A.L. Builders Pty Ltd v Fatseas [2015] QCATA 185
CITATION: A.L. Builders Pty Ltd v Fatseas [2015] QCATA
185
PARTIES: A.L. Builders Pty Ltd ACN 113 964 711
(Applicant/Appellant)
V
Nicholas Fatseas and Tricia Fatseas
(Respondents)
APPLICATION NUMBER: APL224-15
MATTER TYPE: Appeal
HEARING DATE: 7 October 2015
HEARD AT: Brisbane
DECISION OF: Senior Member Stilgoe OAM
Member Steven Holzberger
DELIVERED ON: 15 December 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. Leave to appeal is refused.
CATCHWORDS: APPEAL - LEAVE TO APPEAL – BUILDING
DISPUTE - Domestic building dispute – effect of
s55(4) of Domestic Building Contracts Act 2000
- discharge of applicant’s onus – test for
overturning finding of fact.
Domestic Building Contracts Act 2000 (Qld) ss
30, 55
Dearman v Dearman (1908) 7 CLR 549
Waterford v The Commonwealth (1987) 163
CLR 54 Australian Broadcasting Commission v
Bond (1990) 170 CLR 321
Fox v Percy (2003) 214 CLR 118
Chambers v Jobling (1986) 7 NSWLR 1
Slater v Wilkes [2012] QCATA 12
APPEARANCES and REPRESENTATION (if any):
Applicant: Mr LD Bowden of counsel instructed by Nicholas Radich, solicitor.
Respondent: Mr M Williams of counsel instructed by Royston Carlyle
-- 1 of 8 --
2
REASONS FOR DECISION
[1] Nicholas and Patricia Fatseas wanted to build a new home. Their first
builder went into receivership. After some time, and negotiation, they
engaged AL Builders Pty Ltd (‘AL’) to complete the build. AL had provided
a quote for $1,098,939.60 but, because Mr and Mrs Fatseas wanted to
make substantial alterations to the plans, the parties entered into a costs
plus contract.
[2] The parties fell into dispute. AL filed a claim for unpaid progress claims. Mr
and Mrs Fatseas filed a claim for the cost of repairing defective work. The
tribunal dismissed AL’s claim but found for Mr and Mrs Fatseas in the sum
of $205,624.20.
[3] AL wants to appeal that decision. It says the tribunal erred in dismissing its
claim for payment under the costs plus contract. It also takes issue with the
tribunal’s decision to award damages to Mr and Mrs Fatseas for the cost of
rectifying a number of defects set out in their counterclaim.
[4] The appeal grounds are either challenges to various findings of fact by the
learned Member or questions of mixed law and fact. All require leave to be
obtained before the appeal can proceed.
[5] Both counsel agree that the appropriate test for leave to appeal is that
articulated in Fox v Percy.1 It was submitted by counsel for AL that while,
that test applies to finding of facts, it does not apply to an error in the fact
finding process because that is an error of law.
[6] An appeal tribunal will not usually disturb findings of fact on appeal if the
facts inferred by the Tribunal, upon which the finding is based, are capable
of supporting its conclusions, and there is evidence capable of supporting
any inferences underlining it.2
[7] An appellate tribunal may interfere, however, if the conclusion at first
instance is ‘contrary to compelling inferences’ in the case.3 As the High
Court said in Fox v Percy:
In such circumstances, the appellate court is not relieved of its statutory
function by the fact the trial judge has, expressly or implicitly, reached a
conclusion influenced by an opinion concerning the credibility of witnesses.
In such a case, making all due allowances for the advantages available to
the trial judge, the appellate court must “not shrink from giving effect to” its
own conclusion.4
1 (2003) 214 CLR 118.
2 Dearman v Dearman (1908) 7 CLR 549 at 561; Fox v Percy ibid at 125-126.
3 Chambers v Jobling (1986) 7 NSWLR 1 at 10.
4 Fox v Percy ibid at 128 per Gleeson CJ, Gummow and Kirby JJ.
-- 2 of 8 --
3
[8] There is no error of law simply in making a wrong finding of fact unless there
is no evidence to support that finding5.
Did the tribunal err in dismissing AL’s claim under the contract?
[9] The learned Member found that the contract between AL and Mr and Mrs
Fatseas was an unsigned cost plus contract and, as a consequence, was
not enforceable by AL.6
[10] AL’s claim for payment has, at various stages of these proceedings, been
particularised as:
a) an application to the Tribunal to exercise its discretion under s 55(4)
Domestic Building Contracts Act 2000 (Qld) (DBCA);
b) an application for exercise of the Tribunal’s discretion under s 84(4)
DBCA;
c) a quantum meruit claim (raised for the first time in submissions of the
original hearing); and
d) a claim for an account stated (the prospect of which was first raised in
AL’s submissions in these proceedings).
[11] Counsel for AL confirmed that only the first of these was being pressed in
the application for leave to appeal. He also confirmed that AL did not assert
that an account stated had been established and that AL did not adduce
evidence at hearing to support a claim made in amended pleadings for
exercise at the tribunal’s discretion under s 84(4) DBCA. In other words,
AL‘s first ground of appeal7 succeeds or fails on the tribunal’s application of
55(4) DBCA.
[12] Counsel for Mr and Mrs Fatseas, in oral submissions, submitted that if AL
had any remedy it is in those grounds it abandoned and not the one pressed
at hearing. He says that AL never gets to s 55(4) because it assumes that
there is an otherwise enforceable contract. We can see nothing in the
wording of section 55 that supports that conclusion but nothing turns on this.
[13] AL bears the onus of proving that an award under section 55(4) ‘would not
be unfair to the building owner’ and ultimately the learned Member found
that it failed to discharge that onus.8 In coming to that conclusion, the
learned Member found:
a) Obvious discrepancies in AL’s invoices including double charging9;
b) Deficiencies in AL’s accounting system and delegation of the task to
an office girl (who was not called)10;
5 Waterford v The Commonwealth (1987) 163 CLR 54 at 77; Australian Broadcasting
Commission v Bond (1990) 170 CLR 321 at 341.
6 Domestic Building Contracts Act 2000 (Qld) ss 30, 55(4) .
7 Ibid, ss 30, 55.
8 Reasons for decision at [64].
9 Ibid at [52], [54].
10 Reasons for decision at [57]
-- 3 of 8 --
4
c) That Mr Haley, director of AL, had no independent knowledge of the
accuracy of the company’s accounts11;
d) Payments made by Mr and Mrs Fatseas were consistent with the
original contract price, although the learned Member conceded ‘a
degree of artificiality’ in that exercise.
[14] Counsel for AL submits that the parties’ process of dealing with the progress
claims resulted in an agreement as to the quantum of claims and the parties
should be bound by that agreement. Counsel confirmed that he did not
intend that submission to be an argument for an account stated claim but
rather an ‘admission by conduct’ that the costs were not unfair. Counsel
further submitted that, through this exercise, Mr and Mrs Fatseas
compromised their rights in relation to these claims.
[15] The discretion to award the cost of providing the contracted services lies
with the tribunal. The fact that the parties may have agreed some of those
costs may inform the tribunal’s exercise of its discretion but it does not
compel the tribunal to adopt that agreement.
[16] Counsel for AL submits that the learned Member’s assessment of the
reasonable costs12 ‘involves too many uncertainties and cannot be relied
upon’. Counsel gives examples: he submits that the claims did not have
consistent numbering. He submits that the work AL did was not necessarily
the same as the work quoted, so that the reconciliation process was not
reliable.
[17] Counsel’s submissions on appeal, together with the learned Member’s
findings, rather prove the learned Member’s point. AL had the onus of
proving that the costs were not unfair and it was unable to do so because
of the inherent difficulties in its accounting process.
[18] We can find no reason to disturb the learned Member’s finding that AL failed
to discharge the onus of establishing that an award by the tribunal under
section 55(4) would be unfair to the building owner.
Did the tribunal err in giving Mr and Mrs Fatseas damages for defective
building work?
[19] Mr and Mrs Fatseas sought damages in respect of some 130 items which
they claimed were defective. The learned Member found for them in respect
of 40 of these items. As Mr and Mrs Fatseas’ Counsel submits, in
considering the various claims the learned Member accepted the evidence
of the expert witnesses on some points but not others, and he did not
necessarily agree with their proposals for rectification. This is consistent
with a careful consideration of the evidence in respect of each of the items.
[20] In considering each of these grounds of appeal, we are mindful of the
considerable hurdle that Counsel for AL must overcome. It is not enough to
11 Reasons for decision at [57].
12 Reasons for decision at [61] to [63].
-- 4 of 8 --
5
demonstrate that the evidence can support an alternative funding; Counsel
for AL must demonstrate that the learned Member’s finding is contrary to
the compelling inferences.
[21] The test to be applied is set out comprehensively in the appeal tribunal’s
decision of Slater v Wilkes13:
The applicant for leave must show that the decision in question is affected,
arguably at least, by an appealable error, resulting in a substantial injustice.
It is not such an error to prefer one version of the facts to another, or to
attribute more weight to the evidence of witness “A” than to the testimony of
witness “B”. Findings of fact will not usually be disturbed on appeal if the
findings of fact by the original decision maker have rational, albeit debateable
support in the evidence. Where reasonable minds may differ, a decision
cannot properly be called erroneous, simply because one conclusion has
been preferred to another possible conclusion. Leave is not to be given
where a party simply desires to re-argue the case, on the existing or
additional evidence. One clear purpose of a “leave” requirement is to
preclude any attempt to conduct a retrial on the merits.
Fractured paving tiles
[22] In his reasons for decision the Learned Member said:
I accept the evidence of Dr Hensell, particularly where his evidence differed
with Mr McLeod. I was of the opinion that Mr McLeod’s recollection of events
was hazy. He gave his evidence by telephone from Thailand where he was
holidaying. He demonstrated little interest in the issues being canvassed.14
[23] Counsel for AL was critical of Dr Hensell’s evidence which he said was not
reliable because:
a) He did not correctly identify the adhesive used by Mr McLeod;
b) He relied heavily on the adhesives labelling instructions and
specifications; and
c) He changed his opinion as to the cause of the damage from the
adhesive used to the consistency of the screed on which the tiles were
laid.
d) His expertise was as a geologist, not a tile expert.
[24] The learned Member received reports and heard evidence from
Mr Betteridge, a building expert, Dr Hensell, a geoscientist, and
Mr McLeod, AL’s tiler.
[25] Counsel for AL submitted that the evidence about the cause of the fractured
tiles was ‘all over the place’, He submitted that the evidence called by Mr
and Mrs Fatseas was vague, inconsistent and contradictory and Counsel
took us to examples in the transcript. He urged us to prefer the evidence of
13 [2012] QCATA 12 at [6] (footnotes omitted).
14 Reasons for decision at [119].
-- 5 of 8 --
6
AL’s tiler which, he submitted, was clear and unchallenged as to the way
the tiles were laid.
[26] The learned Member canvassed the evidence as a whole. There was no
dispute that the tiles were defective; the question for the learned Member
was whether AL was responsible for the defective tiles. The learned
Member accepted Dr Hensell’s report that noted15 ‘…the saturation of the
screed and consequential movement of the slab was more likely the cause’
(of the cracking). That finding did not depend upon any conclusion about
the adhesive. It was within Dr Hensell’s expertise and the learned Member
was entitled to rely on it in forming his conclusions.
[27] That another conclusion was open to the learned Member is not the test
that we are required to apply. The evidence can support the learned
Member’s conclusions and we can find no compelling reason to come to a
contrary view.
Incomplete waterproof membranes
[28] Counsel submits that AL should not be liable for work that it did not do and
for which it did not charge.
[29] The learned Member heard competing evidence about whether the
waterproof membranes was part of the scope of works. The learned
Member said16:
According to Mr Davidson this was not evident in the drawings. I assume
therefore that the applicant installed them at the request of the owner in which
case the applicant is liable as a cost plus matter.
[30] The evidence can support a finding that the concrete block planters to which
this item refers were included in the contract drawing and schedule of
finishes and specified that the interiors be waterproofed. There is no
evidence that any agreement was reached between the parties to exclude
waterproofing from the contract.
[31] In those circumstances the learned Member’s finding of fact can be
supported by the evidence and we can find no compelling reason to come
to a different view.
Efflorescence and algae – stairs from River Terrace
[32] While the learned Member conceded that this point was “difficult to decide”17
that is not to say, as Counsel for AL asserts, that he was ‘unsure on this
issue’.18
15 Ibid at [116].
16 Ibid at [130].
17 Ibid [130], item 30.
18 Appellant’s outline of submissions.
-- 6 of 8 --
7
[33] The learned Member heard competing evidence about the cause of the
efflorescence and algae. Mr Aitken told the tribunal it was a maintenance
issue. The learned Member also had the evidence of Mr Betteridge and
Dr Hensell, which he clearly preferred to that of Mr Aitken. Counsel for AL
is critical of the learned Member’s reliance on Mr Betteridge and Dr Hensell
because, he says, those reports focus on the issue of the adhesive.
[34] The learned Member accepted that a considerable amount of Mr and Mrs
Fatseas’ claim was due to deterioration because of lack of maintenance19.
However, in relation to the efflorescence, he noted “Mr Aitken agreed this
was the responsibility of the Applicant”20. The learned Member was entitled
to find as he did and we can find no compelling reason to come to a different
view.
[35] This ground is dismissed.
Cracked tiles, pool waterline
[36] Mr Aitken considered that five tiles needed replacing. Mr and Mrs Fatseas’
expert, Mr Betteridge, relying on Dr Hensell’s report, gave evidence that all
existing tiles needed to be replaced as the adhesive was defective.
[37] As with the defective tiles, the learned Member accepted Dr Hensell’s
evidence as he was entitled to do. The learned Member did not however
accept Mr Betteridge’s evidence that all pebblecrete in the pool would
require replacement as a consequence. He found for Mr and Mrs Fatseas
only in respect of the replacement of all of the tiles.
[38] It is not the case that there was no evidence to support the leaner Member’s
finding. Counsel for AL might urge upon us a different conclusion from the
evidence but that, as we have mentioned, is not the test. The learned
Member is entitled to prefer the evidence of Mr and Mrs Fatseas’ experts to
that of AL’s experts and accordingly this ground is dismissed.
Delamination of the front entry gate
[39] Whether the problem with the front entry gate was caused, or at least
contributed to, by a lack of maintenance was not a relevant consideration
for the learned Member. He found, and there was no dispute, that the gate
was not the one specified by the contract, it was of a lesser quality and,
therefore, more likely to delaminate. He found that Mr and Mrs Fatseas were
entitled to the gate as specified. The evidence can support that view.
Laminated timber trim delaminating around portholes
[40] The learned Member did not know whether AL installed the trim or whether
the previous builder installed it. Counsel for AL submits that, because of this
19 Reasons for decision at p 27.
20 Ibid at p 29.
-- 7 of 8 --
8
uncertainty, the learned Member should not have made AL liable for the
delamination.
[41] AL’s main objection on this item, as with the front entry gate, was that the
delamination was a maintenance issue. The learned Member found that it
was a defect that AL should have noticed and rectified. In taking over the
building from the previous contractor, AL assumed responsibility for the
quality of the work done to date. The learned Member found that it was not
a maintenance issue. We can find no evidence that would cause us to come
to a different view.
Bathroom tiles
[42] Counsel for AL submits that Mr McLeod was the only tiling expert called and
his evidence, that the tiling was not defective, should have been accepted.
[43] The learned Member also had evidence from Mr Betteridge, a registered
builder. Although he was not a “tile expert”, the learned Member obviously
found him a persuasive witness about whether or not the joints in tiles were
properly aligned.
[44] Whether or not expert evidence is necessary to prove that tile joints do not
align, the learned Member preferred Mr Betteridge. The learned Member
expressed his views about Mr McLeod21. We have no reason to come to a
contrary view.
[45] This ground is dismissed.
New internal timber stairs
[46] The learned Member’s finding that the internal stairs are non-compliant is
supported by the report of Mr Betteridge.
[47] While there is some evidence from Mr Haley in cross-examination of an
agreement to rectify the defect by placing a landing at the foot of the stairs,
the evidence showed that the stairs are still non-compliant and, accordingly,
still defective.
[48] The Member has found the work to be defective because it is non-compliant
and that finding should stand.
[49] This ground is dismissed.
Conclusion
[50] Leave to appeal is refused.
21 Ibid at [119].
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2015/185