuant to Practice Direction 4 of 2009 to prepare a joint report setting
out the areas of agreement and disagreement. Unfortunately, the
anticipated joint report was not filed. Both filed separate reports which they
each confirmed at the hearing included a narrative of the confidential
discussions held at the conclave.15 Those reports containing the narrative
were not accepted into evidence. At the hearing, Mr Pourasad attempted
to tender yet another Scott Schedule prepared by Mr Fry sometime in July
2014. However, this was prepared after the expert conclave and was not
accepted into evidence at this late stage either.
[47] I make the observation that Mr Fry’s report prepared after the conclave
which had been filed but which was not accepted into evidence attached
some 400 plus photographs. Some of the photographs were tendered at
the hearing and are exhibits in the proceeding.
[48] It was ultimately agreed by Mr Moore and Mr Fry, who gave their evidence
in the proceeding concurrently, that an amended version of Mr Moore’s
report filed on 25 July 2014 after the conclave, with the two most right-
hand columns deleted, properly set out the outcomes of the conclave.
That is, it sets out the areas of agreement and disagreement without
15 See QCAT Practice Direction 4 of 2009.
-- 12 of 64 --
13
recording any confidential discussion. In the far left-hand column it recites
the details of the defect as originally specified/alleged by Mr Fry. It also
summarised the earlier comments of both of them in their pre-conclave
reports.
[49] It was also agreed that the total on page 14 of $107,900 is incorrect as
changes were made by Mr Fry to dollar amounts in his ‘expected cost’
column which make the total $150,700. This reflects only Mr Fry’s current
estimate of what he says rectification or completion may cost. Although
Mr Moore agrees that the column totals $150,700, he does not otherwise
agree with the estimated costs except where indicated. Mr Moore’s
estimates are set out in his comments, although not separately totalled.
That said, at the hearing additional evidence was received about some
costs estimates, as it was apparent that Mr Moore and Mr Fry had different
understandings about what the earlier estimates included in some cases.
[50] The amended report (photocopied by the Tribunal to exclude the two most
right-hand columns) is Exhibit 21.
[51] Mr Fry’s report (Exhibit 20) is highly repetitive and appears to contain
clauses which are suggestive of use of standard or precedent clauses and
paragraphs. During the hearing, although Mr Fry asserted that all other
comments in his report were applicable to this particular property,
conceded that his comments about the weep holes in Item 8.0 were from
a precedent and not about this particular property.
[52] At times, Mr Fry’s behaviour while giving his oral evidence during the
hearing was of concern. At one point, he threatened Mr Piran, suggesting
that he ‘Come and say that to me in the street’ or words to that effect.
He was somewhat dogmatic in the views he presented. Both experts
made some concessions, but Mr Fry only when presented with
documentary evidence to refute his expressed views, and even then
sometimes not.
[53] He also added belated but significant evidence which then could not be
tested by Mr Moore. For example, in relation to alleged defect item 1,
although it had not been referred to in his report and not mentioned by him
in his oral evidence when asked by me to explain the issue, subsequently
in response to Mr Piran’s suggestion that there was not a water leak,
Mr Fry alleged he had very recently seen a water leak as a result of the
allegedly defective configuration of the roof tiles.
[54] He demonstrated a general lack of professional judgment. For example,
he included items which he said required remedial works which he
acknowledged during the hearing were contractual matters (that is, the
items were not strictly in accordance with the contract specifications but
were not defective), rather than defective. He also presented views of
alleged requirements under the National Construction Code (NCC) and
the Australian Standards (AS) which were either inconsistent with the
sections of those documents relied upon, or not supported by them.
-- 13 of 64 --
14
[55] Both experts to some extent, inconsistently with the duty of an expert to
provide independent evidence to the Tribunal, but most particularly Mr Fry,
demonstrated a partisan attitude. In this regard, Mr Moore occasionally put
forward his client’s instructions in response to questions about alleged
defects, although these generally related to alleged variations to the
contract and he disclosed that these were his instructions. Mr Fry however
appeared partisan in a broad manner. For example, by threatening
Mr Piran as discussed above; by adding late significant evidence which
could not then be tested; and by putting his opinions to the roof supplier
about the roof being defective, rather than making the enquiries of a
supplier that an expert may legitimately make.16
[56] Mr Fry proffered and relied upon a Queensland Building and Construction
Commission publication, ‘Standards & Tolerances’, published May 2014
(Exhibit 22). Mr Fry asserts that it sets out what is in the AS. However, it
provides only limited reference to the AS and their content. Also, the guide
itself specifically says that where it is inconsistent to the AS, the AS (of
course) take precedence. Having regard to my expressed reservations
about the usefulness and reliability of the guide, Mr Fry on a later day of
the hearing then presented extracts from several AS which became
exhibits in the proceedings. His initial insistence that the guide was
sufficient for the Tribunal’s purposes and his own apparent reliance on it,
rather than the AS themselves, cause me concern. In any event, as I
indicated earlier, I do not accept his interpretation of some of the extracts
provided.
[57] I concluded that Mr Fry did not provide the Tribunal with independent
expert opinion, rather he has adopted the role of advocate for Mr
Pourasad and was unable to be objective about the subject matter.
Accordingly, I have generally given his evidence less weight than I have
given Mr Moore’s.
[58] That said, Mr Fry had inspected some items which Mr Moore had not.
For example, he had climbed onto the roof to inspect the tiles and
inspected every window and reached the view that eight in all needed
attention. Mr Moore had not climbed onto the roof and based his opinion
on about the roof tiles on photographs taken by Mr Fry. Nor had he
inspected each and every window. Although I have reservations about Mr
Fry’s evidence generally, I have accepted Mr Fry’s evidence in respect of
items about which there is no inconsistent evidence from Mr Moore unless
there are reasons for not doing so in respect of a particular item.
[59] Mr Moore is a quantity surveyor. Mr Fry is not. Accordingly, I am satisfied
that Mr Moore has greater expertise in estimating the costs of completion
or rectification. I have accordingly preferred Mr Moore’s views about the
estimated costs. However, it must be said that there were significant areas
of agreement about what the cost would be if Mr Fry’s evidence about the
items being defective was accepted.
16 Exhibit 31.
-- 14 of 64 --
15
[60] Mr Fry is a registered building and pest inspector and Mr Moore is not.
Mr Pourasad submits that he is better qualified to give an opinion. I do not
accept this a general proposition, given Mr Moore’s experience. Further,
I do not accept it in this case particularly because of Mr Fry’s obviously
partisan attitude and his errors in interpreting the requirements in the NCC
and AS.
The issues for determination
[61] The key issues which I must determine are as follows:
a) What was agreed between the parties: the issues concerning the
plans and Schedule 6 of the tender?
b) When did Mr Pourasad take possession?
c) Who terminated the contract?
d) Is Castle Constructions entitled to recover the final claim of $20,530?
e) Were there any variations? If they were not documented as required
under the contract, should any variations be allowed by the Tribunal
under the Domestic Building Contracts Act 2000 (DBC Act)? If so,
how much should be allowed for those items?
f) Is Mr Pourasad entitled to claim for incomplete and/or defective
works, are there any defective and/or incomplete works? If so, what
is the measure of damages?
The contract documents: the plans and schedule 6 of the tender
document
[62] There is an issue about which set of architectural plans drawn by Alan
Sullivan Pty Ltd for Castle Constructions and both dated 5 October 2012
are the operative contract documents, Exhibit 3 or Exhibit 12.
[63] The plans vary in several respects. When the parties signed the contract,
Council approval had not been sought or granted. The original plans are
Exhibit 12. The contract in item 5A obliged the builder to obtain Council
approval. Exhibit 3 bears the endorsement of Council approval on
11 December 2012. Exhibit 12 attaches a contour survey which does not
appear at Exhibit 3. At page 2, Exhibit 3 includes only one blade wall in
the study, whereas Exhibit 12, contains two blade walls. The only other
difference of which I was informed was relocation of the water tank from
one side of the house to the other (page 1/1 in each case). The latter is
not a matter of dispute.
[64] Mr Piran says that he and Mr Pourasad discussed the blade walls. He
says it was agreed to include only one in the plans for Council approval
(and add a second later if Mr Pourasad wanted it), rather than the other
way around which he says is a more difficult process once Council
approval had been obtained. Mr Piran says that he included only the cost
of one blade wall in the contract price as requested by Mr Pourasad. Mr
Piran suggested to Mr Pourasad that one blade wall would delineate the
-- 15 of 64 --
16
study area, while allowing natural light to enter from the lounge room. Mr
Pourasad denies that this was the case, although he acknowledged the
other change to the plans was agreed, that is, that the water tank was to
be moved to the other side.
[65] As discussed above, I found Mr Pourasad’s evidence generally unreliable
and accept Mr Piran’s plausible explanation for the minor changes to the
plans regarding the blade walls. I find that it was orally agreed at the time
the contract was signed that the plans were to be amended in these minor
respects before Council approval was sought. This agreement is not a
variation to the contract, it was part of the contract terms agreed orally.
It should have been documented at the time the contract was signed, but it
was not. That said, in light of my findings, it follows that Exhibit 3
embodies the works as agreed.
[66] A version of Schedule 6 of the tender document17 was signed by Mr Piran
several days after the parties signed the contract, on 14 November 2012.
All of the listed items were to be included as extras free of charge.
Mr Piran says that after further discussions, the list of items in Schedule 6
was amended to accord with later agreement reached between him and
Mr Pourasad about the extras. It appears that the later created version
was not signed at any stage.18
[67] The original Schedule 6 included at Item 14, ‘upgrade standard bath tub to
jaccuzzi spa’. The later produced Schedule 6 does not contain reference
to this item. There are also other differences. Mr Piran suggested to
Mr Pourasad that the list was changed by agreement, for example,
because the bathroom was too small to accommodate a Jacuzzi spa.
Also, he suggested that the arrangement was for Mr Pourasad to have
items to the same value. For example, instead of 19 extra ceiling down
lights, he could elect to have other electrical work, such as additional
double power points, to an equivalent value. Mr Pourasad denies any later
agreement to change the list and denies the agreement that he could have
other items to equivalent value. In respect of the Jaccuzzi spa, he said he
did not know whether it would fit.
[68] Neither party suggests that there are any other relevant versions of the
tender document, other than the two referred to. Therefore, it is
reasonable to infer from the evidence of both Mr Piran and Mr Pourasad
that the tender document attached to Exhibit 11, is the document which
existed at the date that the contract was signed by them, that is 11
November, 2012, although at that stage, it was, it seems, an unsigned
document. Although there is no provision for it to be signed by the
homeowner, ‘Kaveh’ has been written on each page next to ‘initials’.
[69] If Mr Piran’s version of events is accepted, the later agreement was a
17 The Tender is at Exhibit 11, Attachment B, pages 59 – 68; a legible copy of Schedule 1
is at Exhibit 6 — Schedule 6 appears at page 68 and dated 14 November 2012.
Another unsigned and different version of Schedule 6 appears at Exhibit 2, Attachment
KP 6.
18 Exhibit 2, Attachment KP 6.
-- 16 of 64 --
17
variation to the contract. Although the contract price was unaffected, a
variation document should have been prepared by Castle Constructions
for signing by both parties in accordance with clause 19 of the contract
and the Domestic Building Contracts Act 2000 (DBC Act). Exhibit 2
attachment KP 6 is itself some evidence of the alleged variation, although
not expressed as a variation document and not signed by the parties as
required.
[70] Mr Piran’s explanation is plausible. It makes sense that if a Jacuzzi could
not fit because of the size of the bathroom (which seems more probable
than not: see discussion about Item 3.8 in Annexure 1 to these reasons for
decision), that the parties would agree to amendment as Mr Piran
suggests. Mr Pourasad does not make a claim about the Jacuzzi. Given
his extensive claims of incomplete and defective works, it is reasonable to
infer that he would have done so, if he considered it was agreed that he
receive it. Also as explained earlier, I found Mr Piran’s evidence more
compelling and Mr Pourasad’s evidence unreliable. Therefore, although a
variation document was not prepared, I find that Schedule 6 was amended
by agreement between the parties and that the final agreed version
appears at Exhibit 2 at attachment KP6.
When did Mr Pourasad take possession? Was he entitled to do so?
[71] Clause 24 of the contract provides for practical completion, at which time
the builder may render the claim for the final stage payment under the
contract. Under clause 10, the builder is entitled to exclusive possession
of the site. Under clause 25 (especially 25.1 and 25.3), the owner is not
entitled to take control of, possession of or use the works or any part of
them or receive the keys, until the builder has been paid the contract price
(adjusted for variations) without the builder’s written consent, unless the
owner has lawfully terminated the contract. The consequences of taking
possession before payment are further discussed later, but if the owner
does so, the owner commits a substantial breach of the contract: clause
25.3.
[72] Mr Piran says that Mr Pourasad had been demanding to move in because
he wanted to install the flooring, but that he refused to give permission.
He said he told him not to store the flooring in the house as things had
been going missing (such as a vanity top, as earlier discussed) and that
he did not want the flooring installed until after the house was finished. He
was concerned that his contractors may scratch the flooring while finishing
the house. However, Mr Piran says essentially that he discovered that by
15 May 2013 that Mr Pourasad had helped himself to the laundry key and
was storing flooring items in the house. On 16 May 2013, Mr Piran says
that he had a conversation with Mr Pourasad about the flooring when
Mr Pourasad told him that he had already opened the packs and
commenced installing it. He says Mr Pourasad took this action unilaterally
and without his permission and in the face of Mr Piran’s opposition to it.
The final claim was then prepared and given by Castle Constructions to
Mr Pourasad on 17 May 2013. Mr Pourasad says he did not move in until
21 May 2013 and that he did not store anything in the house until then.
-- 17 of 64 --
18
[73] I accept Mr Piran’s evidence, and I reject Mr Pourasad’s evidence for the
reasons earlier given. I accept that Mr Pourasad took a key for the
premises stored onsite by the builder and commenced storing flooring
items in the house by 15 May 2013. I am also satisfied that he
commenced laying the flooring by 16 May 2013. I find that Mr Pourasad’s
acts amounted to taking possession of and using the works. I find that Mr
Pourasad did not have the permission (either oral or written) of the builder
to take possession of or use the works when he took these steps.
[74] Practical completion had not been reached and Castle Constructions had
not rendered its final account when Mr Pourasad took possession of and
used the works on and from 15 May 2013. A notice of practical completion
and the final claim had not been given to Mr Pourasad under clause 24 of
the contract and the final claim had not been paid. Therefore,
Mr Pourasad was in breach of clause 25 of the contract.
[75] When a homeowner takes control, possession of or uses the works
contrary to clause 25, clause 25.3 of the contract entitles a builder to elect
to either:
a) Treat the owner’s action as repudiation of the contract and elect to
accept it;
b) Give the owner notice to remedy breach under clause 27 of the
contract;
c) Accept the owner’s actions as a variation to omit that part of the
works not carried out and completed as at the date the owner
breaches under subclause 25.1.19
[76] Under clause 25.6 if the builder accepts the variation under clause 25.3(c)
as above, the builder is to give to the owner a variation document to that
effect and a notice of practical completion and final claim. Clause 25.7
deems the builder discharged and released from all liabilities costs, losses
and damages which the owner may suffer related to works omitted under
paragraph (c) of clause 25.3.
[77] I accept that Castle Constructions rendered its final claim on 17 May 2013.
However, it took no action under clause 25.3. Indeed, at that stage, Castle
Constructions through Mr Piran continued to act as though the contract
remained on foot. Mr Piran compiled a minor defects list. He met with
Mr Pourasad at the house on 7 June 2013. They considered the minor
defects list, added to it and both signed it on that date.
[78] Castle Constructions attended at the house and did some works
subsequently. It appears that some was done in June 2013, but it
continued into July 2013, after the Pro-check report had been obtained,
although before it was given to Castle Constructions.
Who terminated the contract?
19 Exhibit 11, Annexure A, page 45, 25.3.
-- 18 of 64 --
19
Was the notice to remedy breach validly given by Mr Pourasad?
[79] On 11 July 2013, lawyers for Mr Pourasad wrote to Castle Constructions
purporting to issue a notice to remedy breach alleging substantial breach
for failure to complete within the building period and failure to carry out the
work in an appropriate and skilful way.
[80] Mr Piran says that all agreed defects in Exhibit 5 had been attended to by
that date.
[81] In any event, because Mr Pourasad took possession contrary to
clause 25.1, he committed a substantial breach of the contract.
Under clause 27.7, a party who is in substantial breach is not entitled to
give a notice to remedy breach and a notice given by a party in substantial
breach is ineffective. I find that Mr Pourasad was in substantial breach at
the time he gave the notice to remedy breach and that it was therefore
ineffective.
[82] Having come to this conclusion, I do not need to decide whether Castle
Constructions had failed to complete within the building period. However,
in case I am wrong (and in case the decision is appealed) I make the
following observations. The building period is poorly and confusingly
expressed in the contract as 14 weeks plus rain days. On its face, it
appears that the rain days is a reference to rain days specified as
calculable delays (34 days). However, calculable delays are under the
contract specified to be delays included in the building period.
[83] However, it is uncontroversial that the tender document is a contract
document. It contains further information about what the parties agreed.
It suggests (ignoring the small disparity between the rain days referred to
in the two documents) that the rain days were not intended to be included
(as calculable delays) in the building period, rather that they are in addition
to the 14 week period. This is consistent with the actual words used in
item 10 of the contract specifying the building period, that is, ‘14 weeks
plus rain days’.
[84] If it was necessary for me to resolve this inconsistency, I would be
satisfied that the building period agreed was 14 weeks plus 34 days. That
is, 18 weeks and six days (or 132 days in total). This means completion
was due on 30 April 2013. Of course, this excludes any extensions of time
for any claimable delays (including for agreed variations) under clause 16
of the contract. The builder claims a variety of extensions of time,
including 21 days for the delays associated with the homeowner’s
instructions for the extra concreting and 21 days to replace the stolen
vanity top. These are reasonable claimable delays. These two delays
(without considering other extension of time claims) would extend the time
for practical completion under the contract past the date on which Mr
Pourasad took possession or used the premises on 15 May 2013; and
also past when the defects list was agreed between the parties on 7 June
2013.
-- 19 of 64 --
20
[85] Irrespective of this, the contract does not contemplate that late completion
represents a substantial breach. It provides specifically for late completion
damages in the event that the building period is exceeded in item 11 and
clause 31. As a matter of construction, I am satisfied that damages are the
remedy for late completion under the contract. However, if the delay was
of inordinate length, a common law right to terminate may arguably arise.
However, in this case, the delay is of at most several weeks duration.
[86] Was Castle Constructions in substantial breach if it failed to do the work in
an appropriate and skilful manner? The contract (in clause 35) and the
DBC Act20 provides for a warranty that the works will be carried out in an
appropriate and skilful manner. If the works are not done in accordance
with the warranty, a homeowner is entitled to damages, but is not
generally entitled to terminate the contract.21
Termination of the contract?
[87] Mr Pourasad purported to terminate the contract by correspondence dated
5 August 2013. Under the contract, he was entitled to terminate only after
giving a valid notice to remedy breach. I have found that because he was
in substantial breach of the contract, he was not entitled to give a notice to
remedy breach. Therefore, it follows that he was not entitled under the
contract to give a notice ending the contract.
[88] For the sake of completeness, I make the observation that the building
contract does not expressly or impliedly exclude the common law right to
terminate the contract. Indeed, clause 27.9 appears to preserve operation
of the common law by providing that if a party breaches (including by
repudiation) the clause does not prejudice the other party’s right ‘to
recover damages or exercise any other right or remedy’.22 Accordingly, I
am satisfied that as a matter of construction, the common law right to
terminate the contract was not excluded.23
[89] At common law, if one party renounces his or her liabilities under a
contract demonstrating an intention to no longer be bound or to fulfil it in a
manner substantially inconsistent with its obligations, then an innocent
party is entitled to accept the repudiation and terminate the contract.24 All
of the circumstances relevant to performance may be taken into account
in deciding whether there has been a repudiation. A party that is in breach
of a contract may still accept repudiation by the other party, provided that
it has not itself repudiated the contract.25 However, a party cannot take
advantage of its own non-compliance with the contract.26 If there is a
20 DBCA s 44.
21 Bettini v Gye (1876) 1 QBD 183.
22 Emphasis added.
23 The common law right to terminate will only be excluded when the contract contains a
clear intention to exclude it: Holland v Wiltshire (1954) 90 CLR 409; Cooper v Ungar
(1958) 100 CLR 510.
24 Shevill v Builders Licensing Board (1982) 149 CLR 620.
25 For example see Kelly v Desnoe [1985] 2 Qd R 477.
26 Quinn Villages Pty Ltd v Mulherin [2006] QCA 433.
-- 20 of 64 --
21
causal relationship between the breach by the party purporting to
terminate and the default of the other party, a presumption operates that a
party can not take advantage of their own default to terminate.27
[90] The facts as I have found them do not reveal that Mr Pourasad had a
basis at common law to terminate the contract at 5 August 2013.
[91] Then by correspondence dated 8 August 2013, Castle Constructions’
lawyers wrote to Mr Pourasad stating that it accepted his repudiation of
the contract, elected to terminate the contract and that it was now relieved
from its obligations under the contract and to perform it further.
Castle Constructions submits that the election was made by it under
clause 25.3, asserting that it is entitled under clause 25 to receive its
contract price and under clause 25.7 is deemed discharged and released
from all liabilities, costs and other damages suffered by the owner which
relate to the works omitted.
[92] I find that Mr Pourasad’s purported termination was a repudiatory act.
Castle Constructions was entitled to accept it at common law, and
terminate the contract. Mr Pourasad’s earlier act of taking possession
without permission before practical completion was also a repudiatory act,
which Castle Constructions was entitled to accept under clause 25 of the
contract. It is somewhat unclear from the correspondence of 8 August
2013 whether Castle Constructions intended to terminate at common law
or under clause 25.3.
[93] Clause 25.3 provides a number of options to a builder if a homeowner
takes possession before practical completion. Castle Constructions letter
of 26 July 2013 indicates an intention to terminate pursuant to clause
25.3(c) and process a variation and notice of practical completion unless
the final claim is paid. The letter of 8 August 2013 does not attach such a
variation and notice of practical completion, and nor is there any evidence
to suggest these were separately given by Castle Constructions to Mr
Pourasad. In any event clause 25.3(a) entitles a builder to treat the taking
of possession as a repudiatory act which it may accept.
[94] However, the letter of 8 August 2013 refers to accepting Mr Pourasad’s
repudiatory act of giving an invalid notice of breach and subsequent
invalid notice of termination amounting to a repudiatory act, which Castle
Constructions accepts, (rather than accepting the act of entering into
possession as the repudiatory act under clause 25). This tends to suggest
a repudiation at common law. The right to repudiate at common law is
preserved by virtue of clause 27.9 which preserves other rights and
remedies in the case of breach including repudiation, other than those
available under the contract.
[95] I find that Castle Constructions terminated the contract at common law by
its letter of 8 August 2013, because of the repudiatory act of purported
termination by Mr Pourasad. As a consequence, clause 25.7 which would
27 Nina’s Bar & Bistro v MBE Corporation [1984] 3 NSWLR 613.
-- 21 of 64 --
22
deem the builder discharged and released from all liabilities, costs, losses
and damages suffered by the owner related to the works omitted under
paragraph (c) of clause 25.3 does not apply.
Is Castle Constructions entitled to its final claim of $20,530?
The legal consequences of termination by Castle Constructions at common law
[96] After termination for repudiation, the parties are relieved of their
obligations under the contract from that time.28 Obligations, other than
accrued obligations, are therefore discharged. After discharge, only
unconditionally acquired rights are enforceable.
[97] A defaulting party may be entitled to damages for a prior breach by an
innocent party. Instalments of contract price are recoverable if they have
unconditionally accrued before termination.
[98] A contractor, even if in breach of the contract, is generally entitled to
recover if work for an instalment is substantially complete, subject to a set-
off for defects in the performance.29 Where the defect(s) are serious and
the cost of rectification is significant compared to the contract price, the
conclusion may be reached that a party has not substantially complied
with his or her obligations: it is a question of degree.30
[99] Damages for completion and rectification of building work are generally
assessed as the difference between the contract price and the cost of
making the work conform with the contract.31 However, that general rule is
qualified: the work to produce conformity must be a reasonable course to
adopt.32 In respect of defective work that the cost to remedy is
unreasonable and defective work which can not be remedied, then the
measure of damages respectively becomes diminution in value of the
property and damages for loss of amenity.33 Damages to remedy defective
work which can reasonably be remedied is the reasonable cost of doing
so.
The final claim of $20,530
[100] If the right to payment for the final instalment unconditionally accrued
before termination, Castle Constructions is entitled to recover it.
[101] Mr Pourasad’s financing bank inspected the property on 24 May 2013 but
declined to pay the final payment, but pointed only to minor omissions and
defects as the reason. It says its valuer assessed that ‘a number of items
28 McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457.
29 See for example, Hoenig v Isaacs [1952] All ER 176 at 180.
30 Bolton v Mahadeva [1972] 1 WLR 1009.
31 Bellgrove v Eldridge (1954) 90 CLR 613.
32 Ibid.
33 D Galambos & Son Pty Ltd v McIntyre (1974) ACTR 10.
-- 22 of 64 --
23
including cupboard doors, plastering, painting and a manhole were yet to
be completed’.34
[102] There is no evidence to suggest that a notice of practical completion was
given at any time as required under clause 24 of the contract. However,
Mr Piran says and I accept, that despite Mr Pourasad taking possession of
the site on 15 May 2013, Castle Constructions, continued preparation of
the list of minor defects and omissions, which he had commenced
preparing in expectation that practical completion would soon be reached,
as required by clause 24 of the contract. Mr Pourasad had already taken
possession of the premises from 15 May 2013. Mr Piran made
arrangements, despite apparent reluctance on Mr Pourasad’s part, for
them to meet and go through the minor defects list. They did so eventually
on 7 June 2013. The list as amended and signed by the parties is Exhibit
5. Mr Pourasad was apparently satisfied with the list at that stage,
although he now says the Castle Constructions took advantage of him
when preparing the list.
[103] It is common ground that Castle Constructions undertook items on the
minor defects list (finishing them by 11 July 2013), even though, as Mr
Pourasad concedes, some of them (some holes in the plaster above the
skirting boards in a variety of rooms) related to defects caused by Mr
Pourasad and his agents while laying the flooring. It is then common
ground that once Castle Constructions received the ProCheck Report it
did no further work at the premises.
[104] I find that Castle Constructions rendered substantial compliance with the
contract to the practical completion stage, although practical completion
was ultimately not achieved in accordance with the terms of the contract.
Further, I find that it is entitled to payment for the final stage payment in
the sum of $20,530.
The claim for variations by Castle Constructions
[105] Castle Constructions alleges the variations set out earlier. It acknowledges
that the variation documents were not signed by Mr Pourasad. It contends
that all of the items were instructed by Mr Pourasad save item 15. For the
reasons earlier outlined, I accept Mr Piran’s evidence about these matters
and accept that Mr Pourasad did instruct variations as set out in items 1
to 14, with the exception of the clothes line which is variation 7.
[106] There was some confusing evidence about the clothes line, and whether
the homeowner was dissatisfied with the clothes line initially provided.
However, the tender document35 includes a clothes line. There are no
particular specifications for it. Nor do I have evidence about the particular
clothes line provided. However, I do not have evidence which satisfies me
that the clothes line provided was not the clothes line included in the
contract. I dismiss the claim for variation 7.
34 Exhibit 2 attachment Q, page 150.
35 Exhibit 11, at page 63.
-- 23 of 64 --
24
[107] Mr Pourasad submits that the tender includes some of the other claimed
variation items, namely variations 3 and 6. However, on my reading of that
document it does not. He also submits that front landscaping is included,
and as I understand the submission, suggests on that basis that some
other variation item or items were included items as part of the
landscaping. However, it is not apparent which variation/s in particular he
suggests was/were covered by the front landscaping for which a
provisional sum of $2,000 was allowed.
[108] The variation item 4 concerning the costs of the kitchen in excess of
$5,000 provided for in prime costs items is in error. The sum included in
the contract is $6,000. Therefore, if approved, the amount recoverable is
$3,000 plus GST of $300.
[109] Item 15 is for rubbish removal. Mr Piran says item 15 was required
because Mr Pourasad failed to attend to requested rubbish removal (of
items placed on the site by neighbours or Mr Pourasad) and he had to
make arrangements for it, if works were to be able to continue. I accept
that the rubbish removal was necessary for works to continue.
[110] Castle Constructions failure to document the variations in accordance with
the contract means that it may only recover the costs of the variations in
accordance with s 84 of the DBC Act.
[111] The variations sought by the homeowner must be considered under
s 84(2) and (4), and a builder may only recover an amount for the variation
with the Tribunal’s approval. In respect of variation item 15 sought by the
builder, the builder may only recover in accordance with s 84(3) and (4).
Section 84(4) provides that the Tribunal may only approve recovery if
there are either, exceptional circumstances or the builder would suffer
unreasonable hardship, and (in either case), it would not be unfair to the
building owner for the contractor to recover the amount.
[112] I find that Castle Constructions has done the work, incurring costs in doing
the work in variation items 1-6 and 8-14. Especially since I am satisfied
that construction was undertaken by Castle Constructions without any
profit margin, and in light of my findings as to the facts set out earlier, I find
that in respect of these items, that the builder would suffer unreasonable
hardship by the operation of s 84(2)(a). The variation items were
instructed by Mr Pourasad. I find that it would not be unfair to the building
owner for the builder to recover the amounts. Accordingly, I am satisfied
that Castle Constructions is entitled to recover the amounts claimed for
those variation items, reduced by $1,100 for item 4 as discussed earlier.
Therefore the amount recoverable by Castle Constructions for these items
is $12,452.33.
[113] Further, in respect of variation item 15, I am similarly satisfied that the
homeowner should reasonably pay the costs of removing rubbish from the
site of $572. Mr Pourasad had the opportunity to remove the rubbish and
avoid the costs but failed to do so. I find that the cost of removal
represents an unreasonable hardship on the builder in circumstances
-- 24 of 64 --
25
when he had no margin in the job, and that it is not unfair to the building
owner for the builder to recover the amount.
[114] Variations totalling $13,024.33 are therefore approved.
Castle Constructions claim for interest under the contract
[115] Castle Constructions also seeks interest under the contract. Clause 32
provides that if the owner does not pay any amount owing in full by the
due date that the owner must pay default interest to the builder.
The interpretation clause (clause 37) provides that default interest is the
annual rate equal to the Commonwealth Bank overdraft index rate
quarterly charging cycle plus 5%. Castle Constructions advises that the
overdraft index rate is currently 8.48%. The addition of 5% makes the rate
applicable under the contract 13.48%.
[116] I have concluded that interest is not payable under the contract. In respect
of the final stage claim of $20,530, I have found that there was substantial
compliance and on that basis that Castle Constructions is entitled to be
paid the final stage claim. However, practical completion was not effected
under the contract. Under clause 24.2 on reaching practical completion,
the builder must give the owner a notice of practical completion and the
final claim as well as the minor defects document under clause 24.4. A
notice of practical completion was not issued at any time by Castle
Constructions. Accordingly, I am not satisfied that the time for payment of
the final claim arose under the contract. It arises as a result of my finding
of substantial compliance and orders in this proceeding.
[117] I also disallow the claim for interest on the variations approved.
Because Castle Constructions did not prepare the appropriate variation
documents, it is only entitled to the amounts allowed by virtue of the
Tribunal’s approval of them at the date of these orders. Therefore, no
interest has accrued under the contract on the amounts claimed for
variations.
[118] Accordingly, I dismiss the claim for interest under the contract.
Castle Constructions Claim for costs under the contract
[119] Clause 33 provides for the owner to pay the builder any debt collection
costs including legal fees on a solicitor and own client basis associated
with recovery or attempted recovery of an amount under the contract.
[120] Because neither of the amounts allowed were payable under the contract,
as distinct from as a result of my findings, approvals and orders, debt
collection costs similarly are not payable under the contract.
[121] The claim for these costs is dismissed.
Mr Pourasad’s counter-claim for incomplete and defective works
-- 25 of 64 --
26
[122] Each of the items claimed by Mr Fry to be in need of rectification and/or
completion is considered in the table at Annexure A to these reasons,
which largely adopts the format used in Exhibit 21, except that I have
identified the evidence as that of Mr Fry and Mr Moore, rather than the
corporate structures (which are abbreviated to CABI and BSA in Exhibit
21) through which they operate
[123] The column entitled ‘Item’ sets out the alleged defect item as specified by
Mr Fry in his report at Exhibit 20. The column entitled Mr Fry’s evidence
sets out a summary of Mr Fry’s evidence, written (from Exhibit 21) and
oral, about the item. The ‘Costs’ column is self-explanatory, setting out
Mr Fry’s estimate, and where Mr Moore disagrees with it, his estimate. It
was acknowledged that the estimates for each item were separately
costed: if multiple items were allowed, there would be savings because
tradespersons could undertake multiple tasks in attending to the items.
The column entitled Mr Moore’s evidence sets out a summary of the
written (again from Exhibit 21) and oral evidence of Mr Moore. My
conclusions and reasons for them in respect of each item are set out in
the far right-hand column.
[124] Abbreviations are used for the National Construction Code (NCC),
Building Code of Australia (BCA) and Australian Standard (AS).
[125] As discussed earlier, Mr Fry and Mr Moore gave their evidence
concurrently. As it transpired, this occurred over three days of hearing,
22 August 2014, 25 September 2014 and 2 October 2014. The need for
additional hearing days provided the unexpected (and from my
perspective undesirable) opportunity for additional evidence to be
presented on subsequent hearing days by Mr Fry about items which had
already been covered on earlier hearing days. For example, my requests
for references to the NCC or AS rather than Exhibit 22, resulted in
tendering of extracts from those documents on later days, as well as
emails from various suppliers contacted in the interim by either Mr
Pourasad directly or Mr Fry relating to the items, about which he
apparently thought his earlier evidence may have been inadequate.
Invariably, more explanation, sometimes recanting and substituting for or
adding to the previous evidence also occurred in this process. The
expectation is, of course, that an expert will give evidence succinctly and
adequately when given (one) opportunity to do so, there not usually being
any further occasion on which it may be added to or recanted. This also
led to my overall impressions about Mr Fry’s evidence as discussed
earlier.
[126] Mr Fry’s evidence is that the house specifications include high quality
finishes, and that the only difference between a cheaper house and a
high-end house is the cost of the components. He does not consider it a
budget home. Mr Moore considers it is a budget home or project house.
He said budget homes are in the order of $1,000 to $1,500 per square
metre. This house cost about $1,000 per square metre. As they both
agree (and I accept), whatever the cost, the required construction
standards must of course be met.
-- 26 of 64 --
27
[127] In respect of the items which I have found in Annexure A are defective or
incomplete, I am satisfied that Castle Constructions obligation to perform
the work to the appropriate standard accrued or complete it (as the case
may be) before termination of the contract and that the work was defective
or incomplete as specified. The total of the individual amounts allowed is
$28,950. However, multiple items have been allowed. I accept Mr Moore’s
evidence that there will be savings in having rectification works performed
because each item will not be separately instructed. I accept, therefore,
that the amount allowed contains a loading. I consider it must be reduced
to remove the loading, by the reasonable amount of 10% of the total: that
is, $2,895. I therefore find that the total damages payable by Castle
Constructions is $26,055.
Form 21 and associated certificates
[128] The final certificate and all associated certificates should be provided to
Mr Pourasad in exchange for the monies due to Castle Construction under
these orders.
Mr Pourasad’s claim for interest under the QBCC Act
[129] Mr Pourasad seeks interest under the QBCC Act, which the Tribunal may,
in its discretion, order on damages allowed. I do not have evidence to
suggest that Mr Pourasad has incurred any cost of rectifying any of the
defects allowed by me. In the circumstances, I am not satisfied that it is
appropriate to award interest. I refuse the claim for interest.
Orders
[130] I have allowed Castle Constructions claim in the total sum of $33,554.33
for the final claim under the contract and the variations approved. I have
allowed Mr Pourasad’s claim in the amount of $26,055.00.
[131] The amount allowed for damages to Mr Pourasad offsets the amount
owing to Castle Constructions. Accordingly, Mr Pourasad must pay Castle
Constructions the difference between the two amounts of $7,499.33.
The certificates must be provided to Mr Pourasad in exchange for the
payment.
[132] Mr Pourasad claims legal costs under the QBCC Act. However, both of the
parties have had some success on their respective claims. If either or both
of the parties wishes to pursue a claim for costs, they must provide some
further submissions about why they say they should succeed on that claim
in the circumstances and setting out the amount claimed. I will then further
decide the issue of costs on the basis of the submissions without an oral
hearing.
[133] I make orders accordingly.
-- 27 of 64 --
Annexure A
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
1 External Roof:
Roof Covering Condition
in Detail:
A small number of broken
and poorly placed roof
tiles were noted and
should be replaced
Replace
Oral evidence:
Mr Fry clarified that only one of
four columns is affected: 3 are cut
and fitted snuggly, but he says on
the affected 4th column (two) tiles
are broken. He says vermin can
enter the roof cavity and that the
current arrangement allows water
to leak into the house, belatedly
suggesting that on 18 July 2014
he saw evidence that water had
entered.
He said there was deflection of
tiles and referred to non-
compliance with AS 2049,
referring to sections 6.07 and 6.09
of Exhibit 22.
On a later hearing day, he
tendered an email trail between
himself and a representative of
the supplier and installer of the
roof tiles, Bristile Roofing (Exhibit
31). Apparently, Mr Fry had given
photographs to them which a
Bristile representative suggested
indicated flashings had been
installed subsequently and
‘several roof tiles have been
$500
Mr Moore
considers the
estimated cost
reasonable if the
item is
considered a
defect
No evidence as inspected
Oral evidence:
Mr Moore opines that the tiles
are not broken but cut to fit the
roof pitch. He did not climb
onto the roof but viewed
Mr Fry’s photographs of the
area. He says that the lead
flashing provides the required
water-proofing and sisilation
stops vermin entering.
He commented that
section 6.09 of Exhibit 22
referred to by Mr Fry relates to
undulation and is not relevant
to cut tiles.
Mr Fry inspected and Mr Moore viewed
photographs only. The belated mention by
Mr Fry of ‘evidence’ that water had entered was
unable to be tested by Mr Moore. In explaining
the alleged defect, in his oral and written
evidence, he had indicated only that the current
arrangement would allow water to enter until
Mr Piran directly questioned him about any
leak, when he then suggested there was very
recent evidence which had been seen by him
only after the experts conclave (and which was
then unable to be disputed or verified by Mr
Moore). Had there been a leak, or evidence of
it, that is an important point, which I am
satisfied would have been disclosed earlier in
his oral evidence about the issue.
That said, the untested evidence of the Bristile
representative suggests he considered the tiles
on one column to be broken from his
observations of the photographs.
I prefer Mr Moore’s evidence (which accords
with my own reading of it) about the
inapplicability of section 6.09 of Exhibit 22 to
these circumstances. However, 6.07 concerns
cutting of roof tiles and states that tiles are
defective if not cut neatly to present a straight
line at ridges, hips verges and valleys.
This seems applicable to the circumstances.
Mr Moore did not suggest otherwise and did
not suggest that the requirements of the AS are
-- 28 of 64 --
2
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
removed, moved, broken and re-
installed incorrectly’ (which it is
said will void any installation
warranty) and that a reinspection
to be done had not occurred
because Castle Constructions
said they did not have control of
the site.
not properly reflected in the summary provided
by Exhibit 22.
Although I have reservations about Mr Fry’s
evidence as explained earlier, Mr Moore did not
inspect the alleged issue personally. On the
balance of probabilities, having regard to the
requirements as set out in 6.07, I find that there
are two broken tiles on one column and that
this is a defect.
I allow damages in the amount of the estimate
agreed at $500.
1.1 Restrictions - Roof
Interior:
Cavity Present/Not
Accessible:
A roof void is present but
is not accessible as, the
entry point is currently
inaccessible due to the
position of the trap.
The trap needs be
relocated to a position
which permits access to
the roof space.
Reposition or provide additional
trap to an area with greater
access to the roof area
Oral evidence:
Contravenes AS1418 Timber
Framing Code and
AS4349.1/2007 Building and Pest
Inspection Code.
Subsequently, when the hearing
reconvened on 25 September, he
told the Tribunal that in fact it was
AS4349.1 which had not been
complied with.
He subsequently tendered a copy
of AS4349.1/2007 on 2 October,
asserting that Table 3.2 is the
$500
Cost considered
reasonable by
Mr Moore
Garage ceiling access hatch
has tight but adequate access
Oral evidence:
There is no requirement for an
access hatch, but there is
restricted access to the roof
and access to the garage.
He said that there is nothing
unusual about this situation.
Mr Moore said that in his
opinion AS4349.1/2007 did not
specify access required: it is
an AS for pre-purchase
inspections only, not a building
standard.
Eventually, on the fourth day of hearing
(2 October 2014), Mr Fry tendered a copy of
the AS 4349.1/2007. It is clearly an AS about
Inspection of Buildings, that is, pre-purchase
inspections of residential buildings. It specifies
in 3.2.2 that an inspector conducting an
inspection shall determine and inspect areas
which are accessible and reasonably safe to
inspect. In table 3.2 it specifies dimensions
which are considered to provide reasonable
access (for the purposes of an inspector
determining whether he must to enter the
space during the inspection). It is not a
standard specifying requirements for
construction of a roof trap and is irrelevant to
whether or not the current trap complies with
any standard.
I accept the evidence of Mr Moore.
-- 29 of 64 --
3
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
relevant part. I am not satisfied that the current access trap
contravenes any AS.
Accordingly, I do not accept the claimed defect.
1.2 Bedroom Three
Internal Walls Condition:
Light switch between
entry door architrave and
robe architrave should be
centrally located this is
poor workmanship to
place it in the manner it
has been rectification
(sic).
Centre switch between the
architraves
Oral evidence:
Placement not contrary to any
standard, but not best practice for
light switch not to be centred.
$400
Mr Moore
considers the
cost reasonable
if defect
accepted.
Adequate location
Note : double stud
Oral evidence:
Placement is not contrary to
any standard: in a budget
home, placed at the discretion
of the electrician
It is apparent from the evidence of both
Mr Moore and Mr Fry that there is no defect.
Accordingly, I do not accept the claimed defect.
2 Windows condition
1) Adjustment required to
some windows to ensure
smooth operation
2) Insect screens are a
poor fit, all windows
should be installed with
operational screens
Windows are binding in frames,
all windows may require
replacement
Oral evidence:
8 windows only are binding, not
all of them: 2 in the master
bedroom; 2 in the family area; 3 in
the lounge room; and 1 in
bedroom 3. The windows do not
comply with the Australian
Windows Association (AWA)
Installation Standards. Mr Fry
later accepted that AWA is a
guide only and does not
$8,000
Oral evidence:
Mr Fry says this
estimate is to
remove the
windows, adjust
them and put
them back in
Mr Moore had
thought the
estimate was to
replace all
windows.
No evidence as inspected
Oral evidence:
He did not test all windows, but
those tested were not binding.
The AWA Installation
Standards are only a guide
and not intended to supersede
manufacturers’ instructions.
The AS applies.
He conceded that as per the
AWA guide, (whether it applied
or not), 10 mm clearance
under the extrusion is required.
The alleged defect item as described does not
reveal reference to the issue raised by Mr Fry
concerning the render.
Mr Moore did not test all windows. It is of
concern that Mr Fry refers to windows in rooms
where there are none, both in terms of his
credibility generally, and the estimated costs he
has advanced.
The issue regarding the screens is trivial,
involving only some insects observed between
the glass and the screen. It appears the
estimated costs do not actually anticipate any
work to rectify this.
-- 30 of 64 --
4
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
supersede manufacturers’
instructions.
Although unaware whether the
manufacturer had provided
specifications, Mr Fry asserted
that he believed they applied.
He opines that no window has a
10 mm gap between the brick sill
and the underside of the
aluminium frame because the
render applied has removed any
tolerance for movement.
His report refers to windows in the
laundry, entry and dining area.
He reluctantly accepted the
‘window’ in the entry might be a
sidelight and is not screened.
He asserted it had 20mm
clearance underneath (which he
said should be 5mm); 6-8mm up
the side (which he said should be
3mm). He said that although none
of this was in his report, he
recalled it.
He saw some insects between the
glass and screen, suggesting the
screens were poorly fitted.
On 25 September 2014, he
recanted his evidence, conceding
that AS 4654 did not support his
To remove,
adjust and
replace
8 windows, he
estimated a cost
of $5,000 to
$5,500.
He considers they are fit for
the purpose but did not look at
all of them to ascertain if there
is a 10mm gap in each case.
There is a side light in the
entry which is part of the door
which opens and closes.
In response to the evidence of
Mr Fry on 25 September,
2014, he produced several
photographs (as did Mr Fry at
Exhibit 27) which he said
demonstrate that there is black
rubber flashing under various
windows and that there is a
10 mm gap: Exhibits 26 and
28.
He opined that if render has
been applied over any of the
gaps (which he does not
concede), that this was outside
of the defect as specified.
Mr Moore expressed hesitation
about whether Exhibit 41A was
current, having been published
on 29 June 2001. He relied
upon his previous evidence in
relation to the issues raised by
Mr Fry from Exhibit 42.
Mr Moore considered
The alleged defect in 2. 1 relates to adjustment
being required to some windows, essentially
because they are binding in their frames.
Exhibit 29 is a Form 15 stating that the
windows were manufactured by Boral to meet
the required standards. It appears that Boral
manufactures windows under the trade name
of Dowell: Exhibit 42.
It is common ground that a gap is required,
although Mr Fry has amended his opinion
between hearing days about whether 10 or
12 mm is required. I accept as Mr Moore says
that that a gap of 10 mm is required.
I have looked at the photographs in Exhibits 26
to 28. Mr Fry complained that some
photographs tendered by Mr Moore were
during construction, that is, before the render
was applied. However, I have a variety of pre
and post render photographs. I can see the
black rubber flashing on the post render
photographs suggesting that the gap was not
rendered over and that movement is possible.
I was not referred to any specific part of
Exhibit 41A and as far as I can see, it contains
no information relevant to this issue, even if it is
accepted as current. Exhibit 42, as far as I was
referred to it, relates to casement, rather than
the double-hung windows in the house in
question. Mr Moore disputes the accuracy of
-- 31 of 64 --
5
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
previous evidence. However, he
asserted that an (unspecified)
document on Boral Windows
website supported, as Exhibit 23
(page 12) indicates, that a gap is
required, although he now says it
is a gap of 12 mm which is
required.
He says that if there was a gap
left when the windows were
installed, then the render has
been applied over it and it has
therefore been compromised so
that any movement in the frame
distorts the action of the window.
On 2 October, he sought again to
add to his evidence tendering
Exhibits 41, 42 and 43, claiming
now that AS4654 was not
applicable, but AS2047-99 was
relevant. In any event, Exhibit 41
is only a copy of Amendment No
2 to AS2047-1999. In Exhibit 42,
he referred me to details at page
25 relating to casement windows,
saying the sill detail was
nevertheless typical. He claimed
Exhibit 43 is a copy of a Dowell
sill detail, with his handwritten
notes endorsed to say where
essentially that the handwritten
notes of Mr Fry on Exhibit 43
misrepresented what had been
done in the construction and
did not add to what Mr Fry had
already said.
Mr Fry’s handwritten comments in Exhibit 43.
On 2 October 2014, Exhibit 53 was tendered.
It is an email dated 30 September 2014 from a
Dowell representative to Mr Pourasad which
responds to certain complaints made by him
about the operation of windows and fit of some
screens. It states that the screens fitment is
standard. In relation to the windows, it notes
that a gap is required and indicates that gaps
are present, some greater than design due to
the screens sitting higher than usual because
of the render. It notes that in double-hung
windows variations to sliding are inevitable.
Service of some windows is suggested.
One window in Bedroom 1 is noted to have a
slight bow and service is suggested.
Although the email writer was not made
available for cross-examination, the email
suggests that the screens are fitted as
expected, in keeping with the screen issue
being minor and not being a defect. I am not
satisfied on the available evidence that the
screens are defective.
In respect of the windows, the email also
appears to confirm Mr Moore’s evidence and
my own observation of the photographs. I am
satisfied that a gap is present as required.
Mr Moore did not ascertain an issue with any of
the windows tested by him. In keeping with this,
the windows complained about by Mr Pourasad
-- 32 of 64 --
6
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
‘things should be’. to Dowell, do not appear from the email from
their representative to have suggested the
need for more than a service to the windows. I
am satisfied that to the extent that any of the
windows are sticking that this is a maintenance
issue, which some 18 months after construction
was concluded, is Mr Pourasad’s responsibility.
I am not satisfied on the basis of the evidence
before me that there is a defect for which the
builder is responsible. I dismiss this aspect of
the claim.
3 Doors Condition:
The gap around the door
is excessive and uneven
and will require refitting to
rectify.
Remove and replace all doors
and door frames and ancillaries.
Oral evidence:
Mr Fry suggests that a gap of
5mm under a door and 3mm at
the sides is required with a
deviation of no more than 1mm.
He said that internal door
clearances could not be more
than 5mm under AS4654, 8.04
internal door clearances.
He suggest that the gap under the
bathroom door is 10mm.
He tendered 6 photographs at
Exhibit 32, which he claims
demonstrate inconsistencies in
the gaps. Photos 1a, 1b and 1c
and 3 are all of the bathroom
$3,000.00 to
remove and refit
all doors with
new frames.
Mr Moore
estimates $450
per door, but
considers
$3,000 for all
doors
reasonable.
Fit for purpose and functional,
no defects other than cavity
sliding door was jammed in the
cavity.
Oral evidence: Mr Moore
suggested that the usual gap
tolerances are as per
Exhibit 22, paragraph 8.04.
It is defective if less than 2 mm
or more than 5mm. He said
that external door clearances
are different, but was unable to
refer to the relevant AS. He
says when he inspected he
closed some of the doors
although not all and they
latched. He considered they
were fit for purpose. He
conceded that photographs 2
I accept that there are tolerances within which
the internal door gaps should fall as set out in
AS4654 as extracted at Exhibit 22 in paragraph
8.04.
It is difficult to ascertain the size of the gaps
from the photographs in Exhibit 32, despite a
measuring tape in photos 1a, 1b and 1c.
However, I am reasonably satisfied that the
gaps are inconsistent in photos 2 and 4.
I accept that a hinged door is not required in
the bathroom as Mr Fry says: Mr Moore did not
appear to have considered whether it was
required or not.
On the balance of probabilities, I accept that
there are inconsistent gaps in the gaps around
the 3 doors in the photographs which exceed
the tolerances. Further, Mr Moore
acknowledges an issue with the cavity sliding
-- 33 of 64 --
7
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
door, photo 2 is a bedroom door
and photo 4 is a cupboard in the
hall. He states that lift off hinges
are not required on the bathroom
door photographed.
and 4 in Exhibit 32 show a
larger gap down one side of
the door. He suggested in wet
areas some doors must have
lift off hinges requiring a larger
gap.
door. The latter is dealt with again in item 5.0 in
more detail and so is not covered here.
At a cost of $450 per door, I would allow
$1,350 to rectify the 3 doors (other than the
cavity door) concerned.
3.1 Woodwork
1) Architraves are loose
and poorly fitted these will
require removal and
refitting
2) Incorrect paint to
timberwork. Paint applied
is incorrect gloss paint is
required to comply with
the written specification.
All timber work to be
repainted to comply with
the builders written
specification.
3) Gaps in skirting.
4) Finish between
connection point of
doorjamb and wall is poor
and will require
rectification.
Repair repaint and gap fill as
required.
Oral evidence:
3.1 2) Mr Fry accepts this item is
a contractual issue and the work
is not defective. Mr Fry
acknowledged item may be
misleading as it doesn’t refer to a
particular identified area.
3.1.4) the door jamb would
usually have a moulding and it
does not.
$650.00 for all
of 3.1.
Oral evidence:
Although broken
down it consists
of $300 for
3.1 1); $350 for
3.1 2), and $50
for 3.1 3); and
$100 for 3.1 4).
Mr Moore
disagrees $350
for the paint.
He says it would
be $1,500 as
the floor
coverings and
walls would
need to be
protected.
Several gaps to architrave
mitre joints
Owner request for variation as
discussed with builder
Minor defects
No evidence as inspected
Oral evidence:
3.1. 4) A moulding is industry
practice but not necessary,
especially in a budget home.
Not a defect. Not contravene
any AS.
3.1 1) It is common ground that the architraves
are loose and require refitting. The estimated
cost was also agreed at $300. I would allow the
defect and rectification at a cost of $300.
3.1 2) The painting is not defective, although
the contract specified gloss paint. There is a
controversy about whether the homeowner
requested a variation. However, I do not need
to resolve this controversy. I am satisfied that it
would be unreasonable to require the builder to
pay for the cost of repainting in gloss paint
when the painting is not defective.
3.1 3) I am satisfied on the evidence that any
gaps in the skirting is attributable to the actions
of Mr Pourasad and/or his agents during the
floor laying. It is not defective work for which
Castle Constructions is responsible.
3.1 4) Mr Fry clarified that he does not allege a
defect: he refers to the moulding only. I accept
Mr Moore’s evidence that a moulding is not
required and that there is no defect.
3.2 Entry/Foyer: Provide cornice and paint. $800.00 Owner request for variation as There is controversy about whether the square
-- 34 of 64 --
8
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
Ceiling Condition:
No cornice has been
provided, this will require
rectification.
Oral evidence:
At the hearing, Mr Fry
acknowledged that this is a
contractual issue although he
insisted nevertheless that it was a
defect. That said, he
acknowledged that the square set
finish ceiling to wall provided is
not contrary to any AS and has no
damage, he simply contended
that the contract provided for
cornice.
discussed with builder.
Required to be square-set.
Oral evidence:
Mr Moore stated that there is
no defect.
set finish was substituted by agreement.
There is no variation concerning it. However,
ultimately, I do not consider that I need to
resolve this controversy.
It is in essence common ground that the square
set finish is not defective. I am satisfied that it
would be unreasonable to require the builder to
pay for the costs of a cornice finish in the
circumstances that there is no defect with the
current work.
The claim is dismissed.
3.3 Internal Walls Condition:
Blade wall is missing and
will need placement.
Provide additional blade.
Oral evidence: Mr Fry
acknowledged that this is a
contractual issue only.
$1,800 Unable to assess No defect is alleged. In view of my earlier
finding that Mr Pourasad instructed one blade
wall which was factored into the price and
appears in the approved plans, this claim must
fail.
It is dismissed.
3.4 Woodwork
Paint is incorrect as it
calls for full gloss in the
specification.
Paint as per schedule
Oral evidence: Mr Fry
acknowledged that this is a
contractual issue only.
$500 Owner request for variation as
discussed with builder
This is the same issue as specified at item
3.1. 2). Once again, there is no defect and I am
satisfied that it would be unreasonable to
require Castle Constructions to pay for the
costs of repainting.
The claim is dismissed.
3.5 Lounge Room:
Ceiling Condition:
Provide cornice and paint.
Oral evidence: Mr Fry
$1,200.00 Owner request for variation as
discussed with builder.
This is the same issue as specified in item 3.2.
Once again, there is no defect and I am
-- 35 of 64 --
9
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
90mm cornices are
missing and will require
placement this will be
more difficult hs(sic)
achieve a long term
adhesion to walls and
ceilings due to the fact
that surfaces have
already been painted.
acknowledged that this is a
contractual issue only.
Required to be square-set satisfied that it would be unreasonable to
require Castle Constructions to pay for the
costs of repainting.
The claim is dismissed.
3.6 Windows Condition:
1) Adjustment is required
to some windows to
ensure smooth operation.
2) Insect screens are a
poor fit, all windows and
should be installed with
operational screens.
Price allowed for in item 2. No evidence as inspected. This is the same issue as identified in item 2.
Once again, the claim has been dismissed.
3.7 Woodwork
Some skirting boards
have been placed in short
pieces where a full length
of skirting is available and
should have been used
the joints are poorly fitted
replacement required as
this is deemed poor
workmanship and should
be avoided where ever
Remove and replace with correct
length material.
Oral evidence: One piece of
skirting board is only 300mm in
length, when typically fitted in full
room length. The 300mm piece is
also mitred the wrong way.
The piece concerned is on the
right hand wall as the room is
entered.
$550.00 Minor defects
Oral evidence: Mr Moore
understands that the
homeowner removed and
replaced the skirting to lay
flooring. He did not recall
observing the piece
complained about, but
accepted that any piece
300 mm in length would not be
to industry standard.
Mr Pourasad acknowledged that he and his
agents laid flooring and that during that
process, skirting boards were removed and cut
or broken. I do not have evidence from either
Castle Constructions or Mr Pourasad about
whether the 300mm piece of skirting was
installed by Castle Constructions, or whether it
results from the actions of Mr Pourasad and his
agents.
On the available evidence, I am not satisfied
that Castle Constructions is responsible for
-- 36 of 64 --
10
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
possible. installing the 300mm piece. Further, as the
skirting has been removed and refitted by
Mr Pourasad, I am satisfied that Castle
Constructions is not responsible for the current
state of the poorly fitted joints.
I dismiss the claim.
3.8 BATHROOMS
Bathroom:
Area:
Area within the bathroom
is minimal and should be
confirmed that it meets
compliance, any person
with any kind of disability
would not be able to use
this area. The restrictive
nature of the setout of
appliances and facilities
makes this area
potentially unsafe for
general use by all that
may need to use the area
we do not believe the
meets with the general
terms of a habitable area.
Cost unknown
Oral evidence: Mr Fry contended
that the bathroom is small and he
believes it does not meet the
National Construction Code, in
particular concerning safe egress.
He was unable to nominate any
particular provision which he
considered had been
contravened.
After viewing the BA approved
plans at Exhibit 3, he
acknowledged that he could not
sustain his comments in respect
of this issue.
Owner request for variation as
discussed with builder.
Required to alter the bathroom
to facilitate a separate wc
cubicle
Oral evidence: Mr Moore
pointed to the BA approved
plans.
It was ultimately common ground that there is
no defect.
The claim is dismissed.
3.9 Doors Condition:
Doors have been fitted
Price allowed for in item 3. Fit for purpose and functional,
no defects other than cavity
sliding door was jammed in the
This issue has been dealt with in item 3.
-- 37 of 64 --
11
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
poorly in jambs the gap is
excessive and uneven the
door and jambs should be
rectified if this is not
possible then removed
and replaced with a
product that is of an
acceptable quality.
cavity
3.10 Glazing:
Mirrors and shower
screens should be
confirmed that they
comply with the relevant
Australian Standards.
Cost unknown to be determined if
mirrors fail audit.
Oral evidence: Mr Fry contended
that in the absence of a Form 15
or Form 16 that he did not accept
that the glazing complied with the
AS. He was unable to point to any
particular aspect of an AS said to
have been contravened or any
identifiable defect.
After viewing the documents
offered by Mr Moore, Mr Fry
withdrew the issue and
acknowledged compliance with
the AS.
Fit for purpose and functional,
no defects
Oral evidence: Mr Moore said
he had seen documents and
showed Mr Fry several
documents supplied to him by
Castle Constructions including
the Form 15 for the shower
screen.
It was ultimately common ground that there is
no issue.
The claim is dismissed.
3.11 Woodwork
Paint applied is incorrect
gloss paint is required to
comply with the written
specification. All timber
Repaint window only $150 Owner request for variation as
discussed with builder
This claim relates to the bathroom woodwork
only. This contractual issue has been dealt with
in item 3.1 2).
The claim was dismissed.
-- 38 of 64 --
12
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
work to be repainted to
comply with the builders
written specification.
3.12 Tiles:
The condition of the tiles
is generally poor. Tiles
have marks which cannot
be removed removal and
replacement of tiles is
required. These tiles may
be second quality.
Floor tiles in ensuite fall
away from the floor waste
this is a non-compliance
with the relevant
Australian Standard.
Remove and replace tiles,
waterproofing and wall sheet and
ancillaries.
Oral evidence: Mr Fry described a
blemish over the surface of the
tiles, which he said was like a
‘scuff mark.’ He said they should
be ‘full-gloss shiny,’ and
suggested that it was as though
something had been applied
which had taken the gloss off. He
was unable to identify any AS
which had been contravened by
the finish on the tiles. He did not
accept Mr Piran’s suggestion that
the tile was intended to mimic a
marble tile.
In relation to the fall, Mr Fry
suggests that the NCC in SA3.1
requires a fall to the bathroom
floor waste of between 1:80 and
1:100. Confusingly, since this item
deals generally with issues in the
main bathroom, the issue
concerning the fall refers to the
ensuite bathroom. Mr Fry says the
tiles fall away from the waste by
$8,500.00
Mr Moore
estimates that
$8,500 would
cover the costs
in both
bathrooms, if
the Tribunal
considers that
there is a defect
to be rectified.
See also
item 4.2.
Tiles as nominated and agreed
to by owner. No defects other
than a minor section of
splashback tile grout dislodged
Oral evidence: Mr Moore
acknowledged marks on the
tiles, but suggested they could
be cleaned. He did not believe
it had been tested, suggesting
that tilers use industrial
cleaners. He opined that the
tile had a look alike marble
type finish.
Mr Moore clarified that the
waste concerned is not the
waste in the shower. It is in the
bathroom floor. He says that
he tested the waste and it
drained. He said that falls with
large tiles can be difficult and
that the industry allows a time
frame (which is not in an AS or
the NCC) for the inflow to
waste to drain: 3 minutes for
floor waste.
This claim relates to the bathroom tiles only.
Mr Fry does not allege that the condition of the
tiles breaches an AS. Part (half) of one of the
tiles is Exhibit 33. The tile does not have a
standard full gloss finish. It has, what I would
describe, as very obvious uneven etching
marks which give the appearance of an
imitation marble finish. It is quite apparent that
they were not intended to be full gloss tiles.
The ‘scuff marks’ identified on this piece of tile
by Mr Fry are not, however, the clearly defined
etching type marks which I am describing.
Those marks are much smaller, and to my
mind in the nature of very small indentations
which appear in the gloss randomly on the tile.
It appears to me that the marks are part of the
overall marble-look intended effect. In any
event, I am not satisfied on the evidence that
there is any defect in the condition of the tiles.
Exhibit 44 commences with an explanation that
the primary consideration for falls in floor is to
ensure water does not remain on finished floor,
by ensuring it exits at the floor waste or
doorway (if it is the designated exit point). It
should not pond. The recommended fall ratio
for wet areas other than showers is specified at
between 1:80 and 1:100. It says where falls
-- 39 of 64 --
13
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
.05mm in the ensuite bathroom.
Photographs taken by Mr Fry are
at Exhibit 34. He contends that
both bathrooms have the same
issue.
In response to Mr Moore’s
comments, he said the same
issue existed in the ensuite, and
that large tiles are often cut to
achieve the required fall. He said
he was not aware of any industry
norm as described.
On a subsequent day of hearing
(2 October 2014), Mr Fry
tendered Appendix D to
AS3958.1-2007 which is
Exhibit 44.
steeper than 1:100 are not achievable, the
effectiveness of the drainage should be
confirmed to ensure it meets the primary
consideration. On my reading of it, whether the
recommended ratio is achieved, if it works to
ensure water does not remain on the floor,
rather than ponding, it is adequate to meet the
primary objective. It is not a strictly prescribed
fall.
Further Exhibit 44 refers back to the guidelines
in clause 5.4.6(a) (presumably in AS3958.1-
2007), regarding falls and drainage. I was not
provided with these, and therefore do not know
whether they provide any additional relevant
context or information.
Mr Moore tested the waste, and he says it
drained within the industry standard of 3
minutes. I accept his evidence. Based on the
evidence before me, I do not accept that the fall
is defective.
I dismiss the claim.
3.13 Basin & Taps and Shower
Screen:
Basin and taps and
shower screen should be
confirmed as a quality for
use in Australia as the
brand is unknown and
taps have no brand name
Identify and confirm if these items
comply if not then replace with
materials that meet with
Australian Standards.
Oral evidence: After viewing the
relevant Form 15 provided to him
by Mr Moore, Mr Fry conceded
$1,100.00 Fit for purpose and functional,
no defects
Mr Fry ultimately concedes that there is no
defect. The claim is dismissed.
-- 40 of 64 --
14
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
affixed. that there was no defect.
3.14 Vanity Unit:
The build quality is poor.
Replace
Oral evidence: Mr Fry contends it
is a ‘high end’ quality vanity and
that it must be replaced rather
than repaired.
In response to Mr Piran’s
questioning about whether
silicone sealing would solve the
problem, he responded with
words to the effect of ‘not 100%. It
may still allow damage (to occur).’
$1500.00 is the
estimated cost
to replace the
vanity.
Mr Moore
estimates $500
to repair the
vanity.
Fit for purpose and functional,
minor defects
Oral evidence: Mr Moore
concedes that the vanity has a
penetration hole in the base,
and is therefore not sealed,
which could trap moisture and
cause premature decay. He
says it could be repaired by
placing a stainless steel colour
cover inside the vanity. He
considers it a minor defect.
Mr Fry suggests replacing a stone top vanity
because of a penetration hole in the base, and
replacing it with another new one. I do not
accept that this is a reasonable manner in
which to rectify, what I accept is, a minor
defect.
I am satisfied on the basis of Mr Moore’s
evidence that the defect can reasonably be
repaired for a cost of $500.
I allow the claim in the amount of $500.
4.0 Ensuite Bathroom:
Windows Condition:
1) Adjustment is required
to some windows to
ensure smooth operation.
2) Insect screens are a
poor fit, all windows and
(sic) should be installed
with operational screens.
Replace cost covered under
item 2.
No evidence as inspected This issue has been dealt with in item 2.
4.1 Woodwork
Paint applied is incorrect
gloss paint is required to
comply with the written
Repaint $150 Owner request for variation as
discussed with builder
This issue has been dealt with in item 3.1. 2).
The claim is dismissed.
-- 41 of 64 --
15
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
specification. All timber
work to be repainted to
comply with the builders
written specification.
4.2 Tiles:
The condition of the tiles
is generally poor. Tiles
have marks which cannot
be removed removal and
replacement of tiles is
required. These tiles may
be second quality. Tiles
fall away from floor waste,
rectification required.
Tiles fall away from floor
waste in general area of
ensuite.
Remove and replace tiles,
waterproofing and wall sheet and
ancillaries.
Oral evidence: Exhibit 34 was
taken in the ensuite bathroom.
The floor waste in contention is
the waste in the floor, not the
waste in the shower.
Mr Fry stated that NCC 3.1 and
3.2.2 come into play.
$8,500.00 to
replace all tiles
and waterproof
ensuite
bathroom.
Mr Moore says
as the waste is
not in the
shower recess
that
waterproofing is
minimal and
$8,500 would
cover both
bathrooms, if
the Tribunal
finds the work
defective.
Tiles as nominated and agreed
to by owner. No defects
Oral evidence: Mr Moore had
understood the defect
complained about to relate to
the waste in the shower recess
of the ensuite bathroom, not
the floor waste. He says that
there is no requirement in the
NCC or the AS for a floor
waste in an ensuite bathroom,
as opposed to in the shower.
However, he conceded that if
there is one, NCC 3.2.2
applies.
This issue has been dealt with in item 3.12.
Exhibit 34 is no more than one apparent
reading on one angle and one end of the level
is not visible on the photograph on which the
level is readable. I did not find it compelling.
I make the observation that I was not provided
with a copy of the NCC at any stage, although I
was subsequently provided with Exhibit 44,
Appendix D to AS 3958/2007 which Mr Fry said
contained the ‘same information.’ I have noted
the shortcomings in the information in dealing
with item 3.12.
I otherwise adopt my reasoning in relation to
item 3.12.
The claim is dismissed.
4.3 Basin & Taps and Shower
Screen:
Basin and taps should be
confirmed as a quality for
use in Australia as the
brand is unknown and
taps have no brand name
Identify and confirm if these items
comply if not then replace with
materials that meet with
Australian Standards.
$ Part of vanity
there is no
shower screen.
Fit for purpose and functional,
no defects
As per item 3.13, Mr Fry ultimately conceded
that there is no defect.
-- 42 of 64 --
16
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
affixed.
4.7 Vanity Unit:
The vanity unit is poor
quality and damaged this
will require replacement.
Oral evidence: Mr Fry says that
the base is broken and an artificial
base is in place. He says it will
fail, because it is in a wet area.
Once again, he claims it is a high
quality installation. He contends
that it must be replaced.
$1,500.00
Mr Moore
contends that
the necessary
repairs can be
done for about
$200.
Fit for purpose and functional,
no defects
Oral evidence: Mr Moore says
that that the broken base has
been repaired with a Formica
base. He says it is functional
as it is, but not waterproof. He
suggests that it needs only to
be sealed around the edge.
I accept that the base of the vanity has been
broken, and that a Formica base has been
used to replace it, which is not waterproof.
I do not accept that it is reasonable for the
stone top vanity to be replaced because the
base has been broken. I am satisfied, as
Mr Moore suggests that it can be repaired by
sealing the base at a cost of $200.
I allow damages to repair the defect at $200.
5.0 KITCHEN
Kitchen:
Doors Condition:
The sliding doors (sic)
binds to the point where
operation does not exist
and is in need adjustment
and/or repair/
replacement.
Entire replacement maybe
necessary
$1,000.00
Mr Moore
agrees that the
door requires
repair or
replacement
and that $1,000
is a reasonable
estimate of cost.
Door binds in cavity The experts agree, and the parties accept, that
the door is defective and must be repaired or
replaced.
I allow damages in the amount of $1,000.
5.1 Woodwork
Paint is incorrect and will
require repainting with
correct gloss paint.
Repaint to specification. $500.00 Owner request for variation as
discussed with builder
This contractual issue has been dealt with in
item 3.1. 2). I adopt my reasoning as set out in
relation to it. The claim is dismissed.
5.2 Kitchen Fixtures: Oral evidence: Mr Fry suggested $40,000.00 1, 2 and 3) Mr Fry considers that the entire kitchen should
-- 43 of 64 --
17
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
The condition of the
fixtures is generally poor.
1) Gable ends are
missing.
2) Gable ends fitted are
loose and have not been
fitted correctly.
3) Stone Benchtop and
gable's (sic) appear to
have been made from
several pieces of material
instead of one piece this
is an indication that these
sections have been put
together from waste
material replacement is
necessary to ensure
quality.
Stone Gable End is
incomplete and is of poor
finish and build quality
removal and replacement
is required.
4) Sink mastic has been
fitted poorly sink wiIl
require removal and
refitting.
5) Drainage to sink is
that the stone gable end may
have been cut and epoxyed,
because he thinks he can see a
buff line. He says there are a
number of pieces of stone used in
the bench-top. Exhibit 35 and 36
refers.
Mr Moore
considers that
any item
considered
defective can be
separately
repaired. He has
broken down the
estimated costs
as follows
(Exh 37):
1) $900
2) Nil
3) $12,000
4) $300
5) $500
6) $2,000
7) $3,000
8) $8,000
9) $12,000
10) Reuse
11) $1,000
Builder offered to go to the
manufacturer to replace a
defect
Owner directed to install
No evidence of loose panels
Oral evidence: The gable end
has a defect and was to be
replaced. He agrees with
5.2.1) and the final sentence of
5.2.3). He saw no evidence of
loose gable ends. Photo BM
13 to Exhibit 19 shows a fault
line in the gable end (rather
than a join in his opinion).
He explained it is not possible
to join it mechanically.
4) Sink infill sealant is poorly
installed
5) No evidence as inspected
6) Fit for purpose
Oral evidence: Relies on the
Form 15 Glazing Certificate.
7) Crack to cook top
splashback
Oral evidence: Mr Moore
acknowledges that there is
insufficient setback as per
be entirely removed out and replaced at a cost
of $40,000.
There is some agreement that there are issues
with the stone gable end which has a line
across it which is visible on photographs in the
Exhibits, and that gable ends are missing. I do
not otherwise accept the alleged defect set out
in 1) to 3). In my view it is unreasonable to
remove and replace the entire kitchen (in view
of my findings in relation to 5.2.1-5.2.12 as set
out below). However, I accept that the gable
ends are missing and/or defective respectively.
I would allow damages for 5.2.1) in the amount
of $900 as estimated by Mr Moore. In respect
of the defective gable end referred to in the
final sentence of 3), I do not have a separate
costing for it, as opposed to replacing the all
bench-tops. However, I allow the reasonable
amount of $2,000 to replace that piece.
4) I would allow the cost to reseal it in the
amount of $300.
5) I accept Mr Moore’s evidence and dismiss
this claim.
6) The Form 15 including the Glass
Splashbacks is at Exhibit 45. I do not accept
that the items are defective. I dismiss this
claim.
7) I accept Mr Moore’s evidence that the set-
back is insufficient. Castle Constructions
-- 44 of 64 --
18
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
leaking.
6) Glass Splash backs
are poorly fitted and do
not fit the area they have
been placed in, they do
not appear to made from
safety glass as required.
(Glazing Audit required.)
7) Glass Splash back
behind cook top appears
to be to close to the
burners and has cracked
replacement is required.
(Glazing Audit Required.)
8) Floor tiles have marks
on the surface these tiles
appear to be factory
seconds. (Replacement
required.)
9) There are gaps
between the kickboards
and the underside of the
carcase (sic), some
sections appear to be
broken, these kickers
have been fitted poorly
and will require
replacement.
10) Range hood does not
Exhibit 21.
8) No evidence as inspected
9) Minor kickboard laminate
dislodged, broken
Mr Moore agrees as per
Exhibit 21. He estimates costs
for replacing the kickboards at
$12,000: see Exhibit 37.
10) Fit for purpose
11) No evidence of an
encumbrance
12) Fit for purpose
accepted that it is defective as per Exhibit 1.
I would allow damages to replace it as
estimated by Mr Moore at $3,000.
8) This item has been dealt with in item 3.12.
I adopt my reasoning in 3.12 in relation to the
tiles and dismiss the claim.
9) As per Exhibit 1, Castle Constructions
accepts the kickboards are defective. Mr Moore
has estimated $12,000 to remove and replace
them. I allow damages in the amount of
$12,000.
10) I am not satisfied that the item is defective.
I dismiss the claim.
11) I accept Mr Moore’s evidence. I am not
satisfied that the item is defective. I dismiss the
claim.
12) This item is a double-up encompassing the
earlier alleged defects. I dismiss this claim.
-- 45 of 64 --
19
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
fit the space provided
rectification required.
11) Gable end adjacent to
laundry door extends
beyond door opening and
will require rectification.
12) Kitchen is of poor fit &
build quality it is our
opinion removal and
replacement of all
components is required to
rectify problems.
6.0 LAUNDRY
Laundry:
Doors Condition:
The condition of the doors
is generally poor. See
notes regarding same in
kitchen section.
Previously costed.
Oral evidence: Mr Fry says that
there is a scuff mark on the side
of the door where it catches on
the cavity.
Both agree that
the cost to
repair this door
is $100.
Fit for purpose
Oral evidence: Mr Moore
agrees it is catching on the
cavity, but did not observe a
scuff mark. He agrees it is a
defect.
I am satisfied that the door is defective in that it
catches on the cavity. I allow the sum of $100
as damages to rectify it.
6.1 Woodwork
Paint is incorrect and will
require repainting with
correct gloss paint.
Repaint $200.00 Owner request for variation as
discussed with builder
This is the same contractual issue which has
been dealt with in item 3.1. I adopt my
reasoning in 3.1. 2). I dismiss this claim.
6.2 Tub & Taps:
1) Some leakage was
Replace bench top, replace
splashback.
$1,200.00
Mr Moore
1)Laundry tub infill sealant is
poorly installed BM-19
1) It is common ground that the sealant is
poorly installed, although a dispute about
-- 46 of 64 --
20
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
noted at the drain
rectification required.
Sealant to tub has been
poorly placed entire
removal and refit
required.
2) Bench Top does not fit
the cabinet installed
edges have been finished
poorly.
3) Glass splashback has
not been made to
suite(sic) area and
overhangs benchtop and
has not been made to suit
area replacement
required.
4) Glass splashback there
is no evidence that this
has been made with
safety glass. (A Glazing
audit is required for this
area.)
Oral evidence:
2) Mr Fry says that there is an
overhang of the stone bench top
which is unsupported. He also
says that the stone top has a
sharp edge which has been saw
cut and not buffed.
3) Mr Fry says that the
splashback does not meet the
bench top and has not been
purpose-made.
4) Oral evidence: Mr Fry does not
accept the Form 15 (exhibit 45) is
adequate to establish that the
splashback is made of toughened
glass (because he says the glass
in the kitchen has cracked but
would have shattered if
toughened glass). He tendered
Exhibit 46 which is part of the
BCA, namely 3.6 ‘Glazing’. He
believes the current version is not
significantly different.
considered the
cost reasonable
if all defect
items are
accepted.
No evidence of leaking
2) Fit for purpose BM-19
Oral evidence: Mr Moore
points out the small overhang
in Exhibit 18 in BM 19 which
provides a small useable area.
He says the stone tops are
manufactured and cannot be
saw cut. The edge complained
about faces the washing
machine.
3) Fit for purpose BM-19
4) Fit for purpose BM-19
Oral evidence: Exhibit 46 is not
the current version and does
not in any event refer to
splashbacks.
whether there is leakage. I have no separate
cost estimate to rectify the sealant. However,
I note that the kitchen mastic was poorly fitted
and $300 was the estimated cost to reseal. I
am satisfied that it is a similar issue and would
involve similar work. I allow damages of $300
to rectify this similar defect.
2) I do not accept that a defect is identified. It is
not alleged that an AS or the NCC has been
breached. The overhang appears to be a part
of the design. The finish at the side of the
bench top facing the washing machine and is
clearly intended to abut the washing machine.
A different finish to the visible part of the top is
not a defect in my view. I accept Mr Moore’s
evidence.
3) I do not accept that a defect has been
identified.
4) I have no evidence that the splashback is
defective: Mr Fry’s comments are conjecture.
Exhibit 46 is irrelevant to splashbacks.
I allow damages of $300 for 6.2.1 but reject all
other claims in 6.2.
6.2 Tiles:
The condition of the tiles
is generally poor. Tiles
have marks which cannot
be removed removal and
Remove and replace $1,800.00 No evidence as inspected This item has been dealt with in item 3.12.
I adopt my reasoning in 3.12 and I dismiss the
claim.
-- 47 of 64 --
21
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
replacement of tiles is
required.
7.0 TOILETS
Toilet:
Doors Condition:
The toilet door swings
inwards and is restrictive
to the toilet area lift off
hinges have not been
installed and need to be
as a safety measure.
Previously costed
Oral evidence: Mr Fry says that
there is a gap above door to allow
hinged door to be lifted but that
the door he inspected was not
hinged. He said he had inspected
it at least twice, and he believed
since Mr Moore’s inspection.
Separately costed, the estimated
cost is $450.
Lift off hinges have been
installed
Fit for purpose
Oral evidence: Mr Moore says
he lifted off the door he
inspected. It had lift off hinges.
$450 is reasonable if defect
allowed.
Mr Fry has done several inspections, the
earliest in mid-2013 and several since including
on 18 January 2014 and sometime in July
2014. It is not known when he last tested the
door. Mr Moore’s inspection was done recently
on 2 June 2014.
I accept that when Mr Moore inspected there
was a hinged lift off door. If it has since been
removed, that is not the builder’s responsibility.
The claim is dismissed.
7.1 Woodwork
Paint is incorrect and will
require repainting with
correct gloss paint.
$ 400.00 Owner request for variation as
discussed with builder
This item has been previously dealt with in item
3.1. 2). The reasoning is adopted from 3.1. 2).
The claim is dismissed in respect of this
contractual issue.
7.2 Tiles:
1) Floor tiles have marks
on the surface these tiles
appear to be factory
seconds. (Replacement
required.)
2) Top edge of tiles has
not been finished
correctly.
Remove and replace.
2) This issue relates to the skirting
tiles behind the toilet (not in
ensuite). The cut edge of the tile
is exposed at the top of the
skirting tile, contrary to industry
standards.
$1,200.00
Mr Moore said
that each
separately
costed room
includes call out
fees which
would not be
payable if
multiple rooms
No evidence as inspected
2) The defect identified does
not refer to the skirting tile and
he did not understand it to be
the defect complained about.
Mr Moore was unable to recall
it, but accepts industry
standards require cut edge to
be hidden.
1) This item has been previously dealt with in
item 3.12. I adopt the same reasoning.
The claim is dismissed.
2) The alleged defect complained about was
not accurately identified until during the
hearing. Castle Constructions is disadvantaged
because Mr Moore therefore did not look at the
tile in the particular area now identified by
Mr Fry. Exhibit 47 was tendered by
Mr Pourasad, but Mr Fry said that these tiles
-- 48 of 64 --
22
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
3) Architraves have been
fitted poorly and require
replacement.
were to be
allowed and
attended to.
were not defective and do not demonstrate the
issue.
Given how unreliable I have found Mr Fry’s
evidence to be, I am not satisfied from his
explanation that a defect exists. I dismiss the
claim.
3) This item has been dealt with in item 3.1 1).
I adopt my reasoning in relation to that item.
The item has already been allowed and
damages allowed. Any claim for an additional
amount here is dismissed.
8.0 EXTERIOR
Weep Holes and Vents:
Weep Holes:
The weep holes (vertical
slots to the base of the
brick walls) are blocked in
some areas. These may
have been blocked by
gardens or levels of
external paths and/or
patios. Weep holes are
necessary to allow
moisture to be removed
from and to ventilate the
wall cavity. This issue
may also compromise any
pest management to the
Repair and make good.
If damage to external walls occurs
entire external repaint maybe
required.
Repair and Make good without
damaging DPC and Termite
Barrier
Oral evidence: Mr Fry explained
that the house has been bagged.
He says that typically renderers
do not clean out the weep holes
and they are blocked by render
and bagging material. He
admitted that the wording in his
initial report was taken from a
template. There are no gardens
which impede the weep holes. He
$400.00
$6,000.00
$2,000.00
(Fry: $400 for
clearing; $6,000
to repaint entire
house; $2,000
to chip away
render)
Mr Moore
accepts the
costs as
reasonable if
defect accepted,
but says if the
work is done it
No evidence as inspected
Fit for purpose
Oral evidence: Mr Moore says
that there is no evidence of
any obstruction to weep holes.
He refers to photos attached to
Exhibit 18, BM41 and BM 42.
He observed that the weep
holes were not blocked.
He says that if there was a
blockage, there would be
evidence of damp.
Mr Moore says it is now
common practice that the DPC
does not need to protrude
through the vertical face.
He referred to AS2870-1996,
Mr Fry’s general assertion to the effect that
renderers do not clean out the weep holes is
based upon his typical experience, rather than
what he saw at this particular house. This is
consistent with the general tenor of his
evidence about this issue. This impression is
reinforced by his use of his template
comments, some of which he admits, do not
apply to this house. I do not accept that his
evidence about this issue is reliable.
Acknowledging Mr Fry’s assertions that photos
do not allow the issue to be seen, I am not
satisfied that there is any blockage, let alone
any significant blockage. I accept as Mr Moore
says that there is no evidence of damp, which
would be anticipated if there was any
significant blockage. Having said that, every
homeowner is responsible for maintaining their
-- 49 of 64 --
23
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
structure. Rectification is
recommended.
DPC and Termite Barriers
are not visible these items
are required to be visible
and identifiable.
denies that anything else
specified is incorrect. He
suggested that you cannot see
the issue from photos and that
renderers do not clean the weep
holes out properly, saying that
more than 50% would be blocked.
He apparently relied on his
observation of some 700 homes
per year all of which he says need
the weep holes to be cleaned out.
Although he seemed to concede
that the house has a DPC and
Termiblast, Mr Fry says that
unless you can visually inspect
the DPC and termite barrier, you
can’t say it’s there. He says it is
not visible because it has been
bagged and rendered over. He
says the Termiblast should extend
beyond the render. He
acknowledges that the builder has
‘struck a line’ (see Exhibit 18,
BM62 below the weep holes), but
says that it should have a
‘straight-edge along it’ so that the
termite barrier and the DPC are
visible. He relies on (Section 7) of
AS3660.1-2000 (Exhibit 48) in
7.3.3 and 7.3.4 and 7.4.2
concerning deemed to satisfy
would destroy
the DPC and
termite barrier.)
but did not provide a copy to
the Tribunal. In relation to the
termite barrier, he pointed to a
Form 16 dated 1 February
2013 (exhibit 49). He said that
now there is a slab edge visual
barrier and that accordingly,
the Termiblast does not need
to be revealed outside of the
face of the wall. He relies upon
Exhibit 48 at 7.4.2 as
highlighted by him, where it
says that when external walls
are rendered masonry, the
shielding shall finish flush with
outside of render. In Exhibit 18
BM 62, the line under weep
holes is the termite treatment.
He says that Exhibit 48 in
Figure 1 shows how this visual
barrier is provided in this
house.
He says there are numerous
alternatives which comply with
the required standards and
considers it is compliant.
property post construction, and I do not doubt
that this is an issue which should be part of a
regular maintenance program.
It is uncontroversial, and I accept, that there is
a DPC and Termiblast barrier. There was a
great deal of evidence about whether it had to
be visible and precisely how it had been done,
with both experts revising their views about
various points until Exhibit 52 was tendered to
show the construction. I accept that Exhibit 48
makes it clear that a visual termite barrier is
adequate in prescribed circumstances. I am
satisfied that there is a visual barrier on the
basis of Mr Moore’s evidence. In the end result,
as long as the house has a termite barrier and
DPC in compliance with the relevant standards,
I do not consider it is reasonable to require
rectification simply because it may have been
done in a manner other than contemplated by
the contract.
I dismiss the claim.
-- 50 of 64 --
24
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
provisions where there are graded
stone particles.
He ultimately said that it should
have been constructed in
accordance with Exhibit 16,
page 5.
8.1 Render to outside of
garage wall has not been
completed.
Remove and replace fence, place
render and paint.
$1,900.00 Adjacent owner did not allow
access for builder
It is common ground that this was not
completed. Exhibits 13, 62 and 63 refer. It is
apparent from the exhibits that the builder was
unable to gain access (after earlier permission
was revoked). It is incomplete.
This item was the subject of agreement
between the parties (Exhibit 1) and is
accordingly allowed as agreed at $1,900.
8.2 Windows:
Windows Condition:
1) Front door is of poor
quality there is what
appears to be factory
damage which may
indicate these doors are
factory seconds, door will
need to be replaced to
rectify the problem.
Remove and replace
Oral evidence: The door has
surface marks and it is poorly
varnished. It was also damaged
during installation of door locks
and has router marks at its base.
He says the workmanship is poor,
but no standard contravened.
Exhibits 50 and 51 refer.
He says the door must be
replaced.
$1500.00
Mr Moore
estimates $100
would be
adequate to
remedy 8.2 and
8.3 if both were
accepted.
Fit for purpose
Oral evidence: Mr Moore
understands the door was
custom made. He does not
consider the door is defective.
Exhibit 50 indicates that where the locking
mechanism at the base of the door is engaged,
4 small marks are visible where paint or varnish
appears to have been removed. Mr Fry opines
this was done by a router. Exhibit 51 indicates
a couple of indistinct marks in or on the timber
or inconsistencies in the varnish on the door.
These items are very minor.
The suggestion by Mr Fry that the door must be
replaced to rectify these issues is unreasonable
in my view.
On the balance of probabilities, I accept that
there are 2 small patches of inconsistent
varnish and that a tool has marked the door
-- 51 of 64 --
25
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
during installation of the lock.
I allow damages of $50 for rectification being
50% of Mr Moore’s estimate, as I do not accept
8.3 as defective.
8.3 2) Silicon to glazed
sections on the door have
been poorly finished, all
silicone will need to be
removed
Mr Fry says the excess silicon
was not cleaned off the glass
panels to give a clean edge.
$100.00 Fit for purpose
Mr Moore says he saw no
problem as inspected.
I accept Mr Moore’s evidence. The issue
identified is not a defect.
The claim is dismissed.
8.4 3) Storm moulds to front
door are incomplete and
will require rectification.
Provide and paint.
Oral evidence: A storm mould is a
bead between the door and the
door frame and wall which is
typically done, although it is not
required by any AS.
$250.00 Oral evidence: Mr Moore
agrees that it should be done
in accordance with industry
practice.
I accept that as a matter of industry standard,
this is required and has not been done.
I allow damages of $250 for rectification.
8.5 4) Rear sliding screen
door catches on the glass
sliding door this requires
rectification and possible
replacement.
Previously Priced in window
section.
Oral evidence: He considers there
is a bow in the bottom of the
frame of the screen door because
it was not installed correctly. He
says it is not impact damage.
Mr Fry: replace
$800 or repair
for $500
Mr Moore:
replace $500 or
repair $300-400
Impact damage to screen door
Oral evidence: He believed
that the screen door had been
pushed. It was removed and
fixed during his inspection.
Mr Pourasad tendered Exhibit 53, being an
email from Darin Dineen at Dowell, suggesting,
among other things, that the screen interlock is
clashing due to the door sill being out of level.
Mr Dineen was not a witness and his assertion
can not be tested. However, it tends to support
Mr Fry’s contention that there is a problem with
the frame. On the balance of probabilities, I
accept that the sill/frame is defective.
It is not apparent that there is a defect in the
door, as opposed to the bottom sill/frame for
the door. It appears that the sill or frame should
-- 52 of 64 --
26
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
be replaced, rather than the entire door and
rather than repair.
I allow reasonable damages in the sum of $400
for rectification.
8.6 Render to Ensuite window
is incomplete
Remove repair and repaint $800.00 No evidence as inspected I was informed that there was agreement
concerning this issue (Exhibit 1).
By consent, I allow damages in the amount of
$800.
8.7 Render to Entry Door Sill
is incomplete
Remove repair and repaint
Oral evidence: Mr Fry provided
Exhibit 54. The area encased in
the red pen outline is the sill he
refers to.
He says it must be chipped back
to create a bond and the sill tiles
will have to be removed.
$1,000.00 No evidence as inspected
Oral evidence: Mr Moore
considers the defect as
explained is not the alleged
defect he understood from the
description. He does not
consider it a defect in any
event: the top and underside of
the tile is different to render.
The sill area is a small area under the tile at the
front door as shown in Exhibit 54. It is a
different material. I accept Mr Moore’s evidence
that this is not a defect.
This claim is dismissed.
8.8 Provide Gullies to risers
where required in yard
area cap all others off.
Repair
Oral evidence: The risers have
been provided as per Exhibit 16,
page 3, paragraph 1, but the
gullies have not. They should
have been there during
construction although backyard
landscaping was not included.
$400.00 Landscape levels not complete
therefore the pipe stem cannot
be capped
Oral evidence: Drainage,
especially field drainage one of
last issues to be done: the
landscaping levels desired by
the owner are unknown.
Should be done as part of the
Exhibit 16, in the paragraph I was referred to,
points out the builder is responsible for
adequate drainage during construction, and the
homeowner is responsible for it post-
construction. I accept Mr Moore’s evidence that
field gullies must be placed as part of the
landscaping process which, in the area
concerned, is not covered by the contract.
I am not satisfied that a defect or incomplete
-- 53 of 64 --
27
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
landscaping. work is identified.
I dismiss the claim.
8.9 Control joints have not
been filled and will require
mastic jointing, these
joints have not been
projected to the slab
however it appears that
there is only one brick
course without the joint
we do not feel this will
cause any real issue with
the structure however we
are not engineers and this
should be confirmed by
the consulting engineer
for the project.
We are of the opinion that
extending these joints
maybe (sic) unreasonable
and cause more damage
than it is likely to prevent
as movement at this
location is likely to be
minimal.
Place Paintable Mastic $1,200 Articulation joints require infill.
Builder unable to complete the
contract works as the owner
took early possession of the
residence
I was informed that there is agreement about
this item: Exhibits 1 and 21.
By consent, I allow the item for this incomplete
work in the amount of $1,200.
8.9a Telstra Communications
have not been connected.
It is unclear as to whether
the connection has been
Cost Unknown Owner not willing to pay for
connection
There is agreement that this is a contractual
issue.
The contract did not provide for the connection.
-- 54 of 64 --
28
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
contracted to the builder
this connection would
normally be conducted by
the owner Telstra should
be contacted to advise as
to whether all work is
complete on the owners
end to establish a
connection and viable
service, if the works are
incomplete the builder
should be advised and
instructed to make good
any remedies that may be
required.
There is no evidence that the work performed
in the house to establish a viable service is
defective.
The claim is dismissed.
9.0 INTERIOR
Painting:
Painting to walls and
ceilings:
Painting throughout the
residence is at a poor
standard. Rectification is
required.
Painter to repaint throughout.
Oral evidence: Mr Fry considers
the paint appears to be ‘watered
down’. He claims that ‘you can
see through it in places,’ although
he asserts that it cannot be
discerned from a photograph. He
says the surface has an orange-
peel appearance. The cost
claimed is to repaint the interior of
the entire house.
$9,000.00 No evidence as inspected
Oral evidence: Mr Moore
considers the paint work is of
quality. He disagrees that you
can see through the paint. He
did not observe an orange-
peel effect but acknowledged
that most painters use rollers
and this can result in that type
of look. He did not observe
unpainted areas.
I prefer Mr Moore’s evidence. I do not accept
that the painting is defective.
The claim is dismissed.
9.1 Walls and ceilings:
Walls have defective
surfaces throughout the
Plasterer to repair affected walls
Oral evidence: Mr Fry explained
that there is an area in the hall
$2,000.00 was
Mr Fry’s
estimate,
No evidence as inspected
Oral evidence: Mr Moore
states that the wall surfaces
Mr Fry’s explanation of the alleged defect is
surprising. It does not fit with the alleged defect
as described.
-- 55 of 64 --
29
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
residence. Rectification is
required.
where there are at least 2 nail or
screw heads that were not
plastered over before painting. He
denied the suggestion that he was
biased in asserting a problem
throughout the house which
related to 2 nail heads in the hall.
although during
the hearing he
acknowledged it
was probably
excessive
reducing it to
$800.
are not defective and says that
this item can not translate to 2
nail heads having been
painted.
I prefer Mr Moore’s evidence that the wall
surfaces are not defective.
The claim is dismissed.
9.2 Timber/Woodwork
This is to be done in a
gloss finish paint it
currently appears to be
done in a low sheen satin
with inadequate
coverage.
Previously Noted
Oral evidence: This comment is
general, rather than in relation to
a specific room. Mr Fry concedes
that this item doubles-up with
other items already considered
and can be struck out.
Owner request for variation as
discussed with builder
The claim for the item is struck out.
Cornices:
Ceiling Cornices:
Specification calls up
90mm cornices these
appear to have been
replaced with square set
cornices need to be
installed throughout.
Gyprocher (sic) to be engaged to
place where cornice is missing.
Oral evidence: Mr Fry concedes
that this item is also a double-up
of an issue raised in other items
and can be struck out.
$3,600.00 Owner request for variation as
discussed with builder.
Required to be square-set
The claim for the item is struck out.
10 GARAGING
Garage:
General Overall
Oral evidence: Mr Fry says that
the ceiling paint is patchy around
the man-hole; and that areas
around the entry door to the
garage are not finished properly.
No evidence as inspected
Oral evidence: Mr Moore
denied the paint is patchy.
Regarding the entry to the
Consistent with Mr Moore’s evidence, I can see
no evidence of patchiness in the paint around
the man hole in BM7 to Exhibit 18. In respect of
the entry configuration, I accept that this minor
defect. However, the defects list at Exhibit 5 did
-- 56 of 64 --
30
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
Condition:
The overall condition of
the garage has defective
or unfinished area's (sic).
Mr Fry tendered Exhibit 55, being
2 photographs of part of the entry,
one a close up of the area taken
with a zoom lens.
Mr Fry says the entry door area
shows poor building practice,
although it does not contravene
any particular AS. Mr Fry says
that there might typically be a
timber reveal, but says there
should be a brick nib rather than a
timber frame. He estimates $2500
to fix, saying that he has not seen
a new house built in this manner
for some time.
garage, he referred to BM 6 of
Exhibit 18 and says that the
construction used in it is a
common configuration,
although he acknowledges that
it is a problem area in all
residential homes because the
garage door needs to be
higher than the driveway and
the panel door in a recess. If
timber is used in the recessed
area, it is problematic for water
rot. He says it is an ‘easy fix’
on practical completion: the
timber is trimmed high enough
not to be affected. He
estimates $150 to rectify.
not identify it. I make the observation that it is
difficult to gain perspective from the zoom
photo which looks untidy, whereas in the other
photo in exhibit 55, it is apparent that the area
of concern is very small.
I accept Mr Moore’s evidence and allow
damages in the amount of $150.
10.1 1) Ceiling setting is
incomplete.
2) Skirting is missing on
both sides of the garage
door.
3) Manhole to ceiling void
has been positioned
incorrectly and prevents
access to any area of the
roof void with the
exception of directly
above the roof access
panel. Due to the poor
All items will require repair ceiling
will require full repaint
$1,200.00 No evidence as inspected Mr Fry acknowledged that this item is a double-
up and can be struck out or deleted.
The claim for the item is struck out.
-- 57 of 64 --
31
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
posting of the Noid
access panel it is
necessary for a second
access point.
4) Wall lining sheet to
both sides of door frame
has been poorly fitted to
the garage door frame
and will need rectification.
10.2 Front Doors - Type &
Condition
The main garage door is
a panel lift style door and
is in good condition. Door
is currently not
operational and will
require additional
electrical work to allow
operation.
Cost unknown we will estimate an
allowance of
Oral evidence: Mr Fry suggests in
response to questions that that
the door may never have been
commissioned.
$600.00 Owner decommissioned the
door
Oral evidence: Mr Moore says
it is part of an operational
system which has been
decommissioned.
There is no dispute that the system is not
currently in commission. Whether the door was
commissioned appears to be a matter of
conjecture on Mr Fry’s part. It seems
Mr Moore’s instructions are that it was. In
neither case is the evidence a matter of expert
opinion. There is no evidence from
Mr Pourasad that it was not commissioned, and
this is part of his counter-claim in respect of
which he must establish his case.
I am not satisfied on the basis of the evidence
presented that the system is defective or was
not commissioned/completed by the builder.
The claim is dismissed.
10.3 Floor - Type & General
Condition
The concrete floor is
generally in fair condition.
Front edge has not been
Concretor (sic) to repair edge.
Oral evidence: Mr Fry says the
front edge of the garage slab is
poorly finished typical of what
occurs when the formwork is
$400.00 Fit for purpose
Oral evidence: Mr Moore
points to BM37 of Exhibit 18,
and points out that Exhibit 56
must be quite highly magnified.
I am satisfied that the complaint made
concerns a very small area of the front lip of the
edge of the garage slab. I am further satisfied
that it has not affected the soundness of the
concrete and that it is not defective. At most, it
-- 58 of 64 --
32
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
finished in a tradesman
like manner rectification
required
removed too early. He tendered
Exhibit 56 to show what he
means. He denied there is no
effect claiming that the garage is
not being used, because if it was,
he’d see tyre marks.
It therefore appears to be
minor and confined to a small
area and has had no apparent
effect since house constructed.
is a minor and inconsequential visual blemish.
I dismiss this claim.
11 SITE
Driveway:
Type & Condition:
The concrete driveway
has some visible cracking
that should be monitored
for further movement.
The crack should be cut
out and filled with a
sealant suitable for
driveways.
Grind out and provide suitable
joint filler
Oral evidence: Mr Fry tenders
Exhibit 57, which he says
demonstrates visible cracking
which could have been avoided
through use of a control joint. He
believes it contravenes an AS
although he could not nominate it.
When asked to consider whether
Exhibit 59 demonstrated saw cuts
in the driveway, he said he did not
consider they were accurate or
complete control joints, saying ‘he
may have tried to provide a
control joint.’
$450.00 No evidence as inspected
Oral Evidence: Mr Moore
considers the hairline crack in
Exhibit 57 is not of
consequence. He says that
this is very common in slabs
and referred to AS 2870
(although he did not have a
copy to tender) as de-
emphasising the significance
of hairline cracks. He denied
that the use of control joints
eliminated them, and
considered that he would not
anticipate that a residential
driveway required more than
the two saw cuts in Exhibit 59,
by way of control joints.
I prefer the evidence of Mr Moore. The hairline
crack in the driveway as shown in Exhibit 57 is
minor and of no consequence. I am not
satisfied that it suggests, much less
establishes, that the driveway is defective.
I dismiss the claim.
11.1 Paths/Paved Areas:
Type & Condition:
1) Pavement at entry
holds water as there is a
Remove and replace providing
adequate falls as detailed in
engineering documentation.
Remove and replace pavements
to a level compliant with the
$15,000.00
(Mr Fry’s
estimate is to
remove and re-
do all of the
No evidence as inspected,
adequate slope
Concrete pavement slopes
away from the building to
1) Exhibit 58 does not establish that there is not
a fall. I can not see water under the spirit level
and even if it is there, that does not establish
the issue. I am also not satisfied of its
orientation on the concrete given the general
-- 59 of 64 --
33
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
hollow in the pavement
this requires rectification
to prevent water ponding
issues.
2) Concrete paths to the
rear of the property are
approximately 85 mm to
(sic) high as they are
approximately 10mm
above the height of the
ORG this allows water to
pond towards the ORG
allowing storm water to
flow into the ORG.
Pavements have not been
placed in accordance with
the engineering details.
Removal and
replacement required
3) Pavement to front and
rear has soil placed under
which does not appear to
be adequately compacted
and protected as it is
washing out and will
require replacement. This
may require the removal
of pavements to rectify
the problem.
engineering documentation.
Remove and replace with
compacted fill.
1) Oral evidence: Mr Fry
explained that his comments
relate to the pavement outside the
front entry, which he says has no
fall. He tendered Exhibit 58,
saying that in Photo 1 the spirit
level which reads ‘0’, and which
he says is sitting ‘front to back’ is
sitting on water.
2) Oral evidence:
Mr Fry says that the concrete
paths do not comply with the
drawings, as the fall must be 1:20
to the pavements (in accordance
with Exhibit 16, page 5), that is,
be 75mm below the edge of the
concrete lip. He says he took
laser levels.
He says the overflow relief gully is
in a concealed area and he says it
is creating ponding. It is illegal to
have the ORG where storm water
can enter through ponding.
The ORG is now non-compliant
because it is supposed to be
75mm above the ground area: the
paths and the
driveway)
Mr Moore
estimates for
11.1.1) $8,000;
and for 11.1.2)
and 11.1.3)
$7,000
permit necessary run-off
Soil subsidence
Minor maintenance required to
garden bed
1) Oral evidence: Mr Moore
disagrees, and points to BM 62
to Exhibit 18 as demonstrating
the fall. He does not consider
Exhibit 58 is conclusive of the
issue, as there is a clear fall.
2) Oral evidence:
Mr Moore disagrees. He
considers that the falls to the
perimeter edge adequately
sheds water away from the
building.
He also considers the ORG is
correctly placed, and noted
that there is a plumbing
approval from the Brisbane
City Council which he says
would not have been given if
that was not so. He disagrees
that it cannot sit out in the
open. The ORG is in the slab,
not in the land. He does not
agree the surrounding land is
higher than the concrete slab.
unreliability of Mr Fry’s evidence. Exhibit 18 in
BM 62 appears to show a fall, In any event I
place more weight on Mr Moore’s evidence.
Therefore, I accept that there is a fall.
I dismiss this claim.
2) Mr Fry say that the fall in the concrete paths
away from the slab is not as required in Exhibit
16, but has not said what he considers it to be.
Mr Moore did not measure it, but says it falls to
the perimeter edge adequately to shed water.
I am not satisfied that the evidence before me
establishes that the fall is not adequate or that
it is not in accordance with Exhibit 16.
AS 3500.2-2003 in 4.6.6.7 sets out that the
height of the gully riser, or the invert of the
overflow pipe, and the finished surface level
shall be 75 mm, except where the gully riser is
located in a path or paved area, where it shall
finish at a level so as to prevent the ponding
and ingress of water. 4.6.6.8 sets out the height
for gully risers in flood affected areas. There is
no evidence to suggest that the subject
property is in a flood-affected area. It is
therefore irrelevant.
The ORG is in a concrete path. Therefore
under 4.6.6.7, the requirement is that it finish at
a level so as to prevent ponding or ingress.
Mr Fry says it is non-compliant because it is not
75mm above the ground area, and as I
-- 60 of 64 --
34
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
fall is back to front.
He relies on AS 3500.2-2003,
4.6.6.7 and 4.6.6.8 (Exhibit 60).
3) Oral evidence:
Mr Fry says that the soil under the
pavement has now subsided
away from the pavement.
He tendered photos at Exhibit 61
(1) and (2) taken on 18 January
2014, respectively said to show 2
inches of subsidence at the rear
left hand corner and at the front
left hand corner.
Mr Fry says that maintenance is
cutting the grass and fertilising.
He says that because the
pavement slab is unsupported
because of the subsidence that it
will eventually crack or tilt.
He agrees that the AS referred
to is applicable.
3) Oral evidence:
Mr Moore also took photos of
the area at Exhibit 18, BM
44,48, 59 and 60. He points
out that landscaping was only
included at the front of the
house. He says that he
considers the ‘subsidence’
seen is a maintenance issue
which should have been
avoided by landscaping the
back yard in particular.
Mr Moore says that there is no
evidence of cracking or
movement of the pavement
slab. He says subsidence at
edges is common relative to
turf planting. As it has been
finished for 18 months, he
thinks its current state is
testament to how it will
perform.
understand his evidence, it therefore creates
ponding. However, the 75 mm requirement
does not apply.
It appears that Mr Fry has misunderstood the
requirement in the circumstances presented.
I accept Mr Moore’s evidence, which accords
with what the AS says.
I dismiss the claim.
3) Landscaping in the backyard was not
included in the contract. It is apparent from the
photographs that landscaping of the backyard
has not been done, (with the possible(since I
do not have evidence about who laid it)
exception of the laying of gravel beside the side
path as seen in Exhibit 18 in BM 48): no top
soil or turf has been laid. The level of the
landscaping would typically meet the path level.
If this was done promptly, soil would not have
washed out from under the paths as it would
have been supported to stay in place.
The homeowner is responsible for maintaining
the property after construction: I accept as
Mr Moore says, that Mr Pourasad has not
fulfilled that responsibility in respect of the back
yard. I am satisfied that maintenance covers a
broader range of issues than cutting the grass
and fertilising: this assumes there is grass,
when in fact none has been laid. Mr Fry leaves
out the earlier step of landscaping in making
this statement. On the evidence presented, I do
-- 61 of 64 --
35
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
not accept that Castle Constructions is
responsible for the subsidence.
With respect to the front yard, landscaping was
included in the contract. Exhibit 61, photo (2) is
a close-up photograph of the same area as
appears in Exhibit 18 BM 55 and 56, and again
in BM 59. Exhibit 61 was taken on 18 January
2014. Mr Moore took the photographs in
Exhibit 18 during his inspection on 2 June
2014. There are no photographs to show the
dirt levels at May 2013. However, it is apparent
in all of the photographs that the dirt has
washed out from under the path near the bins.
It appears that the landscaping done did not
protect from this undesirable situation. I make
the observation that the photographs suggest
that the front retaining wall is too low and that
soil that may have been present has been able
to wash away.
Mr Moore says that maintenance would
overcome the issue. Mr Fry says that it cannot
because underneath the slab is unsupported
which the photos demonstrate. On the balance
of probabilities, I accept that there is a defect
issue here because Castle Constructions was
responsible for the landscaping in the front
yard.
On the evidence (and in particular the
photographs), I am satisfied on the balance of
probabilities that maintenance will be
-- 62 of 64 --
36
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
inadequate to overcome the issue. Mr Moore
estimates that 11.1.2 and 11.1.3 would cost
$7,000 to rectify both: he did not apportion
them, but I apportion them equally for these
purposes at $3,500 for each item. I allow
damages for the rectification of the front path
only in 11.1.3, being one half of the defect
complained about. I allow 50% of the amount
attributable to 11.1.3, that is, $1,750.
11.2 Drainage - Surface Water:
Description:
The drainage at the right
side of the property
between garage wall and
boundary fence is
inadequate. As a result,
evidence suggests that
surface water has been
ponding. Poor site
drainage can create
unstable foundations that
may have an adverse
structural effect over time.
Rectification is required.
Ground levels directly
adjacent to the building
should be reduced and
graded appropriately
away from the structure
alternatively drains may
Reduce levels and allow for
adequate drainage grades away
from residence.
Oral evidence:
The area in contention is an area
about 6 inches wide as can be
seen in Exhibit 18 BM46. Mr Fry
says that the builder has not
reinstated damage caused during
construction and that it should
have been handed over well-
drained. He says that an
agricultural drain could have been
constructed at the time of
construction and that the ground
should have been graded or a
concrete spoon drain built.
He acknowledged that the plans
do not require an agricultural
drain or a spoon drain, although
$1,500.00 Landscaping required
Oral evidence: Mr Moore says
this area is encumbered by the
boundary fence which the
builder could not do anything
about. He says there is no
problem with this localised
area. He acknowledges that
there must be a fall away from
a building in every situation,
but that boundaries are
different.
Mr Moore says that the plans
required risers only as
provided. He says this
complaint is not about
construction drainage, but
ongoing drainage which the
plans did not require.
Mr Fry’s evidence about this issue was
confusing. The plans do not require a
permanent drain in the area concerned. I do
not have any evidence about the drainage in
the area during construction. There is no
evidence to suggest it was either adequate or
inadequate.
Exhibit 16, the report from Geotechniques
Foundation Engineering includes a section on
Site Maintenance at page 3. It says that the
builder must ensure effective site drainage
during the period of the contract. After the
period of the contract, the builder must pass
the report on to the homeowner and draw their
attention to the importance of site drainage and
that it is then the owner’s responsibility to
ensure proper site maintenance (and pass on
the report). It further states that failure to
maintain the site may result in damage to the
structure and that the engineer and builder will
not be responsible for damage due to lack of
-- 63 of 64 --
37
Item Identified by Mr Fry Mr Fry’s Evidence Expected Cost
as estimated
by Mr Fry (and
where
disputed, by
Mr Moore)
Mr Moore’s Evidence Tribunal’s conclusions and reasons
need to be installed to
divert seepage and
surface runoff water away
from the house. The
drains should be
connected to the existing
stormwater drainage
system. Please contact a
Licensed Landscaper or
Builder for further
information. Please note
changing ground levels
where there is a chemical
timber pest barrier in
place affect the
performance of this
barrier and void
warranties.
they provide for other drainage
(risers) in the back yard. He then
seemed to shift his focus to say
that this was not about ongoing
drainage but drainage during
construction, and that none had
been provided.
on-going site and foundation maintenance.
On the evidence provided, I am not satisfied
that any of the options suggested by Mr Fry as
necessary were required by the plans, or that
drainage was inadequate during construction.
I agree with the statements in Exhibit 16 to the
effect that after construction, ongoing drainage
and site maintenance is the homeowner’s
responsibility.
If any further drainage is now required in the
area between the garage and the fence, it is
the responsibility of the homeowner.
I dismiss the claim for this item.
11.3 Reinstate Landscaping
after remedial works are
complete
Reinstatement
Oral evidence: Mr Fry suggests
that the ground will be damaged
during lowering of rear paths.
When it was pointed out to him
that there has been no
landscaping in the back yard, he
suggested that he meant
reinstatement as it was at
handover.
Mr Fry says
$15,000.00
Mr Moore says
nil.
Landscaping to front only
Oral evidence: Mr Moore
suggested that the costs of
any reinstatement necessary
were covered by the estimate
in 11.1.
As I have not accepted that the rear paths
require rectification, this issue does not arise.
However, if it had, I would not have accepted
damages of $15,000 reasonable to reinstate
landscaping of an area that had not in any
event been landscaped. I consider the estimate
entirely unreasonable.
I accept as Mr Moore says that the estimate of
costs for 11.1 does cover any reinstatement
that may be necessary.
-- 64 of 64 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2015/017