CMF Projects Pty Ltd v Riggall & Anor [2014] QDC 90
DISTRICT COURT OF QUEENSLAND
CITATION: CMF Projects P/L v Riggall & Anor [2014] QDC 90
PARTIES: CMF PROJECTS PTY LTD (ACN 114 539 212)
Respondent/plaintiff
v
BRIAN NOEL MANSON RIGGALL
applicant/first defendant
and
JANE REIMAN RIGGALL
applicant/second defendant
FILE NO/S: BD4085 of 2013
DIVISION: Civil Applications
PROCEEDING: Application
ORIGINATING
COURT: Brisbane
DELIVERED ON: 24 April 2014
DELIVERED AT: Brisbane
HEARING DATE: 15 April 2014, written submissions to 16 April 2014
JUDGE: Andrews SC DCJ
ORDER: 1. That the amended statement of claim and
paragraphs 4(d), 10 and 11 of the reply and 1, 3(b)
and 4 of the answer to the amended counter-claim
be struck out.
2. That the plaintiff pay the defendants’ costs of the
application on the indemnity basis.
3. That with respect to the order for costs the
plaintiff have liberty within seven (7) days to make
submissions on notice to the defendants seeking to
set aside the order for costs and seeking an
alternative order for costs.
CATCHWORDS: BUILDING ENGINEERING AND RELATED
CONTRACTS – REMUNERATION – STATUTORY
REGULATION OF ENTITLEMENT TO AND RECOVERY
OF PAYMENT – DOMESTIC BUILDING CONTRACTS
ACT 2000 ss 55(2), 55(3), 55(4) – effect on other remedies –
where building contractor did building work pursuant to cost
plus contract – where contract a regulated contract – where
contract did not contain a fair and reasonable estimate by the
-- 1 of 14 --
2
building contractor of the amount which the building
contractor was likely to receive under the contract as required
by s 55(3) – whether builder may recover on quantum meruit
basis from District Court
ESTOPPEL – BY REPRESENTATION – EFFECT OF
STATUTORY PROHIBITION AGAINST CONTRACTING
OUT – where builder alternatively claims that owners
estopped from disputing that builder’s quantum meruit claim
may be brought in the District Court – whether s 55 confers
rights which it is in the public interest to maintain – where s
93(2) prohibits contracting out of the Act – whether s 93(2)
relevant to whether owner estopped from disputing builder’s
quantum meruit claim – whether builder confined to claim in
tribunal under s 55(4)
PRACTICE AND PROCEDURE – Pleadings – whether to
strike out statement of claim and parts of reply and answer –
where plaintiff seeks to allege that monies claimed are a debt
due upon a fully executed contract rather than money payable
pursuant to contract – whether plaintiff obliged to plead that
contract fully executed or whether defendant obliged to plead
that the contract was not fully executed – UCPR r 153 –
whether the allegation that contract was fully executed is a
condition precedent for the case of the plaintiff which may be
implied in the plaintiff’s pleading
PRECEDENTS – stare decisis – whether statement in a
judgment of the Supreme Court was obiter dictum or ratio
decidendi – where obiter dictum on interpretation of statute –
whether appropriate to follow the obiter dictum without
reconsidering the point
Domestic Building Contracts Act 2000 ss 3, 30, 55(2), 55(3),
55(4), 84 and 93
Property Agents and Motor Dealers Act 2000 (Qld)
Queensland Building Construction and Commission Act 1991
Uniform Civil Procedure Rules 1999 (Qld) r 171
Beckford Nominees Pty Ltd v Shell Co of Australia Ltd (1987)
73 ALR 373
Day Ford Pty Ltd v Sciacca [1990] 2 Qd R 209
Gemini Nominees Pty Ltd v Queensland Property Partners
Pty Ltd [2008] 1 Qd R 139
Keen v Holland [1984] 1 WLR 251
Kok Hoong v Leong Cheong Kweng Mines Ltd [1964] AC
993
Maritime Electric Co v General Dairies Ltd [1937] AC 610
-- 2 of 14 --
3
Metropolitan Health Service Board v Australian Nursing
Federation [2000] FCA 784; (2003) 176 ALR 46
Neumann Contractors Pty Ltd v Traspunt No. 5 Pty Ltd
[2011] 2 Qd R 114
Pavey & Matthews Pty Ltd (1987) 162 CLR 221
Plaintiff S157/2000 v Commonwealth of Australia (2003) 211
CLR 476
Sultana Investments Pty Ltd v Cellcom Pty Ltd (No 1) [2008]
QCA 357; [2009] 1 Qd R 589
Telstra Corp Ltd v Treloar (2000) 102 FCR 595; [2000] FCA
1170
COUNSEL: G I Thomson for the applicant/defendants
G Coveney for the respondent plaintiff
SOLICITORS: H W L Ebbsworth for the applicant/defendants
Arrow Law for the respondent/plaintiff
Issues
[1] The defendants apply to strike out an amended statement of claim and, to prevent an
estoppel being raised, some parts of the reply and some parts of the answer to an
amended counterclaim. As well, the defendants require particulars.
[2] The plaintiff is a builder. The defendants are home owners. The home owners
requested that the plaintiff renovate their house. The builder and the home owners
reached an agreement which was a “cost plus contract” within the meaning of the
Domestic Building Contracts Act 2000 (“the DBCA”). The agreement was also a
“regulated contract” as that term is defined in the DBCA and it was not signed by
the home owners and it did not itself contain any estimate of the amount which the
builder was likely to receive under the agreement.
[3] A consequence of that is that the builder “can not enforce the contract against the”
home owners.1The builder maintains that its amended statement of claim does not
seek to enforce the contract, (the amended statement of claim does seek to enforce
the contract) that it has pleaded a claim in debt (it has not). The builder pleaded an
alternative claim in quantum meruit and argues that it may do so in this court
notwithstanding the wording of DBCA s 55 (3) and (4). (It may not).
Statutory framework
1 DBCA s 55(3).
-- 3 of 14 --
4
[4] For understanding arguments raised in this application, relevant sections of the
DBCA are:
3 Purpose of Act
The purpose of this Act, in regulating domestic building contracts, is
–
(a) to achieve a reasonable balance between the interests
of building contractors and building owners; and
(b) to maintain appropriate standards of conduct in the
building industry.
…
30 Contracts must be signed
A regulated contract has effect only if it is signed by the building
contractor and building owner…
55 Cost plus contracts
…
(2) a building contractor must not enter into a cost plus contract
that would be a regulated contract unless the contract
contains a fair and reasonable estimate by the building
contractor of the total amount the building contractor is likely
to receive under the contract.
Maximum penalty – 100 penalty units.
(3) if a building contractor enters into a cost plus contract in
contravention of this section, the building contractor can not
enforce the contract against the building owner.
(4) however, the tribunal may, on an application made, as
provided under the QCAT Act, to the tribunal by the building
contractor, award the building contractor the cost of
providing the contracted services plus a reasonable profit if
the tribunal considers it would not be unfair to the building
owner to make the award.
…
84 Right of building contractor to recover amount for
variation
(1) This section applies if –
(a) the building contractor under a regulated contract
gives effect to a variation of the contract; and
(b) the variation consists of –
(i) an addition to the subject work…
(2) If the variation was originally sought by the building owner,
the building contractor may recover an amount for the
variation –
(a) only if the building contractor has complied with
sections 79, 80, 82 and 83; or
(b) only with the tribunal’s approval given on an
application made, as provided under the QCAT Act,
to the tribunal by the building contractor…
(4) the tribunal may approve the recovery of an amount by the
building contractor for a variation only if the tribunal is
satisfied that –
(a) either of the following applies –
-- 4 of 14 --
5
(i) there are exceptional circumstances to warrant
the conferring of an entitlement on the
building contractor for recovery of an amount
for the variation;
(ii) the building contractor would suffer
unreasonable hardship by the operation of sub-
section (2)(a)…; and
(b) it would not be unfair to the building owner for the
building contractor to recover an amount…
93 Contracting out prohibited
(1) a domestic building contract is void to the extent to which it –
(a) is contrary to this Act; or
(b) purports to annul, exclude or change a provision of
this Act.
(2) an agreement (other than a domestic building contract) is
void to the extent to which it seeks to exclude, change or
restrict a right conferred under this Act in relation to a
domestic building contract…”
Does the amended statement of claim contain a claim under a contract for money
owing?
[5] The answer to the question posed immediately above has become relevant only to
costs of the home owners’ application to strike out. It became clear in the builder’s
counsel’s written submissions2 delivered minutes before the application was heard
and crystal clear in his oral submissions that the builder’s claim for $182,252.00 is
not a claim for moneys payable pursuant to contract and that the proceeding “is not
brought upon or to enforce the contract”.3
[6] The home owners’ submissions in support of their application to strike out the
statement of claim were clearly premised upon the home owners’ assumption that
the statement of claim included a claim for money owing pursuant to contract, that
is to say a claim “brought upon or to enforce the contract”. It did not become clear
that the builder disavowed such a basis until one read the builder’s counsel’s
submissions.
[7] Before the statement of claim was amended, it contained no quantum meruit claim.
The home owners filed their application to strike out the builder’s statement of
claim on 1 April 2014. Before the application was heard, the builder filed an
amended statement of claim to include an alternative basis, being quantum meruit,
claiming an identical $182,252.00.
[8] When the application was heard before me the amended statement of claim included
the following paragraphs which appear consistent with a claim for money pursuant
to contract:
“2 By an agreement entered into between the Plaintiff… and …
the Defendants… the Plaintiff at the request of the
Defendants agreed to provide Services to the Defendants…
2 Para 6
3 Submissions on behalf of the plaintiff, para 8
-- 5 of 14 --
6
2A The Agreement between the Plaintiff and the Defendants was
partly oral and partly written.
2B Insofar as the Agreement was in writing it consisted of:
(a) ongoing email correspondence… as follows…
(b) the following progress claims as agreed between the
parties.
…
(“the Agreement”)
3. It was an implied term of the Agreement that the Defendants
would pay the Plaintiff for the progress claims provided at the
request of the Defendants.
4. Pursuant to the Agreement… the Plaintiff provided the
Services…
5. During the Period, the Plaintiff rendered its progress claims
to the Defendants…
7. Despite demand by the Plaintiff and in breach of the
Agreement, the Defendants have neglected, failed and/or
refused to pay the Plaintiff the final invoice, being Invoice
Number CMF074-10 and Progress Claim 10, in the sum of…
$182,252.00 (‘the Debt’)…
12. The Plaintiff is entitled to claim and does claim from the
Defendant the Debt as moneys due, owing and payable
pursuant to the terms and conditions of the Agreement or
alternatively as quantum meruit…”
[9] For the builder it was submitted that, in the amended statement of claim, references
to an agreement between the builder and the home owners were not intended to
suggest that the builder was suing upon an agreement. Instead, the references to the
agreement were pleaded to show that work done by the builder was not intended to
be done gratuitously. Where the basis for a claim for money is not the usual basis
that it is payable according to the terms of an agreement it can be appropriate to
plead an agreement to do the work even where the agreement is not enforceable.
This would be so where it is necessary to prove an intention that the work be paid
for and to disprove that there was no intention to perform work gratuitously.4
[10] To reinforce his submission that the proceeding “is not brought upon or to enforce
the contract”, counsel for the builder during oral argument orally applied to amend
the amended statement of claim at paragraph 7 to delete the words “and in breach of
the Agreement” and “the final invoice, being Invoice Number CMF074-10 and
Progress Claim 10, in” and from paragraph 12 the words “pursuant to the terms and
conditions of the Agreement”.
[11] The impression from the amended statement of claim that the builder was basing
one cause of action on a claim for money payable pursuant to contract was
reinforced by the builder’s pleading at paragraph 3(b) of the Answer to the
Amended Counterclaim which alleged that “the Agreement was and is enforceable.”
Counsel submitted that this plea was intended to assert an estoppel. If that is correct,
the plea at 3(b) failed to reveal its intent. I contrast a hypothetical plea
foreshadowed in the builder’s submission that the home owners “are estopped from
4 Pavey & Matthews Pty Ltd (1987) 162 CLR 221 at 257.5 per Deane J.
-- 6 of 14 --
7
relying on s 55(3) of the DBCA” and from denying that “the Agreement was and is
enforceable.”
[12] The application to strike out the statement of claim was plainly justified when it was
filed.
[13] When the amended statement of claim was filed to include a claim for quantum
meruit the home owners were justified in applying to strike out at least those parts
of the statement of claim which appeared to claim money pursuant to contract.
Thus, the home owners were justified in seeking leave to file an amended
application to strike out the amended statement of claim. The justification for this
was because the amended statement of claim created the clear impression that the
alternative to the quantum meruit claim was a claim for money due pursuant to an
agreement.
If not a claim for money payable pursuant to a contract, what are the bases of
the builder’s claim?
[14] The builder explained by submissions that it claims $182,252.00 by:
(a) “an action to recover money for a fully executed agreement” which
is “an action for debt and not an action brought under the contract”;
and further and alternatively;
(b) an action for quantum meruit; and
(c) by the amended statement of claim the builder also alleges that the
home owners are “estopped from denying that any money is owing
as a result of their conduct.” The builder gave as particulars of this
that the home owners “acquiesced and agreed to the terms of the
agreement, by making payment of progress claims 1 to 9”. By
written submissions the builder added that it will amend the
relevant paragraph of the amended statement of claim to refer to
paragraph 4(d) of the builder’s reply. That sub-paragraph alleges
matters which create another basis for arguing an estoppel. Instead
of founding an estoppel on the home owners’ payment of invoices
for progress claims, after amendment it would be clear that it is
founded on the allegation that the home owners knew or ought to
have known that the agreement did not comply with the DBCA, that
the home owners represented to the builder that they knew the
agreement did not comply with the DBCA and represented that they
did not intend to rely on the DBCA to defend any claim, that the
builder relied on those representations to commence and continue
performing works and “therefore” did not formally contract in
accordance with the DBCA and that it is unconscionable for the
home owners to rely on the DBCA to render the agreement
unenforceable.
Does the statement of claim contain a claim to recover money on a fully executed
agreement?
[15] The builder surprised the home owners with a submission that the builder maintains
an action to recover money for a fully executed agreement, that as such it is an
action for debt and not an action brought under the contract. I do not mean to
-- 7 of 14 --
8
suggest that the home owners’ counsel was unaware of the law relating to such an
argument but rather that the home owners were unaware that the builder founded its
claim for $182,252.00 on an allegation that there was a fully executed agreement:
that the builder for its part had performed all work that it had agreed to do.
[16] Has the builder pleaded a fully executed agreement? Its counsel does not expressly
submit so. The amended statement of claim does not expressly allege that the
builder has fully executed an agreement. The builder’s counsel submitted that there
is no dispute that the services requested have been fully provided and that this
emerges from reading paragraph 4 of the amended statement of claim with the
admission at paragraph 4(a) of the defence. I reject the submission. Since “the
Services” alleged at paragraph 4 of the amended statement of claim are defined at
paragraph 1 (c) of paragraph 4 of the amended statement of claim to be “building
and construction services” generally and without reference to any agreement with
the home owners, an admission that the builder provided “the Services” is an
admission that it provided “building and construction services” generally and
without reference to any agreement. The amended statement of claim does not plead
sufficient facts from which one may infer that the builder for its part has fully
executed an agreement.
[17] The builder’s counsel had an alternative argument. He implied that the pleading
does not plead a fully executed agreement by his alternative submission that it is for
the defendant home owners to plead that performance by the builder was not
complete.
[18] No authority for or argument in support of that submission was given by the
builder’s counsel. UCPR r 153 permits the implication of performance of a
condition precedent for the case of a party and places an onus on the other party to
deny performance of the condition precedent. The allegation of facts to show that
there has been a fully executed agreement seems to me to be qualitatively different
from a mere condition precedent. Such facts would be material facts which are a
substantial component of an action in debt. They are in the case before me to
distinguish the debt actio from an action in contract, so as to show that the builder
seeks to recover money for a fully executed agreement. I reject the builder’s
submission that it was for the home owners to raise the issue in their defence and
the implied submission that there is no need for the builder to plead the material
facts supporting its claim of a fully executed agreement in its statement of claim.
[19] The home owners submit that the pleading does not allege that an entire contract
was performed. I accept that submission.
[20] A nice question arises as to whether the builder may bring a claim in debt
notwithstanding DBCA s 55. I infer that the builder desires a finding on that issue.
As the claim that the agreement was fully executed was not pleaded and as there is
no identifiable claim for a debt due on a fully executed contract, a finding on the
nice question would be an advisory opinion by the court. As such, it would be
inappropriate to decide it. It would also be obiter and would not bind the parties.
Can the builder maintain a claim for quantum meruit in this court
notwithstanding that it may not enforce the contract because of s 55(3) of the
DBCA and that it may obtain a quantum meruit style of remedy it may seek from
QCAT?
-- 8 of 14 --
9
[21] In Gemini Nominees Pty Ltd v Queensland Property Partners Pty Ltd [2008] 1 Qd
R 139 Mullins J was required to consider s 55 of the DBCA and her Honour made
an unequivocal interpretation that “the Legislature has restricted a builder who
breaches s 55(1) or (2) of the DBCA to recovering costs for the work undertaken
pursuant to that contract to the extent provided in s 55(4)”.5 Her Honour added that
“It cannot be concluded that in addition to s 55(4) a builder who breached s 55 of
the DBCA would be able to make a claim based on quantum meruit.”6 There is a
plausible argument that her Honour’s two observations were obiter dictum. The
builder’s counsel submits they were obiter and the home owner’s counsel submits
they were part of the ratio. It is difficult to determine whether her Honour regarded
the findings as integral to the reasoning that led to her finding that the scheme under
the Building and Construction Industry Payments Act 2004 “which seeks to
facilitate progress payments under a construction contract could” not “apply to
facilitate a progress payment in respect of an amount that may be awarded under s
55(4) of the DBCA where the domestic building contract has been made
unenforceable pursuant to s 55(3) of the DBCA”. One might have reached that same
conclusion without finding that s 55(4) of the DBCA was the exclusive source of a
restitutionary quantum meruit remedy. On balance I conclude that it was not
necessary to so hold for the purpose of determining that a builder cannot claim to be
entitled to a progress payment under an unenforceable contract. I conclude that her
Honour’s additional observation was obiter, that I am not bound to accept it by the
rule of stare decisis. That raises the issue of whether I am obliged to consider the
correctness of her Honour’s construction of s 55(4) and to determine the
construction myself. I infer that the builder would submit that I must.
[22] When a judge of the District Court of Queensland is assisted by reference to obiter
dicta of a single judge of the Supreme Court of Queensland the dicta are treated as
persuasive though not binding. While the situation for appellate courts confronted
with other appellate decisions on point is quite different, some of the practical
considerations which guide appellate courts in determining whether to reconsider a
point previously decided by another appellate court are helpful to bear in mind for
this court when considering whether to reconsider a point about a Queensland
Statute’s interpretation upon which there is obiter dictum from a single judge of the
Supreme Court of Queensland. The Full Court of the Federal Court of Australia in
Telstra Corp Ltd v Treloar7observed, so far as is relevant to the issue of a District
Court’s application of obiter relating to statutory interpretation:
[23] The doctrine of stare decisis takes its name from the Latin phrase "stare
decisis et non quieta movere" which translates as "stand by the thing decided and
do not disturb the calm". It is a doctrine based on policy. The rationale for the
doctrine can be grouped into four categories: certainty, equality, efficiency and the
appearance of justice. Stare decisis promotes certainty because the law is then able
to furnish a clear guide for the conduct of individuals. Citizens are able to arrange
their affairs with confidence knowing that the law that will be applied to them in
future will be the same as is currently applied. The doctrine achieves equality by
treating like cases alike. Stare decisis promotes efficiency. Once a court has
determined an issue, subsequent courts need not expend the time and resources to
reconsider it. Finally, stare decisis promotes the appearance of justice by creating
impartial rules of law not dependent upon the personal views or biases of a
particular judge. It achieves this result by impersonal and reasoned judgments.
…
5 At [36] on pg 150 lines 4-8
6 At [36] on pg 150 line 10
7 (2000) 102 FCR 595; [2000] FCA 1170
-- 9 of 14 --
10
[27] The problem is very real when what is at issue is the construction of a statute.
For one thing, statutory language is often ambiguous. Courts can struggle to
determine the legislative intent. It is often impossible to discover any legislative
intent. In many instances the generality of the statutory language is deliberate and
allows the courts to develop a body of law to fill the gaps. This may lead to
disagreement among judges about what the statute means. It would be sound policy
that once that intent has been discerned by an appellate court then that should be
the end of the matter.
[28] The view which we prefer is that unless an error in construction is patent, or
has produced unintended and perhaps irrational consequences not foreseen by the
court that created the precedent, the first decision should stand. In other areas of
the law a precedent may be reconsidered if its underlying reasoning is outdated or
is inconsistent with other legal developments. Perhaps, with some modification, in
some instances these factors could also be applied to cases concerned with the
construction of statutes…
[23] The builder submits that her Honour’s construction of s 55 is wrong. The
submission targets more particularly her Honour’s finding that “It cannot be
concluded that in addition to s 55(4) a builder who breached s 55 of the DBCA
would be able to make a claim based on quantum meruit.” The builder implies an
argument which was not put to her Honour and which is plausible, that s 55(4)
creates a jurisdiction in the tribunal to entertain a restitutionary claim of the type
described in s 55(4). The builder implies that the creation of the tribunal’s
jurisdiction was not intended to remove jurisdiction from any courts which
otherwise had jurisdiction to give a builder restitution when its contract was
unenforceable. The builder supports its submission by reference to Plaintiff
S157/2000 v Commonwealth of Australia8 which is authority for the proposition that
common law rights are not curtailed unless an intention is manifested by
unmistakeable and unambiguous language. The builder implies that the language in
s 55(4) is ambiguous and contrasts it with the wording used in s 84(2).9 I have not
found a case directly considering the meaning of the words of s 84(2). In my
opinion, s 84(2) excludes a builder’s capacity to recover an amount on account of a
variation10 on any basis other than by satisfying one of the subparagraphs in s
84(2)(a) or s 84(2)(b). This is for two reasons. The first is that that is the natural
meaning of the words used at s 84(2). The second is that there would be little point
in the legislature creating a specific, and quite restricted right at s 84(4) to, in effect,
a restitutionary remedy in certain circumstances if the legislature did not intend
otherwise to exclude any right to recover, including in restitution. I accept that the
wording at s 84 is clearer than the wording at s 55 in expressing an intention to limit
the builder’s remedy to the remedy the tribunal may grant (where the builder failed
to give the required estimate). I accept the builders’ argument that the words of s
84(2) more clearly demonstrate an intention to curtail other common law rights than
the words of s 55(3). But a comparison of s 55(4) and 84(4) gives some support to
the home owners. Section 84(4) is an instance of the legislature creating a specific
and restricted right to a restitutionary remedy for builders who failed to obtain
properly documented variation agreements, a remedy available only from the
tribunal and to the exclusion of other rights of recovery. It would be odd if the
legislature took a different approach with s 55(4) when creating a specific and
restricted right to a restitutionary remedy for builders who failed to supply properly
documented estimates of the total amount the builder is likely to receive. It would
8 (2003) 211 CLR 476
9 Set out above.
10 Of a domestic building contract which is a regulated contract
-- 10 of 14 --
11
be more likely that the legislature would take a consistent approach with the remedy
created at s 55(4) by making that remedy the only remedy available to the builder.
[24] If her Honour’s construction of s 55 is applied, it does not follow that all builder’s
common law rights to seek a restitutionary remedy in quantum meruit are curtailed.
Only the rights of a building contractor who enters into a domestic building contract
which is a cost plus contract that would be a regulated contract and who has not
included a fair and reasonable estimate of the total amount the building contractor
was likely to receive under the contract is affected and is affected to the limited
extent that its common law right to claim restitutionary quantum meruit is replaced
by a statutory right to claim in the tribunal for the cost of providing contracted
services plus a reasonable profit if it would not be unfair.
[25] On the hypothesis that her Honour’s finding is obiter I am not satisfied that there is
a patent error in her Honour’s construction and related obiter finding. I am not
satisfied that her Honour’s finding is wrong. As it was a finding about the proper
interpretation of a statute it seems to me sensible that having satisfied myself that
there is no patent error in her Honour’s construction I should be at liberty to apply
her Honour’s finding without taking the time to reconsider the issue. It is sensible
that I apply her Honour’s finding and I do.
[26] The process of concluding that there was no patent error did result in my
reconsidering the point. I am, with respect, also satisfied that her Honour’s obiter
finding is correct.
[27] It follows that, subject to one further argument, the builder may not maintain its
quantum meruit claim in this court. That finding means that I am required to
consider the merits of the builder’s estoppel arguments which are designed to
preserve its right to proceed in this court on a quantum meruit claim even if by s 55
of the DBCA the legislature had intended that builders should be restricted to
seeking a quantum meruit style of restitutionary remedy from the tribunal.
Can the builder rely upon an estoppel to maintain its quantum meruit claim in
this court?
[28] The amended statement of claim purports to raise an estoppel at paragraph 8. That
paragraph alleges:
“The Plaintiff will further rely upon the Defendants’ conduct in
making payment of all invoices in line with each progress claim and
the Defendants are estopped from denying that any money is owing
as a result of their conduct.”
Counsel for the builder accepts that paragraph 8 “ought to include the much more
fulsome plea that now appears in the reply”.
[29] I infer that the builder does not rely upon paragraph 8 of the amended statement of
claim as being satisfactory to set out all the matters necessary to establish an
estoppel and infer that, subject to my finding about the builder’s argument that it
may maintain the estoppel point raised in its reply, the builder will either
incorporate matters set out in paragraph 4 of its reply into paragraph 8 of its
amended statement of claim or alternatively that the builder will delete paragraph 8
of its statement of claim and rely exclusively on paragraph 4 of its reply. Paragraph
-- 11 of 14 --
12
4 of the builder’s reply alleges, in essence, that “at all material times” the home
owners knew and understood their rights under the DBCA, knew that the agreement
did not comply with the DBCA and gave instructions to allow the builder to
undertake the works and thereby represented to the builder that they knew the
agreement did not comply with the DBCA and that they did not intend to rely on the
DBCA and the builder acted to its detriment by relying on those representations and
not contracting in accordance with the DBCA rendering it unconscionable for the
home owners to rely on the DBCA.
[30] The builder submits that it may raise an estoppel against the home owners’ reliance
upon s 55 because that section is enacted for a private benefit and may be
disclaimed by the home owners and that it can be distinguished from a provision
which is enacted for the protection of the public generally.
[31] In most cases there is no estoppel against a defendant who wishes to set up the
statutory invalidity of some contract.11 Whether an estoppel is to be allowed or not
has been said to depend on whether the obligation imposed by the statute will be
nullified by an estoppel.12It is probably more correct to enlarge the question to ask
whether an obligation imposed for the public benefit will be nullified by an
estoppel.
[32] The builder submits that the DBCA, unlike, for example, the Property Agents and
Motor Dealers Act 2000 (Qld), does not state that the protection of consumers is
one of its objects, that s 3 of the DBCA states that the purpose of the DBCA is to
achieve a reasonable balance between the interests of building contractors and
building owners. I do not accept that object is unequivocally for conferring a private
benefit.
[33] Another of the purposes of the DBCA is “to maintain appropriate standards of
conduct in the building industry” which is concerned with the public interest. I
accept the builder’s submission that the limitations imposed upon builders by the
DBCA are less in scope than those imposed by the Queensland Building
Construction and Commission Act 1991 whose objects are set out in s 3 of that Act.
Those objects include some which are more easily recognisable as public interest
objects. I refer, for example, to the object of regulating the building industry to
ensure the proper maintenance of standards in the industry.
[34] The builder submits that s 55 of the DBCA is enacted for a private rather than for a
public purpose and that building owners are not a general class of consumers who
would require protection. I note that the building owners protected by s 55 are
defined partly by their interest in “domestic building work” and a “domestic
building contract” for, at most, the construction of one detached dwelling. A
member of that class of “building owner”, generally speaking, is likely to be much
less often a party to a domestic building contract than the builder with whom the
agreement is reached. One of the DBCA’s objects may be the achievement “of a
reasonable balance between the interests of building contractors and building
owners” but that does not mean that it is not also for a purpose of protecting the
11 Kok Hoong v Leong Cheong Kweng Mines Ltd [1964] AC 993 at 1015-1016 and Sultana Investments
Pty Ltd v Cellcom Pty Ltd (No 1) [2008] QCA 357; [2009] 1 Qd R 589 at [50].
12 Day Ford Pty Ltd v Sciacca [1990] 2 Qd R 209 at 216 approving Maritime Electric Co v General
Dairies Ltd [1937] AC 610 at 620 and referred to with approval in Sultana Investments Pty Ltd op cit
at [51].
-- 12 of 14 --
13
generally less experienced “building owners”. S 55 has three features which suggest
that the reasonable balance is one which clearly favours and seeks to protect the
other party. Only the builder commits an offence. Only the builder is prevented
from enforcing the contract. The tribunal’s power to award the builder the cost of
providing the contracted services and a reasonable profit is conditional upon finding
that it would not be unfair to the building owner.
[35] For the home owners it was submitted that s 55 has a consumer protection focus. I
accept that.
[36] DBCA s 93(2) is set out above. It refers to “a right conferred under this Act”. A
proper inference from DBCA s 55 (2) is that the home owners have a statutory
right which corresponds with the prohibition on the builder against entering into
the contract without including the builder’s fair and reasonable estimate of the total
it was likely to receive. The home owners’ right was to have the estimate included
in the contract. A proper inference from DBCA s 55 (3) and (4) is that the home
owners have a statutory right which corresponds with the prohibition on the
builder’s enforcing the contract other than in the tribunal pursuant to DBCA s 55
(4). If the builder and home owners had hypothetically gone so far as to enter into
a separate contract that the home owners would give up the rights arising from
DBCA s 55 (2), (3) and (4) the effect of DBCA s 93(2) would be to make that
separate contract void. It would be odd if something less than a separate contract,
namely a representation by the home owners relied upon by the builder, would
give a greater protection to the builder than it could obtain from a separate
contract. That proposition was put more eloquently in Keen v Holland [1984] 1
WLR 251 at 261 C-F which was applied in Beckford Nominees Pty Ltd v Shell Co
of Australia Ltd (1987) 73 ALR 373 at 378 – 9 by Pincus J as his Honour then was
and both cases were referred to with approval by Muir JA in Neumann Contractors
Pty Ltd v Traspunt No. 5 Pty Ltd [2011] 2 Qd R 114 at 133 [69]. However, while
Muir JA regarded a prohibition against contracting out as providing a strong
indication that a provision conferred public rights or rights which it is in the public
interest to maintain and which cannot be eroded by estoppel, it was unnecessary
for his Honour to express a concluded view in that case. I note also that in
Metropolitan Health Service Board v Australian Nursing Federation (2003) 176
ALR 46 at 54-55 French J sitting as a member of the Full Court of the Federal
Court concluded that neither estoppel nor waiver applied in that case because the
legislation precluded contracting out and his Honour stated the guiding principle,
citing the decision of Pincus J in Beckford Nominees, thus:
“There is nothing novel in the general proposition that statutes which
preclude contracting out of the rights and obligations they confer will
defeat the application of estoppel and waiver to like effect…”
[37] I conclude that the prohibition against contracting out confirms that DBCA s 55
conferred “public rights or rights which it is in the public interest to maintain” and
that the builder cannot rely upon the alleged estoppel to maintain its quantum meruit
claim in this court.
Particulars
[38] As a result of the findings I have made, it is unnecessary for me to consider the
request for particulars of paragraph 8 of the amended statement of claim and
-- 13 of 14 --
14
paragraph 4(d)(iii) of the reply which contained allegations for the purpose of
maintaining the estoppel argument.
Conclusion
[39] Having regard to these findings it is appropriate to order that the amended statement
of claim be struck out. Because I have held that the builder may not maintain its
estoppel argument it is appropriate that paragraphs 4(d), 10 and 11 of the reply be
struck out together with paragraphs 1, 3(b) and 4 of the answer to the amended
counter-claim. The parties have not made submissions as to costs.
[40] The general rule is that where the court strikes out all or part of a pleading there will
be an order that the costs of the application be paid by the unsuccessful party on the
indemnity basis. I am reluctant to impose that order without first giving the
unsuccessful builder liberty to make submissions to the contrary. However, in an
effort to spare the parties from wasted expense it seems sensible to order that the
plaintiff pay the defendants’ costs of the application calculated on the indemnity
basis and to give the plaintiff liberty for 7 days to apply to set aside that order for
costs.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2014/090