CMF Projects Pty Ltd v Riggall & Anor [2014] QCA 318 [2016] 1 Qd R 187
SUPREME COURT OF QUEENSLAND
CITATION: CMF Projects Pty Ltd v Riggall & Anor [2014] QCA 318
PARTIES: CMF PROJECTS PTY LTD
ACN 114 539 212
(appellant)
v
BRIAN NOEL MANSON RIGGALL
(first respondent)
JANE REIMAN RIGGALL
(second respondent)
FILE NO/S: Appeal No 4459 of 2014
DC No 4085 of 2013
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: District Court at Brisbane
DELIVERED ON: 2 December 2014
DELIVERED AT: Brisbane
HEARING DATE: 17 September 2014
JUDGES: Holmes, Gotterson and Morrison JJA
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made
ORDERS: 1. Appeal allowed.
2. Vary Order 1 made on 29 April 2014 to read:
“Paragraph 7, 8, 9 and 12 of the amended
statement of claim and paragraphs 4(d),
10 and 11 of the reply and paragraphs 1,
3(b) and 4 of the answer to the amended
counterclaim be struck out.”
3. Set aside Order 2 made on 29 April 2014 and
substitute the following order:
“There be no order as to costs.”
4. Order that the respondents pay the appellant’s costs
of the appeal on the standard basis except those costs
with respect to Grounds 2(a) and (c) in the notice of
appeal filed on 8 May 2014.
5. Order that the appellant pay the respondents’ costs
of Grounds 2(a) and (c) in the said notice of appeal
on the standard basis.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
RECOVERY ON QUANTUM MERUIT – IN GENERAL –
where the home owner respondents entered into an agreement
-- 1 of 13 --
2
with the builder appellant to renovate the former’s home –
where the contract was a “cost plus contract” for the purposes
of the Domestic Building Contracts Act 2000 (Qld) (“DBCA”) –
where the appellant carried out the work between 10 June
2011 and 2 May 2012 – where the respondents made payments
on 10 progress claims totalling $1,938,932 – where in
October 2013 the appellant commenced proceedings against
the respondents for an outstanding sum of $182,252 – where
the respondents defended the action on the basis that the
agreement was unenforceable for non-compliance with the
DBCA – where the appellant filed an amended statement of
claim pleading quantum meruit – where the learned primary
judge struck out the amended statement of claim – whether
the provisions of the DBCA preclude an action based on
quantum meruit
PROCEDURE – COSTS – POWERS OF COURT – ORDER
FOR COSTS ON INDEMNITY BASIS – where the learned
primary judge ordered the appellant to pay the respondents’
costs of the application on the indemnity basis – whether the
quantum meruit argument was unreasonably maintained
Domestic Building Contracts Act 2000 (Qld), s 3, s 30, s 55(3),
s 55(4), s 84
Berowra Holdings Pty Ltd v Gordon (2006) 225 CLR 364;
[2006] HCA 32, applied
Gemini Nominees Pty Ltd v Queensland Property Partners
Pty Ltd [2008] 1 Qd R 139; [2007] QSC 20, reversed
PACD Pty Ltd v Depas Pty Ltd [2007] VCC 1683, cited
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221;
[1987] HCA 5, cited
Sargood Bros v The Commonwealth (1910) 11 CLR 258;
[1910] HCA 45, applied
Thompson Residential Pty Ltd v Tran & Anor [2014] QDC 156,
cited
COUNSEL: A Crowe QC, with G Coveney, for the appellant
J K Bond QC, with G I Thompson, for the respondents
SOLICITORS: Arrow Law for the appellant
HWL Ebsworth for the respondents
[1] HOLMES JA: I agree with the reasons of Gotterson JA and the orders he
proposes.
[2] GOTTERSON JA: CMF Projects Pty Ltd (“the appellant”) is a builder. Brian
Noel Manson Riggall and Jane Reiman Riggall (“the respondents”) own a home at
Chelmer in Brisbane. The appellant and the respondents entered into an agreement
(“the Agreement”) whereby the former was to carry out renovation work on the
latters’ home between April 2011 and May 2012. The Agreement was a “cost plus
contract” for the purposes of the Domestic Building Contracts Act 2000 (Qld) (“the
DBCA”). It was also a “regulated contract” as that term is defined in the DBCA.
-- 2 of 13 --
3
[3] The appellant carried out renovation work at the respondents’ home for which it
rendered 10 progress claims between 10 June 2011 and 2 May 2012, for a total
amount of $2,121,234. The respondents made payments on the progress claims in
a total amount of $1,938,982.
[4] On 23 October 2013, the appellant commenced proceedings against the respondents
by filing a claim and statement of claim in the District Court at Brisbane. The sum
of $182,252, being the difference between the respective total amounts, was claimed.
Claims were also made for interest on the amount claimed and costs.
[5] As the short summary of the evolution of the pleadings set out in these reasons
reveals, the respondents defended on the basis that the Agreement was unenforceable
for non-compliance with the DBCA. They also counterclaimed repayment of what they
had paid the appellant on a related restitutionary basis. The appellant put in issue
the basis of the defence and counterclaim by way of a reply and answer.
[6] The respondents filed an application to strike out the statement of claim dated
23 October 2013 and certain paragraphs in the reply and answer on 1 April 2014.
On 11 April 2014, and several days before the date of hearing of the application, an
amended statement of claim was filed by the appellant. A substantial amendment
made to the pleading was the addition by paragraph 7A, as an alternative, a claim in
quantum meruit for the $182,252. At the hearing of the application on 15 April 2014, the
respondents filed by leave an amended application by which they sought striking
out of the “the proposed amended statement of claim dated 11 April 2014” and the
same paragraphs in the reply and answer.
[7] On 24 April 2014, reasons for judgment were delivered.1 Orders giving effect to
those reasons were made on 29 April 2014.2 The amended statement of claim and
the nominated paragraphs in the reply and answer were struck out (Order 1) and the
appellant was ordered to pay the respondents’ costs of the application on the indemnity
basis (Order 2). A third order gave the appellant liberty to make written submissions
within seven days seeking to have the indemnity costs order set aside in favour of
an alternative order. After consideration of further submissions from each party, the
learned primary judge published reasons on 8 May 2014 for his decision not to set
aside the indemnity costs order.3
[8] On 8 May 2014, the appellant filed a notice of appeal to this Court. The notice of
appeal identifies the judgment appealed against as having been given on 24 April
2014. The appeal evidently is also against the orders made on 29 April 2014.
The pleadings
[9] The statement of claim filed on 23 October 20134 pleaded a basis of recovery that
was entirely contractual in nature in that it was based upon breach of an implied
term of the Agreement by the respondents in failing to pay in full the progress
claims submitted to them: paragraph 7; and that the unpaid amount was payable
pursuant to the terms and conditions of the Agreement: paragraph 12. This pleading also
contained two arguably curious allegations for a pleading of this nature. One was
1 AB210-223.
2 AB224.
3 AB225-228.
4 AB147-150.
-- 3 of 13 --
4
that by their conduct in making payments on progress claims that had been
submitted to them, the respondents were estopped from denying that any money
was owing on the unpaid progress claims: paragraph 8. The other was that in order
to mitigate its loss, the appellant had offered to accept the sum of $120,000 in
satisfaction of its claim: paragraph 9.
[10] The respondents’ initial pleading was superseded by a defence and amended
counterclaim document filed on 14 January 2014 in which the paragraphs in the defence
were numbered 1 to 13 and those in the amended counterclaim 1 to 38 respectively.
This pleading maintained the defence that had been pleaded in the initial pleading.
The essence of that defence was pleaded in paragraph 2 thereof. Entry into the
Agreement for the renovation work was admitted: paragraph 2(a).
[11] Paragraph 2(c), however, pleaded a number of facts and certain legal conclusions
that flowed from them. Significantly, it was there pleaded that the Agreement was a
“cost plus contract” and a “regulated contract” as those terms are defined in the DBCA:
paragraph 2(c)(ix); that the Agreement was not signed by the respondents:
paragraph 2(c)(x); and that the Agreement did not contain any estimate of the
amount which the appellant was likely to receive under it: paragraph 2(c)(xi).
[12] The respondents’ pleading then alleged that by virtue of their not having signed the
Agreement and the operation of s 30 DBCA, the Agreement was unenforceable by
the appellant: paragraph 4(b)(i); and that by virtue of the omission from the Agreement of
a fair and reasonable estimate of the amount that the appellant was likely to receive
under it as required by s 55(2) DBCA, the Agreement was also unenforceable pursuant to
s 55(3) thereof. The respondents pleaded that, accordingly, they owed no amount to
the appellant: paragraphs 10, 11.
[13] As noted, the respondents’ counterclaimed for repayment of the payments they had
made on the basis of payment under a mistake as to the legal enforceability of the
Agreement: paragraphs 2, 6. In the alternative, they counterclaimed for lesser amounts as
damages pursuant to s 236 of the Australian Consumer Law: paragraph 22; and for
breach of warranties implied into the Agreement pursuant to the provisions of the
DBCA: paragraph 30. It is unnecessary to consider the counterclaims for damages
as they have no relevance to the issues on appeal.
[14] The appellant pleaded to the defence and amended counterclaim by a reply and
answer thereto5 filed on 3 February 2014 in which the paragraphs in the reply were
numbered 1 to 12 and those in the answer 1 to 20 respectively. Significantly, all of
the allegations in paragraph 2(c), including those in paragraphs in 2(c)(ix), (x) and
(xi), were admitted: paragraphs 2(b) and 4(b). There was a denial that the
Agreement was unenforceable on account of the matters alleged in paragraphs
2(c)(x) and (xi): paragraph 4(c). There followed in paragraph 4(d) a list of alleged
facts and circumstances which culminated in an allegation that, in any event, it
would be unconscionable for the respondents to rely upon the provisions in the
DBCA “to render the Agreement unenforceable”: paragraph 4(d)(viii). Paragraphs 10
and 11 of the reply put in issue the allegations in paragraphs 10 and 11 of the
defence on the basis of the preceding allegations in paragraph 4 of the appellants’ reply.
With regard to the answer, paragraphs 1 and 3(b) thereof denied that the Agreement was
unenforceable, placing reliance upon the matters pleaded in paragraph 4(d). Paragraph 4
of the answer put in issue the respondents’ restitutionary claim, relying in part upon
the same matters.
5 AB163-171.
-- 4 of 13 --
5
[15] It is convenient to mention at this point that the respondents’ amended application
sought the striking out of paragraphs 4(d), 10 and 11 in the reply and paragraphs 1,
3(b) and 4 of the answer to which reference has been made in the immediately
preceding paragraph. All of those six paragraphs were struck out by the order
which struck out the amended statement of claim.
[16] I now turn to 7A of the amended statement of claim. It contained the alternative
quantum meruit claim in the following terms:
“7A. Alternatively:
(a) the Plaintiff has performed the work the subject of
the invoices at the instruction and for the benefit of
the Defendants;
(b) the Defendants have accepted the benefit of that
work without payment of all of the Invoices and
have been unjustly enriched thereby;
(c) the Plaintiff is entitled to be paid a reasonable sum
for the work on the basis of quantum meruit;
(d) a reasonable sum for the work is the amount of the
invoices rendered by the Plaintiff to the Defendants,
being $2,121,234.00;
(e) to date, the Defendant have only paid the Plaintiff
the sum of $1,938,982.00;
(f) it would be unjust for the Defendants to retain the
benefit of the work without making payment of the
entire $2,121,234.00 to the Plaintiff;
(g) in the premises, the Defendants are liable to the
Plaintiff in the sum of $182,252.00 as quantum meruit.”6
[17] The respondents did not plead to the amended statement of claim prior to the hearing
of the application. As noted, however, by amendment of the application, that pleading
became the principal object for the strike out relief. At the hearing of the
application, the respondents’ challenge to it disputed that the appellant could seek
payment on a quantum meruit basis in the pending proceedings in the District Court.
The applicable legislation
[18] A number of the provisions of the DBCA were referred to in oral and written
submissions on appeal. They are:
“3 Purpose of Act
The purpose of this Act, in regulating domestic building
contracts, is—
(a) to achieve a reasonable balance between the interests of
building contractors and building owners; and
(b) to maintain appropriate standards of conduct in the
building industry.
…
6 AB180-181.
-- 5 of 13 --
6
30 Contracts must be signed
A regulated contract has effect only if it is signed by the
building contractor and building owner (or their authorised
agents).
…
55 Cost plus contracts
(1) A building contractor must not enter into a cost plus
contract that would be a regulated contract unless—
(a) the contract is included in a class of contracts
prescribed under a regulation; or
(b) the cost of a substantial part of the subject work can
not reasonably be calculated without some of the
work being carried out.
Maximum penalty—100 penalty units.
(2) A building contractor must not enter into a cost plus
contract that would be a regulated contract unless the
contract contains a fair and reasonable estimate by the
building contractor of the total amount the building
contractor is likely to receive under the contract.
Maximum penalty—100 penalty units.
(3) If a building contractor enters into a cost plus contract in
contravention of this section, the building contractor can
not enforce the contract against the building owner.
(4) However, the tribunal may, on an application made, as
provided under the QCAT Act, to the tribunal by the
building contractor, award the building contractor the
cost of providing the contracted services plus a
reasonable profit if the tribunal considers it would not
be unfair to the building owner to make the award.
…
84 Right of building contractor to recover amount for
variation
(1) This section applies if—
(a) the building contractor under a regulated contract
gives effect to a variation of the contract; and
(b) the variation consists of—
(i) an addition to the subject work; or
(ii) an omission from the subject work that results in
the building contractor incurring additional costs.
(2) If the variation was originally sought by the building
owner, the building contractor may recover an amount
for the variation—
-- 6 of 13 --
7
(a) only if the building contractor has complied with
sections 79, 80, 82 and 83; or
(b) only with the tribunal’s approval given on an
application made, as provided under the QCAT Act,
to the tribunal by the building contractor.
(3) If the variation is not a variation that was originally
sought by the building owner, the building contractor
may recover an amount for the variation—
(a) only if—
(i) the building contractor has complied with
sections 79, 80, 82 and 83; and
(ii) the ground of unforeseen circumstances
applies; or
(b) only with the tribunal’s approval given on an
application made, as provided under the QCAT Act,
to the tribunal by the building contractor.
(4) The tribunal may approve the recovery of an amount by
a building contractor for a variation only if the tribunal
is satisfied that—
(a) either of the following applies—
(i) there are exceptional circumstances to warrant
the conferring of an entitlement on the
building contractor for recovery of an amount
for the variation;
(ii) the building contractor would suffer
unreasonable hardship by the operation of
subsection (2)(a) or (3)(a); and
(b) it would not be unfair to the building owner for the
building contractor to recover an amount. …”
[19] Two of these provisions, ss 30 and 55, were relied upon by the respondents in their
defence. The latter was a focus for argument in the appeal.
[20] It may be noted that a number of other provisions and definitions in the DBCA were
referred to in paragraph 2(c) of the defence for the purpose of pleading that the
Agreement was a “regulated contract” as defined in s 8 thereof. In view of the admission
of paragraph 2(c)(ix), it is unnecessary to set out those provisions and definitions.
The reasons at first instance
[21] At first instance, the learned primary judge considered a range of arguments
addressed to him. An argument advanced by the appellant in order to avert the
operation of s 55 was that the claim for payment of the unpaid progress claims was
a claim in debt arising from a fully executed agreement, and not a claim to enforce
the Agreement. His Honour found it inappropriate to consider the argument on the
footing that the appellant had not pleaded that the Agreement had been fully executed.7
7 Reasons [15]-[20].
-- 7 of 13 --
8
[22] His Honour accepted an argument advanced by the respondents based on s 55(3)
DBCA that the appellant was not entitled to pursue recovery of the unpaid amount
in the proceeding on a quantum meruit basis as was pleaded in paragraph 7A.8
[23] Lastly, his Honour accepted an argument by the respondents that the contracting-out
provisions in s 93(2) DBCA precluded the appellant from invoking the doctrine of
estoppel against them in their reliance upon s 55(3), or otherwise.9
The grounds of appeal and orders sought on appeal
[24] The notice of appeal filed on 8 May 201410 set out four grounds of appeal. Ground (a)
challenged the conclusion on the debt argument and Ground (c) the conclusion on
the estoppel argument. Neither of those grounds was maintained in an amended
notice of appeal filed on 15 September 2014 for which leave was given at the
hearing of the appeal.
[25] The two other grounds which were maintained in the amended document, became
the sole grounds of appeal. They are:
“(b) The primary judge erred in holding that s 55(4) of (the
DBCA) prevented the appellant from maintaining a claim
for quantum meruit in the District Court proceeding.
(d) The primary judge erred in ordering indemnity costs against
the appellant.”
[26] In an apparent concession that the contractually-based claim is not maintainable in
the District Court proceeding, the orders on appeal sought by the appellant include a
variation to Order 1 made on 29 April 2014 so that it reads:
“Paragraphs 7, 8, 9 and 12 of the amended statement of claim and
paragraphs 4(d), 10 and 11 of the reply and 1, 3(b) and 4 of the answer to
the amended counterclaim be struck out.”
[27] Thus, the two issues on appeal concern the quantum meruit claim and costs,
including costs of the appeal.
Ground (b) – quantum meruit claim
[28] In Pavey & Matthews Pty Ltd v Paul,11 the High Court held that a right of a builder
to recover on a quantum meruit does not depend upon the existence of an implied
contract but on a claim to restitution independent of contract.12 For the builder to
have pursued a quantum meruit claim in that case was not to have sought to enforce
a building contract. That cause of action was therefore not prohibited by a New
South Wales legislative enactment which provided that a building contract was not
enforceable in circumstances that prevailed in that case.
[29] The addition of the quantum meruit claim to the pleading here is explained by the
principle affirmed in that decision; the admitted breach by the appellant of s 55(2);
and the provisions of s 55(3) which provide that where a cost plus contract is
entered into in breach of s 55(2), a building contractor may not enforce the contract
8 Reasons [21]-[27].
9 Reasons [28]-[37].
10 AB230-233.
11 (1987) 162 CLR 221; [1987] HCA 5.
12 Per Mason and Wilson JJ at 228; Deane J at 263.
-- 8 of 13 --
9
against the building owner. The respondents accept that were s 55(3) the only
relevant provision in the DBCA, the decision in Pavey would make it unarguable
that the section also precluded a claim in quantum meruit.13
[30] The parties join issue on whether, upon its proper construction, the DBCA prohibits
a building contractor who has breached s 55(2) from recovery from the building
owner on a quantum meruit. The respondents, who contend that it does, place
reliance on provisions in the statute beyond s 55(3) itself. Principally, they rely
upon s 55(4) and the purpose provision in s 3 which, they submit, clearly evince an
implied legislative intention to deprive such a building contractor of a claim in
quantum meruit. The appellant, on the other hand, relies upon the precise language
of s 55(3) and submits that the other provisions do not disclose such an intention.
[31] The issue has not been considered before by this Court. However, it had received
some attention in Gemini Nominees Pty Ltd v Queensland Property Partners Pty Ltd.14
In that case, Mullins J expressed the conclusion obiter that, as a matter of construction of
s 55 within the context of the DBCA, the legislature had restricted a builder who has
breached ss 55(1) or (2) to recovering costs of the work undertaken pursuant to the
contract to the extent provided in s 55(4). Her Honour added that it cannot be
concluded that, in addition to s 55(4), a builder who breached s 55 would be able to
make a claim based on quantum meruit.15 The learned primary judge considered
that he should adopt this conclusion, having first satisfied himself that it was not
patently erroneous.16 The conclusion was also referred to later by McGill DCJ in
Thompson Residential Pty Ltd v Tran & Anor17 who ventured the opinion that it was
“clearly correct”. That decision, however, concerned another provision of the
DBCA, s 84, and not s 55.
[32] A contrary conclusion was reached by Judge Anderson of the County Court of
Victoria in PACD Pty Ltd v Depas Pty Ltd.18 After a consideration of provision in
the Domestic Building Contracts Act 1995 (Vic) analogous to ss 55(2), (3) and (4),
his Honour, who apparently had not been informed of the conclusion expressed by
Mullins J, held that those provisions did not exclude a claim based on “unjust
enrichment”.19 There does not appear to be any other decision of an Australian
court directly upon the issue.
[33] The decision in Pavey itself illustrates that whether a given right of action has been
abrogated by statute is dependent upon the statutory language used. Further
illustrations of that are given by two decisions of this Court concerning the
differently-worded s 42(3) of the then-named Queensland Building Services Authority
Act 1991 (Qld). They are Marshall v Marshall20 and Sutton v Zullo Enterprises Pty
Ltd.21 As then enacted, s 42(3) stated that “a person who carries out work in
contravention of (s 42) is not entitled to any monetary or other consideration for
doing so”. That formulation was held to be sufficiently comprehensive to exclude
a restitutionary claim by a builder based on quantum meruit.
13 Tr1-28 L41.
14 [2008] 1 Qd R 139; [2007] QSC 20.
15 At [35].
16 Reasons [25].
17 [2014] QDC 156 at [17].
18 [2007] VCC 1683.
19 At [48].
20 [1999] 1 Qd R 173 per McPherson JA at 177.
21 [2000] 2 Qd R 196; [1998] QCA 417.
-- 9 of 13 --
10
[34] From this background of judicial decisions, I now turn to consider the issue in
dispute. The approach to resolution of it is informed by the presumption of
statutory interpretation against abrogation or curtailment of common law rights.
The presumption has been confirmed at the highest level of authority on many
occasions. It requires that a legislative intention to take away a common law right
be clearly expressed. The degree of clarity of expression of such an intention that is
required has been described in slightly differing ways by justices of the High Court.
In Sargood Brothers v The Commonwealth,22 O’Connor J said at 279 that “an Act
will never be construed as taking away an existing right unless its language is
reasonably capable of no other construction”. To similar effect, Gleeson CJ,
Gummow, Hayne, Heydon and Crennan JJ in Berowra Holdings Pty Ltd v Gordon23
restated the position thus:
“The approach of the courts has consistently been to require very
clear legislative intent before treating a statutory provision as taking
away common law rights of a plaintiff, where there is an alternative
construction available”.24
[35] The legislative intention to take away a common law right may be expressly stated
or it may arise by necessary implication.25 Here, an intention to abrogate the
restitutionary right to claim quantum meruit has not been expressly articulated. The
question is whether a clear legislative intention to that effect is necessarily implied
in the provisions of the DBCA. It is a question on which the Explanatory Memorandum
for the Domestic Building Contracts Bill 2000 provides no assistance.
[36] The respondents argue that such an intention can be discerned from s 55(4) and the
scheme of s 55. Section 55(4) empowers the Queensland Civil and Administrative
Tribunal (“QCAT”) on an application to it by the building contractor, to award the
cost of providing the contracted services if it considers that it would not be unfair to
the building owner to make such an award. The section begins with the words
“However, the tribunal may …”. The respondents submit that these words link
s 55(4) to the preceding s 55(3) and signal an intention that where s 55(3) applies,
the only remedy left to the building contractor is under s 55(4). Such a result, the
respondent submits, would harmonise with the sanction in s 55(3) for contravention
of s 55(1) or s 55(2), by providing some recourse for the building contractor. It
would also promote the purpose of the DBCA of achieving a reasonable balance
between the interests of building contractors and those of building owners: s 3(a).
[37] Furthermore, the respondents submit that it would be illogical for the legislature to
have intended that a contravening building contractor have a choice between
a quantum meruit claim and an award of the kind for which s 55(4) provides. Lastly, the
respondents point to those provisions of s 84 DBCA which permit recovery of an
amount for a variation where there has been non-compliance with the payment for
variation provisions. Under s 84(2)(b), the building contractor may recover an amount
only with the approval of QCAT, and not by a quantum meruit claim in a court. It
is unlikely, the respondents contend, that “inconsistent” approaches would have
been intended for cost plus contracts under s 55 and variations under that section.
22 (1910) 11 CLR 258; [1910] HCA 45.
23 [2006] HCA 32; (2006) 225 CLR 364 at [23].
24 See also per Gleeson CJ in Plaintiff S157/2002 v Commonwealth [2003] HCA 2; (2003) 211 CLR 476 at
[30] and Pearce and Geddes, Statutory Interpretation in Australia, 8th ed, para 5.35.
25 Melbourne Corporation v Barry (1922) 31 CLR 174 per Higgins J at 206.
-- 10 of 13 --
11
[38] In written and oral submissions, the appellant advanced arguments against the
respondents’ submissions. The nature and content of those arguments are reflected
in the discussion of the respondents’ submission which follow.
[39] It may be accepted that the introductory word “however” in s 55(4) does provide a
linkage of that section with s 55(3). In the present context, this word is used as
a conjunction. Its customary grammatical use as a conjunction is to signify a concession.
What follows it in s 55(4) is intended to be a concession upon the operation of s 55(3).
[40] It therefore falls to consider whether the language in which the concession is
expressed necessarily implies that the right to claim in quantum meruit is abrogated.
The respondents’ approach is to reason by inference that because s 55(4) is concerned
with a mode of recovering payment for building work and s 55(3) prevents
enforcement of the contract under which the work was done, then the legislature
must have intended that that be the only permissible avenue for the building contractor to
pursue payment. Whilst there is attraction in that line of reasoning, I am not
persuaded that it leads to the correct conclusion here.
[41] I say this for the following reasons. Section 55(4) does not confer an enforceable
right to payment of any amount on the building contractor. It does not create
a statutory right which might be regarded as compensating for an abrogation of
rights to payment on any other basis. What the section does is regulate a jurisdiction
given to QCAT to make an award in favour of a building contractor. An enforceable
right to payment would arise only upon exercise of that jurisdiction in a way
favourable to the building contractor.
[42] Further, the basis and nature of the award that QCAT may make is distinctly
different from an amount that a building contractor might recover on a quantum
meruit. Under s 55(4) what is awarded is the cost of providing the contracted
services plus a reasonable profit. By contrast, costs recoverable in a quantum
meruit claim are reasonable costs of providing the services. Moreover, exercise of
the jurisdiction under s 55(4) is conditioned upon QCAT considering that it would
not be unfair to the building owner to make the award. That significant condition
has no counterpart in recovery on a quantum meruit. These differences are
obstacles to a conception of what s 55(4) provides as having been intended to
displace comprehensively recovery on a quantum meruit claim.
[43] These considerations suggest a construction of s 55(4) as a provision intended to
regulate a jurisdiction conferred on QCAT and not one that, of its own or in
combination with other provisions in the section, is also intended to abrogate a right
to claim on a quantum meruit basis. This construction is one that is more than
respectably arguable. To my mind, it is the preferable construction. I would respectfully
agree with the observations of Judge Anderson in PACD with respect to analogous
provisions in s 13(3)(b) of the Victorian legislation, that it was likely that the
intended role of the provisions was to spell out the precise basis upon which the
Victorian Civil and Administrative Tribunal was to exercise the power given to it
“rather than suggesting that a court’s power to order restitution had been excluded”.26
[44] There is therefore an alternative construction of s 55 available which does not have
the consequence of abrogation of the right to recover in a quantum meruit claim.
The language of the section does not indicate in a very clear way an intention to
abrogate such a right, as the test in Berowa Holdings would require it do in order to
displace the alternative construction.
26 At [26].
-- 11 of 13 --
12
[45] Furthermore, a practical consideration which suggests that abrogation of a quantum
meruit claim was not intended can be seen in circumstances where the building
owner sues the building contractor in a court. Abrogation would have the consequence
that the building contractor could not counterclaim in the court proceeding for an
unpaid amount either under the terms of the contract or on a quantum meruit. The
building contractor would have to take steps to apply to the court for a transfer of
the claim to QCAT.27 The efficacy of that step for both parties would depend upon
the basis of the claims made against the building contractor. Any claim or part of
a claim which was not justiciable in QCAT could not be transferred and would
remain pending in the court. Such would be the case where, for example, the
respondent’s counterclaim is for damages under the Australian Consumer Law.
[46] I do not accept the respondents’ submission that the availability to the building
contractor of a restitutionary claim in quantum meruit would render s 55(4)
redundant or obsolete. As explained, the basis of award under the one is distinctly
different from that under the other. Whether one is more advantageous than the
other will depend upon the circumstances of the particular case. Nor do I see force
in the respondents’ submissions referenced to s 84. The DBCA was enacted after
the decision in Pavey, Marshall and Sutton were published. The formulations of
ss 55 and 84 were informed by those decisions. The choice of different
formulations with known different consequences is apt to suggest that the respective
provisions were intended to operate with different effect.
[47] For all of these reasons, I have concluded that this ground of appeal has been
established and that the appeal must be allowed.
Ground (d) – costs
[48] In light of the success of Ground (b), the indemnity costs orders made on 29 April
2014 must be set aside. The strike out application was warranted but was foiled
only by a very late amendment to the statement of claim. In those circumstances,
the appropriate order is that there be no order for costs on the application.
[49] As to the appeal, the appellant has succeeded on two grounds. It should have its
costs of the appeal on the standard basis except with respect to the two grounds of
appeal that it abandoned at the hearing of the appeal. The respondents should have
their costs of those two grounds paid by the appellant on the same basis.
Orders
[50] I would propose the following orders:
1. Appeal allowed.
2. Vary Order 1 made on 29 April 2014 to read:
“Paragraph 7, 8, 9 and 12 of the amended statement of claim
and paragraphs 4(d), 10 and 11 of the reply and paragraphs
1, 3(b) and 4 of the answer to the amended counterclaim be
struck out.”
3. Set aside Order 2 made on 29 April 2014 and substitute the
following order:
“There be no order as to costs.”
4. Order that the respondents pay the appellant’s costs of the appeal on
the standard basis except those costs with respect to Grounds 2(a)
and (c) in the notice of appeal filed on 8 May 2014.
27 Pursuant to s 53(1) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).
-- 12 of 13 --
13
5. Order that the appellant pay the respondents’ costs of Grounds 2(a)
and (c) in the said notice of appeal on the standard basis.
[51] MORRISON JA: I have read the reasons of Gotterson JA and agree with those
reasons and the orders his Honour proposes.
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2014/318