Fergbilt Pty Ltd v Burnett & Anor [2014] QCAT 517
CITATION: Fergbilt Pty Ltd v Burnett & Anor [2014] QCAT
517
PARTIES: Fergbilt Pty Ltd
(Applicant)
v
Greg Burnett
Jackie Heath
(Respondents)
APPLICATION NUMBER: BDL048-14
MATTER TYPE: Building matters
HEARING DATE: 23 June 2014
HEARD AT: Brisbane
DECISION OF: Member Howard
DELIVERED ON: 21 October 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. Greg Burnett and Jackie Heath must pay
to Fergbilt Pty Ltd the sum of $11,319 by
4:00pm on 19 November 2014.
CATCHWORDS: BUILDING DISPUTE – VARIATIONS – whether
variations should be approved under s 84 of
Domestic Building Contracts Act 2000 –
whether exceptional circumstances – whether
builder will suffer unreasonable hardship by
strict operation of requirements for variations –
whether not unfair to the homeowners for
builder to recover – where work has been done
– where accepted work instructed by
homeowner
Domestic Building Contracts Act 2000 (Qld),
s 79, s 80, s 82, s 83, s 84,
Black, G v Toowoomba Resort Pty Ltd [2007]
QCCTB 122
Brown & Anor v Noosa Constructions Pty Ltd
[2012] QCATA 194
-- 1 of 22 --
2
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Craig Ferguson, director, Fergbilt Pty Ltd,
represented Fergbilt Pty Ltd
RESPONDENT: Mr Greg Burnett represented himself and
Ms Heath
REASONS FOR DECISION
Background to the dispute
[1] This proceeding concerns a relatively small claim for variations in a
building dispute totalling a little over $12,000. However, it generated
voluminous material, although some of the individual variation claims are
for as little as $40.
[2] On 24 July 2013, Fergbilt Pty Ltd entered into a contract for domestic
building work with Mr Greg Burnett and Ms Jackie Heath for works at their
property at Farrington Street, Alderley. It involved renovation of an existing
home. The contract price for the works was $325,865. In total $328,373
has been paid under the contract, including some amount for variations.
There was a credit of $4,230 (because on the day to the contract was
signed the homeowners changed their minds about the linings for the
downstairs living areas and this change reduced the cost by $4,230).
Accordingly, an amount of $6,738 has been paid, for variations.
[3] In its application, Fergbilt Pty Ltd claimed unpaid variations in the amount
of $12,814. This represents the difference between the contract price of
$325,865 and the total of the claimed variations, less the credit of $4,230.
It also claims the fee for filing its application in QCAT and interest in
accordance with the contract.
[4] At the hearing, Fergbilt clarified that an amount of $110 for a letterbox is
no longer in dispute. It reduced its claim by that amount to $12,704, plus
the application fee and interest.
[5] The homeowners acknowledge that there were some variations.
However, in essence, they say that they have paid for agreed variations.
In respect of the issues in the dispute, they say that they are entitled to
offset an amount paid by them as a variation for extra concreting and tiling
at the rear of their home. They now say that this was included in the
contract price and should not have been paid. They say that the other
items claimed should be disallowed. In essence, the reasons given are
that the variations were not instructed; or were not put in writing in
accordance with the contract and were done without detailed costings
being provided.
-- 2 of 22 --
3
[6] Despite some evidence and calculations in Mr Burnett’s witness
statement1 which appears to suggest the homeowners seek a refund of
some amount, Mr Burnett confirmed at hearing that the homeowners seek
only orders that the builders claim be dismissed.
What were the contract documents?
[7] There is some disagreement about the contract documents. It is apparent
that Mr Burnett provided several proposed scope of works documents to
Mr Craig Ferguson, a director of Fergbilt, before the contract was entered
into. Further, a preliminary set of plans was initially provided to Fergbilt
and later a ‘BA Issue’ version of the plans.
[8] The parties agree that the contract documents included the Master
Builders Contract dated 24 July 2013; the costs estimate prepared by
Fergbilt in the amount of $325,865;2 copy of plans dated 10 April 2013
(endorsed BA Issue);3 and a schedule of works prepared by Fergbilt.4 All
of these documents were signed or initialled at the time of the signing of
the Master Builders Contract.
[9] The homeowners contend that a scope of works document prepared by
Mr Burnett which appears at pages 151-207 of Exhibit 6 also forms part of
the contract. Mr Craig Ferguson denies this is so. He says that Mr Burnett
presented this further amended scope of works on the day the contract
was to be signed, but that he refused to sign it. He says he informed the
homeowners he would have to take it away and review it and amend it,
pointing out the lack of clarity in it. Mr Burnett later forwarded an email
version of the scope of works to Craig Ferguson on 4 August 2013, which
he says he had gone through and updated ‘as discussed’ in the meetings
leading to the final quotation.5 Mr Ferguson says he amended it in
accordance with the building specifications and returned an amended
document with the amendments written in red. Mr Burnett acknowledges
that it was amended and returned. This version with Mr Ferguson’s
amendments appears at pages 211-240 of Exhibit 6.
[10] Mr Burnett does not dispute that this is what occurred, however, he says
that the document he prepared, without Mr Ferguson’s allegedly
unauthorised amendments forms part of the contract documents. I do not
accept this. It did not embody agreement reached between the parties.
[11] It is common ground that when he was provided with a scope of works
document by Mr Burnett at the time the contract was signed, Mr Craig
Ferguson said he would take it away make any necessary changes, initial
it, and send it back. In the end result, he amended and returned yet
another version of the document which had subsequently been emailed to
1 Exhibit 6.
2 Exhibit 6, pages 21 – 24.
3 Exhibit 6, pages 125 – 138.
4 Exhibit 6, pages 143 – 146.
5 Exhibit 6, paragraphs 17 – 20 and pages 147 – 207.
-- 3 of 22 --
4
him by Mr Burnett. The homeowners dispute the changes that he made to
the document.
[12] Except as concerns the items included in the scope of works which were
not changed by Mr Ferguson (which on both versions of events were
therefore agreed), the contents were not agreed. Therefore, the scope of
works document which, with some exceptions, forms part of the contract,
is at pages 211 to 240 of Exhibit 6. The items included by Mr Burnett
which are subject to deletions by Mr Ferguson are not agreed items and
nor are the additions made by Mr Ferguson in red.
[13] That said, the scope of works as accepted by me as forming part of the
contract contains a large number of items.
What variations are in dispute?
[14] There were 7 variations issued in respect of the works, although multiple
items were included in most variation documents and there were
2 variations called variation 6.
[15] Variations 1 (for a total of $1,373), 2 (which included a debit of $717, as
well as the credit of $4,230 for the wall linings), and 4 (for a total of $560)
were accepted and satisfied in full by the homeowners. In respect of
Variation 3 totalling $4,418, an amendment was made to the variation
document by the homeowners, reducing it to $4088 (that is, an amount of
$330 was deleted and has not been paid) by the homeowners. The $4,088
has been satisfied.
[16] The remaining $330 from Variation 3, as well as Variations 5, (both
numbered) 6, and 7 are unpaid.
[17] The claim by Fergbilt concerns the unpaid portion of Variation 3 of $330,
Variations 5 ($150), 6 ($7,206) and 7 ($5,128 minus letterbox $110,
leaving claimed amount of $5,018). An item for additional concreting is
included in Variation 7, which in part relates back to the amount of $330
by which the homeowners reduced Variation 3. The other variation
numbered 6 ($291) was not claimed by Fergbilt but has been conceded by
the homeowners in the proceedings as owing.
[18] The Tables below set out the items claimed in variations 3, 5, 6 and 7.
Variation 3
Description Cost
Supply and spread top soil to elevated area at rear of
site
$550.00
Additional areas of reinforced concrete slab to rear and
sides of building 46 sqm x $ 55 plus supply of pump
$550
$3,080.00
-- 4 of 22 --
5
Lay and grout additional external tiles (provided by
proprietor) to the area at the back of the house 17.5 sqm
x $45
$788.00
Variation 5
Description Cost
Additional 2 Single GPO for security system $150.00
(First) Variation 6
Description Cost
Supply 2 x 1200 double fluro fittings $106.00
Supply 1 double spot light $45.00
Earthing to 4 external light fittings $140.00
(Second) Variation 6
Description Cost
Centre lower floor shower waste under rose $240.00
Provision of Shower niches $920.00
Reframe external stair and landing – provide new footing
brackets and stair stringers and associated labour incl
steel work
$2,940.00
Patching old down light holes in living rm. Ceiling $130.00
Supply and install AC support bracket $180.00
Additional light over downstairs toilet $85.00
Replace wall light over vanity upstairs bathroom $40.00
Renovation of east and west window awnings repaint
and provide and fix new miniorb sheeting and mini gable
roll
$878.00
Realign stair well wall to meet line of upstair walls – and
associated structural works incl cutting and welding of
beam and column
$1,793.00
Re-framing ensuite shower and relocating plumbing out
let
$0 as agreed
Variation 7
Description Cost
-- 5 of 22 --
6
Description Cost
New sill stop to underside of existing living room bifold
doors
$195.00
Increased height of tiles to ensuite walls and provision of
hanging rail to cover variations in wall thickness
$128.00
Installation of additional framing and setout for wall hung
basins
$265.00
Installation of letter box provided by proprietor $110.00
Additional wall framing for insertion of recessed
bathroom cabinets
$195.00
Pier Caps less credit on Gate & fence panel PC $48.00
Provide and install electric strike to pedestrian gate $162.00
Original allowance for external concrete 21sqmx$55 +
42sqmx$53.5
Additional concrete cost per var3 – additional 46
sqmx$55
Total actual area of external concrete 157.5 sqm
Less previous allowances 109 sqm
Excess area 48.5 sqm x $53.5
$2,595.00
Construct external stair $710.00
Tiling to external stair $600.00
Provide new laundry taps and mixer $120.00
[19] Craig Ferguson says that the costs charged for each variation item
claimed is the actual cost of having the work done plus a 10% margin for
overheads and profit. He says, and I accept, that this is a modest and
reasonable margin in the industry.
[20] Further, he says that many of the variations arise from directions given by
Mr Burnett within a very short time before the work was done or to be
done. He says, and it is not disputed, that Mr Burnett visited the site
almost daily. Mr Ferguson says that Mr Burnett sometimes issued
instructions to Fergbilt’s subcontractors directly and in many cases without
conferring with a Fergbilt representative prior to doing so. Haemish
Ferguson, who was usually present during the works, confirms this and
says Mr Burnett was aware that there would be costs associated with the
extra work he instructed.
[21] Overall in the course of the proceeding, the homeowners have ultimately
conceded some $2,029 in variations, some evident from the material filed
-- 6 of 22 --
7
and several other small amounts as the hearing progressed. The
variations conceded are as follows:
a) Variation 5 $150;
b) (the first) Variation 6 $291;
c) (the second) Variation 6—items 4 ($130), 5 ($180),6 ($85) and
8 ($878), totalling $1,273; and
d) Variation 7— items 1 ($195) and 11 ($120), totalling $315.
[22] In reliance on the homeowners concessions, these amounts are included
in the orders made. I make the observation that in the absence of
concessions, I would in any event have been satisfied that they should be
allowed, as the work has been done in each case on the homeowners
instructions by the builder, who has incurred the costs of supplying
materials and labour.6 I would have been satisfied that the builder would
suffer unreasonable hardship as a result of the strict operation of the
Domestic Building Contracts Act 2000 (Qld) (DBC Act), and that it would
not be unfair to the homeowners for the builder to recover these amounts.
[23] The balance of the variations claimed are disputed by the homeowners.
Of those in dispute, only Variation 3 was put in writing before the work
specified in them was done. Each of them specifies the effect on the
overall price.
What are the requirements for variations to the contract?
[24] In this case, the contract entered into by the parties is in the form of a
Standard Master Builders Contract Version RRC March 2012. Clause 7
provides for variations by agreement. Under the contract either party is
entitled to request a variation.7 If the parties agree to a variation, the
builder must put it in writing in a variation document signed by both parties
within the shortest practical time and before the work is done.8 If the
contractor requests the variation, it is payable only if it was necessary
because of circumstances that could not reasonably have been foreseen
when the contract was entered into.9
[25] The DBC Act applies to this fixed price contract for domestic building work.
It provides that variations must be put in writing, and if the variation is for
an addition to the works, before the subject work is carried out.10 Variation
6 Detailed reasons are not required where a party consents to the basis of an order or
part of it (that is, where a party concedes an issue): Brown & Anor v Noosa
Constructions Pty Ltd [2012] QCATA 194, [69].
7 Exhibit 6, attachment 12, page 113, clause 7.1.
8 Ibid, clause 7.3. Also, 7.7 provides that as soon as possible and within 5 days of
agreement about a variation, the contractor must give the homeowner a copy of the
signed variation document.
9 Ibid, clause 7.6.
10 DBC Act s 79(1). However, there is an exception if the work is urgent and it is
impractical to reduce it to writing before it is done: DBC Act s 79(2).
-- 7 of 22 --
8
documents for fixed price contracts must state the change to the contract
price or how it is to be calculated.11 As soon as practicable after the
variation document is made, the builder must sign the document and take
all reasonable steps to have the homeowner sign it.12
[26] The right of a builder to recover for variations is provided for in s 84 of the
DBC Act. If a variation was sought by a homeowner, a builder may recover
an amount for the variation only if the relevant sections of the DBC Act
have been complied with (s 79, s 80, s 82 and s 83), or alternatively with
the Tribunal’s approval.13
[27] If the variation was not originally sought by the homeowner, the builder
may recover for a variation only if it complied with s 79, s 80, s 82 and s 83
and the ground of unforseen circumstances (that is, because of
circumstances which could not have been reasonably foreseen by the
builder when the contract was entered into)14 applies, or alternatively with
Tribunal’s approval.15
[28] The Tribunal may approve recovery for a variation only if, either, there are
exceptional circumstances warranting such an order, or the builder would
suffer unreasonable hardship as a result of the requirement to comply with
s 79, s 80, s 82 and s 83.16 However, it may only do so if it would not be
unfair to the homeowner for the builder to recover the amount.17
[29] The Appeal Tribunal has accepted that when instructions have been given
by a homeowner to perform works which are a variation to the contract,
those works have been carried out, and the homeowner has received the
benefit of them, a builder will usually suffer unreasonable hardship by not
being able to recover an amount for those works and it would not be unfair
to the homeowner for the builder to recover it.18
The Evidence and Credibility Issues
[30] Witness statements and a volume of attachments were provided by the
directors of Fergbilt, Craig Ferguson and Haemish Ferguson, who are both
builders and who both had dealings with the homeowners. Mr Burnett
provided a witness statement also with a large volume of attachments, in
which some concessions were made concerning some variation items.
Ms Heath provided a very brief statement. Mr Anthony Trevor, the
draftsman/designer who drew the plans for the homeowners gave oral
evidence pursuant to a notice to attend.
11 DBC Act s 80(2)(e).
12 DBC Act s 82.
13 DBC Act s 84(2).
14 DBC Act s 84(5).
15 DBC Act s 84(3).
16 DBC Act s 84(4)(a).
17 DBC Act s 84(4)(b).
18 Brown & Anor v Noosa Constructions Pty Ltd [2012] QCATA 194, [58] – [60], accepting
the statements made in Black, G v Toowoomba Resort Pty Ltd [2007] QCCTB 122.
-- 8 of 22 --
9
[31] It is clear that the homeowners made many alterations to the proposed
works in the lead-up to the contract being entered into, ruling some items
in and out, and then in again as discussions progressed. They initially
asked for a costs estimate based on preliminary drawings obtained by
them and a detailed scope of works prepared by Mr Burnett. Finding this
outside their preferred budget, they asked for suggestions, which Fergbilt
gave, to reduce costs. They had the plans drawn again and Mr Burnett
produced a new detailed scope of works. The amended/updated
documents were then provided to Fergbilt, the homeowners noting
specifically items they had now deleted from the project.19
[32] Unfortunately, and somewhat misleadingly in my view (given how detailed
they were about what they were now excluding), they failed to point out
that they had nevertheless included in some new additions (including a
significant volume of additional external concreting and tiling).
Also, according to Craig Ferguson, in non-compliance with industry
standards, the revised ‘BA version’ of the plans prepared for the
homeowners and at their instruction by the designer/draftperson did not
contain a revision cloud which would enable a builder to see at a glance
what had been changed since the previous set of plans.
[33] During cross-examination, Mr Burnett made some further minor
concessions concerning small cost items. However, on numerous
occasions, he claimed to have no recollection or knowledge of alleged
events and discussions. For example, in respect of additional concreting in
the front yard alleged by Fergbilt to have been instructed by him at short
notice before the pour, he asserted he had instructed a very small
additional slab (for the rubbish bins to sit on), but that he had no idea why
the rest was concreted. However, inconsistently, he makes no complaint
about it having been done. It is apparent from his material and oral
evidence that Mr Burnett is not a person who is likely to accept something
other than what he believes he bargained for. If he had not instructed the
extra concreting, it would be reasonably expected that he would have
raised as an issue that he had concrete in places where it should not be.
That the extra concreting was apparently entirely to his satisfaction,
suggests to me that Mr Haemish Ferguson’s version of events is accurate.
[34] Mr Burnett also claimed, for example, that although he recalled a
discussion initiated by him about shower niches, but he could ‘not recall’
instructing construction of niches. I did not find his assertion credible.
Once again, the niches were apparently entirely to Mr Burnett’s
satisfaction as no complaint is made about them.
[35] Mr Burnett sought at all times to hold Fergbilt to his detailed scope of
works and the plans, but was reluctant to acknowledge instances when his
instructions amounted to variations to them. For example, vanities to be
provided by the homeowners were to be installed in the bathrooms.
However, the homeowners provided wall hung basins and recessed
19 Exhibit 6, attachments especially at pages 31 and 39.
-- 9 of 22 --
10
cabinets, requiring additional framing works for which instructions were
also provided to the builders.20
[36] In respect of the claimed variations for these items, Mr Burnett said he did
not realise there would be an additional cost. This is at odds with the
approach taken by him to detailing the scope of works. His very detailed
documents suggest to me that he was extremely aware that everything
done in the works cost money and that he wanted to be clear about what
the homeowners were going to get for their money. Similarly, his
assertions that he only looked at the ‘bottom line’ and did not pay attention
to what was included are at odds with his approach to the project and his
prepared scope of works documents. For these reasons, I found his
evidence unconvincing about these matters and I have given it less weight
than the evidence of the Fergbilt representatives.
[37] Ms Heath said she took little part in the discussions. She said in essence
that (although acknowledging being present for three to five discussions in
total) she was not actively involved in discussions and did not have
specific recollection of anything. She further said that she did not
participate in decisions and conversations as a matter of course when she
was present at the premises: she often just looked at what had been done.
The extent of her asserted lack of recollection is surprising. That said, it is
apparent that she largely left the running of the project to Mr Burnett.
[38] It is common ground that there were two measurement errors in the plans
instructed and obtained by the homeowners in respect of which variation
claims arise. Mr Burnett’s evidence was that by virtue of the designer’s
contract with the homeowners the designer was to have liaison with the
builder. He does not allege any such inclusion in the contract with the
builder. The designer, Mr Trevor, gave evidence at the hearing. He said
that he had no contact with the builder and essentially provided a drafting
service. He seemed to deny that his contract with the owners provided for
liaison with the builder. He did implicitly acknowledge that a detailed
survey was undertaken to do measurements for the plans he prepared,
although asserting that the builder should have measured twice and acted
once.
[39] It is apparent from the evidence that Mr Craig Ferguson did not look as
closely at the various versions of voluminous documents forwarded to him
by Mr Burnett as he could have to ascertain that there were undisclosed
changes made, in addition to the disclosed ones. It is also apparent that
he did not as a matter of course attend to preparing all variation
documents and having them signed before the work was done in
accordance with the contract.
[40] The evidence of both Craig Ferguson and Haemish Ferguson presented
as plausible and consistent with the documentation available and with the
events which occurred. In contrast, some of Mr Burnett’s evidence about
not recalling giving instructions as discussed above, was inconsistent with
20 Exhibit 9.
-- 10 of 22 --
11
events which then occurred. For this reason, I have preferred their
evidence over Mr Burnett’s and given it more weight where there is a
conflict between them, or either of them, and Mr Burnett.
Variation 3 dated 17 September 2013 and concreting in Variation 7 dated
13 December 2013
[41] Craig Ferguson says that he signed the ‘BA plans’ as part of the contract
without appreciating some changes that had been made to them after the
preliminary plans on which he had based his initial costings. In particular,
the differences included extensive increases in the areas of concreting
and paving to the exterior of the building. His original cost estimate
included provision for the external concreting was $1,155 and for external
tiling $1,035. The tiles themselves were to be provided by the
homeowners.
[42] In approximately mid-September 2013, Craig Ferguson realised the
difference in the BA Plans. He met with the homeowners and discussed
the issue. The homeowners asked for a price for the increase and he
provided them with Variation 3 totalling $4,418 as follows:
Variation 3
Description Cost
Supply and spread top soil to elevated area at rear of
site
$550.00
Additional areas of reinforced concrete slab to rear and
sides of building 46 sqm x $ 55 plus supply of pump
$550
$3,080.00
Lay and grout additional external tiles (provided by
proprietor) to the area at the back of the house 17.5 sqm
x $45
$788.00
[43] Mr Burnett says that the homeowners initially rejected the variations for
concreting and tiling drawing Mr Craig Ferguson’s attention to the contract
documentation. However, he says that Mr Ferguson would not accept this
and as they did not want to get off-side with the builder, the homeowners
reluctantly agreed to accept the variation. However, Mr Burnett replied,
suggesting that Mr Ferguson had overestimated the additional square
meterage, asserting that the external concrete and tiled area in the revised
BA plans was in total 109 square metres, but accepting the rates quoted.
Mr Ferguson responded that he would remeasure the area following the
completion of the works and charge only for the actual increase using the
rates set out.
[44] The homeowners amended and signed the variation on 1 November 2013,
reducing the square metres to 40 and reducing the price for concreting to
$2,750 (from $3,080).
-- 11 of 22 --
12
[45] The concreting was done in December 2013. Late on the day before the
pour, Mr Haemish Ferguson was supervising at the site when he says,
Mr Burnett came onsite and instructed additional areas at the front of the
property be concreted as well. Mr Craig Ferguson was advised and he
passed these instructions on to the subcontractor engaged to do the
concreting works. The following day, the concreting was done in
accordance with Mr Burnett’s instructions.
[46] Mr Ferguson subsequently measured the increased areas and found the
total to be 157.5 square metres. That is, 48.5 square metres greater than
Mr Burnett’s earlier measurement. I accept Mr Ferguson’s measurement
as correct (and the final meterage does not appear to be disputed by the
homeowners, although responsibility for the cost of it is).
[47] Fergbilt then claimed as part of Variation 7, another additional amount for
concreting of $2,595 as follows:
Original allowance for external concrete 21sqmx$55 +
42sqmx$53.5
Additional concrete cost per var3 – additional 46
sqmx$55
Total actual area of external concrete 157.5 sqm
Less previous allowances 109 sqm
Excess area 48.5 sqm x $53.5
$2,595.00
[48] Mr Ferguson explains that the additional amount of $2,595 incorporates
the balance of the increase in concrete costs between the preliminary
plans and the BA Issue plans (which had been included in Variation 3 but
was unpaid by the homeowners of $330) and the additional concreting at
the front of the property instructed the day before the pour. Accordingly,
the difference of 6 metres of concrete (at a cost of $330) between what
the homeowners paid for variation 3 ($4,088) and the actual amount of
Variation 3 ($4,418) was claimed in Variation 3 and again in Variation 7,
presumably because of the homeowners amendment to Variation 3. I note
that the cost charged per square metre in Variation 7 is $1.50 per square
metre less than in Variation 3, that is, in total $321. The amount of $2,595
is otherwise to cover the additional concreting in the front yard.
[49] Mr Burnett now says, after taking further advice, that the homeowners
dispute the variation for additional concreting and tiling in Variation 3
because it was covered by the contract. He says in essence that they are
entitled to offset the amount paid for the additional concreting and tiling of
$3,538 against any variations allowed.
[50] Each of the costs estimates prepared by Fergbilt include an amount of
$1,155 for the external slab and tiling of $1035. It is clear that Craig
Ferguson did not increase the estimate after receiving the BA Issue Plans
which included a significantly greater area of concreting at the rear of the
property than the preliminary plans. As discussed earlier, the plans did not
-- 12 of 22 --
13
contain a revision cloud to indicate the changes made, which I accept as
Mr Ferguson says, is standard industry practice. It is plainly unrealistic that
every revision should require that a builder compare each and every
construction item on revised plans to ascertain precisely what has
changed. Further, despite pointing out changes made by them to delete
items from the project, the homeowners failed to point out when they
made additional inclusions which any reasonable person would expect to
increase costs.
[51] That aside, Fergbilt’s representative signed the contract which included
the BA Issue Plans. Despite the failures of the designer and homeowners
discussed above, as a director of Fergbilt, Mr Ferguson had responsibility
for his dealings on its behalf and signed the contract. Accordingly, I would
have held Fergbilt to the contract signed by him on its behalf in respect of
this item.
[52] However, on both versions of events, the contract was varied by later
agreement. The homeowners agreed to pay the additional costs for the
concreting and tiling in the back yard, except for $330. The homeowners
signed Variation 3, although altering the concreting amount to $2,750 (for
40 sqm at $55 and pump fees) and decreasing the total to $4,088.00.
They subsequently also acted on that later agreement and satisfied the
amount.21 The homeowners cannot now unilaterally go back on that later
agreement. Therefore, the homeowners are not entitled to offset the
amount for other variations.
[53] Mr Ferguson says that he was to remeasure the concreted area following
completion and the actual increase was to be paid for. He did not accept
that the square meterage calculated by Mr Burnett was correct.
[54] In respect of the $330 which was not paid in variation 3 for which $321
and is later again claimed in variation 7, the variation was requested by
the builder because of changes to the plans, which had not been identified
by the builder at the time the contract was entered into. The circumstances
leading to the request could have been reasonably foreseen by the builder
at the time the contract was entered into had he looked more closely at
the BA plans. I am not satisfied that the builder would suffer unreasonable
hardship by the operation of s 84(3)(a), nor that it would not be unfair to
the homeowner for the builder to recover the amount. I would dismiss the
builder’s claim for this amount.
[55] With respect to the front yard, Mr Burnett acknowledges giving instructions
to Haemish Ferguson for a small amount of additional concreting where
the garbage bins were to be stored. He says that he did not ask for the
more extensive concreting referred to in the variation.
[56] I consider that it is inherently unlikely that Haemish Ferguson was
mistaken about the request, particularly because the homeowners later
made no complaint about the concreting of a large area of their front yard,
21 Exhibit 2, attachment 5.
-- 13 of 22 --
14
which was not their desire and contrary to their instruction. It is clear from
his material that Mr Burnett is quite particular, and was very involved in
setting the detail for the project. I accept that it is more likely than not that
Mr Burnett instructed the concreting. I find that Mr Burnett did make the
request and instruct the additional concreting in the front yard as Fergbilt
alleges.
[57] Variation 7 is dated 13 December 2013. It has not been signed by the
homeowners. When the homeowners finally responded to the variation
claim on 13 February 2014, they refused to pay any amount specified in
Variation 7, including the $2,595.
[58] I find that the variation in respect of this item was not prepared in
accordance with the contract: amongst other things, it was not prepared
before the concrete was laid, except in respect of the $330, which had
been included in Variation 3 and which I have already indicated I would
disallow.
[59] However, the Tribunal can make an order approving recovery of an
amount in accordance with s 84(2)(b) and s 84(4).
[60] I have found that to the extent that the amount in Variation 7 was for the
front yard, Mr Burnett instructed it late on the day before the pour. I am
satisfied that the amount for concreting referable to the front yard is
$2,595 less the $321 claimed for the back yard. That is, $2,274.
[61] It is common ground that the work has been done. The builder has
therefore incurred the labour and materials costs to carry out the work. I
am satisfied that the builder would suffer unreasonable hardship by
operation of strict compliance with s 79, s 80, s 82 and s 83 of the DBC
Act. I am also satisfied that it would not be unfair to the homeowners for
them to pay for the additional concreting works that they instructed.
[62] Therefore, I would allow the amount of $2,274 for the concreting
component of Variation 7.
Variation 5 dated 14 November 2013: $150
[63] This variation was for an additional 2 single GPOs for the security system
at a cost of $150. The builder says that during construction Mr Burnett
advised that he wanted a security system installed. It was not covered by
the contract. In November 2013, the builder later discovered that Mr
Burnett attended at the site and gave instructions directly to his electrical
subcontractor to install 2 single power points for the security system.
[64] The homeowners now concede that they rejected this item in error. It has
not been paid and is owing to Fergbilt.
The first variation 6 dated 19 November 2013: $291
-- 14 of 22 --
15
[65] The variation is in the amount of $291 for specified electrical fittings.
As discussed earlier, the homeowners now also concede this amount is
owing to Fergbilt.
The second variation 6 dated 13 December 2013: $7,206
[66] Centre lower floor shower waste under rose: $240. As the builder says,
the contract specifies the placement of the waste in the downstairs
bathroom, but not the placement of the shower rose. During construction,
Mr Burnett told Haemish Ferguson to move the shower waste to a position
nominated by him under the shower rose. Haemish Ferguson says that
this required an extension of the drainage system. Also, he says that Mr
Burnett instructed a square drain rather than a strip drain. Haemish
Ferguson says that he advised Mr Burnett of additional costs involved.
[67] Mr Burnett says that the plumber had not installed the waste under the
rose as he had specifically told him to do. He also says that Haemish
Ferguson recommended a square drain rather than strip drain. It is implicit
in these concessions that he told the plumber to move the waste outlet as
alleged and instructed the square drain. I draw the inference that he did
so. He says that the cost was because of the plumber’s error.
[68] I find that the contract did not require placement of the waste under the
shower rose. I accept that placement of the square drain in accordance
with Mr Burnett’s instructions required an extension of the drainage
system.
[69] The variation was requested by the homeowner. The work has been done
and the builder has incurred the costs of it. I find that the builder would
suffer unreasonable hardship by the operation of s 84(2)(a). Further, I find
that it would not be unfair to the homeowner for the builder to recover for
the variation instructed by them in the sum of $240.
[70] Provision of shower niches: $920. Haemish Ferguson says that
Mr Burnett instructed him to construct niches in the walls of the shower
recesses (which were not on the plans), which required additional timber
framing, wall sheeting, waterproofing and tiling.
[71] Mr Burnett concedes he initiated a discussion with Haemish Ferguson
about shower niches at the premises at which he was staying during the
renovation. However, he claims that he does not recall the end of the
conversation, that is, whether he instructed them to be constructed in the
works. He says that there is no evidence to say that he did, and in any
event if he had been given a variation document, he would not have
instructed them at the cost of $920 for soap dishes.
[72] I do not accept Mr Burnett’s assertion that he does not recall whether he
instructed the niches. It makes no logical sense. He raised the issue of
niches, because of the niches where he was staying, not the builder.
Haemish Ferguson gives evidence that he instructed niches in the works.
I am satisfied that, as Haemish Ferguson says, Mr Burnett requested and
-- 15 of 22 --
16
instructed the niches. However, under the contract and the DBC Act, a
written variation should have been given before the work was done
including advising the homeowners of the cost associated with installing
them before the work was done.
[73] I accept that $920 is a relatively significant cost for what are essentially
soap dishes. However, in the context of the renovation and the costs of
the labour and materials required to install them, I consider that it is a
reasonable cost being only the cost of the work plus a 10% margin. I find
that the building contractor would suffer unreasonable hardship by
operation of s 84(2)(a) if the variation was not allowed and that it would
not be unfair to the homeowners for Fergbilt to recover the amount
claimed for this work instructed by them.
[74] Reframe external stair and landing: $2,940. The builder says that the
plans provided by the homeowners contain two errors. One error involves
the front stairs. A leaf of the window in the master bedroom could not be
fully opened once the stairs were in place because it hit the new handrail.
[75] Both Mr Fergusons and Mr Burnett met onsite to discuss the best way to
overcome the problem. Craig and Haemish Ferguson both say it was
agreed that the stairs would be demolished, the new patio landing cut
back, and new stairs constructed. They say that Mr Burnett instructed
those works. Mr Burnett then went away for work for several days. Mr
Craig Ferguson says Mr Burnett subsequently asked for more information
about the work required so that he could endeavour to recoup some costs
from the drafting company that prepared the plans. He provided this
information by email to Mr Burnett on 30 January 2014.
[76] Mr Burnett acknowledges that the homeowners wanted full function of the
affected street-facing window and that he rejected the proposed solution
of Craig Ferguson that the affected leaf of the window could be nailed
shut. He says he instructed modification of the handrail. He also says he
requested (which is denied by Craig Ferguson) that Craig Ferguson
contact the draftsperson/designer to discuss options.
[77] Mr Burnett submits, but produced no independent expert evidence to this
effect, (although the designer was called to give evidence, he is not
independent as he does not wish to be considered responsible) that it is
not uncommon for measurements to be ‘slightly out’ on plans for
renovation of older homes and that it was incumbent upon the builder to
double check the draftsperson’s calculations. I have no evidence that
good building practice required this in the context of a detailed survey
having been obtained by the designer. In these circumstances, it seems
reasonable that the homeowners plans were relied upon by the builder. In
any event, it is acknowledged that the issue results from a mistake in the
plans in respect of which the homeowner was asked for instructions. If the
builder had considered it his error, he may have found a solution other
than the one that was instructed by the homeowners, of demolishing the
stairs.
-- 16 of 22 --
17
[78] Also, Mr Burnett says that he did not receive a written variation before the
work was done, and that he was ‘completely unaware’ that the builder
intended to demolish the stairs and issue a variation for $2,940.
[79] I give greater weight to the evidence of Craig Ferguson and Haemish
Ferguson. What they say makes logical sense. I do not accept that they
demolished new stairs and incurred the cost of replacing them,
reconfigured slightly, in the absence of clear instructions to do so. Mr
Burnett’s evidence makes it clear that he considered that only a solution
which allowed all of the front street-facing windows being able to fully
open was acceptable, referring to the substantial investment being made
in the home. I find that Mr Burnett did give the instruction alleged by the
builder.
[80] However, once again the builder failed to provide the written variation
document as required, among other things setting out the costs before the
work was done. On this occasion, this failure occurred in the context of
Mr Burnett going away for several days and completion of the works being
imminently due under the contract, in circumstances that Mr Burnett was
exerting pressure on Fergbilt for the works to finish on time. However, it is
reasonable to infer that Mr Burnett knew that giving the instruction to
demolish and reconfigure the stairs would involve some significant costs.
[81] I find that there were exceptional circumstances. The builder could not
have known that there were errors in the plans instructed obtained and
provided by the homeowners, particularly in circumstances when a
detailed survey had been undertaken by the designer before drawing the
plans. The builder has done the work instructed by the homeowner,
incurring the costs of labour and materials. I am satisfied that the builder
would suffer unreasonable hardship by operation of the requirements in s
84(3)(a). I am satisfied in the circumstances that it would not be unfair to
the building owner for the builder to recover the amount claimed of $2,940.
[82] Patching down light holes: $130; Supply and install AC bracket:
$180; and additional light over downstairs toilet: $85. These items
were conceded by the homeowners at the hearing.
[83] Replace wall light over vanity upstairs bathroom: $40. The builder
says that no electrical work in the upstairs bathroom was included in the
contract (it having been ruled out of the works by the homeowners at that
stage).22 Craig Burnett says that Mr Burnett directly instructed the
electrical subcontractor to replace the light.
[84] Mr Burnett initially insisted that it was included in the works, but later
conceded the item.
[85] Renovation of east and west window awnings repaint and provide
new sheeting and mini gable roll: $878. This item was conceded by
22 Exhibit 6, page 137 sets out the electrical works included.
-- 17 of 22 --
18
Mr Burnett, although Mr Burnett insisted a variation was not issued.
Presumably, he means before the work was undertaken.
[86] Realign stair well wall to meet line of upstairs walls and associated
structural works: $1,793. This item arises out of the second alleged error
in the plans. As the works progressed, it was discovered that the internal
stair position did not line up with the upstairs walls. Once again, both Craig
and Haemish Ferguson met onsite with Mr Burnett to discuss how to
overcome the problem. The builders say that it was agreed that an
additional wall would be constructed downstairs, a supporting beam cut
back, and a steel beam relocated to overcome the error in the plans. A
new column also had to be constructed and additional carpentry work to
the existing floor frame. Craig Ferguson says once again that on Mr
Burnett’s request, he subsequently prepared a detailed explanation of the
work and costs which Mr Burnett hoped to claim from the designer.
[87] Mr Burnett says the error in the plans was about 100mm, so that the
critical lower floor wall did not line up with the upstairs wall of the internal
stairs. Once again he says he was not given an estimate of costs before
the work was done and that the homeowners were unprepared for the
high additional costs. Once again, he claims that the designer says that
the builder should have checked his measurements rather than relying on
them. However, the designer has an interest in ensuring that blame is not
attributed to him. I have no independent evidence that good building
practice required independent measurement in these circumstances. A
detailed survey had been done by the designer. I consider that it was
reasonable in the circumstances for the builder to rely on the homeowners
plans.
[88] Once again, the contract and the DBC Act were not complied with: the
signed variation document was not obtained as required before the work
was done. The variation was originally sought by the builder. I am satisfied
that there were exceptional circumstances, as the builder could not
reasonably have foreseen the error in the homeowners plans upon which
he was entitled to rely. The builder has done the work instructed by the
homeowner, incurring the costs of labour and materials. I am further
satisfied that the builder would suffer unreasonable hardship by the
operation of s 84(3)(a). I find that it is not unfair to the homeowner for the
builder to recover the amount.
Variation 7 dated 13 December 2013
[89] New sill stop for underside of existing living room bifold doors: $195.
At hearing, this item was conceded as owing by the homeowners,
although I note that again Mr Burnett says a variation document was not
provided. Once again, it appears he means before the work was done.
[90] Increased height of tiles to ensuite walls and provision of hanging
rail to cover variations in wall thickness: $128. During construction,
Haemish Ferguson says that Mr Burnett instructed him to increase the
height of the tiles on the ensuite wall over the allowance in the contract
-- 18 of 22 --
19
documentation. Mr Burnett says that he told the builder that he wanted the
tiles to the height of the picture rail before the contract. He acknowledges
a discussion with Haemish Ferguson, but says he was referring to his
earlier discussion with Craig Ferguson about the height of the tiling.
However, when cross-examined about this, he was unable to point to
anything in the contract documentation which provided for tiling to this
height.
[91] Fergbilt’s schedule of work23 refers to installing tiles in the bathrooms in
showers to 1.8m but elsewhere to ‘1000 high.’ Even the detailed scope of
work prepared by Mr Burnett, as far as I have found it forms part of the
contract, does not refer to the tile height contended for by Mr Burnett.
[92] I find that this variation was instructed by Mr Burnett on behalf of the
homeowners. The work has been done, and the builder has incurred costs
of labour and materials. I am satisfied that the operation of s 84(2)(a) of
the DBC Act would cause the builder unreasonable hardship in these
circumstances and that it would not be unfair to the building owner for the
contractor to recover the amount for the tiling instructed by Mr Burnett.
Installation of additional framing and setout for wall hung basins: $265;
and Additional wall framing for insertion of recessed bathroom cabinets:
$195.
[93] It is common ground that the contract documentation includes vanity units
with basins set into them in the bathrooms. However, the homeowners
provided wall hung basins and recessed vanity units for installation which
required additional work.24 In response to questions, Mr Burnett said that
nothing had been said about there being any additional costs to install
them. He acknowledged providing instructions to the effect that that this is
what the homeowners required only once it reached the time for them to
be installed. He gave the units, together with installation instructions to the
builder. There were three of these provided for installation.
[94] However, Mr Burnett says that variations had not been raised and yet he
was being charged $265 for the extra framing and $195 for the extra work
in installing the recessed cabinets although he had not been provided any
details. Mr Burnett further said essentially that he did not think there would
be any additional costs for installing these items notwithstanding that they
were different from what was in the plans, because he was not a builder
and he did not ask the question. He said there was no schedule to say
specifically the type of fitting to be provided. He considers this variation
totalling almost $500 unreasonable.
[95] I do not accept that Mr Burnett thought there was no cost to undertake
additional framing and other work. For the reasons explained earlier, I am
satisfied that Mr Burnett was aware that all items of additional work cost
money. The builder has performed the work, incurring the costs of labour
23 Exhibit 6, page 143-146, at item 5.06 (page 145).
24 Exhibit 9, Installation sheet for recessed vanity unit.
-- 19 of 22 --
20
and materials. In the circumstances that the homeowners instructed the
variation, I am satisfied that the builder would suffer unreasonable
hardship by the operation of s 84(2)(a) and that it would not be unfair to
the homeowner for the builder to recover the amount claimed for this
variation.
Installation of letterbox: $110.
[96] This item is not in contention: Fergbilt’s claim was reduced by the amount
of this item.
Pier caps less credit on gate & fence panel PC: $48.
[97] The plans show piers with a square finish. Craig Ferguson says that
Mr Burnett requested pier caps, which he agreed to supply and off-set the
cost against savings on the provisional cost for the front gate. The
additional cost after the off-set was $48.
[98] Mr Burnett says that he had advised Craig Ferguson that he wanted a
fence exactly the same as a neighbour’s fence which had pier caps, and
that this detail was included in his scope of works. The scope of works
document refers to a block and metal rendered fence ‘as per plans,’
although (inconsistently with the plans) a photograph is provided of a
fence with pier caps.25
[99] However, I am satisfied that there is no discrepancy between the plans
and the words in the scope of works documents. The plans are a part of
the contract. Despite including a photograph with pier caps, the scope of
works refers back to the plans. The plans do not include pier caps.
[100] The homeowners instructed the pier caps which were not included in the
contract. The builder has supplied and fitted the pier caps, incurring labour
and materials costs. I find that the builder would suffer unreasonable
hardship by operation of s 84(2)(a) of the DBC Act and that it is not unfair
for the homeowner to pay the builder for the pier caps instructed by
Mr Burnett.
Provide and install electric strike to pedestrian gate: $162.
[101] Haemish Ferguson asserts that towards the end of construction, Mr
Burnett requested installation of an electric lock release to allow the front
pedestrian gate to be unlocked from inside the house. Craig Ferguson
says that an additional electrical wire to the front fence was paid for by the
homeowners, but an electric strike was required to be connected to the
installed wire to allow it to be operated from within the house.
[102] Mr Burnett acknowledges that the interior pad was not part of the contract:
it was installed and fitted off by an installer engaged by the homeowners
for this purpose, but he maintains that that the electrical strike was part of
25 Exhibit 6, attachment 7, page 75 and attachment 17, page 199.
-- 20 of 22 --
21
the scope of works. He referred in cross-examination to it being covered
under item 4.8.4 or 7.3.10, neither of which refers to it.
[103] The electrical strike was part of the requirement for the in-house lock
release, which was only instructed at the end of construction. Logically,
there could have been no agreement about it or provision for it in the
contract since it was not anticipated when the contract was entered into.
[104] I find that Mr Burnett on behalf of the homeowners instructed this item as
alleged by Fergbilt. It has been provided, and the builder has incurred the
costs of providing it. The builder would suffer unreasonable hardship by
the operation of s 84(2)(a). It is not unfair for the homeowners to pay for
the item requested by them.
Additional concrete: $2,595.
[105] This item has been dealt with earlier.
Construct external stair: $710 and Tiling to external stair: $600.
[106] Although originally the pre-contract negotiations included the construction
of rear stairs off the back deck, these were deleted from the project by the
homeowners after the first budget, as is apparent from the second budget
provided by Fergbilt. The preliminary plans did not include the stairs.
However, the BA approved plans do include concrete stairs. Craig
Ferguson says that Mr Burnett was made aware that the cost was not
included in the contract price. Craig Ferguson says that he requested that
they be constructed and tiled in any event.
[107] As Mr Burnett points out, the BA plans include concrete stairs from the
rear ground floor patio to the rear yard upper grassed area (rather than
from the back deck). He contends that they were therefore included in the
contract. He did not specifically respond to Craig Ferguson’s assertions
that it was discussed as alleged.
[108] The preliminary plans did not include the stairs. However, unlike the
situation concerning the additional concrete in the back yard, Fergbilt does
not allege that there was an agreement to vary the contract following the
discovery by Mr Ferguson that the BA Plans had considerably altered
what was to be done in the back yard.
[109] I find that the external stairs and tiling form part of the original contract.
There was no agreement to vary: the work was simply done. Fergbilt’s
representatives are responsible for the initial oversight of changes in the
plans which had not been disclosed. I consider that there is no basis upon
which the claimed variation should be allowed under s 84(3) and (4).
I dismiss the claim for it.
Provide new laundry taps and mixer: $120.
[110] Craig Ferguson says that the homeowners were to provide all plumbing
fittings under the contract. He says that they nominated that the laundry
-- 21 of 22 --
22
taps were to be reused. Haemish Ferguson says that in his presence
Fergbilt’s plumbing contractor advised Mr Burnett that the existing taps
were defective and that Mr Burnett instructed the subcontractor to source
and install new laundry taps and a mixer for the tub.
[111] Although responding that the homeowners were not issued with a
variation for the item, Mr Burnett concedes this item is a variation.
Amount outstanding for variations approved or conceded
[112] Having regard to the amounts conceded by the homeowners as payable
and the variations allowed by me the amount of $11,034 remains owing
for variations to the builder by the homeowners, calculated as follows:
(part) Variation 3 $ nil
Variation 5 $150
(First) Variation 6 $291
(Second) Variation 6 $7,206
Variation 7 $3,387
Total $11,034
Costs and interest
[113] The contract specifies interest of 10% is due on overdue payments.
However, Fergbilt did not document the variations in accordance with the
contract or the DBC Act. Therefore, it was entitled to payment for the
amount only with the Tribunal’s approval. Accordingly, I do not consider
that the payments are overdue. I refuse the claim for interest.
[114] Fergbilt also claims its filing fee of $285. Fergbilt has been substantially
successful on its claim. I accept that it is in the interests of justice that the
homeowners pay their costs in this amount.
Orders
[115] I make orders requiring that the homeowners pay the builder the sum of
$11,319 within 28 days of the date of these orders.
-- 22 of 22 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/517