Ball Construction Pty Ltd v Conart Pty Ltd [2014] QSC 124
SUPREME COURT OF QUEENSLAND
CITATION: Ball Construction Pty Ltd v Conart Pty Ltd [2014] QSC 124
PARTIES: BALL CONSTRUCTION PTY LTD
ABN 94 108 548 778
(applicant)
v
CONART PTY LTD
ABN 50 153 867 228
(first respondent)
and
RICS AUSTRALASIA PTY LTD
ABN 18 089 873 067
(second respondent)
and
JENNIFER WYATT
ADJUDICATOR REGISTRATION NO J1070846
(third respondent)
FILE NO: BS 7482 of 2013
DIVISION: Trial Division
PROCEEDING: Originating application
ORIGINATING
COURT: Supreme Court of Queensland
DELIVERED ON: 6 June 2014
DELIVERED AT: Brisbane
HEARING DATE: 4 February 2014
JUDGE: Douglas J
ORDER: Adjudicator’s decision quashed. Further submissions
sought as to the form of order and costs.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS AND
CONDITIONS – VARIATIONS – where the applicant and a
company entered into a building contract – where that
company and the first respondent entered into a deed of
assignment with the consent of the applicant – where the
director of the original construction company swore a
statutory declaration – where the director of the first
respondent also swore a statutory declaration – where the
-- 1 of 13 --
2
statutory declarations stated that no variations, claims or
disputes existed – whether the statutory declarations and the
agreement to enter into a deed of assignment created an
estoppel
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
ADJUDICATION OF PAYMENT CLAIMS – where a
dispute about the date for practical completion under the
contract arose – where liquidated damages and variations
were also disputed – where an adjudicator appointed under
the Building and Construction Industry Payments Act 2004
adjudicated a payment claim – where the applicant and first
respondent entered into a deed – where by that deed the first
respondent undertook not to enforce the adjudication
certificate – where the third respondent then adjudicated a
further payment claim – whether there were jurisdictional
errors in the third respondent’s adjudication decision –
whether the first respondent had engaged in an abuse of
process – whether the adjudication should be declared void or
quashed
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
PROGRESS PAYMENTS – whether work carried out before
the deed was work under the construction contract
CONTRACTS – DISCHARGE, BREACH AND
DEFENCES TO ACTION FOR BREACH – DISCHARGE
BY AGREEMENT – NOVATION – whether the agreement
between the applicant and the first respondent was an
assignment or a novation
Building and Construction Industry Payments Act 2004
(Qld), s 3(2)(c), s 7, s 12, s 13, s 14, s 17, s 25, s 26
BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty
Ltd [2013] QCA 394, followed
Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421, cited
David & Gai Spankie & Northern Investment Holdings Pty
Ltd v James Trowse Constructions Pty Ltd & Ors (No 2)
[2010] QSC 166, cited
J Hutchinson Pty Ltd v Galform Pty Ltd [2008] QSC 205,
cited
John Holland Pty Ltd v TAC Pacific Pty Ltd & Ors [2009]
QSC 205, cited
McNab NQ Pty Ltd v Walkrete Pty Ltd [2013] QSC 128, cited
Northbuild Construction Pty Ltd v Central Interior Linings
-- 2 of 13 --
3
Pty Ltd [2012] 1 Qd R 525; [2011] QCA 022, cited
Olsson v Dyson (1969) 120 CLR 365, considered
Rickard Constructions Pty Ltd v Rickard Hails Moretti Pty
Ltd [2006] NSWCA 356, cited
Roseville Bridge Marina Pty Ltd v Bellingham Marine
Australia Pty Ltd [2009] NSWSC 320, cited
Shorten v David Hurst Constructions Pty Ltd [2008] NSWSC
546, cited
South East Civil & Drainage Contractors Pty Ltd v AMGW
Pty Ltd [2013] QSC 45, cited
Spankie James Trowse Constructions Pty Ltd [2010] QCA
355, cited
Walton Construction (Qld) Pty Ltd v Corrosion Control
Technology Pty Ltd [2012] 2 Qd R 90; [2011] QSC 067, cited
Walton Construction (Qld) Pty Ltd v Robert Salce [2008]
QSC 235, cited
COUNSEL: B Codd for the applicant
M Labone for the first respondent
No appearance for the second and third respondents
SOLICITORS: O’Reilly Lillicrap for the applicant
Gadens Lawyers for the first respondent
No appearance for the second and third respondents
[1] This is an application to quash an adjudication application and to set aside an
adjudication decision made under the Building and Construction Industry Payments
Act 2004 (Qld). The adjudication decision is said to be affected by jurisdictional
error for a number of reasons which I shall set out shortly.
Background facts
[2] The construction contract between the applicant (“Ball Construction”) and the first
respondent (“Conart”) was the result of their entry into a deed of assignment dated 5
December 2011 in respect of an earlier construction contract between the applicant
and a company called That Builder Pty Ltd. That contract was dated 2 August
2011. Conart undertook the obligations of That Builder under that contract pursuant
to the deed of assignment on 5 December 2011 with the consent of Ball
Construction.
[3] Before the formation of the contract involving Conart, the director of That Builder
swore a statutory declaration, on 31 October 2011 that “no variations, claims or
other disputes (other than those previously agreed to) have been agreed to or exist at
this time”. On 1 December 2011, the same man, Maurice Granger, this time as
managing director of Conart swore a further statutory declaration to the same effect.
Conart appears to have been a “Phoenix” company for That Builder which had
fallen into financial difficulties.
-- 3 of 13 --
4
[4] Conart continued the building work under the contract until practical completion
was achieved on or about 19 June 2012. On practical completion a dispute arose
between the applicant and the first respondent in relation to the date for practical
completion under the contract, the applicant’s entitlement to liquidated damages and
to payment for variations. Subsequently the first respondent also asserted an
entitlement to delay costs.
[5] Mr Davenport, an adjudicator appointed pursuant to the Act, adjudicated a payment
claim made by Conart on 31 August 2012. Ball Construction indicated that it
intended to file an originating application with this court seeking orders that the
decision be declared void and an injunction preventing Conart from enforcing the
adjudication decision made by Mr Davenport. By a deed made 20 October 2012
(“the compromise deed”) the parties compromised that aspect of their dispute by
Conart undertaking not to file the adjudication certificate as a judgment for a debt
pursuant to the Act or otherwise to enforce it. Then, on 11 March 2013, the third
respondent made the decision the subject of this application in adjudicating a further
payment claim made by the first respondent.
[6] The argument for the applicant is that there are several jurisdictional errors in the
decision, including a denial of natural justice. It is also submitted that, by pursuing
some claims inconsistent with the statutory declarations made by That Builder and
Conart, the first respondent has engaged in an abuse of process. The result
contended for by Ball Construction is that the adjudication should be declared void
or quashed. The grounds argued were:
1. that the decision incorporates an amount relating to “construction work”
carried out before the formation of the “construction contract” pursuant to
which payment is claimed;
2. that the statutory declarations to which I referred were relied upon by the
applicant in respect to its financing arrangements and in respect to its
agreement to enter into the deed of assignment dated 5 December 2011
which gave rise to an estoppel against two extension of time claims and a
claim for retention moneys in particular being made by the first respondent;
3. that the third respondent had failed to perform the statutory task of valuation
properly in accordance with the contract and the Act;
4. that the third respondent had failed to accord natural justice to the parties in
her assessment of delay costs in that she departed from the positions asserted
by each party where notice was not given to them of the intention to assess
those costs in that fashion;
5. that the third respondent relied on the compromised previous adjudication
decision by Mr Davenport as binding on her when she should have treated it
as non-binding, which led her not to adjudicate on matters in issue.
[7] Mr Codd’s submission for the applicant went on to argue that severance is not
available in respect of the offending parts of the decision so that it should be set
aside as a whole.
[8] It is convenient to deal with the first and second issues together. The third and
fourth issues also deserve joint consideration.
-- 4 of 13 --
5
Incorporation of work performed before entry into the contract and the
estoppel argument
[9] The first and second arguments were that the claims for work performed before the
deed came into existence did not give rise to a potential progress claim and that
Conart was estopped because of its statutory declaration from making such claims.
[10] At least three parts of the payment claim made by the first respondent related to
costs incurred before the formation of the contract with Conart on 5 December
2011. These included two extension of time claims for periods between 1 August
2011 to 25 October 2011 and 16 August 2011 to 15 September 2011 and the
retention of monies paid to That Builder pursuant to cl 15(a) of the contract.
[11] The submission was that an adjudication decision made pursuant to the Act may not
incorporate an amount relating to “construction work” carried out before the
formation of the “construction contract” pursuant to which payment is claimed.
Reliance was placed on ss 3(2)(c), 7, 12, 13, 14, 17, 25 and 26 of the Act, including
the provision in s 7 that the object of the Act was to ensure that a person is entitled
to receive and able to recover progress payments if the person undertakes to carry
out construction work “under a construction contract”. Similarly, ss 12 and 13 in
dealing with rights to progress payments and the amount of progress payments refer
to “the amount calculated under the contract”. As McMurdo J said in Walton
Construction (Qld) Pty Ltd v Robert Salce:1
“Work which was not carried out under the contract, because it
preceded the making of the contract, would appear to be outside the
operation of the Act.”
[12] In context, that statement by his Honour was not necessary to his decision but it
reflects a similar approach to the construction of the expression “under a
construction contract” to that adopted by Peter Lyons J in Walton Construction
(Qld) Pty Ltd v Corrosion Control Technology Pty Ltd. 2 One must also bear in
mind that: “the Act does not create a right to remuneration for construction work –
that right is created by the construction contract. What the Act does is to create and
regulate a right to obtain a progress payment.”3
[13] The applicant’s argument that these claims for payments arose earlier than its entry
into the construction contract proceeded on the basis that the assignment deed was
actually a novation. The applicant submitted that the effect of cl 2 and cl 3.4 of that
deed was to create a new contract. The parties to that deed were That Builder as
assignor, Conart as assignee and Ball Construction which was described as the
owner in the deed. Those clauses provided:
1 [2008] QSC 235 at [22].
2 [2012] 2 Qd R 90, 98 at [42]-[45]; see also McNab NQ Pty Ltd v Walkrete Pty Ltd [2013] QSC 128
at [28].
3 Roseville Bridge Marina Pty Ltd v Bellingham Marine Australia Pty Ltd [2009] NSWSC 320 at [43]
adopted in BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors [2012] QSC 346
at [56].
-- 5 of 13 --
6
“2. Assignment of Contract
The Assignor with effect from the Assignment Date hereby
expressly assigns, transfers and sets over all the Right, title
and interest in the Contract (including all Claims, Rights and
Obligations, arising out of or under the said Contract) free of
all encumbrances and liens in exchange for the Assignment
Fee on the assignment date and the Assignee accepts this
assignment.
The Assignee shall meet the obligations of the Assignor
under and by virtue of the Contract and undertakes as from
the Assignment Date to punctually and faithfully carry out
and observe all the covenants and stipulations on the part of
the Assignor contained in or required to be carried out,
observed or performed under the Contract as if the Contract
had been made and entered into between the Assignee and
the Owner, including but not limited to, all Obligations of
the Assignor arising under the Contract that relate to any
work performed by the Assignor prior to the Assignment
Date.
…
3.4 The Owner consents to the assignment and agrees to be
bound by the Contract as from the Assignment Date as if the
Contract had been made and entered into between the
Assignee and the Owner.”
[14] In a well known passage in Olsson v Dyson,4 Windeyer J, discussing the difference
between an assignment and a novation, said:5
“The ultimate distinction, in juristic analysis, between a transfer of a
debt by assignment and by novation is simple enough. Novation is
the making of a new contract between a creditor and his debtor in
consideration of the extinguishment of the obligations of the old
contract: if the new contract is to be fully effective to give
enforceable rights or obligations to a third person he, the third
person, must be a party to the novated contract. The assignment of a
debt, on the other hand, is not a transaction between the creditor and
the debtor. It is a transaction between the creditor and the assignee
to which the assent of the debtor was not needed. The debtor is
given notice of it; for notice is necessary to complete an assignment
pursuant to the statute or in the case of an equitable assignment to
preserve priorities. But the debtor’s assent is not required. He is not
a party to the transaction.”
4 (1969) 120 CLR 365, 388-390; see also Rickard Constructions Pty Ltd v Rickard Hails Moretti Pty
Ltd [2006] NSWCA 356 at [131].
5 Olsson v Dyson at 388.
-- 6 of 13 --
7
[15] The submission was that that analysis, applied in these circumstances, led to the
conclusion that a new contract had come into existence with Conart as a party rather
than it having become simply an assignee of That Builder’s rights and that the
amounts claimed before entry did not arise under that contract between Ball
Construction and Conart.
[16] The right to a progress payment under s 12 of the Act arises if the person claiming
the progress payment has undertaken to carry out construction work or to supply
related services under the contract. Conart had not so undertaken in respect of any
rights of That Builder to the extension of time claim for the period before the
novation. It is difficult to see how it became entitled to a progress payment under
the Act stemming from the period when That Builder was the contracting party, not
Conart. It may be entitled to claim pursuant to the contract for the rights assigned to
it, as Ball Construction conceded through its counsel, but the submission was that
those claims were not covered by s 12.
[17] Conart’s submission was that the deed of assignment was not a novation because
the earlier contract with That Builder was not discharged. It was submitted that the
applicant as “owner” under the deed continued to hold retention monies withheld
from That Builder for the purpose of the contract works as a whole. That Builder’s
rights to the retention moneys were, however, assigned to Conart by cl 2. In
consenting to the deed in cl 3.4, Ball Construction agreed to be bound by the
contract as from the assignment date as if the contract had been made and entered
into between Conart and it. As Windeyer J said in discussing whether a novation
had occurred under our system of law:6
“Justinian met the difficulty [of the provision of consideration for the
extinguishing of a prior obligation] by providing that a stipulation
should not operate as a novation unless the parties expressly declared
that their object in making the new contract was to extinguish the
prior obligation … However, the requirements of our law are
satisfied by a tacit agreement to extinguish the former obligation, and
this is inferred when an inconsistent obligation is by agreement
substituted.”
[18] Here, such a substitution of That Builder’s obligations occurred, with the effect that
a new contract came into existence as between the applicant and Conart. What had
not occurred in respect of these disputed claims in the language of s 12, however,
was the carrying out of construction work or the supply of related goods and
services by Conart. That had been done by That Builder. Conart was not entitled to
a progress payment under the Act covering those sums.
[19] In this case also, any rights Conart may have had as assignee under the deed in
respect of the extension of time payments and other claims made by it relating to the
period before the deed of assignment were caught by the statutory declarations so as
to disentitle it from claiming them as progress payments.
6 Olsson v Dyson at 390.
-- 7 of 13 --
8
[20] The statutory declarations said to establish the estoppel were made before Ball
Construction entered into the deed of assignment and were relied on by it, not least
because its bank required them in connection with the bank’s construction loan
provided to it.7 Prima facie, therefore, the preconditions for an estoppel by
representation have been met.
[21] The adjudicator was told that these extensions of time appeared to be contrary to
Conart’s previously sworn position. Conart argued that no specific estoppel
argument was put to the adjudicator so that she did not commit a jurisdictional error
in failing to take that argument into account. The submission to her was, however,
that the statutory declarations provided that there was no pending claim or dispute
before the deed so that those claims had not been sought in accordance with the
contract and the claimed extensions of time appeared to be contradictory to Conart’s
previously stated sworn position.8
[22] That makes the position sufficiently clear to establish that those claims should not
have been brought pursuant to the contract for a progress payment owing under the
Act. It was either not work carried out under the contract to which Conart was a
party or Conart is now estopped from claiming that it was because of the statutory
declaration made by it dated 1 December 2011.
[23] If I were not satisfied of that position I would have acceded to the further
submission that the pressing of those claims before the adjudicator was an abuse of
process which should result in the setting aside of the decision.9
[24] The adjudicator did not try to sever these claims for extension of time payments and
for the payment of retention moneys when That Builder was a contractor from the
amount assessed by her. The taking of those sums into account was, in my view, a
jurisdictional error rendering her decision of no legal effect. That failure to sever
those claims is not curable in this court under the current statutory regime.10 It
makes the decision, therefore, one that should be set aside.
Performance of the statutory task of valuation and breach of the rules of
natural justice
[25] The claim for delay by Conart was for 120 days payable at a rate of $1,041 per day.
The argument for Ball Construction was that, when the extension of time claims
were set out in chronological order to avoid double counting, 63 days were claimed
before 5 December 2011 and 56 days thereafter. The third respondent concluded
that the total delay was either 107 or 108 days, although no claim for such a period
was made in the payment claim or the adjudication application. She then allowed
77 days, apparently allowing for a five day week, as five sevenths of that claim at a
rate, not of $1,041 per day, but at $800 per day. That daily rate was not based
7 See the affidavit of D B Ball filed 12 August 2013 at para 32.
8 See the affidavit of D B Ball filed 12 August 2013 at p.141 of the exhibits.
9 See J Hutchinson Pty Ltd v Galform Pty Ltd [2008] QSC 205 at [47]-[52].
10 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd [2013] QCA 394 at [62]-[78].
-- 8 of 13 --
9
obviously on the evidence, but on her own assessment of the claimant’s breakdown
of its claimed costs. She did not reveal clearly how she arrived at that result.
Neither party had advocated for the approach taken by her. Nor were the parties
given an opportunity to be heard on her preferred approach to the task.
[26] Ball Construction’s argument was that the third respondent as adjudicator did not
apply the contract in reaching the valuation. The relevant contractual provision was
cl 22(f) which provided:
“Where the progress of the Works is delayed as a result of any of the
causes set out in Clause 22(a), any increase in the cost to the
contractor in carrying out the Works, including supervision and off-
site overheads, arising directly or indirectly out of the delay shall be
added to the Contract Sum.”
[27] Mr Codd for Ball Construction proceeded to argue that, of the 75 days claimed
before the formation of the contract with Conart, only one claim on 25 November
2011 could have resulted in an adjustment to the date for practical completion
because a right accrued prior to the novation of the contract. The balance
determined by the third respondent included an assessment related to the challenged
extensions of time for the period before entry into the contract by Conart which Mr
Codd maintained she lacked jurisdiction to consider. Of the claims made after 5
December 2011, they yielded 65 days of delay, giving a total, with the 25
November 2011 claim, of 67 days delay.
[28] Perhaps more significantly, Mr Codd submitted that the third respondent did not
actually analyse the delay claims so as to ascertain any relationship with the matters
set out in cl 22(a) of the contract as potential causes for delay. That clause
provided:
“22. EXTENSION OF TIME
(a) The Contractor is entitled to an extension of the Date
for Practical Completion if the progress of the Works
is delayed as a result of any of the following causes:
(i) an act or omission of the Owner, the Owner’s
consultants, agents or contractors or
authorised officers of the Lending Authority;
(ii) a Variation of the Works;
(iii) a Latent Condition;
(iv) a breach of the Contract by the Owner;
(v) a suspension of the Works in accordance with
Clause 20 or Clause 23(f);
(vi) inclement weather or conditions resulting
from inclement weather;
(vii) a claim or proceeding being taken, or
threatened to be taken, by a third party;
(viii) a dispute with an adjoining or neighbouring
owner or occupier;
-- 9 of 13 --
10
(ix) a strike, lockout, civil commotion or
industrial action affecting:
(A) any person in tile carrying out of the
Works; or
(B) the manufacture or supply of
materials to be used in the Works;
(x) a shortage, or delay in the delivery, of
materials to be used in the Works;
(xi) the unavailability of any labour (whether
under a subcontract or a contract of
employment) necessary for the Contractor to
carry out the Works with reasonable
diligence;
(xii) an act of prevention by the Owner not
otherwise covered by this Clause; or
(xiii) any other matter, cause or thing beyond the
control of the Contractor.”
[29] In that context, reliance was placed on the decision in South East Civil & Drainage
Contractors Pty Ltd v AMGW Pty Ltd11 where Jackson J decided that an adjudicator
was required to perform the adjudication in accordance with the contract and the
Act, whether or not the parties had made submissions as to the proper approach.
[30] Here the approach taken by the adjudicator was to conclude that, because the work
finished late, the client was entitled to an adjustment under cl 22(f) but, on the
applicant’s submission, she did not link a particular delay with a particular cause
said to arise under cl 22(a) so as to properly crystallise the entitlement to an
adjustment. Mr Codd for Ball Construction submitted that the error was not
accidental or erroneous but systemic and avoided consideration of the requirement
that there be causation between the event and the delay. This led to a jurisdictional
error otherwise vitiating the decision. Again, he asserted that the right claimed
needed to be one arising “under the contract” as discussed previously.
[31] The submissions for Conart were that any error by the third respondent was of a
non-jurisdictional kind where at best she wrongly construed Conart’s entitlement to
delay costs arising from cl 22(a). She also relied upon variations decided in the
earlier adjudication by Mr Davenport which, in Conart’s submission, she was
obliged to adopt by operation of s 27 of the Act.
[32] The complaints by Ball Construction connect here with the argument that the third
respondent denied the parties natural justice in respect of the method of assessment
of the delay claims made by her.
[33] In Walton Construction (Qld) Pty Ltd v Corrosion Control Technology Pty Ltd,12
Peter Lyons J said:
11 [2013] QSC 45 at [45].
12 [2012] 2 Qd R 90, 101 at [58]-[60].
-- 10 of 13 --
11
“[58] In Brodyn Hodgson JA identified the absence of any
“substantial denial of the measure of natural justice that the Act
requires to be given” as essential for a valid adjudicator’s decision.13
That conclusion was adopted by Applegarth J in John Holland Pty
Ltd v TAC Pacific Pty Ltd & Ors.14 His Honour’s view was in turn
applied by McMurdo J in David & Gai Spankie & Northern
Investment Holdings Pty Ltd v James Trowse Constructions Pty Ltd
& Ors (No 2).15 It appears to have been endorsed by the Court of
Appeal in Northbuild Construction Pty Ltd v Central Interior Linings
Pty Ltd.16 The correctness of the proposition was not in issue in
these proceedings.
[59] A number of the New South Wales decisions referred to by
Applegarth J in John Holland held that there is a substantial denial
of the measure of natural justice of the legislation required to be
given, when an adjudicator has decided a dispute on a basis for
which neither party has contended.17 Again, this proposition was
not in issue in these proceedings.
[60] In John Holland, Applegarth J held that there was a substantial
denial of the required measure of natural justice, when the matter
about which the adjudicator did not provide an opportunity to be
heard was a point on which the adjudicator’s decision was based,
and was significant to the actual determination.18 This proposition,
too, was not in issue.19 It may well encompass the proposition from
the New South Wales cases referred to by Applegarth J.”
[34] The principal that natural justice requires an adjudicator to notify the parties of an
intention to decide a dispute on a basis for which neither party has contended does
not necessarily vitiate a decision where the issue is not material to the decision
made.20 Conart submitted that, here, the adjudicator did not decide the issue in a
manner not contended for by either party. Rather, she decided that the causes of
delay stipulated by Conart affected the progress of works as it had claimed but she
did not accept Conart’s quantification of delay costs. The submission was that there
was no material denial of natural justice because the issue was not decided in a way
not contended for by either of the parties.
[35] It seems to me, however, that, as Ball Construction complained, the third respondent
approached the task by identifying the date for practical completion under the
contract and the date of practical completion and inferred that all of the time
between those dates gave rise to a compensable delay without applying the contract
and approached the question of assessing the number of days relevant to the delay
13 Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421 [55].
14 [2009] QSC 205.
15 [2010] QSC 166 [10].
16 [2012] 1 Qd R 525: see for example 571 [127] per White JA.
17 See also Spankie James Trowse Constructions Pty Ltd [2010] QCA 355 [10].
18 John Holland Pty Ltd v TAC Pacific Pty Ltd [2010] 1 Qd R 302, 315 [40].
19 Spankie v James Trowse Constructions Pty Ltd [2010] QCA 355 [10].
20 Shorten v David Hurst Constructions Pty Ltd [2008] NSWSC 546 at [27]-[28].
-- 11 of 13 --
12
claim in a manner which neither party contended for without giving them notice of
how she intended to proceed.
[36] When one reads the third respondent’s reasons,21 it is apparent that she proceeded
on the basis that the claimed causes of the delays pursuant to cl 22(a) on which she
relied were those stated in the extension of time claims. She did say that Ball
Construction had provided her with little to convince her that the delaying events
relied on did not delay the progress of the works to some degree.22 She did not,
however, undertake the task of linking those claims to the causes listed in cl 22(a).
That failure led to an omission to assess the claim in accordance with the contract in
that respect.
[37] In respect of the variation she applied to the amount claimed by Conart of $1,041
per day, making it $800 per day, she pointed out that Ball Construction had not
provided any alternative amount to her in its submission. In those circumstances
where any error by her was in favour of Ball Construction and not inconsistent with
any positive case made by it, I would be reluctant to conclude that there had been a
material breach of the obligations to provide natural justice to Ball Construction in
this case simply because of the course she adopted in setting the daily rate for
extension of time claims.
[38] There does seem to me, however, to have been a jurisdictional error coupled with a
denial of natural justice at least in respect of the claims for the sums I have earlier
decided to have been precluded by the Act and the statutory declaration and the
failure to clearly identify how the claimed delays were related to the causes arising
under cl 22(a) of the contract. Neither party was given an opportunity to make
submissions on the basis of her calculation of the number of days to be allowed and
that does seem to me to be a material issue where there was a denial of natural
justice.
The effect of the compromise of the earlier decision by Mr Davenport
[39] The third respondent relied upon parts of Mr Davenport’s earlier decision, the
subject of the compromise deed dated made 20 October 2012, as binding on her and
proceeded not to adjudicate on those matters in reliance on s 27 of the Act which
provides:
“27 Valuation of work etc. in later adjudication application
(1) Subsection (2) applies if, in deciding an adjudication
application, an adjudicator has, under section 14,
decided—
(a) the value of any construction work carried
out under a construction contract; or
21 See the affidavit of D B Ball filed 12 August 2013 at pp.77-81 of the exhibits.
22 See para 93 of her reasons at p.80 of the exhibits to the affidavit of D B Ball filed 12 August 2013.
-- 12 of 13 --
13
(b) the value of any related goods and services
supplied under a construction contract.
(2) The adjudicator or another adjudicator must, in any
later adjudication application that involves the
working out of the value of that work or of those
goods and services, give the work, or the goods and
services, the same value as that previously decided
unless the claimant or respondent satisfies the
adjudicator concerned that the value of the work, or
the goods and services, has changed since the
previous decision.”
[40] Ball Construction’s submission was that the effect of the compromise deed, by
which Conart undertook not to file the adjudication certificate in a court of
competent jurisdiction as a judgment for a debt or otherwise to enforce it, was to
preclude reliance on the earlier decision by the third respondent. It argued that the
court should hold that the adjudication application was an abuse of process insofar
as it relied upon rights Conart had undertaken not to rely upon by reason of the
compromise.
[41] It is unnecessary for me to decide this issue because of my decision that the
adjudication should be set aside for other reasons. Conart’s submission was that it
had taken no step to enforce the Davenport decision and that allowing s 27 of the
Act to have its usual operation did not enforce the earlier decision. Reliance upon
the decision did not correspond to the concept of enforcement. Prima facie that
submission seems to me to be rational. The mere fact that a party has undertaken
not to enforce an earlier decision does not remove it from the category of an earlier
decision deciding the value of any construction work carried out or the value of any
related goods and services under a construction contract. It remains a decision
where an adjudicator must assess the same value for the work or goods and services
as in the earlier decision. Were it necessary I would have concluded that the private
decision of the parties not to enforce an earlier decision does not affect what the
subsequent adjudicator must take into account for the purposes of s 27.
Conclusion and order
[42] For the reasons I have expressed earlier, the decision of the adjudicator should be
quashed. I shall hear the parties as to the form of the order and costs.
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2014/124