Dadson & Anor v Lance Ryan Electrical Pty Ltd [2014] QDC 261
DISTRICT COURT OF QUEENSLAND
CITATION: Dadson & Anor v Lance Ryan Electrical Pty Ltd [2014] QDC
261
PARTIES: CHRISTOPHER ANDREW DADSON
(first appellant)
and
ZILZIE REAL ESTATE PTY LTD (ACN 105931931)
(second appellant)
v
LANCE RYAN ELECTRICAL PTY LTD
(ACN 122687272) AS TRUSTEE FOR THE RYAN
FAMILY TRUST
(respondent)
FILE NO/S: 19/2014
DIVISION: Civil
PROCEEDING: Appeal
ORIGINATING
COURT: Magistrates Court, Rockhampton
DELIVERED ON: 28 November 2014
DELIVERED AT: Brisbane
HEARING DATE: 10 July 2014
JUDGE: Reid DCJ
ORDER: Appeal dismissed. Second appellant to pay the
respondent’s costs of and incidental to the appeal.
CATCHWORDS: Appeal – electrical contract – credit of witnesses – findings of
magistrate – cogency of reasons – reliability of witnesses –
likelihood of events – quantum meruit – implied term to pay a
reasonable sum – executed consideration
Ashby v Slipper [2014] FCA FC15 considered
Fablo Pty Ltd v Bloore [1983] 1 Qd R 107 considered
Gino D’Alessandro Constructions Pty Ltd v Powis [1987] 2
Qd R 40 considered
Jones v Bradley [2003] NSWCA 81 considered
Pavey & Matthews Pty Ltd (1987) 162 CLR 221 considered
-- 1 of 26 --
2
COUNSEL: C. Tam for the appellants
J. Ahlstrand for the respondent
SOLICITORS: Hickey Lawyers for the appellants
Grant & Simpson Lawyers for the respondent
Introduction
[1] The second appellant was the second defendant in proceedings in the Magistrates
Court at Rockhampton. Although both defendants are named in the notice of appeal
as appellants, only the second defendant had any judgment against it. The claim
against the named first appellant was dismissed. The respondent was however
successful in its action against the second appellant (which I shall in such
circumstances hereafter refer to as “the appellant”). The respondent sought
damages for breach of contract or, alternatively on a quantum meruit basis for the
sum of $69,805.37 together with interest. It claimed such damages pursuant to three
separate agreements relating to a golf course at Zilzie which the appellant was
building. The plaintiff claimed:
1. $77,327.24 in relation to floodlighting of part of the golf course;
2. $7,477.83 in relation to installing lights for a “chip and putt” course;
3. $5,000.30 in relation to electrical work in the clubhouse and restaurant of the
course;
4. that only 20,000 of those sums had been paid, leaving a balance of
$69,805.37.
[2] The learned Magistrate gave judgment against the appellant for that amount,
together with interest in the sum of $14,989.95 and costs.
-- 2 of 26 --
3
[3] The first named appellant, Mr Dadson, was the director of the appellant. The claim
against him was, as I have said, dismissed on the basis that it was not proven that he
had contracted in his personal capacity. No issue arises with respect to that on the
appeal. It seems his being named as an appellant was in error. Nothing now turns on
that matter.
Pleadings
[4] At trial, the respondent relied on its amended statement of claim and the appellant
on its amended defence. In the pleadings it was not disputed that Lance Ryan, the
sole director of the respondent, was an appropriately qualified electrical contractor.
It was also admitted that the appellant entered into an agreement with the
respondent for the respondent to install floodlighting at the golf course and,
subsequently to perform other work. The respondent alleged:
1. that an oral quote was given to do the work for $100,000, including
providing cables, but that it would be less if the applicant purchased the
cable;
2. that its normal charge out rate for tradesmen of $52 plus vehicle costs would
be reduced to $45 per hour in respect of this initial floodlighting agreement.
[5] The terms of the agreement were in dispute, including the amount of any quote, as
was the issue as to whether the work was performed in accordance with the
agreement. Indeed, the appellant alleged it performed much of the work associated
with the floodlighting project itself to assist the respondent to reduce its costs. The
appellant alleged in its amended defence that the respondent initially gave an
-- 3 of 26 --
4
estimate of only $22,000 inclusive of labour and materials, to complete the
floodlighting project. The appellant also alleged:
1. in or about June 2008, the plaintiff issued a statement no. 124 for $28,128.74
for the work and that the appellant paid that sum to the respondent on or
about 2 June 2008;
2. in or about October 2008, the respondent and appellant agreed to vary the
cost of the initial floodlighting project to “the vicinity of 32 to 33 thousand
dollars”.
[6] Those matters were denied by the respondent. The respondent also alleged that
after sending an invoice for $77,327.74 Lance Ryan and Christopher Dadson spoke
about it. The respondent said it was agreed that payment of the invoice would be
delayed until the 2009/10 financial year. His evidence about this is contained at T1-
34: L38 ff. That agreement in respect of the payment of the invoice was denied by
the appellant. The appellant alleged that the real situation was that Mr Dadson
contacted Mr Ryan to dispute the tax invoice because it was some $44,327.74
greater than the quoted cost and that Mr Ryan said, “You should not have to pay it
… I am carrying it.” That conversation was disputed by Mr Ryan.
[7] The respondent alleged that after completing the floodlighting work, it was engaged
to perform work at the chip and putt course and at the clubhouse. It alleged that,
unlike the original floodlighting work, there was no agreement to discount the usual
hourly charge out rate as happened with the earlier agreement. The respondent
alleged such work as was required was performed and that it rendered invoices for
the amounts claimed.
-- 4 of 26 --
5
[8] It alleged all invoices were “fair and reasonable for the work carried out” or “a
reasonable charge for the work”. (See, for example, T1-23: L1-28; T1-25: L25 to
T1-26: L7; T1-81: L40 to T1-82: L10; and T1-93: L13-18).
[9] In its amended defence, the appellant alleges that the terms of the floodlighting
agreement included that the respondent would supply all material and labour, except
for lights and poles and some cable, and that it would charge out tradesmen at only
$25 per work hour and would not charge for the respondent’s apprentice. It was
also said to be a term that the respondent would dig the trenches and erect the light
poles, and also cover cables once they had been laid.
[10] The appellant’s pleading alleges that work progressed very slowly, that the
respondent’s employees and/or contractors were not licensed to operate machinery
of the nature required to complete the job and that the appellants in fact purchased a
cherry picker “to assist the (respondent) to erect the light poles and install the
lights”. That cherry picker, it was alleged, was damaged by the respondent’s
employees filling it with petrol instead of diesel and on another occasion the
respondent’s employees and/or contractors bogged it.
[11] The appellant alleged that as a result if performed work “to assist the (respondent)
and to reduce costs”. The work the appellant said it did included digging trenches,
erecting some 96 light bulbs, assisting to lay cables and to pour concrete,
backfilling, and attaching fittings and lights to the poles. It was alleged by the
appellant that the respondent:
dug no cables;
-- 5 of 26 --
6
erected no light bulbs;
twice poured concrete incorrectly, damaging cable and requiring the appellant
to dig up the cable and concrete and assist the respondent to relay it;
did not refill trenches;
mounted three lights which fell off and provided unsuitable light fittings,
resulting in the appellant designing, supplying and installing heavier fittings;
mounted only 15 lights, whereas the appellant said it mounted 80 lights.
[12] Despite the appellant’s allegation that the respondent had estimated the cost of the
completed works was only $22,000 (including all cable), the respondent, in or about
June 2008, was sent an invoice by the appellant, being invoice no. 124, in the sum
of $28,128.74. More surprisingly still, the appellant said it paid that invoice in full
on about 2 June. Mr Ryan had said that invoice was to pay only for the cable to be
used (see T1-19: L5-30).
[13] Remarkably, especially in view of what the appellant says occurred as detailed in
[11] hereof, the appellant says the parties then agreed to vary the cost of the
floodlights project to “32 to 33 thousand dollars” in or about October 2008.
[14] The applicant alleges the work performed by the respondent was defective and/or
not fit for its purpose in a number of ways.
-- 6 of 26 --
7
[15] The respondent delivered its invoice for $77,327.24 on or about 14 December 2008.
$20,000 of that was paid, and, as I have said Mr Ryan says he had the conversation
with Mr Dadson as outlined in [6] hereof.
[16] The respondent says that the appellant also breached of the agreements with respect
to the chip and putt course and work performed in the clubhouse by not paying
invoices rendered for that work.
[17] The appellant alleged that the agreement with respect to the clubhouse and
restaurant was not with it but with another company, Great Barrier Reef Golf
Resorts Pty Ltd, which it is said owned and operated the complex. Mr Dadson was,
it is said, also the agent of that company. There appears nothing to indicate this was
made known to the appellant and it was not an issue raised on the appeal. The
appellant alleged in its defence that all of the amounts claimed were not fair and
reasonable because:
the work was defective and not in accordance with the agreements;
the agreement charge out rate was only $25 per hour for electricians and
nothing for apprentices;
the hours claimed were not worked and the materials claimed were not used to
complete the subject agreement.
[18] In such circumstances, the appellant denied the respondent was entitled to the sum
claimed.
-- 7 of 26 --
8
[19] The appellant also alleged with respect to the chip and putt agreement that the lights
were to be connected to a single switching point that could only be operated from
the clubhouse, although they were nevertheless to be connected to an existing power
supply in the irrigation shed. It was said that to utilise the switch in the shed was a
safety risk.
[20] The applicant alleged that, because of these numerous defects in the work the
respondent performed, the appellant had suffered loss particularised as follows:
1. $4,147 to replace three damaged floodlights;
2. $7,195.54 to repair cable damage by the respondent;
3. $6,490 to rewire lights to a central switching point in the clubhouse.
[21] These sums were claimed by way of counterclaim.
Judgment
[22] The trial was conducted over two days in August 2013, and judgment was delivered
on 12 February 2014. The learned Magistrate:
(i). found that although Mr Dadson contracted with the respondent for it to
perform work, that work was for the appellant Mr Dadson was only the
appellant’s agent. Consequently the claim against Mr Dadson personally
was dismissed (see paras 19 and 21 of the judgment);
(ii). said that on “both parties” version the (respondent) was using this job to try
and get significant long term work on an associated housing development”,
(as to this see T1-15: L20 ff where he said that was “a considerable carrot…
for me to deliver them a fair and reasonable job”);
-- 8 of 26 --
9
(iii). noted that Mr Dadson answered, when asked, why he had paid $28,128, as
he agreed he had, in June 2008, which was a sum in excess of what he said
was the quote for $22,000 to perform the contract, had said:
“because I had agreed that he said 20 to 25, right. So 28000,
right was around 25000 plus GST. And I didn’t see a
problem with that. I’ve never been a mean man in any case
and we was just dealing with Lance which was a friend at
that time.”;
(iv). found that in June 2008, when the invoice was delivered no actual work had
then been performed by the respondent on the site and that the invoice for
$28,000 was for the cost of cable required from Olex Cables for some
$25,806.78 plus GST (curiously a total of $28,387.45, slightly more than the
invoiced sum). This was of course consistent with Mr Ryan’s evidence
referred to in [12] hereof. His Honour referred to the fact that when the fact
that no work had then been performed was pointed out to Mr Dadson, he
said, “I just pay things, you know, like I was asked to pay that and I just paid
it”;
(v). found the respondent’s invoice for $77,372.74 was issued to “Zilzie Bay
Real Estate” on 14 December 2008;
(vi). found the appellant paid the initial invoice of $28,128 on 18 June 2008, and
then later paid a subsequent sum of $20,000;
(vii). found the appellant’s payment of these two sums was “inconsistent” with his
evidence that the contract was for a fixed sum, originally $22,000 and then
no more than $33,000;
(viii). found the explanation of Mr Dadson as to why the respondent would
perform all of the work at a loss (because the hourly rate that Mr Dadson
says the respondent agreed to was less than the rate of $30 per hour he said
he was paying tradesmen) was implausible. He said it was not supported by
-- 9 of 26 --
10
the evidence, in circumstances where no satisfactory evidence of the real
likelihood of further housing work becoming available had been given, to
paraphrase the Magistrate’s findings at paras 35 and 36 of the judgment. I
note, by consent, Mr Ryan’s evidence that I have referred to at [12] hereof;
(ix). referred to the evidence of a Mrs McLennan, a designer and estimator who
did work for Mr Dadson. Although she was not present when the
discussions about the agreements were conducted, she said the respondent
was engaged by her to do work on three houses, presumably being built by
the appellant or another of Mr Dadson’s companies, because “she was told
to do so by Mr Dadson because he told her he owed $70,000 to Mr Ryan for
the lights for the clubhouse”. She thought this conversation was in about
July 2009. The learned Magistrate found this evidence was “consistent with
the (respondent’s) version” (see paras 38 to 40 in the judgment);
(x). found the appellant’s in paying both the $28,128 and the subsequent
$20,000, significantly more than the total sum Mr Dadson says he had
agreed to pay, was “more consistent with the version of the (respondent)”;
(xi). said that a former employee of the appellant, Mr Smith, was present when
Mr Dadson phoned Mr Ryan after receiving the invoice for $77,327.74. Mr
Smith said in giving his evidence that the phone was put onto speaker mode.
The magistrate said when Mr Dadson ‘challenged the amount of the invoice
that Mr Ryan, placated Mr Dadson by saying ‘I’m carrying it.’” The learned
Magistrate found this was “consistent with the (respondent’s) version of
what was agreed”. This is clearly a reference to the fact, as I earlier stated,
that the respondent’s case was that after sending that invoice for $77,327.44
Mr Ryan agreed that payment of the invoice would be delayed until the
-- 10 of 26 --
11
2009/10 financial year. It was in that sense that Mr Ryan said he was
“carrying it”;
(xii). referred to the explanation Mr Dadson gave of his understanding of the fact
that the respondent would “carry” the invoice. Mr Dadson said in his
evidence, in a passage referred to by the learned Magistrate that “we thought
it was some sort of tax lurk … that he was going to claim tax for a non-
payment or … I don’t … I couldn’t work that out”;
[23] In such circumstances the learned Magistrate unsurprisingly found the respondent’s
version more probable than the appellant’s. In doing so he particularly referred to:
(a) the applicant’s having paid $48,128, considerably more than what it
alleged was the agreed price;
(b) Mr McLennan’s evidence that Mr Dadson used the appellant for
work on some houses, as he owed $70,000 for “lights for the golf
course”;
(c) a statement of Mr Dadson that he thought he had paid for work under
the club house agreement when he paid the $20,000 (which appears
implausible as this work was performed after the initial invoice for
$77,327.24 had been sent).
(d) the inherent implausibility the plaintiff would charge out his staff at
less than he paid them;
(e) the implausible explanation of Mr Dadson that he believed the
respondent issued the invoice for $77,327.44 “as a tax lurk”.
-- 11 of 26 --
12
[24] Each of those factors are compelling and there seems little reason to doubt the
Magistrate’s acceptance of them as justifying his finding that the respondent’s case
was more probable than the appellants.
[25] In such circumstances the learned Magistrate, consistently with his understanding of
the evidence of Mr Ryan, found:
1. there were three separate agreements;
2. the golf course agreement was for a quoted price of $100,000 (I shall refer to
this issue later);
3. no separate quote was given for the chip and putt agreement or for the club
house agreement;
4. those two agreements did not involve any reduction in the respondent’s
charge out rate such as applied with respect to the golf course agreement;
5. that some relatively minor differences between the respondent’s invoices to
the applicant and invoices to the respondent from its suppliers are explained
by mark-ups and some differences in the precise use of goods, and also
possibly by the respondent’s use of old prices entered into its computer, but
that the content of the invoices was not “called into question”. The learned
Magistrate accepted there were such discrepancies, but said he found this
“unsurprising” and accepted Mr Ryan’s evidence concerning material
invoiced;
6. that evidence called by the appellant as to alleged inaccuracies in the
respondent’s worksheets was vague and, I infer, of very limited worth.
[26] The Magistrate also accepted the evidence of Mr Preston, an electrician who was
primarily responsible for carrying out work for the respondent at the golf course, as
-- 12 of 26 --
13
to the accuracy of the information contained in the worksheets which set out labour
utilised by the respondent. Mr Preston had said in evidence that they were normally
filled out daily.
[27] The learned Magistrate then turned to the applicant’s counterclaim. He noted
invoices of Jeff Bleney, an electrician, but noted these were dated 14 and 29 July
2011. Some two to two and a-half years after the respondent had completed its
work in late 2008 and early 2009. In circumstances where Mr Preston, whose
evidence he accepted, said that “at handover he believed that all the lights worked”,
the learned Magistrate found that there was no direct connection between the
alleged faults that Mr Bleney repaired and the respondent’s work upon completion
of the contract. Any prior faults had, the learned Magistrate found, been corrected
and repaired it (see T1-16: L23ff). Mr Preston said they found a faulty cable when
the job was tested on completion. I note also the evidence of Mr Ryan (T1-34: L38
ff) that at no time did Mr Dadson on behalf of the appellant raise objection to the
work the respondent had done.
[28] The Magistrate also accepted the evidence of Mr Preston as to the use of the
existing switchboards in the pump house and of the switching used to activate the
floodlights. He noted that although the applicant sought to suggest use of the pump
house was a safety risk, no qualified person gave such evidence. Instead the
appellant sought to rely on the evidence of Mr Dadson’s son. The Magistrate found
“it more likely than not that there was no specific agreement as to where the lights
would be controlled from.”
[29] In such circumstances, the counterclaim was rejected.
-- 13 of 26 --
14
[30] The learned Magistrate lastly referred to the fact that the respondent’s claim was in
contract and alternatively on a quantum meruit in the same amount. He found:
1. the respondent did work for the appellant;
2. the appellant had requested such work;
3. he accepted the evidence of Mr Ryan and Mr Preston on the materials
provided and later supplied and rejected the appellant’s counterclaim;
4. that in the circumstances, alternative to its contractual claim, the respondent
was entitled to succeed on a quantum meruit.
Appeal
[31] The appellant’s grounds of appeal are that the learned Magistrate:
1. took a wrong approach to the evidence and to fact finding in that he:
(a) did not give any proper regard to the standard of proof required in
civil proceedings;
(b) did not have proper regard to significant conflicting and
contradictory evidence;
(c) unduly rejected unchallenged evidence;
(d) unreasonably rejected evidence
(e) drew inferences which were unreasonable, uncertain or not
reasonably open;
2. erred in law in allowing the quantum meruit claim where the respondent
“did not elect to terminate a valid enforceable and subsisting contract”, or,
alternatively;
3. did not have any proper regard to evidence of defective work and delay in
allowing and quantifying the claim for quantum meruit;
-- 14 of 26 --
15
4. gave inadequate reasons;
5. did not have any proper regard to the evidence.
[32] Both parties provided extensive written and oral submissions.
[33] In support of the first ground, the appellant’s counsel submitted that the Magistrate
arrived at the conclusion that the respondent’s version was “more probable” than the
appellant’s (para 42 of the judgment) erroneously and in a way that was “unclear on
the face of his judgment”. He submitted the magistrate in effect “chose between
guesses” so that his findings were not “definite and reasonable”. He submitted the
learned Magistrate “simply made a choice between conflicting inferences and by
that process he engaged in conjecture”. (See [19] and [24] of the appellant’s written
submissions).
[34] I have earlier set out the judgment and the reasons of the learned Magistrate in quite
significant detail because, in my view, they clearly indicate why I do not accept
those submissions. In my view the Magistrate gave careful, detailed and cogent
reasons as to why he accepted the evidence of Mr Ryan and Mr Preston and
correspondingly gave careful and detailed reasons why he did not accept the
evidence of Mr Dadson. It is perhaps unfortunate that in paragraph 42 of the
judgment he said, “On balance I find the (respondent’s) version of what was agreed
more probable than the (appellant’s) version.” That might be thought by some to
suggest that his finding was a finely balanced exercise, perhaps giving tacit support
to the applicant’s counsel’s submission that he “chose between guesses”. A careful
reading of the whole of the judgment however suggests to me that in fact his
findings were not finely balanced and were in fact strongly made after careful
-- 15 of 26 --
16
examination of the evidence and of the likelihood of each of the two parties’
versions.
[35] The appellant’s counsel challenged a number of factual findings made by the
magistrate, namely:
“(a) that it was inherently implausible that Mr Ryan charged his
staff out at rates less than he paid them.
(b) that Mr Dadson’s explanation for paying $48,129 was
‘inconsistent’ with the contract being ‘one agreement’ for a
‘fixed sum’ and was ‘considerably more’ than Mr Dadson
said the ‘agreed price was’.
(c) that Mr Ryan’s statement that he was ‘carrying’ the invoice
for $77,327.74 was ‘consistent’ with Mr Ryan’s version of
‘what was agreed’.
(d) that he accepted Mr Ryan’s explanation of the ‘material
invoiced’.
(e) that he accepted Mr Preston’s explanation of how the
worksheets were produced.”
[36] In respect of the first of these challenges, the appellant relies on the suggestion the
respondent may have so charged his staff in order to win further work I have
referred already to Mr Ryan’s evidence about this at T-15 of the transcript. . The
learned Magistrate’s reference to the tenuous possibility of such further work (he
said no evidence was given by Mr Dadson that he or the appellant were in fact
intending to build those houses) but said there was “some agreement that the
possibility of the ongoing electrical work was a factor”.
[37] In my view, in circumstances where Mr Dadson’s evidence was not accepted for a
significant number of other reasons also, he was entitled to find such a suggestion
“inherently implausible”. It is noted also that this suggestion was not agreed to by
Mr Ryan. Furthermore, Mr Ryan said only that it was a “carrot” to charge a “fair
-- 16 of 26 --
17
and reasonable job”. He did not say it was a sufficient carrot to him to consciously
loose money on this not insignificant job and I agree that such a suggestion was
“inherently implausible”.
[38] In considering the second of the challenged factual challenges, it is also important to
understand that the learned Magistrate’s finding that paying $48,128 was “more
consistent with the version of the plaintiff” and that it was “inconsistent with (Mr
Dadson’s) evidence the contract for all the work done was for a fixed sum” (to use
the words in para 34 of the judgment) were findings in circumstances where the
allegedly fixed sum contract was for “originally $22,000 but in any event no more
than $33,000”, a significantly more limited sum than the amount in fact paid. It is
because the sum actually paid was so far in excess of the sum Mr Dadson says was
agreed that the learned Magistrate made the finding he did, that the payment was
inconsistent with the alleged agreement.
[39] There can be no criticism of his doing so. Indeed, having read the material such a
conclusion was almost inevitable. The explanation offered by Mr Dadson bordered
on fanciful.
[40] So too the criticism of the learned Magistrate’s finding that “the statement by
Mr Ryan that he was carrying the invoice in the sum of $77,327.74 is consistent
with the (respondent’s) version of what was agreed” is unfounded. Mr Ryan’s
evidence (at T1-34: L38 ff) was that after he had sent the invoice for $77,327.74 to
the defendant he was contacted by Mr Dadson who he said could not then pay it.
Mr Ryan agreed to defer payment until the appellant could pay it in the 2009/10
year. Mr Dadson accepted Mr Ryan had said he would “carry it” but, as the
-- 17 of 26 --
18
Magistrate found, his explanation that he thought it did not need to be paid and that
it was issued as some sort of tax lurk was entirely implausible. I note also that Mr
Ryan gave evidence that Mr Dadson in fact said the invoice was “fair and
reasonable for the amount of work you’ve done”.
[41] Those matters, together with the learned Magistrate’s appropriate reliance on other
matters set out earlier in these reasons and largely but not fully gathered together in
paragraph 42 of the judgment clearly justified the Magistrate’s in rejecting the
evidence of Mr Dadson and accepting that of Mr Ryan.
[42] So too was he justified in accepting the evidence of Mr Preston that worksheets
were completed, usually on the day such work was performed. Such credit findings
also informed the Magistrate’s decision in accepting the evidence of Mr Preston and
Mr Ryan as to the materials used. The Magistrate’s approach to that issue,
accepting that there were some inaccuracies in precise quantities and/or prices but
finding the invoices were generally an accurate reflection of the work done and
materials supplied was entirely understandable.
[43] I cannot accept the appellant’s counsel’s submission that the observations of
Mansfield and Gilmour JJ in Ashby v Slipper [2014] FCA FC15 at [62] that
inferences should be “affirmative conclusions from circumstances otherwise proved
in evidence” supports the applicant’s case that the contract price for the works was
$33,000 which has been discharged by payment in fact of $48,128.74) and that the
work was defective. Rather, such an approach in my view underscores the findings
the Magistrate did in fact make.
-- 18 of 26 --
19
[44] The submission that the Magistrate’s approach to fact finding was wrong and
unsupported by the evidence is untenable. I conclude rather that the applicant
version of events was properly rejected by the Magistrate for valid and cogent
reasons set out in the judgment.
[45] I might add that in his submissions counsel for the applicant does not address the
Magistrate’s reliance on the evidence of Ms McLellan that she used Mr Ryan to do
electrical work on houses she was designing for the defendant (or perhaps one of Mr
Dadson’s associated companies) because, she said, Mr Dadson had told her to use
Mr Ryan because he owed Mr Ryan $70,000 for lights for the golf course. That
seems to have been a significant factor relied on by the Magistrate. That he did so
is not surprising. That it was not referred to in the applicant’s written submissions
is perhaps also not surprising. It is difficult to imagine how acceptance of that
evidence could not be seen to be almost entirely undermining of the credibility of
Mr Dadson and so also undermining of what the applicant’s counsel described as
“the three pillars” of the appellant’s case namely:
1. that the contract price for all the works was $33,000;
2. the applicant paid Mr Ryan about $48,000 for the contract works; and
3. Mr Ryan’s work was defective and was not rectified.
[46] In my view her evidence, properly accepted by the Magistrate, is entirely
inconsistent with those pillars. I note too, it is generally consistent with the evidence
of MR Ryan (of T-34) I referred to earlier that Mr Dadson thought the invoice fair
and reasonable.
-- 19 of 26 --
20
[47] I turn to ground four of the notice of appeal – namely that the Magistrate’s reasons
were inadequate – because it is clearly related to the first ground.
[48] For the reasons I have already set out it seems to me the learned Magistrate has very
adequately exposed his reasons for resolving the matter as he did. He adequately
explained why he accepted the evidence of Mr Ryan, Mr Preston and Ms McLellan
and, correspondingly, why he rejected the evidence called in the appellant’s case.
There was a strong body of evidence on which he relied in coming to the
conclusions he did. There can be no proper basis for the appellant feeling any
injustice at the decision. The magistrate did not, as I have said, rely on “bald
conclusionary statements” (to adopt the words of Santos JA in Jones v Bradley
[2003] NSWCA 81 at para [64]). His Honour gave a very considered analysis of
the competing evidence and adequately explained his reasons for accepting the
respondent’s case and rejecting that of the appellant. I have sought to demonstrate
that in my analysis of the judgment and my remarks about the first ground of
appeal.
[49] In such circumstances I conclude there is no force in the submission that the reasons
were inadequate.
[50] The remaining grounds concern the appellant’s submission about the quantum
meruit claim. In order to consider these grounds it is in my view necessary to first
consider a matter that emerged only during the hearing of the appeal. I have said
that the learned Magistrate accepted that Mr Ryan on behalf of the respondent and
Mr Dadson on behalf of the appellant came to an agreement for the plaintiff to
perform floodlighting work on the basis of a “quote of $100,000”. This was the
-- 20 of 26 --
21
basis on which the respondent’s claim in contract was formulated in the pleadings.
It was pleaded that the quote “was for $100,000 (including cable) which would be
less if (Mr Dadson) purchased the cable”. In fact, as I have set out, the appellant
paid $28,128 in June 2008 before work had begun to purchase at least some of the
cable.
[51] The appellant was said to have accepted the quote so that the parties formed a
contract. The appellant disputed the quote of $100,000 but said there was an
agreement the work was to be completed for $22,000, later increased to $32-
$33,000, and this was to include the cost of cable (see para 3(b)(iii) and 7 of the
appellant’s amended defence). When I asked counsel for the respondent to take me
to the evidence of Mr Ryan as to the agreement he referred me to T1-12 L 25.
There however Mr Ryan said;
“I indicated to Chris (Dadson) just verbally… just on the rough with
my experience that typically a job like such would be in and
around… between $100,000 and $150,000 so to speak.”
[52] It does not seem to me that Mr Ryan at any time gave evidence of a binding
agreement that the appellant would pay $100,000 for the initial flood light contract.
That was however the basis on which the judgment proceeded. It appears to me that
the learned Magistrate was in error in so concluding. I suspect that this error can be
explained because both parties accepted that there was a contract between them but
the respondent alleged, as I have said, that the agreed price was much less – initially
$22,000 and then increased to $32-33,000.
[53] Because of the respondent’s alternative claim that it was entitled to recover the
reasonable costs of work on a quantum meruit the learned Magistrate did however,
turn his mind to the question of the reasonableness of the invoice and the value of
-- 21 of 26 --
22
the work provided by the respondent. At paragraph 44 and following of the
judgment the learned Magistrate considered the invoices and work order sheets
which the respondent produced and which became exhibits at the trial. I have
referred to many of his findings about that already.
[54] His Honour accepted the evidence, as I have said, of Mr Ryan concerning material
invoices and that of Mr Preston concerning the daily work sheets which evidenced
the labour utilised in carrying out the jobs. He accepted the work was provided at
the appellant’s request. In circumstances where he “accepted the evidence of
Mr Ryan and Mr Preston on the materials provided and the labour supplied and
rejected the (appellant’s) counterclaim which in part at least goes to a claim that he
work was defective” he found for the plaintiff on the alternative claim for a
quantum meruit also.
[55] The appellant’s counsel submitted:
1. that there was no or no sufficient evidence that the reasonable cost of the
work, after allowing for $48,128 already paid, was $69,805.37; and
2. in any case there was no evidence that the contract was discharged so the
respondent was thus not entitled to sue on a quantum meruit, there being a
valid contract.
[56] This latter argument can I think be readily disposed of. Claims in quantum meruit,
including in respect to building contracts, have been said to arise only if any
contract between the parties has been discharged or is otherwise unenforceable.
Such matters were discussed in Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR
221 and, prior to that, in Fablo Pty Ltd v Bloore [1983] 1 Qd R 107 and Gino
-- 22 of 26 --
23
D’Alessandro Constructions Pty Ltd v Powis [1987] 2 Qd R 40. That latter
decision, was consistent with the earlier judgment (also written by McPherson J)
was specifically approved by the High Court in Pavey & Matthews Pty Ltd v Paul
(supra). Whilst it can be accepted a party cannot sue on a quantum meruit if there is
a valid contract, I think the learned Magistrate was referring, in allowing the
respondent’s alternative claim, to the ability of a party to recover in debt upon an
executed consideration – such of might arise where work had been completed –
independent of the oral contract.
[57] An alternative, and perhaps better, approach where there was no specific agreement
as to price (as I conclude was the case here) but was told a mere estimate that the
work would cost between $100,000 to $150,000, that there was an implied term that
the respondent would be entitled to be paid a reasonable sum for the work
performed. In either case – whether recovering a reasonable sum as an implied term
of the contract or recovering a reasonable sum as a debt due upon an executed
consideration in circumstances where there was no specific agreement as to price,
the issue was the same; what was the reasonable cost of the work which the
respondent performed?
[58] Issues of the reasonable cost of the respondent’s work were significantly addressed
in the evidence. They were summarised in the respondent’s counsel’s witness
submission on the appeal. The Magistrate accepted, consistently with the evidence
called in the respondent’s case that in regard to the flood lighting agreement the
agreed charge out rate by tradesman was $45.00 per hour but on the two subsequent
agreements was $52.00 per hour.
-- 23 of 26 --
24
[59] Furthermore the evidence of Mr Ryan and Mr Preston, accepted by the Magistrate,
was that:
(a) the respondent and its employees were not responsible for any delays
(see T1-14 L 20);
(b) the appellant made no complaints to the respondent or its employees
about any defects with respect to any of the three agreements (T1-15
L 35/40 and T1-34 L1 ff) and on testing lights were operational (T1-
34 L 5-15);
(c) the respondent paid electricians $30 per hours and apprentices
between $15 and $17 per hour (T1-14 L 30-40);
(d) the respondent applied an 11% mark up on the cost of cabling (T1-20
L1-15);
(e) work orders relating to the flood lighting agreement indicated a total
of 1052 hours of work had been performed, but only 870 hours were
charged to the applicant (T1-20 L 35 – T1-25 L 20, L 5/45 and
Exhibit 3);
(f) the material invoices (Exhibit 4) supported materials charged on tax
invoice 156 which was Exhibit 8 at the trial (T1-28 L 1 – T1-32 L
20);
(g) similarly work orders (Exhibit 5) relating to the chip and putt
agreement (T1-35 L 25 – T1-37 L 30) and the club house agreement
(T1-39 L45 – T1-42 L 10) supported the charged amounts. Indeed
with respect to the club house agreement, such work orders showed
104 hours completed work, but only 30 hours were charged;
(h) material invoices (Exhibit 6 and 8 respectively) for those contracts
together with the work orders support tax invoices for $7,077.83
-- 24 of 26 --
25
(Exhibit 12) and $5,030.30 (Exhibit 13, for those two subsequent
agreements).
[60] That evidence must also be seen against the evidence of Mr Ryan that Mr Dadson
said the invoice of $77,327.74 was “fair and reasonable” and that of Ms McLellan
that I have referred to already. She said Mr Dadson acknowledged to her that he
owed the respondent “$70,000 for the lights for the golf course”. (T1-96: L 40).
This evidence was accepted by the learned Magistrate, as he was entitled to do. Her
cross-examination involved no more than suggesting that Mr Dadson at no time said
that to her. There was not any suggestion as to why she might be mistaken or what
may have motivated her to lie if she was doing so. She gave some particularity in
her evidence. For example, she said she would have preferred to use another
company Kepellec, whom she had used previously. Not to have accepted her
evidence, which very severely undermined the appellant’s case, might be said to
have been perverse. It is hardly surprising the Magistrate relied on it.
[61] Against the background that the learned Magistrate accepted the evidence of Mr
Ryan and Mr Preston and rejected the evidence of Mr Dadson, which appeared to be
strongly inconsistent with a number of uncontradicted facts, it might be said that her
evidence gave very strong support not only to the Magistrate’s conclusions about
credit, but also strongly supported his finding that the sum of $69,805.37 was
recoverable as a reasonable sum for the work performed. Mr Dadson’s statement to
her, which she recounted to the court, can be seen as an admission by him that the
appellant owed such a sum to the respondent.
-- 25 of 26 --
26
[62] In such circumstances, I find that there is no substance to the appellant’s grounds of
appeal and the appeal is dismissed.
-- 26 of 26 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2014/261