Bank of Western Australia v Liu & anor [2014] QSC 318
SUPREME COURT OF QUEENSLAND
CITATION: Bank of Western Australia v Liu & anor [2014] QSC 318
PARTIES: BANK OF WESTERN AUSTRALIA
(applicant)
v
BIYI LIU
(first respondent)
and
LEIMING QU
(second respondent)
FILE NO/S: 945 of 2012
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court of Queensland
DELIVERED ON: 7 November 2014 (ex tempore)
DELIVERED AT: Brisbane
HEARING DATE: 28 October 2014
JUDGE: Carmody CJ
ORDERS: 1. Leave to amend initiating documents is granted in
terms of paragraph 1 of the application filed 12
September 2014;
2. The application for summary judgment is granted;
3. The respondents to pay the applicant’s costs as
agreed, or if not agreed by 15 December 2014, to be
assessed on the standard basis;
4. Order as per draft as amended.
CATCHWORDS: PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PROCEDURE UNDER UNIFORM
CIVIL PROCEDURE RULES – SUMMARY JUDGMENT
– where the applicant contends there are no facts to be
resolved at trial – where the respondents deny liability to
vacate mortgaged residential property for which the
applicant claims recovery – where the respondents deny
liability to repay loan on property based on misleading
conduct by the bank – whether the respondent has any real
prospects of successfully defending the claim
PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PROCEDURE UNDER UNIFORM
CIVIL PROCEDURE RULES – PLEADINGS – DEFENCE
AND COUNTERCLAIM – where respondents allege that
the applicant impliedly warranted the valuation of a
-- 1 of 6 --
2
JUDGMENT
mortgage property – where respondents allege that the
applicant made representations about the ability to extend
the loan term and subsequently departed from those
representations – where applicants claim estoppel and
consequent entitlement to restitution or, in the alternative,
federal Consumer Law contraventions – whether material
disclosed in counterclaim evidences any real prospect of
success
PROCEDURE – COSTS – DEPARTING FROM THE
GENERAL RULE – ORDER FOR COSTS ON AN
INDEMNITY BASIS – where contractual clause entitles
respondents to pay all costs related to recovery – whether
clause entitles applicant to claim or recover costs – whether
clause is sufficiently clear to override the court’s discretion
to determine whether indemnity costs are appropriate
Chambers v Bryce [2014] QSC 52, cited
Willmott v McLeay [2013] QCA 84, distinguished
COUNSEL: DA Savage QC with PA Ahern for the applicant.
SC Fisher for the second respondent.
SOLICITORS: Gadens for the applicants.
Ebenezer Legal for the second respondent.
THE CHIEF JUSTICE: The parties are a lending bank and co-borrowers in
default. The bank applies for (a) leave to amend the initiating documents in terms of
the exhibited draft, (b) summary judgment for the claimed relief, (c) dismissal of the
counter-claim, and (d) costs calculated on a full indemnity basis under the facility or, 5
alternatively, on a standard assessment under the rules.
The bank proposes to substitute a claim for interest fees and charges at the rates
agreed in the written loan document, to take advantage of the decision of Chambers v
Bryce [2014] QSC 52. The change does not prejudice the respondents and is not 10
opposed. Leave will be granted in terms of paragraph 1 of the application.
The bank also claims recovery of a mortgaged residential property at Park Ridge and
the debit balance of a loan account in the amount of $3,246,909.08, comprising
$2,350 still owing for the principal under a fixed term commercial advance loan and 15
$883,924.84 for unpaid interest fees and charges debited to an overdraft account set
up to meet monthly interest repayments and accrued but not debited interest fees and
charges.
The respondents admit to accepting and not repaying the loan on maturity or since, 20
but deny liability to vacate the property or remedy the default based on alleged
misleading conduct of the bank. The bank, by contrast, contends that the asserted
grounds of defence have no real prospects of success and a trial of the claim is not
needed because there is no factual or legal issue requiring investigation and
resolution by the Court. The focus, therefore, is on whether the respondents have put 25
-- 2 of 6 --
3
JUDGMENT
on enough material to persuade me that it would be unjust not to allow their defence
and/or counter-claim to proceed.
The Court must, of course, be careful to avoid dismissing viable defences and valid
claims on a summary basis, except in clear cases. On the other hand, justice should 5
not be delayed or defeated by spurious or false controversies being allowed to
continue when they should be halted. The latest version of the defendant’s pleading,
filed on 24 October 2012, asserts that by obtaining a Herron Todd White HTW
valuation of the Park Ridge property at $3.8 million “on or about 14 July 2007” and
later providing it to the respondents with an offer to lend $2.6 million, the bank at 10
least impliedly warranted the 2007 valuation and its methodology.
The respondents allege they were induced to accept the bank’s loan offer and
mortgage conditions because of the valuation representations and an assurance that
the facility term would be extended beyond the nominal expiry date of 21 December 15
2010 as long as they kept the interest repayments up to date. The respondents
complained the bank later “departed” from the valuation and extension
representations to their likely “detriment ... leading to an estoppel and claim
grounded in restitution” and, in the alternative, amount to federal consumer law
contraventions. 20
At issue, therefore, is whether either the valuation or extension representations are
disputed facts, the resolution of which the respective rights of the parties depend and
which, assuming they exist, are capable of establishing a defence or right to relief.
25
The context
The first respondent contracted to buy the 9.9 hectare property at Park Ridge on 6
June 2007 for $3.8 million. On 10 July 2007, after other banks had refused finance
and the settlement date extended for lack of funds, CBRE valued the property at $1.6 30
million for the ANZ bank. On 13 July 2007, the applicant bank emailed an
indicative funding proposal subject to “satisfactory valuation” of a $2.3 million
interest-only cash advance for three years with monthly interest being serviced via
direct debit arrangements on a nominated account, secured by a mortgage and a
$250,000 term deposit to guarantee interest servicing. On 14 July 2014, HTW 35
assessed the current market value of the property as a potential redevelopment site on
a “as is” basis at $3.8 million. Page 1 of the valuation document expressly states that
the report is not to be relied on or used other than by the bank for “first mortgage
security” purposes and “only suitable for an approved lending institution”.
40
Even in such a case, the valuer explicitly disclaimed liability or responsibility for
reliance on the valuation without its prior written authorisation. Section 2.1 of the
appraisal identifies the market risks, including the dependency on demand for
residential “en globo” parcels on the underlying redevelopment potential and zoning
requirements. Section 2.2 refers to the contract of sale over the property for $3.8 45
million, which, according to 8.4, was a relevant valuation factor. This was the first
contract the first defendant signed as a buyer on 6 June 2007. Other comparable
sales are noted in the schedule at 8.5, rated at between $400,000 and $450,000 per
hectare.
50
-- 3 of 6 --
4
JUDGMENT
A revised conditional facility proposal in the amount of $2.6 million was emailed by
the bank to the respondent on 17 July 2007. An approval in those “broad terms” was
confirmed on 19 July 2007. The respondent signed the contract to buy the property
unconditionally 23 July 2007. The bank forwarded a copy of the valuation to the
defendants the next day. Thus, the respondents were committed to the contract 5
before receiving the disputed valuation.
The bank’s formal letter of offer received on 28 August 2007 was for a commercial,
rather than a cash advance, with an expiry of three years from initial drawdown. The
defendants were told that the initial term of the loan would be hard to change so that 10
it would not expire after three years, but that if the repayment schedule was complied
with, the bank “would extend the loan at the borrower’s request”. The facility
offered was accepted on 3 September 2007 despite discrepancies with the alleged
extension representation. The contract settled on 8 October 2007. Under the terms
of the facility, the bank required an updated valuation in September 2010. It 15
suggested that the valuation be done on the same basis as the 2007 HTW valuation,
but the respondents were only willing to pay for a “land-only” appraisal. As the
bank predicted, the market value on the land-only basis came in at a much lower
figure than the alternative potential development basis, that is, at $1.65 million.
20
The disparity between the new market valuation and the HTW assessment in 2007
meant that the loan to value ratio (LVR), which was required to be no more than 70
per cent, grew to over 200 per cent. The bank refused to look at an extension of the
loan term with the LVR at that rate and suggested that the respondents either pay off
principal or have the property re-valued on the development basis. Any extension 25
would only be allowed if the LVR was at between 50 and 55 per cent. To achieve
this, the respondents would have had to reduce the loan by between $510,000 and
$700,000. The bank advised the defendants that if a new appraisal was proposed to
try and achieve a much higher valuation, they would have to show an ability to
service the facility interest and possible principal reductions after the expiry on 22 30
November 2010 solely from income from Australian sources.
The respondents contend that exhibit AL25 evidences the bank’s agreement to
extend, despite the LVR, to November 2012. However, it is clear that the bank’s
concession in that email was based on the mistaken assumption that the facility was 35
initially drawn in 2009 when, in fact, it was drawn in 2007. The $250,000 set-off
deposit was transferred to the loan account on 25 February 2011 and the facility was
extended to 30 June 2011, provided that a further $250,000 reduction in principal
was made by 31 March 2011.
40
Refinancing attempts by the respondents failed. The bank terminated the facility on
3 August 2011.
The respondents argue that the HTW valuations in 2007 and 2010 could not both be
right and suggest at paragraph 62 of their outline that the reason for the disparity was 45
the bank’s use of “special criteria” to mislead them into believing the 2007 $3.8
million valuation was accurate so that they would be induced to accept the terms of
the offer letter on 3 September 2007.
-- 4 of 6 --
5
JUDGMENT
The key defence claim – that by obtaining and providing the 2007 valuation to the
respondents, the bank represented that “it accepted the valuation methodology” – is
not only untenable, but it provides no defence on the respondents’ own case, taken at
its highest. The 2007 valuation was independent of the bank for its exclusive use,
qualified and, most importantly, there is no evidence that, whether accepted by the 5
bank or not, the valuation methodology was flawed in any material way or that the
property was not worth $3.8 million on a redevelopment basis.
Even if the methodology was flawed or the assessment erroneous, the respondents
have not put on enough material to demonstrate on a prima facie basis the assertion 10
that they entered into the contract to buy the Park Ridge Property at $3.8 million on
an unconditional basis “in reliance on the 2007 valuation”. The known facts point
strongly to the contrary. Not only were the terms of the valuation so heavily
qualified that no reasonable person would have been induced or even encouraged to
rely on it for the purposes of deciding whether or not to contract, but there is no 15
evidence-based reason to believe that the respondents themselves were misled, either
about the value of the property or the valuation methodology at the time of
contracting. The first respondent had previous agreed to pay the same price for the
same property before the HTW valuation was even sought. The second respondent
was, obviously, a nominee party to the transaction. Moreover, the contract was 20
unconditional before the respondents even knew what the HTW valuation was. They
may have read too much into the bank’s willingness to lend but the risk was one they
voluntarily and independently assumed. Having misgivings or being reticent about
entering into the contract is not sufficient to lay the blame at the feet of the bank.
There is no substance in the so-called valuation representation ground of defence. 25
Nor, again, assuming it was made, does the extension representation assist the
respondents. At best, the respondents’ case is that the bank represented that despite
the nominal expiry date of the facility being 31 December 2010, it would be
extended, as long as the repayments were up to date. Ironically, the respondents’
asserted case in these proceedings was that the facility was extended to 2012 in 30
reliance on exhibit AL25. In any case, the facility was extended by the bank to 30
June 2011.
The respondents’ material does not say how long the extension they were induced to
believe they were given by the bank after the maturity date of 31 December 2010 35
was intended to be. The respondents’ material is not sufficiently certain as to the
period of extension or its terms to provide them with a viable defence to the bank’s
claim. At any rate, it is now four years since the facility expired and the debt has not
been serviced beyond the $250,000 off-set.
40
The respondents have no real prospect of successfully defending on the pleaded basis
that either or both the valuation and extension representations were acted on or, in
the case of the extension valuation, was certain enough or that, in either case, were
departed from by the bank. A full hearing is not needed because the rights of the
parties do not depend on the resolution of disputed facts. Even if the facts were 45
resolved in the respondents’ favour on the material put on, the Defences would fail
because the valuation representation clearly did not induce the contract as alleged
and there is no reason for thinking that the property was not worth in the order of
$3.8 million in 2007 or, if valued on the same basis in 2010, was worth any more or
-- 5 of 6 --
6
JUDGMENT
less. The alleged extension representation is far too uncertain to support the
allegation that it was departed from by the bank.
The debt is proven, no ground of defence with any reasonable prospect of success
exists and no contested facts need investigation at a trial. The application for 5
summary judgment is granted.
The successful applicant seeks costs on the indemnity basis in reliance on cl 12.1(b)
of the facility – which, in terms, records the respondents’ agreement to pay all the
bank’s recovery costs or costs in connection with the enforcement of its rights in the 10
event of default. The question is whether by that clause the parties have contracted
“plainly and unambiguously” for the payment of costs on an indemnity basis. In
Willmott v McLeay [2013] QCA 84, the Queensland Court of Appeal did not think a
clause in the following terms was sufficiently plain and unequivocal to establish a
clear right under the contract to indemnity costs: 15
The seller may claim damages for any loss it suffers as a result of the buyer’s
default, including its legal costs on an indemnity basis and the cost of any work
or expenditure under (other clauses).
20
The difference between that clause and the one in question here is that the former
referred to what the seller may claim and on what basis, whereas the latter
specifically directs its attention to what is payable by the respondent.
In the end, an order for costs calls for an exercise of the Court’s discretion, even 25
when there is a contractual right to indemnity costs. I think this is a borderline case
and my discretion is informed by the contractual provision. I think the provision is
stronger than the one considered in Willmott v McLeay but, ultimately, just falls short
of being strong enough to plainly and unambiguously constitute a clear contractual
right to recover as opposed to claim indemnity costs so as to warrant the exercise of 30
the discretion in favour of granting costs on an indemnity basis. Accordingly,
paragraph 4 of the order will be amended by deleting the word “indemnity” and
adding the word “standard”. After “12 September 2014” the balance of the term is
deleted and replaced with “as agreed, or if not agreed by 15 December 2014, to be
assessed on the standard basis.” 35
Order as per draft, signed and amended by me.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2014/318