Carter & Anor v HK Developments Pty Ltd [2015] QCATA 59
CITATION: Carter & Anor v HK Developments Pty Ltd
[2015] QCATA 59
PARTIES: Nathan Carter
Damita Carter
(Applicants/Appellants)
v
HK Developments Pty Ltd
(Respondent)
APPLICATION NUMBER: APL345-14
MATTER TYPE: Appeals
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Senior Member O’Callaghan
Member Roney
DELIVERED ON: 23 April 2015
DELIVERED AT: Brisbane
ORDERS MADE: 1. The appeal is allowed.
2. The decision is set aside.
3. The matter is returned to the Tribunal for
rehearing.
4. HK Developments Pty Ltd pay into the
Trust Account of QCAT by 4:00pm on 30
April 2015 the sum of $79,841.45 pending
the rehearing of the matter.
CATCHWORDS: BUILDING – where builder suspended works on
the basis of owners failure to pay progress claim
and variation – where Tribunal held suspension
valid and subsequent termination by owners
invalid – whether findings were an error of law
Domestic Building Contracts Act 2000 (Qld),
s 84
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 142, s 143
HK Developments Pty Ltd v Carter [2014]
QCAT 330
-- 1 of 6 --
2
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
[1] On 23 April 2015 the Appeal Tribunal made orders as set out above .These
are the reasons for that decision.
[2] The appellant appeals the decision of QCAT dated 14 July 2014 pursuant
to s 142 and s 143 of the Queensland Civil and Administrative Tribunal Act
2009 (Qld) (‘QCAT Act’).
[3] The appeal and submissions were filed on 11 August 2014. No response to
the appeal was filed by the respondent.
[4] The Tribunal convened a directions hearing to hear from the respondent on
the 15 April 2015 but the respondent did not appear.
[5] The net position therefore is that the Tribunal has not received any material
from the respondent for the purpose of this appeal.
Leave to Appeal and Appeal as of Right Issues
[6] At QCAT, an appeal as of right is available only in relation to questions of
law.
[7] In the application for leave to appeal and appeal the appellant lists 10
grounds of appeal as follows:
1. The Member has not applied the law in her finding the variations were
due at the time of the suspension notice.
2. The Member has made errors in finding of mixed law and fact that the
suspension notice adequately identified the breaches.
3. The Member has made errors in finding of fact that the owners were in
breach of contract and not permitted to terminate.
4. The Member has not applied the law in not finding that the suspension
notice was invalid for not providing the required amount of time under
the contract to remedy the breaches in notice of suspension.
5. The Member has made errors in finding of fact in her Schedule A.
6. The Member has made errors in finding of fact in her findings of
incomplete and defective works, she has not considered all the
evidence made available as she could not have made findings she
made if all the evidence was considered.
7. The Member has made errors in finding of fact that the variations were
variations.
8. The Member has not applied the law in failing to find it would be unfair
for the owners to owe money for the variations.
-- 2 of 6 --
3
9. The Member has not considered and made findings on claims of
liquidated damages as required to do.
10. The Member has made errors in how she calculated the interest on the
decision as the time for payment of variations only materialised upon
the making of her order and penalty interest cannot apply from the time
the contract was ended.
[8] Some of the aforementioned grounds are stated to be errors in findings of
fact. Grounds 1, 2, 3 and 4 whilst not articulated precisely raise a question
of law regarding the status at law of the variation agreement1 and
consequently the validity of the suspension notice.
[9] These grounds may be dealt with for convenience together. Leave to appeal
is not required in relation to a question of law.
Did the learned Member make an error of law in her findings regarding the
status of the variation agreement and consequently the suspension
notice?
[10] The learned Member held that the respondent builders notice to suspend
works dated 4 February 2011, so far as it relates to variations, was valid.2
She held that the notice was not valid insofar as it related to the practical
completion payment because she found that stage had not been reached
and accordingly there was no entitlement to payment for the practical
completion claim.3
[11] In relation to the variation claims she says in her judgment as follows:4
[46] The variations signed 14 September 2010 and three further variations
signed by Mr Carter on 30 September 2010 form the basis of HK
Developments’ suspension notice. The notice also lists a variation
alleged by the builder as owing because of non-standard tile being
supplied by Mr Carter although no written variation has been provided
for this item.
[47] I am satisfied that Mr Carter did not remedy this breach within the time
required under the notice or under the time requirements of clause 16.3
of the contract.
[48] I am therefore satisfied that Mr Carter was in breach of the contract at
the time the suspension notice was issued by HK Developments and
that the suspension notice was a valid notice insofar as it relates to the
contract variations.
[12] Although the learned Member acknowledges the shortcomings of the
variations when she states:5
[42] As a valid variation to the contract, this document fulfils most of the
requirement of clause 12 – it is written, describes the variations,
1 Exhibit 11.
2 HK Developments Pty Ltd v Carter [2014] QCAT 330 at [48].
3 Ibid at [34].
4 Ibid at [46]-[48].
5 Ibid at [42]-[43].
-- 3 of 6 --
4
generally identifies the reason for the variations, estimates any delay in
the works and is signed by both parties. It does not state any
adjustment to the contract price but records that the owner must pay
the variation price at the correct stage.
[43] Although there is no final figure, each variation item is generally
sufficiently costed throughout the document for the parties to be aware
of their obligations.
[13] There was no dispute between the parties that the variation claim remained
unpaid.
[14] We do not accept the construction of the variation agreement as contended
for by the respondent at the hearing and as found by the learned Member
in that the formal requirements of the Domestic Building Contracts Act 2000
(Qld) have not been met and were not otherwise the subject of an order
under s 84 of that Act.
[15] The variation agreement fails to state a date for payment. On its face, there
is no clear unambiguous expression of when the variation is to be paid.
[16] Neither in our view is the amount agreed for the variation apparent.
[17] The result in our opinion is that there is a lack of clarity about the cost of the
variation and the time for payment. There is an uncertainty as to the terms
of the variations.
[18] This leads to the position where on the face of the document there is no
concluded agreement between the parties about these critical matters, price
and payment. Absent an agreement with respect to these matters, there can
no proper variation at law and no breach for a failure to pay an amount by
a particular time.
[19] There is no proper variation for the purpose of the contract and certainly not
one such that the failure to pay might ground a valid notice of suspension.
[20] Put simply the appellant was not in breach because there was no obligation
to pay variations, certainly not before the contract had reached practical
completion.
[21] It follows that, as there was no breach of an obligation to pay a variation
there was no basis in law to issue the notice to suspend works. A notice to
suspend works for non-payment of variations, could not issue in
circumstances where there was not a proper claim under the contract for
those variations, as we have held above.
[22] It may well be that the respondents demand for a payment that was not
properly due under the contract, was itself unlawful. It may amount to a
breach of a contract entitling the appellants to accept the repudiation and
provide a notice of intention to terminate as was done.
-- 4 of 6 --
5
[23] Thus the position with respect to termination of the contract and the
consequences which flow from that could be entirely reversed from the
position as held by the learned Member at first instance.
[24] In light of our findings the matter should be returned to the Tribunal to rehear
and to consider whether:
a) the giving of the notice to suspend work by the respondent was a
repudiation of the contract;
b) the appellants lawfully terminated the contract on 16 February 2011;
c) the appellants are entitled to damages to be assessed for a breach of
contract by the respondent;
d) the respondent is entitled to a quantum meruit for the value of work it
has performed subject to progress payments already made and the
appellants’ damages claim.
[25] The position in relation to grounds 5, 6, 7 and 8 is quite different.
Grounds 5, 6, 7 and 8
[26] The appellant’s submissions on these grounds are variously that the
learned Member has missed or has misinterpreted the evidence, that she
has failed to consider the evidence before her and that her findings do not
reflect the correct value of incomplete or defective work.
[27] The outcomes in Schedule A to the decision record the Members findings
about the evidence, which she heard and accepted about defects and
incomplete works and her reasons for doing so.
[28] The parties provided extensive expert evidence to the Tribunal: the
applicant provided reports of Messrs Dixon and Dyer, the respondent
provided Mr Ripley. The Tribunal at first instance also had the advantage of
joint reports by experts produced after a final conclave.
[29] The Tribunal had the advantage of reviewing the reports and hearing from
the experts in person. The learned Member has considered competing
views and reached a decision on the evidence before her.
[30] The findings of the primary judge of fact are not easily disturbed. Manifest
error must be apparent to render the findings incompetent.
[31] Our view is that the decisions she has reached in relation to each of the
items of defective work and rectification are not so unreasonable that they
could not have reasonably been made on the evidence before her.
[32] Accordingly, no error is disclosed.
[33] It should be noted that some of her findings record agreement between the
experts or an acceptance of the majority of expert views in relation to each
item, see for example items 1, 3, 4, 16, 20, 21, 30, 39, 41, 42, 43, 44, 45,
47, 52, 63, 68, 78, 81.
-- 5 of 6 --
6
[34] Leave to appeal is required for grounds 5, 6, 6 and 8 and no leave is
granted.
[35] The matter is returned to Tribunal to rehear in light of the findings of this
Appeal Tribunal and the issues raised in [24] above.
[36] The appellants have paid the respondent the amount awarded to it by the
Tribunal below.
[37] It is appropriate in light of the findings of this Appeal Tribunal that the
respondent pay the money into the Tribunal’s Trust Account pending the
rehearing and determination.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2015/059