Black Diamond Group Pty Ltd v Manor of Maluka Pty Ltd & Anor [2014] QSC 219 [2015] 1 Qd R 180
SUPREME COURT OF QUEENSLAND
CITATION: Black Diamond Group Pty Ltd v Manor of Maluka Pty Ltd &
Anor [2014] QSC 219
PARTIES: BLACK DIAMOND GROUP PTY LTD
ACN 161 737 300
(plaintiff)
and
MANOR OF MALUKA PTY LTD (in liquidation)
ACN 153 962 906
(first defendant)
and
GO COUNTRY GROUP PTY LTD
ACN 147 698 342
(second defendant)
FILE NO: BS12206/13
DIVISION: Trial
PROCEEDING: Trial
DELIVERED ON: 8 September 2014
DELIVERED AT: Brisbane
HEARING DATE: 25 and 26 August 2014
JUDGE: Jackson J
ORDERS: The order of the Court is that:
1 The plaintiff’s claim for damages against the
second defendant is dismissed.
2 The second defendant pay the plaintiff’s costs
of the proceeding up to and including 25
August 2014.
CATCHWORDS: TORTS – TROVER AND DETINUE – POSSESSION OR
RIGHT TO POSSESSION – ACTUAL POSSESSION –
where the plaintiff sought damages for detinue against the
second defendant – where the first defendant had hired
demountable buildings from the plaintiff – where the second
defendant was the owner of the land – where the first
defendant occupied the land under an agreement with the
second defendant – where the plaintiff made a demand for
return of the chattels from the second defendant – whether the
second defendant had possession of the demountable
buildings during the term of the agreement with the first
defendant
TORTS – TROVER AND DETINUE – REMEDIES –
-- 1 of 12 --
2
ACTION OF DETINUE – where the plaintiff sought
damages for detinue against the second defendant pursuant to
the principles in Strand Electric – where the plaintiff’s
demountable buildings had remained on the second
defendant’s land but had not been used since the termination
of the second defendant’s lease with the first defendant –
whether the second defendant had “used” the buildings
Bunnings Group Ltd v Chep Australia Ltd (2011) 82 NSWLR
420, applied
Butler v Egg & Egg Pulp Marketing Board (1966) 114 CLR
185, considered
Farah Constructions Pty Ltd & ors v Say-Dee Pty Ltd (2007)
230 CLR 89, applied
Gaba Formwork Contractors Pty Ltd v Turner (1991) 32
NSWLR 175, referred to
Radaich v Smith (1959) 101 CLR 209, cited
Rapid Metal Developments (Australia) Pty Ltd v Rildean Pty
Ltd [2010] NSWSC 7, referred to
Reynolds v Aluma-Lite Products Pty Ltd [2009] QSC 379,
referred to
Sadcas Pty Ltd v Business Professional Finance Pty Ltd
[2011] NSWCA 267, referred to
Strand Electric and Engineering Co Ltd v Brisford
Entertainments Ltd (1952) 2 QB 246, considered
Thomas v APL Co Pte [2013] FCA 911, referred to
Western Australia v Ward (2002) 213 CLR 1, cited
COUNSEL: C Johnstone for the plaintiff
A Ivantsoff (solicitor) for the first defendant
NM Cooke for the second defendant
SOLICITORS: Hazan Hollander for the plaintiff
Shine Lawyers for the first defendant
Cranston McEachern for the second defendant
[1] Jackson J: On 25 August 2014, a consent judgment was entered as between the
plaintiff and the first defendant on the plaintiff’s claim. On the same day, a consent
order was entered as between the plaintiff and the second defendant on part of the
plaintiff’s claim, leaving a claim for damages for detention for the tort of detinue to
be determined. These reasons deal with that claim. It was pleaded in the alternative
as a claim for damages for conversion but the plaintiff pressed only the claim for
damages for detinue in its closing address.
The parties
[2] Black Diamond Group Pty Ltd, the plaintiff, carries on business hiring demountable
accommodation buildings. A typical application is for a camp to accommodate
workers employed in mining operations. Until some time this year, Manor of
Maluka Pty Ltd (in liquidation), the first defendant, carried on business providing
accommodation services at a site which is described as the Banana Accommodation
Village or “the Banana Camp”, near Banana, in Central Queensland. For that
-- 2 of 12 --
3
purpose, it hired 21 buildings from a company. That company later assigned its
property in the buildings and the benefit of the contract to the plaintiff.
[3] An associate company of the first defendant, Go Country Catering Pty Ltd, provided
catering services at the Banana Camp. The first defendant’s major customer was
known as BAJV. The sole director and shareholder of the first defendant and Go
Country Catering Pty Ltd was Robert Johnston.
[4] Go Country Group Pty Ltd, the second defendant, was and is the proprietor of the
land comprising the Banana Camp. Nicole Newman was and is the sole director
and shareholder of the second defendant. She was and is the de facto partner of
Robert Johnston. The second defendant purchased the land with the purpose of the
first defendant developing and operating the Banana Camp on it.
[5] Ms Newman said an agreement was made between her, for the second defendant,
and Mr Johnston, for the first defendant that the first defendant would occupy or
lease the land from the second defendant for $1,000 per month rent, and that at the
end of the agreement the improvements were to remain with the second defendant
as proprietor of the land.
[6] As it turned out, the business venture of the Banana Camp was not successful.
Shortly before Christmas 2013, BAJV terminated its contracts with the first
defendant and Go Country Catering Pty Ltd. Thereafter, the camp was not used to
provide accommodation, with two minor exceptions. The plaintiff’s
accommodation units remained unused in those instances. For a time, the first
defendant sought to interest other customers for the services, including
accommodation services, that could be supplied by it and Go Country Catering Pty
Ltd. The attempts were not successful. Mr Johnston had carriage of any
negotiations.
[7] Ms Newman worked for the first defendant in providing office administrative
services throughout these events. She was aware of how matters were developing or
progressing from time to time.
[8] From a time in 2012 which it is now unnecessary to identify, the first defendant fell
into arrears in the payment of its suppliers’ debts. That included the monthly
instalments of hire payable for the plaintiff’s buildings.
Detention of the plaintiff’s buildings
[9] On 9 December 2013, by letter from the plaintiff’s solicitors to the second
defendant by Ms Newman and its solicitors, the plaintiff intimated that it intended
to recover possession the buildings. The letter sought confirmation from the second
defendant that it would not take any steps to impede the plaintiff’s exercise of the
asserted right to recover the buildings from the land.
[10] On 12 December 2013, the second defendant’s solicitors responded that they held
instructions to accept service of any proceedings and that the second defendant
would strenuously defend any proceedings. The implied statement was that the
second defendant denied the plaintiff’s right to recover the buildings from the land.
[11] On 19 December 2013, the plaintiff started this proceeding by originating
application claiming an order against the second defendant that it deliver up the
-- 3 of 12 --
4
buildings. This was later amended to include an order requiring the second
defendant to compensate the plaintiff by way of damages in the amount of $525,987
(later abandoned) or $58,443 per month. The application was served on the second
defendant’s solicitors on that day.
[12] On 17 January 2014, the second defendant’s solicitors wrote to the plaintiff’s
solicitors. The letter alleged that the buildings were fixtures attached to the second
defendant’s land but, somewhat inconsistently, also stated that the second defendant
objected to the plaintiff coming onto the second defendant’s land without
appropriate insurance cover and a relevant net worth of at least $200,000, against
the risk of damage to the second defendant’s land caused by any removal or
recovery.
[13] On 7 February 2014, the plaintiff’s solicitors again wrote to the second defendant by
Ms Newman and the second defendant’s solicitors, making formal demand for the
second defendant to give up possession of the plaintiff’s buildings and to take all
necessary steps to make the buildings available for collection.
[14] On 7 February 2014, the second defendant’s solicitors responded to the plaintiff’s
solicitors saying that: “To remove any doubt our client objects to the removal of the
buildings and will deem any access to our client’s land by your client or any agent
representative or otherwise on its behalf to be a trespass and will vigorously defend
its rights in this regard.” That was a clear denial of the plaintiff’s claim to return of
the buildings.
[15] On 13 June 2014, the second defendant terminated the agreement to occupy or lease
between the second defendant and the first defendant.
[16] On or about 26 June 2014, the first defendant went into liquidation.
[17] By the consent order made on 25 August 2014, it was ordered that the second
defendant return the buildings to the plaintiff. That order was made upon an
exchange of undertakings given to the Court by the parties. The plaintiff undertook
to hold appropriate insurance. The second defendant undertook to grant access to
the land to enable the buildings to be removed and neither to occupy nor otherwise
deal with the buildings except for the purpose of disconnecting attachments.
[18] By that order, the second defendant accepts that from 25 August 2014 it detained
the plaintiff’s buildings. But it contends that at no time prior to that date did the
plaintiff have a cause of action against it in detinue which supports an order for
damages for detention.
Claim for damages for detention
[19] The remaining claim of the plaintiff against the second defendant for damages for
detention is calculated from either 12 December 2013 or from 7 February 2014.
The damages are claimed at the rate of $58,443 per month representing the hire rate
for the buildings agreed between the plaintiff’s assignor and the first defendant
under the contract made between them. An alternative rate is claimed, of $35,700
per month, being the monthly hire rate for the same number of similar buildings as
agreed between the plaintiff and a number of other customers who hired similar
buildings from the plaintiff in November and December 2013.
-- 4 of 12 --
5
[20] The plaintiff does not claim the amount represented by those periods or amounts as
compensatory damages in accordance with the general principles governing the
assessment of damages in tort. Instead, the plaintiff relies upon a particular rule of
law for the assessment of damages for the tort of detinue, where the plaintiff carries
on business of hiring the chattels in question for reward and the defendant makes
use of them, that results in the plaintiff being entitled to its usual rate of hire for the
chattels in question.
[21] In accordance with the manner in which the plaintiff pleaded and argued its case,
there are three relevant issues to determine. First, from what date did the second
defendant wrongfully detain the plaintiff’s buildings as the starting point for the
assessment of damages for detention? Secondly, has the second defendant made use
of the plaintiff’s buildings within the meaning of the principles which govern the
availability of such a claim for damages? Thirdly, what is the relevant rate to
apply?
Bunnings v CHEP – a concession
[22] Before proceeding to the issues it is appropriate to record the concession by the
second defendant that the plaintiff may be entitled to damages representing its usual
rate of hire without regard to whether that would be its loss applying the
compensatory measure of damages.
[23] Specifically, the second defendant does not submit that the plaintiff’s damages, if
any, fall to be discounted if the plaintiff would not have been able to re-hire the
buildings had they been returned to the plaintiff at the time when any detention by
the second defendant commenced.
[24] In principle, this approach treats the second defendant as a quasi-hirer for the period
of the detention, whether or not the plaintiff’s loss would have been as much as that,
if the chattels had been returned. This measure of damages for conversion or
detinue, where the plaintiff is in the business of hiring the chattels in question, and
the defendant makes use of them, is associated with the decision of the Court of
Appeal of England and Wales in Strand Electric and Engineering Co Ltd v Brisford
Entertainments Ltd.1 In that case, the primary Judge discounted the plaintiff’s claim
for damages for detinue by making an allowance for the prospect that the plaintiff
may not have been able to re-hire the detained chattels for the period of the
detention or for the amount of its usual hire rate. The Court of Appeal set aside the
judgment and increased the damages to the amount of the plaintiff’s usual hire rate
for the chattels for the period of the detention.
[25] Such an approach is arguably inconsistent with the decision of the High Court of
Australia in Butler v Egg and Egg Pulp Marketing Board2 that damages in tort,
including the tort of conversion, are compensatory, so that a plaintiff may not
recover more than the “sum of money [that] would be required to place it in the
same position as it would have been in if the appellants had [not converted the
chattels].”3
1 (1952) 2 QB 246.
2 (1966) 114 CLR 185.
3 (1966) 114 CLR 185, 191.
-- 5 of 12 --
6
[26] However, in Bunnings Group Ltd v Chep Australia Ltd,4 the Court of Appeal of
New South Wales followed and applied Strand Electric as part of the common law
of Australia. The reasons for judgment in Bunnings refer to Butler. I am bound to
follow Bunnings unless it is “plainly wrong”, in accordance with the principle of
precedent stated by the High Court in Farah Constructions Pty Ltd & ors v Say-Dee
Pty Ltd.5
[27] Accordingly, the second defendant conceded that I should apply Strand Electric, as
explained in Bunnings, to which I will return.
Date of detention
[28] The cause of action in detinue is complete when a person entitled to possession of
chattels makes a demand on a possessor and the possessor refuses to return them.
[29] The second defendant submits that it did not refuse to return the plaintiff’s buildings
at any time before the order made for their return on 25 August 2014. It is
necessary to consider the relevant dates contended for by the plaintiff successively.
[30] If the second defendant had a sufficient possession of the buildings from 9
December 2013 onwards, the question becomes whether the plaintiff’s demand was
adequate and the second defendant’s response sufficient to constitute a refusal for
the purposes of the tort of detinue.
[31] In my view, there might have been a question whether the plaintiff’s solicitor’s
letter dated 9 December 2013 was unequivocal enough to constitute a demand.
There are cases where a defendant has been found not to have refused, because the
demand was found to be excessive6 or too vague. However, it would be unrealistic
to find that the demand, on the facts of this case, was inadequate when the response
it provoked from the second defendant’s solicitors was to inform the plaintiff’s
solicitors that they had instructions to accept service of any proceeding to recover
possession. The plaintiff’s solicitor’s letter which provoked that response had stated
that the plaintiff was planning to recover the buildings. In my view, the demand
was enough to engage the second defendant’s response as a refusal to return the
chattels, on any basis.7
[32] Further, the cases recognise that in some circumstances a defendant’s failure to
respond to a demand may not constitute a sufficient refusal and that a defendant
may not have refused sufficiently where the purpose of refusal is to reasonably
investigate the plaintiff’s right to possession before responding further. But this
case does not fit either of those characterisations. The second defendant’s response
was an unequivocal statement that it would accept service by its solicitors of any
proceeding for an order for return of the buildings.
[33] Second, the plaintiff’s solicitor’s letter to the second defendant’s solicitors dated 7
February 2014 made a further demand for the return of the buildings. This demand
provoked a response where the second defendant refused to return the buildings and
4 (2011) 82 NSWLR 420.
5 (2007) 230 CLR 89, 151 [135].
6 For example, Capital Finance Co Ltd v Bray [1964] 1 All ER 603, 606-607.
7 Compare, as to conversion by detention, Flowfill Packaging Machines Pty Ltd v Fytore Pty Ltd
(unreported, New South Wales Supreme Court, Young J, 1901/93), 11.
-- 6 of 12 --
7
warned the plaintiff that any access to the land would be deemed a trespass for
which the second defendant would vigorously defend its rights. Except that it was
made after the proceeding was started, this was plainly a sufficient demand and
refusal as a matter of fact.
[34] It is said in some cases that a demand in detinue must be made before the
proceeding is started. At common law so it had to be. However, in this Court,
Uniform Civil Procedure Rules 1999 (Qld) (“UCPR”) r 375(2) permits the joinder
of a cause of action by amendment that accrues after the date when a proceeding is
started. The proceeding in the present case started on 19 December 2013. It was
started by originating application. The statement of claim was filed and served on
14 February 2014. The statement of claim alleges the facts of the 7 February 2014
demand and following refusal. If the 9 December 2013 demand and refusal were
not enough to constitute a wrongful detention, in my view, the 7 February 2014
demand and following refusal were enough to do so.
[35] However, another consideration is that the second defendant alleges that there was
an agreement to occupy or lease the land on which the buildings were located by the
second defendant to the first defendant from before the time of the plaintiff’s first
alleged demand on 9 December 2013 until 13 June 2014. The question that fact
might raise is whether, because the second defendant was not in possession of the
land or the buildings, any relevant refusal by it is sufficient for the tort of detinue.
[36] The alleged agreement to occupy or lease is an oral agreement made in July 2012
between the second defendant by Ms Newman and the first defendant by Mr
Johnston. The subject was the whole of the land (including the Banana camp) for a
term of five years for a rent of $12,000 per annum payable by the amount of $1,000
per month. The second defendant alleges that a term was that on termination of the
agreement to occupy or lease the second defendant would be the owner of the
improvements to be made by the first defendant during the term of the lease.
[37] The first defendant went into occupation or possession following the alleged
agreement to occupy or lease. It effected improvements including the installation of
the plaintiff’s buildings. Ms Newman said that about $37,000 was paid by the first
defendant to the second defendant by way of rent.
[38] At law, in this State, a lease of land for a term in excess of three years must be made
in writing.8 However, in equity, an agreement for lease followed by entry into
possession and the payment of rent constitutes an equitable lease. And at common
law, as altered by s 129(1) of the Property Law Act 1974 (Qld), those facts create a
tenancy terminable by a month’s notice.9 The lack of a legal lease does not defeat
the conclusion that there was a tenancy or that the first defendant may have been in
possession of the land between 9 December 2013 and 13 June 2014. In that case,
the second defendant will have been the landlord and held the reversion upon the
tenancy, but will not have been in possession of the land at law. Possession of the
tenant is a necessary incident of a tenancy.
[39] The parties did not focus upon or make specific submissions directed to whether the
agreement was an agreement for lease as opposed to an agreement for occupation
8 Property Law Act 1974 (Qld), s 12.
9 Chan v Cresdon Pty Ltd (1989) 168 CLR 242, 248-258.
-- 7 of 12 --
8
not constituting possession but amounting only to a licence. The language of the
evidence given by Ms Newman about the agreement suggested lease not licence.
However, the difference between lease and licence is not always easy to tell.
Notwithstanding that his Honour was in dissent, the penetrating analysis of McHugh
J in Western Australia v Ward10 shows why, as does the recognition by the High
Court in Radaich v Smith11 that the label chosen by the parties does not foreclose
the answer to the question in law. In particular, part of the discussion in McHugh J’s
reasons in Ward12 shows the difficulties that can attend distinguishing between
possession (lease or tenancy) and occupation (licence).
[40] If the true character of the relationship between the first defendant and the second
defendant is that the first defendant had possession of the land under a tenancy, does
that affect the plaintiff’s claim against the second defendant in detinue?
[41] From first principles, the tort of detinue is constituted by a defendant’s wrongful
withholding, that is detention, of chattels to which the plaintiff has an immediate
right to possession.13 It makes little sense that a defendant who does not have
possession of the relevant chattels and has never had possession might commit the
tort of detinue by denying the plaintiff’s right to possession. The case law
recognises that a defendant who was in possession but who has lost that possession
may still be liable to the plaintiff in detinue in some circumstances. But I am not
aware of a case where a defendant who has not had possession at any time before
the plaintiff’s demand for return has been held to have wrongfully detained a
plaintiff’s chattels. The Laws of Australia14 states:
“There are three substantive characteristics of detinue:
(1) The plaintiff must make a demand for the chattel whose possession
the plaintiff is entitled to at the time of making the demand.
(2) The defendant must have refused that demand.
(3) Where the chattel is in the defendant's possession, the refusal to
return the chattel must be unreasonable; where it is not in the
defendant's possession, the defendant must have wrongfully parted
with possession.” (footnotes omitted)
[42] Pollock and Wright, in An Essay on Possession in the Common Law,15 say that
“[p]ossession is presumed from detention”,16 and “[p]ossession is always single and
exclusive.”17
[43] In the present case, if the land was held by the first defendant as the second
defendant’s tenant, by definition the first defendant had the right to (exclusive)18
possession of it. The plaintiff’s buildings were in the possession of the first
defendant from the plaintiff as bailee from a bailor under the hire agreement and
10 (2002) 213 CLR 1, 215-231 [478]-[530].
11 (1959) 101 CLR 209.
12 Ibid, 228-229 [518]-[521].
13 Ming Kuei Property Investments Pty Ltd v Hampson [1995] 2 Qd R 251, 256.
14 The Laws of Australia, Ch 33, par [33.8.920].
15 Pollock F and Wright RS, An Essay on Possession in the Common Law, Oxford, 1888, 20.
16 In this statement, “detention” is used to mean possession in fact.
17 In this statement, “single and exclusive” connotes that possession in law lies with one person even if
two or more persons may claim possession in fact, leaving aside joint ownership.
18 Possession of land, in law, is by definition exclusive, so the addition of “exclusive” to possession is
unnecessary.
-- 8 of 12 --
9
were located on land of which the first defendant had possession from the second
defendant as tenant from a landlord.
[44] If, as between the first defendant and the second defendant, the first defendant was
in possession of the land between 9 December 2013 and 13 June 2014, a point of
concern is that as between the plaintiff and the second defendant, the second
defendant did not take the position that, because it was not in possession of either
the land or the buildings (assuming as against the second defendant that there can be
a separate possession before they are disconnected from the land), no claim could be
made against it in detinue.19 Instead, apparently as proprietor of the land, the
second defendant asserted a right to prevent the plaintiff from coming onto the land
for the purpose of obtaining the return of the buildings. Still, it may not be
inconsistent with that position to find that the second defendant’s refusals to allow
the plaintiff to remove the buildings did not constitute detinue because the second
defendant was not in possession of the buildings. On the other hand, some cases
where the claim was for damages for the tort of conversion point the other way.20
[45] Even if the second defendant was not in possession of the buildings before 13 June
2014, there is no reason to doubt that it has been in possession of them since that
date. Upon termination of the agreement to occupy or lease, the first defendant’s
possession of the land and the buildings would or should have been brought to an
end. There was no suggestion in the evidence that it had not been brought to an
end. However, the plaintiff made no further demand for the return of the buildings
after the agreement was terminated. It does not appear when the plaintiff was
informed of the termination of the agreement. Nevertheless, if the second defendant
did not unlawfully detain the buildings before the agreement was terminated, its
possession of the buildings since then may also not have been an unlawful detention
because of the absence of a further demand by the plaintiff.
[46] In the result, I do not consider that it is appropriate to resolve these questions.
There are two reasons. First, they were not advanced by the second defendant,
although they arguably seem to be open on the facts pleaded. Second, in my view,
there is another basis on which the second defendant is entitled to succeed in its
defence of the plaintiff’s claim for damages as made.
[47] For present purposes, I proceed on the finding that the second defendant wrongfully
detained the plaintiff’s buildings from 12 December 2013, which was the time of
communication of its solicitors’ letter stating that the second defendant would
accept service of any proceeding to recover the buildings.
Strand Electric use
[48] However, assuming that the second defendant’s wrongful detention starts on that
day, it is not necessarily responsible for the claimed damages in the amount of the
plaintiff’s usual hire rate.
[49] As Bunnings held, the second defendant will only be liable to damages in the
amount of the usual hire rate if, inter alia, it used the plaintiff’s buildings. Allsop
JA said of the use required:
19 Cf England v Cowley (1873) 8 Ex 126, 128-9. That case was a claim for trover by detention.
20 Cf Caley v Rogers [1938] St R Qd 25, 32; Oakley v Lyster [1931] 1 KB 148, 155.
-- 9 of 12 --
10
“If use is required for the legitimate employment of a hiring charge to
assess damages or compensation or monetary relief, it is necessary to
consider what kind of use will suffice. Conversion or detinue has been
found. If the wrong is the mere non-return of chattels that lie idle and
contribute not at all to the life, work or business of the wrongdoer it may
be difficult to justify conceptually, in the absence of proof of actual loss
or damage, the awarding of a hiring fee.
Hire is, after all, in its nature, a payment for use. Nevertheless, one need
not be overly precise about the nature of the use. For instance, in Strand
Electric, the switchboards were not actively operated. There was use in
the relevant sense, however, because without the equipment the theatre
could not be let or sold — it made the theatre more attractive and readily
disposable.
Here some of the use was possession, for display and storage.
Possession for these purposes was after a demand to return. In a sensible
commercial sense, it was the deployment of the pallets in the business of
Bunnings, even to the extent that they were recirculating pallets for
returns. The refusal to return enabled the continued smooth operation of
the Bunnings business to take place, without the inconvenience (and
hence business cost) of doing that which they were legally obliged to do
— return all pallets to Chep. This, in my view, is use enough for the
Strand Electric principle.”21
[50] Prior to the termination of the agreement to occupy or lease on 13 June 2014, the
second defendant did not directly use any of the buildings. Until a date in December
2013 before Christmas, the first defendant was using them to conduct its
accommodation services business.
[51] That business was the source of cashflow for the first defendant to pay any rent due
to the second defendant. The first defendant did not pay any rent from a date in
April 2013.
[52] After the date in December 2013 before Christmas, there was no further occasion
when the plaintiff’s buildings were used. The first defendant looked to obtain
customers to use the camp’s facilities, and for that purpose advertised availability,
including on the internet, and showed prospective customers the camp’s facilities. I
infer that that may have included the plaintiff’s buildings. But there was no actual
use of them by either the first defendant or the second defendant.
[53] Since termination of the agreement to occupy or lease, the second defendant has not
re-let or licensed use of the camp so as to permit another person or tenant to use the
plaintiff’s buildings. The second defendant has not apparently deployed the
plaintiff’s buildings in any way.
[54] Among the decided cases, there is no precisely analogous case to the present of
“use” for the purpose of the Strand Electric principle. In Strand Electric itself, the
defendant’s use was confined to the use of the plaintiff’s portable switchboard to
power and light the defendant’s theatre while it was shown to potential tenants by
21 (2011) 82 NSWLR 420, 468-9 [179]-[180].
-- 10 of 12 --
11
agents of the defendant. That was held to be enough. In Bunnings, the defendant’s
use was the use of the plaintiff’s pallets to move, store and display chattels in the
defendant’s warehouses. That was held to be enough. In Sadcas Pty Ltd v Business
Professional Finance Pty Ltd,22 the defendant’s use was re-letting to a new tenant of
the cafe in which the plaintiff’s cooking vat was installed. That was held not to be
enough.
[55] There may be some tension between the outcomes in Strand Electric on the one
hand and Sadcas on the other hand. I note that Sadcas was not referred to in
Bunnings, even though the latter was decided only months after the former. In the
end, I approach the question on the basis that the use required is an inference or
finding of fact as to use which is not “overly precise” but which has regard to the
“life, work or business of the wrongdoer”.
[56] In my view, the second defendant did not “use” the plaintiff’s buildings in a way
that engages the Strand Electric principle of assessment of damages by reference to
the usual rate of hire.23 It follows, in my view, that the plaintiff’s claim against the
second defendant for damages for the usual hire rate of the chattels must fail.
Rate
[57] In case I am wrong in that conclusion, it is appropriate to make a finding as to the
appropriate rate of hire.
[58] The plaintiff claims the rate of $58,443 per month because that was the rate that the
first defendant had agreed to pay for the hire of the buildings. Two of the plaintiff’s
employees gave evidence that where a hirer extends a contract of hire the rate of
hire for the extended period is usually the same as that previously agreed.
Examples were put into evidence.
[59] Alternatively, the plaintiff claimed the rate at which it had agreed to hire
comparable buildings to other customers in November and December 2013, which
was approximately $35,700 per month.
[60] The difference between the two rates reflected that the market for such buildings
was more competitive in December 2013 than it was more than a year before.
[61] The plaintiff’s analogy between this case and an extended hire contract is not
perfect. Under all of the hire contracts put into evidence, the hirer agreed to pay the
plaintiff for, or personally bear the cost of, transporting the buildings to the site,
installing the buildings on the site and returning the buildings to the plaintiff. The
second defendant was not responsible for those things under any pre-existing hire
contract.
[62] In my view, the obligation to pay to have the existing buildings removed and
returned to the plaintiff (and to pay to have replacement buildings transported to site
and installed under any new contract) might weaken the commercial bargaining
22 [2011] NSWCA 267, [79].
23 Other potentially relevant cases are Thomas v APL Co Pte [2013] FCA 911, [31]; Rapid Metal
Developments (Australia) Pty Ltd v Rildean Pty Ltd [2010] NSWSC 7, [20]; Reynolds v Aluma-Lite
Products Pty Ltd [2009] QSC 379, [107]; Gaba Formwork Contractors Pty Ltd v Turner (1991) 32
NSWLR 175, 188.
-- 11 of 12 --
12
position of a party wishing to extend an existing hire contract. Such a person
otherwise faces the alternative of a new contract with another supplier.
[63] On the other hand, in December 2013, had the second defendant applied to the
plaintiff to hire the plaintiff’s buildings as installed at the Banana Camp, it might
have been able to avoid the costs of transporting replacement buildings to the site
and installing them, if it could agree an acceptable hire rate with the plaintiff. This
would have been a commercial factor or reason why the second defendant might
have been prepared to pay a rental for the plaintiff’s buildings, as installed, which
was more than the then market rate, under a contract where the hirer also paid for
those costs.
[64] As well, this hypothetical negotiation would have taken place in respect of a
relatively short hire term or period. Both parties would have been aware of the
relative amounts of the hire over that period and the comparative costs of transport
and installation.
[65] In my view, in those circumstances, it is not unreasonable to infer that the hire rate
agreed in an hypothetical negotiation would have been not less than $45,000 per
month for nine months. That amount is likely to have been less expensive to the
second defendant than the combined costs of a rate of $35,700 per month from
another supplier, and the costs of transport to the site and installation of alternative
buildings, if those items would have had to be paid for by the second defendant.
[66] Although there is a fair degree of speculation involved, I have reached that amount
by inferring from the other contracts in evidence that the cost of transport is likely
to have been no less than $40,000 or $50,000 and that the installation of 21
buildings would cost not less than $50,000 or $60,000. In fact, the cost of
installation was likely to have been more, if the contract from the plaintiff to FKG is
any guide, but the plaintiff led no evidence about it.
Conclusion
[67] In the result, I dismiss the plaintiff’s claim for damages against the second
defendant.
[68] I will hear the parties on costs.
-- 12 of 12 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2014/219