Conveyor & General Engineering Pty Ltd v Basetec Services Pty Ltd and Anor [2014] QSC 30 [2015] 1 Qd R 265
SUPREME COURT OF QUEENSLAND
CITATION: Conveyor & General Engineering Pty Ltd v Basetec Services
Pty Ltd and Anor [2014] QSC 30
PARTIES: CONVEYOR & GENERAL ENGINEERING PTY LTD
ACN 091 865 235
(Applicant)
v
BASETEC SERVICES PTY LTD
ACN 086 798 361
(First Respondent)
and
JOHN SAVAGE (ADJUDICATION REGISTRATION
NO J1057073)
(Second Respondent)
FILE NO/S: BS 9535 of 2013
DIVISION: Trial Division
PROCEEDING: Originating Application
ORIGINATING
COURT: Supreme Court of Queensland
DELIVERED ON: 7 March 2014
DELIVERED AT: Brisbane
HEARING DATE: 29 October 2013
JUDGE: Philip McMurdo J
ORDER: It is declared that the decision of the second respondent,
dated 10 September 2013 from an adjudication between
the applicant and the first respondent is of no effect.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – RENUMERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
ADJUDICATION OF PAYMENT CLAIMS – where the
applicant challenges an adjudicator‘s decision under the
Building and Construction Industry Payments Act 2004 (Qld)
– where some of the adjudication application was served on
the applicant by way of email – where other documents in the
adjudication application were contained in a Dropbox file -
whether the adjudication application was properly served on
the applicant.
-- 1 of 11 --
2
ADMINISTRATIVE LAW – JUDICIAL REVIEW –
GROUNDS OF REVIEW – PROCEDURAL FAIRNESS –
GENERALLY – where the applicant challenges an
adjudicator‘s decision under the Building and Construction
Industry Payments Act 2004 (Qld) – whether the adjudicator
erred in concluding that the applicant was out of time to
provide an adjudication response – whether the refusal to
permit an adjudication response deprived the adjudicator of
jurisdiction.
ADMINISTRATIVE LAW – JUDICIAL REVIEW –
GROUNDS OF REVIEW – PROCEDURAL FAIRNESS –
GENERALLY – where the applicant challenges an
adjudicator‘s decision under the Building and Construction
Industry Payments Act 2004 (Qld) – whether the adjudicator
erred in concluding that the applicant was out of time to
provide an adjudication response – whether the refusal to
permit an adjudication response was a denial of natural
justice.
Acts Interpretation Act 1954 (Qld), s 39
Acts Interpretation Act 1901 (Cth), s 28A
Building and Construction Industry Payments Act 2004
(Qld), s 17, s 18, s 21(3), s 21(5), s 24(1), s 103
Corporations Act 2001 (Cth), s 459G
Electronic Transactions (Queensland) Act 2001 (Qld), s 11,
s 24
Austar Finance Group Pty Ltd v Campbell (2007) 215 FLR
464
Bauen Constructions Pty Ltd v Sky General Services Pty Ltd
& Anor [2012] NSWSC 1123
Capper v Thorpe (1998) 194 CLR 342
Falgat Constructions Pty Ltd v Equity Australia Corporation
Pty Ltd [2006] NSWCA 259
Howship Holdings Pty Ltd v Leslie (1996) 41 NSWLR 542
Metacorp Australia Pty Ltd v Andeco Construction Group
Pty Ltd (2010) 30 VR 141
Penfolds Projects Pty Ltd v Securcorp Limited [2011] QDC
77
COUNSEL: P D Tucker for the applicant
P A Heywood-Smith QC for the first respondent
No appearance for the second respondent
SOLICITORS: Porter Davies Lawyers on behalf of the applicant
Amanda Forsyth as in-house counsel for the first respondent
-- 2 of 11 --
3
[1] This is a challenge to an adjudication decision made by the second respondent under
the Building and Construction Industry Payments Act 2004 (Qld) (―BCIPA‖),
whereby the applicant (―CGE‖) was required to pay to the first respondent
(―Basetec‖) the sum of $121,472.02.
[2] In essence, CGE says that the adjudication application was not duly served upon it,
so that the adjudicator had no jurisdiction. Alternatively, CGE says that the
adjudicator denied procedural fairness to it, by refusing to permit it to make certain
submissions about the merits of the claim. As will be seen, that argument is related
to the service point.
[3] In 2012, CGE and Basetec negotiated what became two contracts for the supply of
pre-assembled pipe rack units for water treatment facilities at, respectively,
Condabri and Reedy Creek. CGE required those units for its performance of a
(single) contract with Leighton Contractors Pty Limited. It appears that at an early
stage of the negotiations, it was proposed that there would be a single subcontract
between CGE and Basetec before there were the two subcontracts, one for each
facility, which were made between the parties.
[4] The subcontract for the Condabri facility has been performed but the subcontract for
the Reedy Creek facility was terminated before much of the relevant product had
been supplied by Basetec.
[5] On 30 July 2013, Basetec delivered payment claims under s 17 of BCIPA for each
subcontract. For the Condabri contract it claimed $403,680.20. For the Reedy
Creek contract it claimed $938,509.20.
[6] On 12 August 2013, Porter Davies Lawyers, acting for CGE, submitted payment
schedules pursuant to s 18 of BCIPA. In each case, CGE disputed the entirety of
the payment claim.
[7] On 23 August 2013, Basetec made an adjudication application for each payment
claim. The outcome of the Reedy Creek adjudication does not appear from the
evidence. This proceeding concerns the Condabri adjudication.
[8] On 8 August 2013, CGE paid an amount of $238,233.04 towards the Condabri
contract. It was common ground that this amount had to be deducted from the
payment claim. It was also apparently common ground that a further amount of
$43,975.14 should be deducted, being an agreed retention sum. Those deductions
resulted in the net amount of $121,472.02 which CGE was required to pay by this
adjudication.
[9] In its payment schedule, CGE disputed its liability for this sum upon the basis that it
represented the amount by which, CGE contended, Basetec had been overpaid for
the Reedy Creek contract. CGE said that this amount should be set off against what
was owing under the Condabri contract. The alleged overpayment for the Reedy
Creek job was put as follows. The true agreement between the parties, CGE
contended, was that there would be, across the two subcontracts, but one deposit
which would be paid by CGE to Basetec, in an amount of $270,000. But as things
happened, Basetec received distinct deposits, each of $270,000, on the two
subcontracts. CGE made no complaint about that deposit for the Condabri job
because, of course, CGE thereby had the benefit of that amount as a part payment.
But on the Reedy Creek job, where the contract had not been fully performed, CGE
-- 3 of 11 --
4
argued that Basetec had been entitled to receive only one-half of the deposit of
$270,000. Allowing an amount for retention, CGE contended that one-half of the
(net) deposit had been overpaid and was an amount which it was entitled to set off
against what might otherwise be due for the Condabri contract.
[10] Because it was set out in the payment schedule, that argument was considered by
the adjudicator who rejected it. But CGE now says that it was denied the
opportunity to present evidence and perhaps some further submissions in support of
this argument.
[11] On 23 August 2013, Ms Forsyth from Basetec sent an email to Ms Scott of Porter
Davies which attached three documents, being the two adjudication applications and
a letter to the Institute of Arbitrators and Mediators Australia. But within the email
itself was also a copy of the email which Ms Forsyth had sent to the Institute on that
day. That email to the Institute began:
―Please find attached letter, Adjudication Application Forms as well
as Dropbox links below for the two Adjudication Applications …‖
below which there appeared two Dropbox links.
[12] According to the undisputed evidence, on 23 August Ms Scott read the email and its
attachments but did not seek to look at the documents which were within those
Dropbox files.
[13] On Monday, 26 August 2013, Ms Forsyth sent to Mr How of CGE an email which
was relevantly identical to that which had been sent to Ms Scott on 23 August.
Again the Dropbox links were specified in the copy of the email which had been
sent to the Institute. According to the undisputed evidence of Mr How, on 26
August he read only the email to him and the attachments and did not seek to look
at the documents which were within the Dropbox files.
[14] Neither Mr How nor Ms Scott became aware of the contents of the Dropbox files
until Monday, 2 September 2013. The Dropbox file for the Condabri application
contained, amongst other things, Basetec‘s submissions to the adjudicator and some
documentation which was described as ―evidence of contract‖. But the submissions
for CGE do not identify any part of that material which it could not have
anticipated.
[15] It was that use of the Dropbox facility which gives rise to the controversy as to
whether, by either of those emails, Basetec duly served the adjudication application.
The Dropbox facility is a service by which an electronic file is stored by a third
party remotely so that any computer (with the relevant authority) can view the file.
The important point here is that the file within the Dropbox was not part of the data
which was contained in the email and its attachments.
[16] The adjudicator concluded that the adjudication application had been served by the
email sent to Porter Davies on 23 August. He had advised the parties of his
acceptance of the adjudication application on 28 August. Therefore the deadline for
an adjudication response, according to s 24(1) of BCIPA, he held was 30 August
2013.
[17] No document which purported to be an adjudication response was provided until 2
September 2013. On that day, Ms Forsyth sent an email, which had been copied to
-- 4 of 11 --
5
the adjudicator and to Ms Scott, which contained submissions about the service of
the adjudication application. Ms Scott sent to the adjudicator and Ms Forsyth a
submission in response on the service question, before receiving a further
submission (by email) from Ms Forsyth on that question. The adjudicator
considered all of these submissions.
[18] Again on 2 September, Ms Scott emailed to the adjudicator and Ms Forsyth an
adjudication response which included submissions and a statutory declaration by
Mr How on the substantial question. But the adjudicator determined that he was
precluded from considering any submission from CGE which was received after 30
August, except on the service question.
[19] The parties exchanged further submissions on the service question on 3 September
before the adjudicator delivered his decision on 10 September 2013.
[20] The essential complaint of CGE is that is was denied the opportunity to provide an
adjudication response because the adjudicator erred in concluding that the time for
that response started running on 23 August, being the date on which, the adjudicator
concluded, Basetec‘s application was served.
[21] This case turns then on that question of when the application was served. Relevant
to that question are several statutes, namely BCIPA, the Acts Interpretation Act
1954 (Qld) and the Electronic Transactions (Queensland) Act 2001 (Qld) (―the
ETA‖).
[22] Section 21(5) of BCIPA requires a copy of an adjudication application to be ―served
on the respondent‖. Section 21(3) of BCIPA sets out certain essential elements of
an adjudication application and also provides that it ―may contain the submissions
relevant to the application the claimant chooses to include‖.1 If a claimant is to
make submissions to an adjudicator, those submissions are to be included within the
application and by s 21(5) they must be served as part of the application.
[23] Section 103 of BCIPA is as follows:
―103 Service of notices
(1) A notice or other document that under this Act is
authorised or required to be served on a person may
be served on the person in the way, if any, provided
under the construction contract concerned.
(2) Subsection (1) is in addition to, and does not limit or
exclude, the Acts Interpretation Act 1954, section 39
or the provisions of any other law about the service
of notices.‖
It is not suggested that the relevant contract between the parties made provision for
the service of a document. Nor was it argued by Basetec that the parties had agreed
that the adjudication application could be served as it purportedly was,
notwithstanding that the parties had used Dropbox in earlier correspondence.
[24] Section 39 of the Acts Interpretation Act provides:
1 s 21(3)(f).
-- 5 of 11 --
6
―39 Service of documents
(1) If an Act requires or permits a document to be served
on a person, the document may be served—
(a) on an individual—
(i) by delivering it to the person
personally; or
(ii) by leaving it at, or by sending it by
post, telex, facsimile or similar
facility to, the address of the place of
residence or business of the person
last known to the person serving the
document; or
(b) on a body corporate—by leaving it at, or
sending it by post, telex, facsimile or similar
facility to, the head office, a registered office
or a principal office of the body corporate.
(2) Subsection (1) applies whether the expression
‗deliver‘, ‗give‘, ‗notify‘, ‗send‘ or ‗serve‘ or another
expression is used.
(3) Nothing in subsection (1)—
(a) affects the operation of another law that
authorises the service of a document
otherwise than as provided in the subsection;
or
(b) affects the power of a court or tribunal to
authorise service of a document otherwise
than as provided in the subsection.‖
[25] Section 39 makes no specific reference to the sending of a document by email.
CGE‘s submissions appear to accept that, in general, a document required to be
served under the BCIPA can be served by email. Irwin DCJ so held in Penfolds
Projects Pty Ltd v Securcorp Limited,2 upon the basis that email is a ―similar
facility‖ within s 39(1) of the Acts Interpretation Act. With respect, that
interpretation is open to doubt. The various means of service which are specified in
s 39(1) are each described as a means of conveying a document to a particular place,
such as a place of residence or business or a certain office of a body corporate. That
is not a characteristic of an email transmission. As Austin J observed in Austar
Finance Group Pty Ltd v Campbell,3 when comparing an email with a facsimile
transmission, ―an email is transmitted to and electronically stored by a server which
is normally not located in the receiver‘s premises, and positive action is needed on
the part of the receiver to read the email (by accessing it through his or her
2 [2011] QDC 77 at [232].
3 (2007) 215 FLR 464.
-- 6 of 11 --
7
computer) and to obtain a hard copy (by directing the computer to send the email to
the receiver‘s printer)‖.4
[26] In many contexts, the provision of information by an electronic communication is
facilitated by the ETA, s 11 of which is as follows:
―11 Requirement to give information in writing
(1) If, under a State law, a person is required to give
information in writing, the requirement is taken to
have been met if the person gives the information by
an electronic communication in the circumstances
stated in subsection (2).
(2) The circumstances are that—
(a) at the time the information was given, it was
reasonable to expect the information would
be readily accessible so as to be useable for
subsequent reference; and
(b) the person to whom the information is
required to be given consents to the
information being given by an electronic
communication.‖
Assuming that s 21(5) of the BCIPA is a State law by which a person (the party
applying for an adjudication) is ―required to give information in writing‖ (by
serving a copy of the adjudication application), still the circumstances stated in
s 11(2) would have to exist for that provision to authorise service by an email. One
of those circumstances is the consent of the recipient to the information being given
by an electronic communication. In some cases, that consent will have been given
by a term of a construction contract, so that irrespective of the ETA, the document
could be electronically served under s 103(1) of BCIPA. Where there is a consent
by the adjudication respondent to service by email, which is not contained in the
construction contract, s 11 of the ETA would appear to permit service to occur by
what is defined for the ETA as an electronic communication.
[27] Schedule 2 to the ETA defines ―electronic communication‖ to mean:
―(a) a communication of information in the form of data, text or
images by guided or unguided electromagnetic energy; or
(b) a communication of information in the form of sound by
guided or unguided electromagnetic energy, if the sound is
processed at its destination by an automated voice
recognition system.‖
[28] In the present case, s 11 of the ETA did not authorise the service of the adjudication
application, inclusive of the material within the Dropbox, for two reasons. The first
is that the present applicant had not agreed to be electronically served. The second
is that the material within the Dropbox was not part of an electronic communication
as defined. None of the data, text or images within the documents in the Dropbox
was itself electronically communicated, or in other words communicated ―by guided
4 (2007) 215 FLR 464 at 473.
-- 7 of 11 --
8
or unguided electromagnetic energy‖. Rather, there was an electronic
communication of the means by which other information in electronic form could
be found, read and downloaded at and from the Dropbox website.
[29] It is perhaps necessary to discuss s 24 of the ETA which provides that unless
otherwise agreed between the parties, an electronic communication is received when
it ―becomes capable of being retrieved by the addressee at an electronic address
designated by the addressee‖.5 If the whole of the adjudication application had been
in the email and if such a document could be served by email,6 then s 24 would
deem that service to have occurred when that email was capable of retrieval: see
Bauen Constructions Pty Ltd v Sky General Services Pty Ltd & Anor.7 But again,
the use of the Dropbox meant that the whole of the application was not within an
―electronic communication‖, thereby precluding the operation of s 24.
[30] In the present case, each of the emails of 23 and 26 August was itself read on the
day on which it was sent. But of course some of the documentation comprising the
adjudication application was not itself within the email. In my conclusion, that puts
paid to the possibility that this adjudication application could be regarded as duly
served pursuant to s 39 of the Acts Interpretation Act. Assuming that an email is a
―similar facility‖ to ―post, telex [or] facsimile‖, in terms of s 39(1), nevertheless the
service must involve something which could be described as the ―sending‖ of the
entire adjudication application to a relevant office of CGE. Only part of the
adjudication application was in any way ―sent‖ to that office. CGE was told where
the balance was located. There is no evidence suggesting that in this instance, the
Dropbox file was not immediately accessible. But that is not to say that it was sent
to CGE‘s office in the sense which is facilitated by s 39.
[31] In Austar Finance Group Pty Ltd v Campbell, Austin J considered the operation of
s 28A of the Acts Interpretation Act 1901 (Cth) in relation to a purported service by
email of an application under s 459G of the Corporations Act 2001 (Cth). Section
28A relevantly provides:
―(1) For the purposes of any Act that requires or permits a
document to be served on a person, whether the expression
‗serve‘, ‗give‘ or ‗send‘ or any other expression is used, then
the document may be served:
(a) on a natural person:
(i) by delivering it to the person personally; or
(ii) by leaving it at, or by sending it by pre-paid
post to, the address of the place of residence
or business of the person last known to the
person serving the document; or
(b) on a body corporate - by leaving it at, or sending it
by pre-paid post to, the head office, a registered
office or a principal office of the body corporate. …‖
5 s 24(1)(a).
6 Such as by s 39 of the Acts Interpretation Act.
7 [2012] NSWSC 1123 at [70] to [79].
-- 8 of 11 --
9
Austin J considered whether an email sent to a natural person‘s (relevant) address
could be said to involve a ―leaving‖ of the document at that address. He concluded:
―… In the case of an email transmission, where the electronic
message is received and held by a remote third-party server rather
than in the receiver‘s computer, and there is no hard copy document
unless the receiver accesses the email and transmits it to a printer,
nothing can be said to have been ‗left‘ at the receiver‘s premises, at
least until the email is accessed.‖8
[32] Applying that reasoning here, it cannot be said that the documents in the Dropbox
file were ―left‖ at or ―sent‖ to CGE‘s office, at least until CGE went to the Dropbox
site and opened the file and probably not until its contents had been downloaded to
a computer at CGE‘s relevant office.
[33] It follows that the adjudication application was not served in any way which was
specifically permitted by s 39 and in turn by s 103 of BCIPA. But there is a further
question whether, apart from service as permitted by s 39, the adjudication
application was in fact served.
[34] In Capper v Thorpe,9 it was said that a document will be served ―if the efforts of the
person who is required to serve the document have resulted in the person to be
served becoming aware of the contents of the document‖.10 Similarly, in Howship
Holdings Pty Ltd v Leslie,11 Young J (as he then was) held that although service of
an application for an order under s 459G was not effected by the deposit of the
document in a document exchange box, the proof of actual receipt of the document
from that box would suffice. Young J said:12
―The ordinary meaning of ‗service‘ is personal service, and personal
service merely means that the document in question must come to
the notice of the person for whom it is intended. The means by
which that person obtains the document are usually immaterial. …
Accordingly, one gets back to the ordinary principle, has there been
personal service, that is has the document come to the notice of the
respondent? …
The ultimate issue is whether the document was received by the
addressee … If it is, then in my view no matter how it got to the
addressee the addressee has been served. …‖
[35] In Falgat Constructions Pty Ltd v Equity Australia Corporation Pty Ltd,13
Hodgson JA said:
―[I]n my opinion it is clear that if a document has actually been
received and come to the attention of a person to be served or
provided with the document, or of a person with authority to deal
with such a document on behalf of a person or corporation to be
served or provided with the document, it does not matter whether or
8 (2007) 215 FLR 464 at 475.
9 (1998) 194 CLR 342.
10 (1998) 194 CLR 342 at 352.
11 (1996) 41 NSWLR 542.
12 (1996) 41 NSWLR 542 at 544, 545.
13 [2006] NSWCA 259 at [58].
-- 9 of 11 --
10
not any facultative regime has been complied with … In such a case,
there has been service, provision and receipt.‖
[36] Therefore, quite apart from s 39 of the Acts Interpretation Act, it would be
consistent with these authorities that at least the email and its attachments, when
opened by the addressees on 23 and 26 August, were then served. And the email
and its attachments informed the addressee that there were relevant documents to be
found in a certain Dropbox file. One of the attachments to the email, which was the
adjudication application form, told the recipient that in addition to that document
there were ―the claimant‘s submissions and supporting documents‖ which were
―provided with and forming part of this Adjudication Application‖. So the
documents which were read by the addressees on 23 and 26 August unambiguously
informed them that there were other documents which were part of the application
and of their location.
[37] Actual service does not require the recipient to read the document. But it does
require something in the nature of a receipt of the document. A document can be
served in this sense although it is in electronic form. But it was insufficient for the
document and its whereabouts to be identified absent something in the nature of its
receipt. The purported service by the use of the Dropbox facility may have been a
practical and convenient way for CGE to be directed to and to use the documents.
But at least until 2 September 2013 (when Mr How became aware of the contents of
the Dropboxes), it did not result ―in the person to be served becoming aware of the
contents of the document‖.14
[38] The result is that the adjudication application was not served on 23 or 26 August.
On the best view for Basetec, it was served no earlier than 2 September. The
adjudicator erred in concluding that CGE was out of time to provide an adjudication
response. Consequently, he erred in depriving CGE of the opportunity to present
submissions and any relevant evidence.
[39] The question then is whether this should result in a determination that the
adjudication decision is of no effect. CGE argues that the adjudicator‘s refusal to
permit an adjudication response deprived him of jurisdiction, an argument which
relies in particular on the discussion by Vickery J in Metacorp Australia Pty Ltd v
Andeco Construction Group Pty Ltd.15 Alternatively, it is said that this was a denial
of natural justice which warrants the same relief unless it can be demonstrated that
the provision of natural justice could have made no difference.
[40] Basetec argues that no relief should be granted, for essentially two reasons. One is
that CGE did not press the adjudicator to grant some extension of time for its
adjudication response. The other is that the case which CGE would have put to the
adjudicator was that which he did consider (because it was expressed in the
payment schedule) and which the adjudicator (it is said) correctly rejected.
[41] This court is not in a position to fairly determine the merit of CGE‘s case to be
credited with half of the deposit paid on the Reedy Creek subcontract. It can be
said, in Basetec‘s favour, that CGE‘s case is inconsistent with the express terms of
the subcontracts and, at least on one view, with the email exchange between the
parties on 4 December 2012. But CGE‘s case involves a factual question of
14 Capper v Thorpe (supra).
15 (2010) 30 VR 141 at 195-198.
-- 10 of 11 --
11
whether in the course of relevant conversations between representatives of the
parties, the true agreement reached was that there would be but one deposit. Whilst
CGE‘s case does not seem to have apparent force, in this proceeding it could not be
dismissed as hopeless.
[42] Mr How says that he was denied the opportunity of presenting evidence in the form
of an extensive statutory declaration by himself in relation to relevant meetings and
correspondence and the circumstances in which the deposit was, inadvertently he
says, paid by CGE on the Reedy Creek contract. He also says that CGE would have
provided evidence from a Mr Flounders as to what took place at a critical meeting.
In my conclusion, it cannot be said that the provision of this evidence and any
submission about it could have had no impact upon the outcome of the adjudication.
[43] As for the argument that CGE should have sought an extension of time for its
adjudication response, it is telling that the adjudicator declined to consider even the
limited response which was provided on 2 September 2013. CGE should not be
denied relief by speculation that the adjudicator might have granted an extension.
[44] It will be declared that the decision of the second respondent, dated 10 September
2013 from an adjudication between the applicant and the first respondent is of no
effect. I will hear the parties as to further orders including costs.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2014/030