Beyfield Pty Ltd v Northbuild Construction Sunshine Coast Pty Ltd [2014] QSC 12
SUPREME COURT OF QUEENSLAND
CITATION: Beyfield Pty Ltd v Northbuild Construction Sunshine Coast
Pty Ltd [2014] QSC 12
PARTIES: BEYFIELD PTY LTD trading as EAST COAST
MECHANICAL SERVICES
(applicant)
v
NORTHBUILD CONSTRUCTION SUNSHINE COAST
PTY LTD
(respondent)
FILE NO/S: 7062 of 2013
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 14 February 2014
DELIVERED AT: Brisbane
HEARING DATE: 11, 20 and 26 September 2013
JUDGE: Martin J
ORDER: Applicant to bring in minutes of order.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONDITIONS AND
IMPLIED CONDITIONS – SECURITY AND RETENTION
FUNDS – where a subcontractor gave a head contractor bank
guarantees as security for the performance of its obligations –
where the head contractor alleged certain breaches on the part
of the subcontractor and sought to call on the guarantees –
where the contract provided for recourse to the retention
following notice being given of a liquidated or unliquidated
demand – whether the provision was inconsistent with s 67E
of the Queensland Building Services Act 1991 and therefore
inoperative
Acts Interpretation Act 1954, s 3, s 14A, s 14B
Queensland Building Services Authority Act 1991 (Qld), s
67A, 67AAA, s 67E, s 67G, s 67J, s 67N
Bachmann Pty Ltd v BHP Power New Zealand Ltd [1999] 1
VR 420
Brisbane City Council v Mainsel Investments Pty Ltd [1989]
-- 1 of 16 --
2
2 Qd R 204
Bull v Attorney-General (NSW) (1913) 17 CLR 370
FMT Aircraft Gate Support Systems v Sydney Ports
Corporation [2010] NSWSC 1108
Minister Administering the Crown Lands Act v NSW
Aboriginal Land Council (2008) 237 CLR 285
Multiplex Ltd v Qantas Airways Ltd [2006] QCA 337
Project Blue Sky v Australian Broadcasting Authority (1998)
194 CLR 355
Warner v Hung (No 2) (2011) 297 ALR 56
COUNSEL: P Dunning QC and B Codd for the applicant
C Wilkins for the respondent
SOLICITORS: Hemming & Hart for the applicant
BCCS Law for the respondent
[1] In October 2011 the applicant (―Beyfield‖) entered into an agreement as a
subcontractor with the respondent (―Northbuild‖). Northbuild was the head
contractor for the construction of a Chronic Disease Centre on Thursday Island.
Under the subcontract, Beyfield was to carry out the mechanical works for the
project.
[2] In accordance with the subcontract, Beyfield provided Northbuild with two bank
guarantees as security for the performance of the work under the agreement.
[3] In May 2013, Northbuild gave notice to Beyfield of its intention to have recourse to
the bank guarantees alleging that Northbuild had incurred additional costs as a result
of an alleged breach of the subcontract by Beyfield with respect to an Indigenous
Employment Policy (―IEP‖) and other matters.
[4] Beyfield seeks declarations that:
(a) Northbuild is not entitled to retain the bank guarantees; and
(b) Beyfield did not breach the IEP.
It also seeks other, consequential orders.
The bank guarantees
[5] The guarantees were provided pursuant to cl 5 of annexure A of the subcontract –
―General conditions of contract‖.
[6] Clause 5 provides:
―(a) Subject to this subcontract, the Builder may deduct and
retain 10% of any progress payment to the Subcontractor
until the total Retention equals 5% of the Subcontract Sum
as security for the performance of the Works.
(b) The Builder may hold the Retention until the expiration of
the Defects Liability Maintenance Period, provided that on
Practical Completion the Builder must release to the
-- 2 of 16 --
3
Subcontractor that part of the Retention in excess of 2.5% of
the Subcontract Sum.
(c) Nothing in this clause affects any entitlement of the
Subcontractor at general law or under statute to substitute an
unconditional Bond or Instrument from a security provider
approved by the Builder, with a branch office in Brisbane,
and in a form acceptable to the Builder for any part of the
Retention.
(d) The retention, or any Bond or Instrument substituted by the
Subcontractor, secures the Subcontractor‘s performance of
its obligations under this Subcontract, including its
obligations to rectify defects and replace materials.
(e) The Builder may, upon the giving of written notice to the
Subcontractor, have recourse to the Retention, or convert
into cash any Bond or Instruments substituted by the
Subcontractor:
(i) where an amount is due to the Builder under the
Subcontract; or
(ii) in respect of any claim to payment (liquidated or
otherwise) the Builder may have against the
Subcontractor under the Subcontract or otherwise.‖
[7] In accordance with sub-clause, Beyfield caused its bank to provide two bank
guarantees in favour of Northbuild, each one in an amount of $96,250.
Notice by Northbuild
[8] Northbuild made the following claims for payment from Beyfield in the amounts
and on the dates set out below:
(a) 2 May 2013 - $101,319.84 for damages for Beyfield‘s breach of
the subcontract in failing to comply with the IEP.
(b) 24 May 2013 - $2,567 for damages for trespass being the use of a
container by Beyfield which Northbuild had hired for its own use.
(c) 29 May 2013 - $135,411.24 for damages for breach of the
subcontract caused by Beyfield‘s failure to pay freight required
under the subcontract.
(d) 30 May 2013 - $7,223.88 for damages for negligent or intentional
damage to accommodation provided by Northbuild to Beyfield.
(e) 21 June 2013 - $6,217.38 for breach of the subcontract caused by
Beyfield‘s failure to pay further freight.
[9] Northbuild has, since 24 May 2013, abandoned the claim in (b) above.
[10] At the same time as notifying the claim for damages for breach of the IEP,
Northbuild informed Beyfield that it intended to call on the bank guarantees for its
claim relating to that matter.
[11] Beyfield obtained an injunction restraining Northbuild from calling on the bank
guarantees on 1 August 2013.
[12] On 27 August 2013 Northbuild gave further notice to Beyfield that it intended to
call on the bank guarantees for the sums referred to in paragraphs (b), (c) and (e)
-- 3 of 16 --
4
above. Northbuild had already given notice of its intention to call on the bank
guarantees in relation to the claim in (d) above when it notified Beyfield of that
claim on 30 May.
The issues
[13] The principal issues which arise in this case are:
(a) Whether clause 5(e)(ii) of the general conditions is void or
unenforceable as a consequence of provisions of the Queensland
Building Services Authority Act 1991 (―the Act‖)1;
(b) Whether the notice given by the applicant was for a ―debt due‖;
(c) Whether Northbuild had the authority to convert the bank
guarantees; and
(d) Whether the claims made by Northbuild are bona fide.
The Queensland Building Services Authority Act 1991
[14] Beyfield argues that Part 4A of the Act regulates the contractual terms able to be
incorporated into a building contract and, in particular, with respect to the exercise
against and conversion of securities or retentions. It argues that cl 5(e)(ii) of the
general conditions is:
(a) void as it contravenes Part 4A of the Act, or, alternatively
(b) inoperative as it is an attempt to contract out of the provisions of the
Act.
[15] Section 14A of the Acts Interpretation Act 1954 provides that ―In the interpretation
of a provision of an Act, the interpretation that will best achieve the purpose of the
Act is to be preferred to any other interpretation.‖ I commence by noting that s 3 of
the Act provides:
―The objects of this Act are—
(a) to regulate the building industry—
(i) to ensure the maintenance of proper standards in the
industry; and
(ii) to achieve a reasonable balance between the interests
of building contractors and consumers …‖
[16] Part 4A of the Act deals with building contracts other than domestic building
contracts. In that part, the following terms are defined in s 67A:
● ―contracted party, for a building contract, means the party to the
contract who is to carry out the building work the subject of the
contract.‖ (In this case Beyfield is the contracted party.)
● ―contracting party, for a building contract, means the party to the
contract for whom the building work the subject of the contract is to
be carried out.‖ (In this case Northbuild is the contracting party.)
● ―retention amount, for a building contract, means an amount
described in section 67C.‖
● ―security, for a building contract, means something –
1 The Act was renamed the Queensland Building and Construction Commission Act 1991 from 29
August 2013. See Queensland Building Services Authority Amendment Act 2013.
-- 4 of 16 --
5
(a) given to, or for the direct or indirect benefit of, the
contracting party for the contract by or for the
contracted party for the contract; and
(b) intended to secure, wholly or partly, the
performance of the contract; and
(c) in the form of either, or a combination of both, of
the following—
(i) an amount, other than an amount held
as a retention amount for the contract;
(ii) 1 or more valuable instruments, whether or
not exchanged for, or held instead of, a
retention amount for the contract.‖
● ―valuable instrument‖ is defined to include a banker‘s undertaking.
[17] The bank guarantees provided by Beyfield are securities within the meaning set out
in s 67A.
[18] A ―building contract‖ is defined in s 67AAA:
―For this part, a building contract means a contract or other
arrangement for carrying out building work in Queensland but does
not include—
(a) a domestic building contract; or
(b) a contract exclusively for construction work that is not
building work.‖
[19] The agreement between the parties is such a building contract.
[20] ―Retention amount‖ is defined in s 67C:
―For this part, an amount is a retention amount for a building
contract if—
(a) the amount is payable as part of the contract price under the
building contract, but, under the contract, may be withheld
from payment to the contracted party for the building
contract—
(i) during the progress of the building work the
subject of the contract; or
(ii) for a period (a maintenance period) after the
completion of the building work; or
(iii) both during the progress of the building work
and for a maintenance period; and
(b) the purpose of withholding the amount is to give financial
protection to the contracting party in relation to the need to
correct defects in the building work, or otherwise to secure,
wholly or partly, the performance of the contract.‖
[21] Clause 5 satisfies this definition.
[22] Section 67E provides:
―(1) Subject to any provision of this part that expressly provides
that a building contract, or a provision of a building contract,
is void, this part does not have effect to make void or
-- 5 of 16 --
6
voidable a building contract, or a provision of a building
contract, even if—
(a) in entering into the building contract, or the building
contract containing the provision, a party to the
building contract commits an offence against this
part; or
(b) the building contract or the provision of the building
contract is inconsistent with a condition to which the
building contract is subject under this part.
(2) However, if a building contract, or a provision of a
building contract, is inconsistent with a provision (the
Act provision) of this part applying to the building
contract, the building contract, or the provision of the
building contract, has effect only to the extent it is not
inconsistent with the Act provision.
(3) Without limiting subsection (2), a building contract is
unenforceable against the contracted party for the
contract to the extent that the contract provides for
retention amounts or security in a way that is
inconsistent with a condition to which the contract is
subject under division 2.
(4) This part—
(a) has effect in relation to a building contract
despite anything in the building contract; and
(b) applies to a building contract even if—
(i) the contract was entered into outside
Queensland; or
(ii) the parties to the contract have agreed that
the law of Queensland does not apply to the
contract or to a provision of the contract.‖
(emphasis added)
[23] The word ―condition‖ used in s 67E(3) is defined in Schedule 2 of the Act as
including a limitation or restriction. The provisions of s 67J, below, constitute a
restriction in that they impose a time limit on claims.
[24] Division 2 of Part 4A has the heading: ―All building contracts.‖ This is a part of the
Act2.
[25] Section 67G(4)(d) provides that a building contract in writing complies with the
formal requirements for a building contract if the contract states, among other
things, ―the parties‘ agreement about retention amounts and securities to be held‖.
The parties have done this in cl 5 of the agreement.
[26] Section 67J provides:
―(1) The contracting party for a building contract may use a
security or retention amount, in whole or in part, to obtain an
amount owed under the contract, only if the contracting party
has given notice in writing to the contracted party advising of
the proposed use and of the amount owed.
2 Acts Interpretation Act 1954, s 14(1).
-- 6 of 16 --
7
(2) The notice must be given within 28 days after the contracting
party becomes aware, or ought reasonably to have become aware,
of the contracting party‘s right to obtain the amount owed.
(3) If, because of subsections (1) and (2), the contracting party is
stopped from using a security or retention amount, the contracting
party for the contract is not stopped from recovering the amount
owed in another way.
(4) This section does not apply if, under the contract—
(a) work has been taken out of the hands of the
contracted party or the contract has been terminated;
or
(b) the security or retention amount is to be used to
make a payment into court to satisfy a notice of
claim of charge under the Subcontractors’ Charges
Act 1974.
(5) In this section—
amount owed, under a building contract, means an amount that,
under the contract, is a debt due from the contracted party for
the contract to the contracting party for the contract because
of circumstances associated with the contracted party’s
performance of the contract.
use of security or retention amount includes the act of converting
securities into cash where the securities are held as negotiable
instruments.‖ (emphasis added)
[27] Section 67J is in division 2 of the Act and is, thus, affected by s 67E.3
[28] Section 67N provides:
―(1) A building contract is subject to a condition that, at any time
after, under the contract, practical completion of building work is
reached, the total value of the following is to be not more than
2.5% of the contract price for the contract—
(a) all retention amounts for the contract that are being
withheld;
(b) all securities for the contract given and still held.
(2) Subsection (1) does not apply to retention amounts or securities
to the extent that the retention amounts or securities do not relate to
the need to correct defects, identified in the defects liability period
under the contract, in the building work under the contract.‖
[29] Section 108D provides:
―A person can not contract out of the provisions of this Act.‖
Is clause 5(e)(ii) of the general conditions void or unenforceable or inoperative?
[30] The general approach to the construction of statutes was set out in Project Blue Sky
v Australian Broadcasting Authority4 where the following appears:
3 See s 67E(3).
4 (1998) 194 CLR 355.
-- 7 of 16 --
8
―[69] The primary object of statutory construction is to
construe the relevant provision so that it is consistent with the
language and purpose of all the provisions of the statute. The
meaning of the provision must be determined ―by reference to the
language of the instrument viewed as a whole‖. In Commissioner
for Railways (NSW) v Agalianos, Dixon CJ pointed out that ―the
context, the general purpose and policy of a provision and its
consistency and fairness are surer guides to its meaning than the
logic with which it is constructed‖. Thus, the process of
construction must always begin by examining the context of the
provision that is being construed.
[70] A legislative instrument must be construed on the prima facie
basis that its provisions are intended to give effect to harmonious
goals. Where conflict appears to arise from the language of
particular provisions, the conflict must be alleviated, so far as
possible, by adjusting the meaning of the competing provisions
to achieve that result which will best give effect to the purpose
and language of those provisions while maintaining the unity of
all the statutory provisions. Reconciling conflicting provisions
will often require the court “to determine which is the leading
provision and which the subordinate provision, and which
must give way to the other” . Only by determining the hierarchy
of the provisions will it be possible in many cases to give each
provision the meaning which best gives effect to its purpose and
language while maintaining the unity of the statutory scheme.
[71] Furthermore, a court construing a statutory provision must
strive to give meaning to every word of the provision. In The
Commonwealth v Baume Griffith CJ cited R v Berchet to support
the proposition that it was ―a known rule in the interpretation of
Statutes that such a sense is to be made upon the whole as that no
clause, sentence, or word shall prove superfluous, void, or
insignificant, if by any other construction they may all be made
useful and pertinent‖.5 (citations omitted, emphasis added)
[31] Beyfield argues that clause 5(e)(iii) is caught by the provisions of the Act. It says:
(a) The bank guarantees are ―retention amounts‖ for the purposes of Part
4A of the Act.
(b) A provision of a Part 4A ―building contract‖ has effect only to the
extent that it is not inconsistent with a provision of Part 4A.
(c) Section 67J requires that 28 days notice be given before a retention
amount can be used for ―an amount owed under the contract‖, that is,
a debt due from one party to the other.
(d) Section 67J sets out the only way in which retention amounts can be
exercised or converted.
(e) Clause 5 purports to grant a power to exercise or convert retention
amounts in circumstances where there is not a debt due, that is,
where damages are claimed.
(f) Clause 5 is void to that extent because it is inconsistent with s 67J.
5 per McHugh, Gummow, Kirby and Hayne JJ at [69]-[71].
-- 8 of 16 --
9
[32] Northbuild argues that there is nothing in the language of s 67J to justify
interpreting it as setting out the only circumstance in which a retention amount can
be converted. It says that neither s 67J nor s 108D provides that parties to a building
contract cannot agree that a retention amount may be used in circumstances other
than where there is an ―amount owed‖. In other words, cl 5 is not inconsistent with s
67J and so it does allow the conversion of a security where only damages are
claimed.
[33] It follows from Northbuild‘s argument that if there was a debt of $1000 under the
contract a retention amount could not be converted unless notice was given. But,
notice would not need to be given if the conversion was to satisfy a claim where the
same amount was sought as, say, damages for trespass. This, Northbuild submits,
simply demonstrates that the legislature intended that the parties to a building
contract would be free to agree as they wished with respect to matters which were
not a ―debt due‖.
[34] Beyfield argues that the Act does not allow for that to occur and submits that
guidance can be obtained from the Explanatory Notes tabled when the Bill which
led to that Act was before Parliament. In those Notes the following appears:
―Clause 28 inserts a new Part 4A – Building Contracts other than
Domestic Building Contracts. This new Part provides
regulatory recognition of building industry practice whereby
there is a chain of contracts governing performance of
building work. The part relieves subcontractors of some
unconscionable contract provisions and deems desirable
provisions into some contracts. The Part only applies to
contracts other than domestic building contracts because of
different conditions in the house-building industry and the
regulatory environment provided by Part 4 of the Act.
…
S67E removes doubt that this Part only makes void any
conditions of contract expressly made void by this Part, and
that it applies to all contracts, even if in entering into the
contract an offence is committed or the contract is entered into
outside Queensland. The Part also has effect despite anything
contained in a building contract. Contractual provisions that
conflict with the provisions of this Part are invalid to the extent of
the inconsistency.
…
S67J limits the scope of set-offs available to contracting
parties. Set-offs are where amounts payable to contractors are
reduced to take account of, for example, site clean-up costs
incurred by the contracting party. Set-off provisions are often
used in contracts in respect of retention amounts held during
the warranty liability period, which may endure for some years.
This section requires such set-offs to be claimable from the
contracted party only if timely notice (28 days) is provided to
the contracted party. The section recognises that in some
instances, the right to set-off may be known well before the
amount of set-off is known. For example, cracks appear in a wall
during the warranty retention period. This would trigger the
section‘s requirement (within 28 days) to provide the contracted
-- 9 of 16 --
10
party with a notice. When engineering investigations define the
scope of work and tenders are called, a second notice is required
to be sent within 3 business days of the amount being known.
This will prevent set-offs being effected when the trail has gone
cold and the contracted party is in no position to dispute alleged
facts. It should be noted that this provision does not prevent a
contracting party who has lost the right to set-off from
subsequently recovering moneys duly owing.‖ (emphasis added)
[35] Recourse can be had to an Explanatory Note in any of the circumstances set out in s
14B of the Acts Interpretation Act 1954, not just where a provision may appear
ambiguous or obscure. An Explanatory Note may be referred to for any of these
purposes:
―(a) if the provision is ambiguous or obscure—to provide an interpretation
of it; or
(b) if the ordinary meaning of the provision leads to a result that is
manifestly absurd or is unreasonable—to provide an interpretation that
avoids such a result; or
(c) in any other case—to confirm the interpretation.‖
[36] In this case, each of those factors is available.
[37] It is argued for Beyfield that the Act and, in particular, s 67J is remedial in character
and is intended to supplant the operation of any contract caught by its operation.
Section 67J, it was submitted, should be construed to ―… give the fullest relief the
fair meaning of it language will allow‖.6 While there is ample authority for the
proposition just referred to, it will only have application where more than one
construction is available or where there is uncertainty about the meaning of the
relevant words. If, for example, the words of a statute properly described as
remedial give rise to a question about the adoption of a ―broad‖ construction or a
―narrow‖ construction, then the principle may be invoked. In the absence of such a
choice the principle has no application.7
[38] The coverage of s 67J was considered in Multiplex Ltd v Qantas Airways Ltd 8. In
dealing with the submissions, Keane JA said:
―[6] It will be noted that s 67J is concerned to regulate the reduction
of ‗an amount payable under the contract‘ by ‗an amount owed
under the contract‘. It is concerned with amounts which are, in truth,
payable or owed under the contract. It is not concerned with
amounts ‗claimed to be owing‘ or with amounts ‗certified as
payable‘. …‖
―[35] Moreover, s 67J is concerned with a wide variety of
circumstances in which an amount may become owing by the
builder to the owner. In the particular case of liquidated damages,
the quantification of the amount owed is effected by the contract
6 Bull v Attorney-General (NSW) (1913) 17 CLR 370 at 384; Brisbane City Council v Mainsel
Investments Pty Ltd [1989] 2 Qd R 204 at 213, 214.
7 Minister Administering the Crown Lands Act v NSW Aboriginal Land Council (2008) 237 CLR 285
at 301.
8 [2006] QCA 337.
-- 10 of 16 --
11
itself, so that the amount owed is quantified by the contract as and
when the right to obtain that amount arises. …‖
[39] Section 67C provides a definition of ―retention amount‖ which applies to Part 4A.
That Part contains a number of sections which subject a building contract to certain
conditions. Sections 67K, 67L and 67M, for example, specifically provide that a
contract is ―subject to a condition …‖. Section 67J is not expressed in that way, but
it is implicit that its terms will apply unless the circumstances set out in s 67J(4)
exist. Thus, no matter what a contract might say, the notice requirements will apply
in the absence of those circumstances. Those requirements are limitations or
restrictions upon the capacity to have recourse to retention amounts and, as such, are
―conditions‖ for the purposes of s 67E(3).
[40] Section 67J also confines the operation of retention clauses to ―debts due‖. To
argue, as Northbuild does, that this section does not apply to matters other than
―debts due‖ is inconsistent with the scheme of this Part of the Act. The Act sets out
to regulate the building industry and to limit the scope of set-offs to contracting
parties. Any ambiguity in the construction of s 67J should be resolved by reference
to those matters. It is remedial legislation in many respects and that can be seen
from the sections which work to impose conditions expressly. While s 67J does not,
in terms, impose a condition it restricts the use which a contracting party may make
of a security.
[41] The term relied upon by Northbuild – cl 5(e)(ii) – is inconsistent with s 67J to the
extent that it purports to allow access to a security for the purposes of satisfying
claims which are not for ―amounts owed‖. The clause is, then, unenforceable to that
extent and Northbuild cannot use the securities for its unliquidated claims.
If the Act does apply to unliquidated claims
[42] If, contrary to my conclusions about the operation of the Act, securities may be
called on for unliquidated claims, it is appropriate that I consider the other
arguments advanced by the parties.
[43] In its Amended Originating Application Beyfield seeks, among other things, three
declarations to the following effect:
(a) That Northbuild is not entitled to retain both bank guarantees.
(b) That Beyfield has not breached the contract in relation to obligations
concerning indigenous employment.
(c) That Beyfield is not liable to the claims for payment identified in
Northbuild‘s notice of 27 August 2013.
[44] Northbuild submitted, correctly, that when a party seeks a negative declaration, that
party bears the onus of proving that negative proposition.9
[45] Beyfield advances two arguments. First, it says that cl 5 does not extend to the
claims made by Northbuild. Secondly, it submits that the claims made are not bona
fide.
9 Warner v Hung (No 2) (2011) 297 ALR 56 at [46]-[47].
-- 11 of 16 --
12
Construction of clause 5
[46] Beyfield argues that cl 5 only extends to matters arising under the contract. Against
that is the contention by Northbuild that the words ―or otherwise‖ in cl. 5(e)(ii)
extend the authorisation to have recourse to the bank guarantees to any ground,
whether under the contract or not. Alternatively, Northbuild argues that the claims it
makes are for amounts due under the contract but that those amounts had not, at the
relevant times, matured into an ―actual amount due as defined‖.
[47] It is convenient to deal first with the nature of the amounts claimed, for, if they are
amounts owed under the contract or the claims are not made bona fide then there is
no need to consider the meaning of the words ―or otherwise‖ in cl 5(e)(ii).
Indigenous Employment Policy
[48] Northbuild informed Beyfield that it would not make a payment pursuant to a
request for payment because, in effect, Beyfield had not complied with the IEP
under the contract.
[49] In July 2013 the amount of $103,728.78 was said by Northbuild to be owing to it by
Beyfield because Northbuild was required to incur additional costs as it had
employed extra indigenous employees to ensure the project complied with the IEP.
[50] Reference to the IEP can be found in Annexures ‗C‘ and ‗H‘ to the subcontract. In
cl 102 of Annexure C the following appears:
―102 Compliance with the 10% Training Policy and 20% Indigenous
Employment Quality (sic) must be achieved. Provide information
concerning actual, total, full time equivalent employments supported
by the project over the construction phase.‖
[51] Annexure ‗H‘ to the subcontract is a form headed ―20% Indigenous Employment
Policy‖ and it contains spaces for the details of employees and the type of work
undertaken and so on to be inserted on the form. The form also contains the
following:
―This Subcontract is subject to the Queensland government 20%
indigenous employment policy.
The intention of the policy is that 20% of all onsite labour hrs in this
sub-contract are by indigenous employees. All endeavours must be
undertaken to comply with this policy.‖
[52] The parties agreed that the ―Indigenous Employment Policy for Queensland
Government‖ applies to the works the subject of this dispute. One of the described
aims of the policy was as follows:
―This policy promotes, encourages and creates skills development,
employment and business and opportunities for Aboriginal people
and Torres Strait Islanders in relation to Queensland Government
building and civil construction projects in specified Aboriginal and
Torres Strait Island communities.‖
[53] The policy describes the broad requirements in the following way:
―This policy applies to all civil construction contracts with no
minimum threshold and building construction projects exceeding
-- 12 of 16 --
13
$250,000 (GST inclusive) in value. However, projects of lesser value
can be clustered together in a contract to reach the threshold value.
This policy requires a 20% minimum benchmark of total labour
hours – with half of the deemed labour hours required to involve
accredited training. The indigenous workforce is to be recruited from
the local Aboriginal and Torres Strait Islander community/ies.‖
[54] The policy goes on to provide details of how it might be implemented and, on page
9 of the policy, the consequence of non compliance is set out:
―Failure to comply in part or in whole with the requirements to
engage indigenous workers/enterprises from the local indigenous
community may result in the contractor being excluded from
tendering for government funded construction projects in indigenous
communities in Queensland.‖
[55] The contract between Northbuild and the Principal was subject to a document
entitled ―Supplementary Special Conditions of Contract‖.
[56] It related specifically to the engagement of indigenous community workers. It also
required that Northbuild prepare a Compliance Plan and submit in accordance with
the Supplementary Special Conditions and that the contractor must obtain the
approval of the applicable local indigenous community or council to its Compliance
Plan. A Compliance Plan was submitted but no approval was obtained. That brings
into consideration cl 29.1A.6 which provides:
―29.1A.6 Where a Compliance Plan is not submitted in accordance
with subclause 29.1A.5(a), the Contractor shall, unless
and until an alternative Compliance Plan is submitted to
the satisfaction of the Principal, in its execution of the
work under the Contract, either directly or indirectly
through subcontractors and in consultation with the local
Indigenous community, engage Indigenous workers from
the local Indigenous community for the number of labour
hours no less than the number derived by multiplying the
accepted GST inclusive Contract Sum by 0.16%: viz
GST inclusive Contract Sum x .16% - number of labour
hours.
A minimum of 50% of the labour hours calculated
pursuant to this clause 29.1A.6 shall be performed by
apprentices/trainees or other employees from the local
Indigenous community, undertaking accredited training.
Where this subclause 29.1A.6 applies, the Contractor
must submit to CSQ with a copy to the Superintendent a
Compliance Plan identifying compliance with ‗minimum
deemed hours‘.‖
[57] Northbuild relies upon cl 4(b) of the Subcontract which provides that Beyfield
―agrees to assume to [Northbuild] the same obligations as [Northbuild] has assumed
under the Head Contract in respect of the Works as part of the Subcontract.‖
-- 13 of 16 --
14
[58] Northbuild argues that the requirements in cl 29.1A.6 of the Supplementary Special
Conditions therefore apply to the same extent to Beyfield.
[59] Northbuild contends that the requirements of the IEP were not complied with by
Beyfield. That arises out of a misconstruction of the requirements of the
Supplementary Special Conditions. Clause 29.1A.4 provides:
―The Contractor, in its execution of the work under the Contract,
either directly or indirectly through subcontractors, and in
consultation with the local Indigenous community, shall comply with
the IEP Policy and the Compliance Plan submitted in accordance
with clause 29.1A.5.‖
[60] As is noted above, the Compliance Plan did not come into force because there was
no agreement to it. The construction of the contract which I favour is that cl 29.1A.6
defines the extent of the requirements of a contractor where a Compliance Plan has
not been submitted and approved.
[61] The calculations pursuant to the provisions of cl 29.1A.6 are contained within the
material and demonstrate to my satisfaction that the requirements of that clause,
assuming that they apply to Beyfield, have been satisfied. Northbuild argues that
one looks at the IEP and finds that there has been a shortfall in the hours worked of
some 50%.
[62] I do not accept that. The IEP contains examples of the manner of working out how
many hours were needed to satisfy the policy and that is consistent with the
approach taken by Beyfield.
[63] In any event, the work which was performed by indigenous employees in order to
satisfy what Northbuild regarded as its obligations under the contract with the
principal was not work which was done under the contract. The work which was
performed, so that Northbuild could comply with what it regarded as its obligations,
was work which was not necessary for the contract and was done simply in order to
build up a sufficient quantum of hours to satisfy the supposed requirements. As
such, it does not constitute an amount due to the building under the subcontract nor
can it be a claim to payment under cl 5(e) of the General Conditions of Subcontract.
[64] Further, the consequence of a failure to comply with the IEP (if it applied) or the
alternative Compliance Plan in cl 29.1A.6 of the Supplementary Special Conditions
resulted only in the possibility of a decision to preclude Northbuild from further
tendering for work in indigenous communities in Queensland. A failure to comply
would not result in any monetary loss by Northbuild but the possibility (and it can
be put no higher than that) of not being able to tender for certain types of work
referred to above. The amount claimed by Northbuild is not an amount able to be
characterised as an amount owed under the contract.
Freight charges
[65] The respondent has claimed from the applicant damages for breach caused by the
applicant‘s failure to pay freight required under the subcontract. The evidence is
clear that the tender for the work to be performed by Beyfield, which was accepted
by Northbuild, was on the basis that no allowance had been made for freight.
-- 14 of 16 --
15
[66] The issue concerning freight has been the subject of an adjudication made under the
Building and Construction Industry Payments Act 2004. The adjudicator held that
Northbuild was not entitled to its claim for freight.
[67] In those circumstances, it cannot be said that the claims for freight are bona fide.
The existence of a bona fide claim is a necessary element in the exercise of a right
to convert a security.10 This was dealt with in greater detail by Pembroke J when he
said:11
―[13] It is stating the obvious to say that a valid claim within the
meaning of clause 5.2 must be non-fraudulent. In that sense, it must
be a genuine claim. It adds nothing to say that it must be bona fide.
On the other hand, despite occasional suggestions to the contrary, I
am satisfied that a mere honest or bona fide ―belief‖ in a claim is
insufficient: cf Clough Engineering Ltd v Oil & Natural Gas
Corporation Ltd [2008] FCAFC 136 at [102]. The test could not be
subjective honesty or bona fides. More is required. A claim that is
irrational and misconceived could not justify recourse to the security
simply because the claimant had an honest, but wrongheaded, belief
in the correctness of its claim. Equally, it is inappropriate to insist
that the claim be "genuine and fair" as the plaintiff submitted. And it
is certainly not necessary that the claim be reasonable. Both would
impose requirements on the principal that could well be onerous and
productive of disputes.
[14] What is required in my view is an arguable claim - one that
is not specious, fanciful or untenable: Hughes Bros v Telede Pty Ltd
[(1989) 7 BCL 210] at 216 (Cole J). This is at least consistent with
decisions that have held that an ―entitlement‖ for the purpose of such
a clause will have been established even though there is a genuine
dispute or serious issue to be tried as to the existence of the right
which underpins the entitlement: Fletcher Construction v Varnsdorf
[[1998] 3 VR 812] at 821-3 (per Charles JA).
[15] For my part, I think that the test of what is a ―claim‖ for the
purpose of a contractual provision such as clause 5.2 is relatively
undemanding. An appropriate analogy is the criterion used for
determining whether there should, or should not be, summary
dismissal of a claim or proceeding: General Steel Industries v
Commissioner for Railways (1964) 112 CLR 125. Such an approach
would, in my view, reflect the commercial purpose and the allocation
of risk which I have explained.‖
[68] None of the claims made either for freight or under the provisions relating to the
employment of indigenous workers have been made bona fide.
[69] The finding that there is an absence of bona fides means that it is unnecessary to
consider further whether the provision of the contract in cl 5(e)(ii) extend beyond
the amounts that might be due under the contract through use of the words ―or
otherwise‖. This finding does not mean that there may not be another method by
which Northbuild can seek those payments.
10 Bachmann Pty Ltd v BHP PowerNew Zealand Ltd [1999] 1 VR 420.
11 FMT Aircraft Gate Support Systems v Sydney Ports Corporation [2010] NSWSC 1108 at [13]-[15].
-- 15 of 16 --
16
Order
[70] The applicant has been successful. The applicant is to bring in minutes of order. I
will hear the parties on costs.
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2014/012