Brimar Electrical Services Pty Ltd v Zi-Argus Australia Pty Ltd [2014] QDC 78
DISTRICT COURT OF QUEENSLAND
CITATION: Brimar Electrical Services Pty Ltd v Zi-Argus Australia Pty
Ltd [2014] QDC 78
PARTIES: BRIMAR ELECTRICAL SERVICES PTY LTD
(ACN 104 143 875)
(applicant)
v
ZI-ARGUS AUSTRALIA PTY LTD
(ACN 140 767 335)
(respondent)
FILE NO/S: 739/2014
DIVISION: Civil
PROCEEDING: Application
ORIGINATING
COURT: District Court of Queensland
DELIVERED ON: 11 April 2014
DELIVERED AT: Brisbane
HEARING DATE: 3 April 2014
JUDGE: R S Jones DCJ
ORDER: 1. The application is dismissed;
2. Subject to order 3 the applicant is to pay the
respondent’s costs of the application;
3. The applicant has liberty to apply in respect to the
question of costs only.
CATCHWORDS: Judgment pursuant to s 19 of the Building Construction and
Industry Payments Act 2004 – where the applicant claimed to
be entitled to a progress payment for work done – where the
respondent contends it is not liable for the amount claimed –
where the respondent asserts that it served a payment
schedule on the applicant which was in accordance with s
18(2) of the Act – where the applicant asserts that it was not
and was thereby entitled to the full amount claimed.
Building Construction and Industry Payments Act 2004 (Qld)
Minimax Fire Fighting Systems Pty Ltd v Bremore
-- 1 of 10 --
2
Engineering (WA) Pty Ltd [2007] QSC 333
Gisley Investments v Williams (2010) QSC 178
COUNSEL: Ms S McNeil for the applicant
Mr G Beacham for the respondent
SOLICITORS: MacKay’s Solicitors for the applicant
Thomson Geer Lawyers for the respondent
[1] This proceeding is concerned with an originating application seeking judgment
against the respondent for the sum of $258,096.51 pursuant to s 19 of the Building
and Construction Industry Payments Act 2004 (the Act) together with interest and
costs. For the reasons set out below the orders of the court are:
1. The application is dismissed;
2. Subject to order 3 the applicant is to pay the respondent’s cost of the
application;
3. The applicant has liberty to apply in respect to the question of costs only.
Background
[2] The applicant is a licensed electrical contractor who, on or about 29 June 2012
entered into a contract with the respondent for the supply and installation of
electrical services on a project known as the Bio Pharmaceuticals’ Australia project
within the precincts of the Princess Alexandra Hospital at Brisbane. Between June
2012 and April 2013 the applicant carried out certain works associated with the
project and on 1 July 2013 served on the respondent a payment claim (the Claim).
It was not in contest that the claim satisfied the requirements of s 17 of the Act. By
way of emails dated 4 July 2013 the respondent contended that it served on the
applicant a valid payment schedule (the Schedule) which accorded with the
statutory requirements of s 18 of the Act. The applicant contended that the
Schedule did not satisfy the requirements of s 18 of the Act and, accordingly,
pursuant to s 19 was entitled to payment.
[3] Sections 18 and 19 of the Act relevantly provide:
“18. Payment Schedules
1. A respondent served with a payment claim may
reply to the claim by serving a payment schedule on
the claimant.
2. A payment schedule –
(a) must identify the payment claim to which it
relates; and
(b) must state the amount of the payment if any
that the respondent proposes to make (the
scheduled amount)
3. If the scheduled amount is less than the claimed
amount, the schedule must state why the scheduled
amount is less and, if it is less because the
-- 2 of 10 --
3
respondent is withholding payment for any reason,
the respondent’s reasons for withholding payment
…”
“19. Consequences of not paying claimant if no payment schedule
1. This section applies if the respondent –
(a) becomes liable to pay the claimed amount to
the claimant under section 18 because the
respondent failed to serve a payment
schedule on the claimant within the time
allowed by the section…”
[4] Section 19 thereafter provides that, in certain circumstances, a contractor may
recover the amount claimed as a debt. Subsection 4 of s 19 provides:
“If the claimant starts proceedings under subsection 2(a)(i) to recover
the unpaid portion of the claimed amount from the respondent as a
debt -
(a) judgment in favor of the claimant is not to be given
by a court unless the court is satisfied of the
existence of the circumstances referred to in
subsection (1); and
(b) the respondent is not, in those proceedings, entitled –
(i) to bring any counterclaim against the
claimant; or
(ii) to raise any defence in relation to matters
arising under the construction contract.”
[5] It was uncontroversial that the schedule was within the time prescribed by the Act
and that it identified the relevant payment claim. Accordingly the dispute between
the parties was limited to whether the schedule stated the amount of the payment
which the respondent proposed to make to the applicant in response to its claim (s
18(2)(b)) and, whether in circumstances where the amount proposed to be paid was
less than the full amount claimed, the schedule provided sufficient reasons as to
why the respondent intended to withhold payment. (Section 18(3)).
[6] The legislative intent behind the Act and the approach the courts should take to it
was, with respect, concisely summarized by Chesterman J (as he then was) in
Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA) Pty Ltd &
Ors1:
“[17] Before considering the first question, I think it necessary to
remember the purpose of the Act because that purpose will
influence the approach one takes to the construction of the
14 December email. As Hodgson JA said in Brodyn Pty Ltd
T/as Time Cost and Quality v Davenport (2004) 61 NSW
LR 421 at 440-1:”
‘the Act discloses a legislative intention to
give an entitlement to progress payments, and
to provide a mechanism to ensure that disputes
1 [2007] QSC 333. See also Gisley Investments P/L v Williams & Anor (2010) QSC 178
-- 3 of 10 --
4
concerning the amount of such payments are
resolved with the minimum of delay. The
payments themselves are only payments on
account of a liability that will be finally
determined otherwise… the procedure
contemplates a minimum of opportunity for
court involvement…’
…
[19] In Brodyn Pty Ltd T/as Time Cost and Quality (ACN 001
998 830) v Phillip Davenport & Ors [2003] NSWSC 1019
Einstein J referred to the legislation as:
‘a fast track interim progress payment
adjudication vehicle.’
[20] The Act emphasises speed and informality. Accordingly
one should not approach the question whether a document
satisfies the description of a payment schedule (or payment
claim for that matter) from an unduly critical viewpoint. No
particular form is required. One is concerned only with
whether the content of the document in question satisfies the
statutory description. To constitute a payment schedule the
applicant’s email of 14 December had to:
(i) identify the payment claim to which it related; and
(ii) state any amount which the recipient of the payment
claim proposed to make in response to it;
(iii) importantly, if that amount is less than the amount
claimed the payment schedule it must state why it is
less.
[21] If these three criteria are satisfied the document will be a
payment schedule. How they are expressed, with what
formality or lack of it, and with what felicity or
awkwardness, will not matter.
…
[27] If the applicant had no objection to paying those amounts
the Act required to say so in its payment schedule. The
whole purpose of such a document is to identify what
amounts are in dispute and why. The delivery of a payment
claim and a payment schedule is meant to identify, at an
early stage, the parameters of a dispute about payment for
the quick and informal adjudication process for which the
Act provides. If a builder wishes to take advantage of the
Act to dispute the claim it must comply with the provisions
and must, relevantly, take the trouble to respond to a
payment claim in the manner required by the Act. The
process is not difficult. The applicant was required to
identify those parts of the claim which it objected to paying
and say what the grounds of its objection were.”
-- 4 of 10 --
5
Discussion
[7] The amount claimed in the sum of $258,096.49 was made up of a number of
invoices:2
Invoice 4130229 - $25,880.26 (Progress Claim 8)
Invoice 4130378 - $9,263.26 (Progress Claim 9)
Invoice 4130594 - $192,263.48 (Final Claim No1)
Invoice 4130112 - $22,102.08 (Progress Claim No1)
Invoice 4130377 - $8,587.41 (Final Claim)
[8] The email response to the claim comprised of a short narrative together with a
number of documents including tax invoices and schedules.3 It relevantly stated:
“Dear Mr McGrath
We acknowledge receipt of the letter from your solicitor dated 5th
June 2013 and your fax dated 30 June 2013. I have discussed this
ongoing matter with my managing director Alan Reece who has
engaged our solicitors and hence he is copied on this email and will
be on all future correspondences [sic].
I may highlight some important series of events here.
1. Project work was done on fixed price and in no
correspondences [sic] did we state that this is a do and
charge work as you seem to imply. We have not interfered
with how you handled your labour force on this job either in
the number of electrician [sic] or the hours worked. Hence,
we consider your submission of the timesheet to be
irrelevant and as such will not be reviewed. (original
emphasis)
2. I have attached a spreadsheet with our current position
which was in reply to Kane’s email to me on 18th June. As
you can see, my reply was sent to Kane on the 27th June
after further investigation with our people and consultation
with my customer A E Smith.
3. I have also attached a spreadsheet highlighting your invoices
and how they correspond to the various claims. Those
items highlighted in red are not legitimate claims. The
following comments pertain to some of your larger
claims. (emphasis added)
4. Invoice 4130594 –‘Overtime Worked Difference –
Automation’. This claim is not legitimate as we did not
instruct any overtime to be done. Furthermore, as all
phases of this project was [sic] done on a fixed price, we
had no control over your personnel to execute the
project. This claim is not approved. (emphasis added)
2 Affidavit of Mr McGrath at p 102. (See also at pp 138-151)
3 Refer to exhibit AEE-1 of the affidavit of Alana Elliot.
-- 5 of 10 --
6
5. Invoice 4130594 – ‘Supervision Extra Work – Automation’.
This claim is not legitimate as all supervision was part of
the fixed price. All additional work have [sic] been
quoted and where we acknowledge a variation work, we
have handled each in isolation and complete in it’s claim.
(emphasis added)
6. Invoices 4130112 and 4130377 – Commissioning support.
On advise [sic] from Danial Smith (see attached email) we
sent our electrician to site for commissioning support. We
do however recognise that we utilised some of Brimar’s
personnel and the extent of this usage was communicated to
you via an email from Romani (see attached). We are
approving $10,053.00 of your variation claim and consider
this to be generous.
7. From our list of variation claims which have been
highlighted in red, these are not legitimate claims as
there [sic] were either not done, not caused by Zi-Argus
or could have been avoided by better site co-ordination.
The site co-ordination was sadly lacking as confirmed by
you dismissing …. We do not feel that our interests were
handled adequately which Zi-Argus paid for
($28,160.00+GST). (emphasis added)
8. We have also included our counter claims for work not done
by Brimar. We did not get a single test document from
Brimar or even a statement of readiness.
…
I urge you to go through our list of approved variations and
agree as getting solicitors will serve no one but one that we
will undertake in order to protect our rights.”
[9] The submission made on behalf of the applicant that the schedule did not satisfy
s 18(2)(b) of the Act were set out in Ms McNeil’s, (counsel for the applicant,)
written submissions:
“29. The payment claim includes a table which contains a
number of invoices. Of those invoices referred to, there are
5 invoices which are stated to be unpaid and therefore form
the basis of the payment claim.
30. In the email of 4 July the respondent chose to address each
invoice separately. …
31. Nowhere in the email does the respondent acknowledge the
total amount of the payment claim and by reference to that
amount state the total amount that it intends to pay by way
of comparison with the $258,096.49.
-- 6 of 10 --
7
32. In paragraphs 4 and 5 there is reference to 1 of the 5
invoices (being #4130594 being for $192,263.48). The
respondent states that the claim for ‘overtime worked
difference – automation’ is not a legitimate claim. The
respondent fails to state what amount, if any, of that invoice
it proposes to pay.
33. In paragraph 6 of the email reference is made to 2 of the 5
invoices (being 4130112 and 4130377) and subsequent to
the reference to those two paragraphs is the statement that
the respondent is ‘approving’ $10,053.00 of the variation
claim. It does not state that the respondent is proposing to
pay that amount but only approves that amount. (original
emphasis)
34. This paragraph cannot be interpreted as a statement that of
the total payment claim amount of $258,096.49 that the
respondent proposes to pay his $10,053.00.
35. The email does not address at all the remaining 2 invoices,
being invoice numbers #4130229 (being for $25,880.26) and
#4130378 (being for $9,263.26). …”
[10] In support of the argument that s 18(3) of the Act was not satisfied it was submitted:
“37. Where is the respondent’s ground of the objection to paying
those two invoices for this work undertaken?
38. The table relied on by the respondents sets out the total
amount of each invoice. In respect of the two invoices
#4130229 and #4130378 the table says nothing in respect of
why the total amount in those invoices is not payable. In
accordance with Minimax the respondent had to: ‘identify
those parts of the claim which it objected to paying and say
what the grounds of its objection were.’ It has not done so.
(original emphasis)
39. If the respondent seeks to argue that by the words ‘not
approved’, it stated what its grounds or objection were, the
applicant says this argument is untenable. It cannot be
stating the grounds of an objection to simply state ‘not
approved’. There must be articulated grounds for the refusal
to pay an amount.
40. The threshold for satisfying the requirements for a payment
schedule cannot be held to be so low as to allow ‘not
approved’ as satisfying the s 19(3) [sic] requirement to state
the reasons for withholding payment … .”
[11] Paragraph one of the e-mail emphasised that as far as the respondent was concerned
the contract was for a fixed price. And also while paragraph three identified that
-- 7 of 10 --
8
only some of the larger claims were going to be specifically dealt with it is clear
from the balance of that paragraph that the attached spreadsheets addressed all of
the claims and identified those considered to be “not legitimate claims”. The reason
for them not being legitimate was because, as stated, as far as the respondent was
concerned it was a fixed price contract and accordingly, none of the claims
concerning overtime and supervision etc were going to be paid.
[12] In my opinion neither of the complaints made against the respondent are valid.
Paragraph three of the email clearly drew the applicant’s attention to the spreadsheet
and to the fact that those items highlighted in red were not considered to be
legitimate claims. The only inference that can be drawn from that assertion is that
they were claims that the respondent had no intention of paying. The spreadsheet
under the heading “outstanding payable” has a table identifying, among other
things, the description of works, the amount claimed for those works, whether the
claim was approved and whether, if approved, the works had been paid for or were
yet to be paid for. At the conclusion of that table there is reference to what is
described as “summary claim from Brimar” and the total amount identified by the
respondent as a consequence of the calculations contained within the table the
amount of was $49,496.00, being the total of the claims approved for payment. On
the following page of the schedule is another table headed “Outstanding
Receivable”, this table identified what the respondent considered the applicant owed
to it. Thereafter, there is what is described as a summary claim from the respondent
in the amount of $24,440
[13] As Chesterman J identified in Minimax, in determining whether or not it satisfies
the requirements of a payment schedule for the purposes of the Act, the document
should not be analysed in an unduly critical way and no particular form is required.
Further, provided the relevant criteria established by s 18 of the Act are satisfied,
the document will be a payment schedule for the purposes of the Act regardless of
how they are expressed, with what formality or lack thereof and with what felicity
or awkwardness. In this case, no doubt it might have been clearer if within the
narrative of the email it was clearly stated that the respondent only intended to pay
the applicant $25,056. However, in circumstances where the email clearly directs
the applicant’s attention to the spreadsheet it is inconceivable that after reading the
words “money owed to Brimar” it did not know that that was the total amount the
respondent proposed to pay in response to the claim and how that amount was
arrived at.
[14] Turning then to the applicant’s argument concerning s 18(3) of the Act, it could not
be sensibly disputed, in my respectful opinion, that the respondent made clear its
reasons for not paying or only paying in part for the works claimed under invoices
4130594 – “overtime worked difference – automation”, 4130594 – “supervision
extra work – automation” ($192,263.48), and invoices 4130112 ($22,102.08) and
4130377 ($8,587.41). Those reasons were identified by reference to paragraphs 1,
4, 5, 6 and 7 of the e-mail.
[15] According to Ms McNeil, the omission on the part of the respondent to specifically
address the remaining two invoices 4130229 ($25,880.26) and 4130378 ($9,263.26)
also failed to satisfy the requirements of s 18(3) of the Act and, accordingly the
-- 8 of 10 --
9
schedule was in effect a nullity. In this regard I agree with Mr Beacham’s
submission to the effect that the applicant’s position fails to give sufficient regard to
the interaction between the email and the attached spreadsheets.
[16] With regard to the so-called unaddressed invoices, 4130229 is concerned with
progress claim 8 and 4130378 with progress claim 9. By reference to the relevant
invoices attached to Mr McGrath’s affidavit, the works claimed are identified by
reference to a description, for way of an example; “variation #20 – level 5 HCV
4.02.1 Cable Relocation Automation”.4 The way the spreadsheet to the email sent
by the respondent operates is to then essentially identify the claim number, give a
brief description of the works and the amount claimed for those works. It then goes
on to identify if payment is (or has been) approved and whether the claim will (or
has been) paid. The first item marked in red in the schedule is described as “level 6
Duct 3HT Installation” for $1,530.00. That figure has been rounded up from the
figure of $1,529.70 being the amount claimed for those works in progress claim 8.5
That process then follows through to the last entry in the schedule marked in red
being “Supervision Extra Work” ($76,797.00). That can be cross-referenced to
progress claim 9 “Supervising Extra Work – Automation” claimed in the amount of
$76,796.75.6 As far as I am able to ascertain, this process applies to all of the
claims made in all of the subject invoices.
[17] Bearing in mind that the applicant would be expected to be fully aware of the
contents of and descriptions used in its claims, there is little room for doubt that
when the applicant read the email and the reference to those claims identified in red
in the spreadsheet it would have known that it was not going to be paid for those
works, and the reasons why it was not going to be paid for those works. If
paragraphs 1 to 6 of the email did not make it sufficiently clear, paragraph 7 must
have. It said in part “from our list of variation claims which have been highlighted
in red, these are not legitimate claims as they were either not done, not caused by Zi
Argus or could have been avoided by better site co-ordination.” Ms McNeil’s focus
on the words “not approved” fails to recognise that those words were never meant to
express the grounds for rejecting particular claims but merely expressed the
consequence of the respondent’s decision about the legitimacy of those claims.
[18] Notwithstanding a degree of complexity associated with the documents I am
satisfied that it is a valid payment schedule for the purposes of s 18 of the Act. The
respondent’s payment schedule adequately identified the amount it intended to
make in respect of the subject claims and the reasons why it was less than the
amount claimed. Accordingly the application must be dismissed. In this context it
also to be borne in mind, that by reference to the documents placed before me, the
works involved were relatively extensive and complex in nature.
4 Mr McGrath’s affidavit at p140
5 See at p 139
6 See at p 145
-- 9 of 10 --
10
Costs
[19] Costs were not addressed during submissions. However, in circumstances where
the respondent was wholly successful in defending the claim against it, it is difficult
to see why the usual rule that costs follow the event ought not to apply.
Accordingly I propose to make such orders. However, in circumstances where the
applicant has not been given the opportunity to be heard, I will allow it to be heard
(if necessary) as to the question of costs by the giving of notice to the respondent of
its intention and after having secured a hearing date from my associate.
Orders
1. The appeal is dismissed.
2. Subject to order 3 the applicant is to pay the respondent’s costs of the
application.
3. The applicant has liberty to apply in respect to the question of costs only.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2014/078