Albion Projects Pty Ltd v Simpson (No 2) [2014] QCAT 515
CITATION: Albion Projects Pty Ltd v Simpson (No 2) [2014]
QCAT 515
PARTIES: Albion Projects Pty Ltd ABN 82 122 540 576
(Applicant)
v
Jonathon Simpson and Kim Simpson
(Respondents)
APPLICATION NUMBER: BDL104-13
MATTER TYPE: Building matter
HEARING DATE: 25 and 26 March 2014
HEARD AT: Brisbane
DECISION OF: Member King-Scott
DELIVERED ON: 15 October 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. Jonathon Simpson & Kim Simpson will
pay Albion Projects Pty Ltd the sum of
$234,650.85 plus GST.
2. Jonathon Simpson & Kim Simpson will
pay interest to Albion Projects Pty Ltd on
the said sum at a rate of 15% for
2.5 years.
3. The Respondents’ Counter-claim is
dismissed.
4. The Applicant must file in the Tribunal
two (2) copies and give to the
Respondents one (1) copy of written
submissions in respect to the calculation
of damages inclusive of GST, interest and
costs, by 4:00pm on 3 November 2014.
5. The Respondents must file in the
Tribunal two (2) copies and give to the
Applicant one (1) copy of their
submissions in reply, by 4:00pm on
10 November 2014.
CATCHWORDS: Building dispute –Parties to the contract –
Relevance of pleadings – Costs Plus Contract
-- 1 of 15 --
2
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr P Freeburn QC instructed by Feehly Project
Law
RESPONDENT: Mr G Del Villar instructed by ClarkeKann
Lawyers
REASONS FOR DECISION
[1] The Respondents are the owners of a residential property situated at
22 Langside Road, Brisbane.
[2] They are in dispute with the Builder, Albion Projects Pty Ltd.
That company entered into a Contract dated 31 May 2010 with the
Respondents to complete the construction of the house pursuant to a
Costs Plus Contract, following the termination of the original Builder’s
Contract in early May 2010. The Contract is in the form of the Master
Builders’ Standard Costs Plus (Residential) Contract, CP-5 January 2010
edition.
[3] The Respondents are named in the Contract as parties but it is a matter of
dispute as to whether Kim Simpson was a party.
[4] The estimated total cost of the works was $1,913,774 exclusive of GST.
[5] The Applicant’s claim is for moneys owing under the Contract. At the
outset of the hearing the Respondents abandoned a significant part
($500,000) of their counter-claim for rectification of bluestone tiles.
[6] The areas of dispute can be categorised as follows:
a) Identity of the parties to the Contract;
b) Value of the Actual Cost of Works;
c) Adjustment for Preliminaries or Costs Plus Fees;
d) The $25,000 agreement in lieu of adjustments;
e) Charges for additional duties;
f) Testing of bluestone tiles and legal costs;
g) Late interest payments;
h) The Westpac Bank guarantee;
i) Counterclaim:
i) delay;
ii) defects.
-- 2 of 15 --
3
Pleadings
[7] The issues before the Tribunal were identified in pleadings filed by both
parties. The Applicant filed a Statement of Claim and then an Amended
Statement of Claim, the Respondents filed a Response and Counter-
Application and then an Amended Response and Counter-Application.
The Applicant has also filed a Reply to the Owners’ Response and
Counter-Application.
[8] The matter was conducted on the basis of the pleadings, at least up to the
door of the Tribunal on the first day of hearing.
[9] It is true that there are no provisions in the Queensland Civil and
Administrative Tribunal Act 2009 or Rules for the filing or exchange of
pleadings. Nevertheless, in complex building disputes before the Tribunal,
it has become the norm, at least in my experience.
[10] The Respondents, in their Submissions, as a general observation suggest
the pleadings are a mere aid to understanding the respective positions of
the parties and that admissions contained in the pleadings are not
admissions in the sense used in the Uniform Civil Procedure Rules 1999.
Though that may be the case, such “admissions”, from an evidentiary
point of view, should be given significant weight. The parties here have
chosen to plead their respective cases in some detail. In those
circumstances, should a party decide to depart from the case pleaded,
then, in the absence of a satisfactory explanation, an adverse inference
may well be drawn.
Parties to the Contract
[11] The Contract identifies Jonathon George Simpson and Kim Simpson as
‘Owners’ in the Contract. Only Jonathon Simpson signed the Contract,
but the Applicant submits he signed on behalf of his wife as his signature
on the Contract is contained in a box prefaced with the description, ‘for
and on behalf of the Owner [s]’.
[12] Section 30 of the Domestic Building Contracts Act 2000 provides that:
A regulated contract has effect only if it is signed by the building contractor
and building owner (or their authorised agents).
[13] In evidence, Mr Simpson said that until recently he thought his wife had
signed the Contract and was a party. Counsel for the Applicant submits
that was some time after February 2014 as the pleadings up to that stage
admitted that they were Owners.
[14] Mrs Simpson is a party to the proceedings. Until recently, no issue was
taken by her that she was not a party to the Contract. Her conduct during
the course of the construction and matters peripheral to it suggest that she
was a party. Counsel for the Applicant referred to insurance documents,
invoices, progress claims, the demand on the bank guarantee,
the engagement of solicitors and the pleadings in this case all of which
-- 3 of 15 --
4
have Mrs Simpson as a party. Counsel submitted that these are all facts
from which an inference could be drawn that she acted and behaved as a
party to the contract.
[15] In determining whether Mrs Simpson was a party to the Contract, it is
instructive to look at the intention of the parties when contracting. In Air
Great Lakes Pty Ltd v KS Easter (Holdings) Pty Ltd (1985) 2 NSWLR 309,
Mahoney JA said at 330 – 331:
The proper view is … that the existence of a contract is a consequence
which the law imposes upon, or sees as a result of, what the parties have
said and done. Actual subjective intention to contract is a factor which the
law takes into account in determining whether a contract exists but is not, or
not always, the determining factor.
…
The result is therefore that intention to contract, in the subjective sense, is
relevant to but not determinative of the existence of a binding contract.
It acts, in a sense, as a limiting factor, that is, as a reason for not giving to
what, on the face of it, is an exchange of congruent promises, the legal
consequences which would otherwise be given to it.
[16] In Babsari Pty Ltd v Wong (2000) 2 Qd R 576, Chesterman J said:
[29] … When deciding whether a contract has been made the law has
preferred to rely upon objective indications of agreement rather than
assertions by one, or both, of the parties that no agreement was
actually intended. As Blackburn J put it in Smith v Hughes (1971) LR
6 QB 597 at 607:
If, whatever a man’s real intention may be, he so conducts
himself that a reasonable man would believe that he was
assenting to the terms proposed by the other party, and that
other party upon that belief enters into the contract with him, the
man thus conducting himself would be equally bound as if he
had intended to agree to the other party’s terms.
[17] From an objective point of view the clear inference is, that in the absence
of Mrs Simpson signing the contract, Mr Simpson signed on behalf of his
wife who it was always intended was to be a party. It may be that it was
an oversight that she did not sign at the time but the authority provision in
the signing clause of the contract was sufficient to overcome that
omission. I am satisfied that Mr Simpson was Mrs Simpson’s authorised
agent when he signed the contract.
[18] I note she was a party to the original Contract which was determined at an
early stage. Mrs Simpson did not give evidence, except by filing a short
statement in which she asserted that ‘she did not request Jonathon
George Simpson to enter the contract on her behalf’. I find those words
have been carefully chosen. I have no doubt that they are true.
The situation did not arise where such a request was required. Clearly, it
was assumed that she had signed. Pointedly, she does not say that he
was not authorised to sign on her behalf, that it was never intended that
-- 4 of 15 --
5
she be a party to the Contract or it was a mistake that her name was
stated to be as Owner.
[19] I find that Mrs Simpson was a party to the Contract.
Actual Costs of Works
[20] The Owner is obliged to pay the Contractor the Contract Price in
accordance with the Contract1. Further provision for payment is as
follows:
11.5 Owner’s obligation to pay the Contract Price
The Owner must pay the Deposit to the Contractor, upon signing of
this Contract.
11.6 Contractor to make progress claims
The Contractor is entitled to claim payment of the Contract Price
progressively on completion of the stages set out in Part D of the
Appendix to the Schedule. A progress claim must be in writing,
certify that the Works have been completed to the relevant stage and
set out the amount to be paid to the Contractor in accordance with
Clause 11.7.
11.7 Owner to make progress payments
On receiving a progress claim, the Owner must pay the Contractor,
within the period stated in item 25 of the Schedule, a progress
payment calculated in accordance with the following:
(a) The Total Cost of the Works calculated in accordance
with Clause 29.1 for completion of the relevant stage; or
(b) The Total Cost of the Works based on a period of time;
(c) any adjustment to the Total Cost of the Works under this
Contract;
(d) any other amount due and payable by the Owner to the
Contractor under the Contract or otherwise.
[21] Total Costs of Works is defined in clause 29.1 as:
29.1 Items constituting the Total Cost of the Works
The Total Costs of the Works shall consist of the sum of the
following:
(a) The Actual Cost of the Works which shall include those
items listed in Clause 29.2 being the cost of the Works
together with items listed in Clause 29.3 being the
Contractor’s Preliminaries for the Works, and
(b) The Cost Plus Fee component in consideration of the
performance by the Contractor of providing services
during the construction phase. The Cost Plus Fee
component comprises the Contractor’s profit and margin
1 Clause 11.4.
-- 5 of 15 --
6
to meet a proportion of the Contractor’s off site overheads
as set out in Clause 29.4.
[22] Actual Costs of Work is defined in the Contract as the costs and expenses
incurred by the Contractor and the Owner in the construction of the Works,
whether paid for or not, excluding any fees, on costs and percentage
charges or payable to the Contractor under Contract for the services or
management of the construction of the Works2.
[23] Items constituting Actual Costs of Works are set out in clause 29.2 and
items forming Preliminaries, which form part of the Actual Costs of Works,
are set out in clause 29.3.
[24] The Actual Costs of Works comprises the items listed in clause 29.2 and
clause 29.3. The former includes the actual costs of materials, supplies
and equipment. It also includes the Preliminaries identified in clause 29.3
(insurance, the wages of foremen, etc). The parties agreed to a
Preliminaries fee of $157,212 (excluding GST). That was subject to
adjustment in accordance with clause 29.6(d). The parties also nominated
a Costs Plus fee of $225,000. That covered matters such as the
Contractor’s salaries and overheads. It too was subject to adjustment.
[25] The Applicant claims that the Actual Costs of Works was $2,051,439.
The Respondents say the figure should be $50,000 less, that is,
$2,001,439.
[26] The $50,000 difference represents a compromise of the sum of $74,722
which is an amount that the Respondents deducted because the sums
were disputed or not substantiated. They comprise:
a) cement render trade $10,000;
b) tiling trade $65,828;
c) painting trade $5,600.
The total of those sums amounts to $81,428 but no explanation is
forthcoming for that discrepancy.
[27] The Applicant submitted a Progress Claim No 25 for an amount of
$117,300.70 (inclusive of GST). The Respondents’ agent, Mintstone Pty
Ltd, by letter dated 23 October 2011 (under the hand of Rohan Butcher),
excluded the above items.
[28] The additional tiling costs are said to arise from the fact that the original
sandstone tiles that were quoted on were replaced by bluestone tiles
chosen by the Respondents. It is submitted that the tiler, engaged by the
Applicant, was required to lay an entirely different product, and charged
accordingly. The bluestone tile required a pre-sealer, unlike the
sandstone. That appears not to have been disputed.3 In their
2 See definition section of the Contract.
3 T2 – 37.18.
-- 6 of 15 --
7
Submissions, the Respondents say that an opinion4 from a Quantity
Surveyor, Gary Robinson & Cottrell, supports their contention that the
assessment costs for tiling variations were inflated. It is suggested that
the opinion has not been refuted. The opinion referred to is lacking in
sufficient detail to provide any real probative value of what it purports to
establish. However, the Respondents say the letter shows that there was
a basis for them to dispute the tiling costs. That, probably, is its only
value.
[29] The Respondents at the time did not address their refusal to pay the other
items amounting to $15,600.
[30] It is noted that clause 11.8 provides that the Owner has no right to set off
or deduct any sum from a progress payment due under clause 11.7.
[31] The Respondents take issue with the disclosure of the compromise sum
as they allege that the correspondence relied upon was ‘Without
Prejudice’ as was the offer to compromise.
[32] The evidence is that there were two pieces of correspondence dated
10 September 2012 that passed between the parties: one was clearly
marked ‘Without Prejudice’, and the other containing the offer of $50,000
was not so marked.
[33] There is no magic in the use of the words ‘Without Prejudice’5. If the
document clearly contains a bona fide offer of compromise, then a court
will treat the communication as privileged.6 The letter certainly contains
offers to compromise.
[34] Here, the contents of the other letter are unknown as the privilege has
been maintained. No explanation in Mr Simpson’s filed material explained
why one letter was marked ‘Without Prejudice’ and the other letter
containing the offer was not so marked. I note that Mr Simpson is an
experienced commercial solicitor. He, initially, appeared confused that
there were two letters. He was shown the correspondence marked
‘Without Prejudice’. From his evidence I draw the inference that the wrong
letter was marked ‘Without Prejudice’. In my opinion the claim for privilege
should be respected. I do not intend to place any weight on the
compromise.
[35] The basis of the rejection of the claim of $74,722 was that part of the claim
was not substantiated and the other part disputed. The letter dated
13 December 2011 from the Respondents’ agent, Mintstone Pty Ltd,
under the hand of Mr Butcher, set out the basis for the dispute with
respect to the tiles.7 No explanation was forthcoming with respect to the
cement render reduction or painting.
4 Exhibit 7.
5 Rogers v Rogers (1964) 114 CLR 608 at 614.
6 Field v Commissioner for Railways (NSW) (1957) 99 CLR 285.
7 See Exhibit 7.
-- 7 of 15 --
8
[36] Although the Respondents disputed the sums claimed, no amount has
been allowed for any of the items. There is no justifiable basis for
rejecting the items entirely. And I doubt that there is a valid basis for the
dispute at all, in view of the lack of detail of reasons for the rejection of the
claim. As I noted above clause 11.8 of the General Conditions do not
permit any deductions or set-offs from the progress claims.
[37] I would allow the full amount of the sum claimed but as the Applicant has
indicated to the Tribunal that it would accept $50,000 in satisfaction of the
amount outstanding, I have allowed that sum.
[38] Therefore, I find that the actual costs of works is $2,051,439.
No Adjustment for Preliminaries or Cost Plus Fee
[39] No adjustment for preliminaries of $157,212 (excluding GST) or cost plus
fees of $225,000 (excluding GST) has been paid. The Applicant says it is
subject to an adjustment as provided by clause 29.5(d) of the Contract.
The Respondents dispute that.
[40] Clause 29.6(d) provides:
Any amount so calculated or nominated by using the Alternative Method
remains subject to adjustment pursuant to the terms of the Contract and
shall be increased by or in relation to the proportion that the Total Cost of
the Works exceeds the estimated Total Cost of the Works (after taking into
account any deductions or omissions allowed under the Contract) and the
adjusted amount shall be claimed and paid progressively.
[41] Clause 29.10 provides adjustment of Costs Plus Fee component:
In the event that any authorised additions, variations and other adjustments
provided for under the Contract, including adjustment of the actual cost of
the Works, increase the total cost of the Works over and above the
estimated Total Cost of the Works, THEN the Contractor shall be entitled to
an adjustment of the Cost Plus Fee component computed on a pro rata
basis in proportion to the total increase after taking into account any
deductions or omissions allowed under the Contract, which shall be claimed
and paid progressively.
[42] The Applicant claims an additional sum of $42,447 (excluding GST) for
preliminaries and $60,750 (excluding GST) for the Cost Plus Fee based
on an actual cost of works of $2,051,439.
[43] The Respondents submit that the amounts are not recoverable because
they should be claimed in the progress claim and not at the end of the
Contract. They submit that the Applicant has no contractual entitlement to
be paid the adjustment fee now. Further, if there was an entitlement, it is
submitted that the entitlement has been compromised by an agreement by
the parties that the Applicant accept a lesser figure, which has been paid.
[44] The Respondents submit that the phrase at the end of the clauses to the
effect ‘… which shall be claimed and paid progressively’ supports their
contention. They argue that the evident purpose of the clauses is to avoid
-- 8 of 15 --
9
a situation where the Owner is faced, at the completion of the Works, with
a demand that the adjusted amount calculated over the life of the Contract
be paid.
[45] The Applicant says that in fact the Costs Plus Fee was in fact paid
progressively which was the case, but what was not claimed
progressively, and what is now being claimed, was the adjusted Costs
Plus Fee.
[46] I do not agree that the sole purpose of the clauses such as 29.6(d) and
29.10 are to ensure that the Owners are not faced with a final claim
calculated over the whole life of the Contract (the rude shock argument).
There are obvious benefits to both parties arising from such a provision.
[47] The Respondents submit that because the claims were not made
progressively, the Applicant has now lost the entitlement to make such
claims. I reject that argument. There is no support to be found in the
Contract for such an interpretation. Further, the Applicant relies upon the
decision of Ward v Eltherington [1982] Qd R 561.
[48] I agree with the Applicant’s submissions that the words at the end of both
clauses referring to adjustment and being claimed and paid progressively
are machinery provisions about the time of claims.
[49] The Respondents also allege that the claims have been compromised.
They were referred to two letters from the Applicant to the Respondents of
4 November 2010 and 2 December 2010. In each of those letters, the
Applicant offers to fix monthly preliminaries prolongation cost of $25,000
exclusive of GST. The first letter assumes a Practical Completion Date of
14 February 2011; the second letter a Practical Completion Date of
14 March 2011. The first letter provides for the Respondents’ agent to
sign as confirming acceptance of the proposal.
[50] The Respondents say the offer was accepted. The Respondents paid the
sum of $25,000 for each month that the Works continued after
16 December 2010, the Date for Practical Completion.
[51] The Applicant submits that even if there was an agreement, it was not
beyond the three months.
[52] Although in evidence Mr Butcher referred to further discussions taking
place between him and Mr Neville, there is no evidence that the Offer was
ever accepted. I find that there was no agreement. The fact that the
payments were made does not necessarily mean that any agreement was
reached as a liability existed to make such payments; in any event, it was
only a matter of how much.
[53] It follows that the Applicant has proved its claim of $42,447 for adjusted
preliminaries and $60,750 for adjusted Costs Plus Fee.
-- 9 of 15 --
10
Additional duties
[54] Clause 29.11 provides:
Reimbursement for additional duties.
The Owner and Contractor may agree that the Contractor undertake
additional duties for which the Contractor shall be reimbursed at the rates
nominated in Part K(4) of the Appendix. The Contractor shall be entitled
to an adjustment of the Cost Plus Fee component in relation to these
additional duties including any other additional labour, materials, plant,
goods or services provided by the Contractor under the Contract.
The Cost Plus Fee component shall be applied additional to, either pro rata
or as a percentage of, all goods and services provided by the Contractor.
In the absence of agreed charge out rates, the Owner and Contractor
shall negotiate a reasonable remuneration.
[55] The Applicant claims the sum of $9,318 representing 5% of $186,364
which comprised 56 items of additional service.
[56] It is submitted by the Respondents that the claim is baseless as no rate
was ever agreed. That is true. There is no Appendix so no Part K(4) to
the Appendix.
[57] In paragraph 17 of the Amended Statement of Claim, the Applicant claims
they made payments of $186,364 (exclusive of GST) for items identified
as Owner-supplied materials in the Contract. The Respondents admit that
the sum was paid on the Respondents’ behalf. However, it disputes its
liability to pay the said sum as there was no contractual agreement as to a
reasonable rate.
[58] The Respondent have admitted that there was some work involved in the
Applicant providing this service. For instance, it calculated quantities and
cutting lists, liaised with suppliers, and coordinated deliveries. It was not
simply a matter of paying an invoice.
[59] It is well established by authority that where a contract does not fix a price
or a rate, a contractor is entitled to a reasonable sum for the work carried
out on a quantum meruit basis. 8
[60] As no rate was provided for in the Contract, the Applicant has applied a
5% administration fee which it alleges is considerably less than a builder’s
usual margin. I agree. I allow the sum.
Test of bluestone tiles and legal costs
[61] This part of the claim dealt principally with the bluestone tiles. Defects in
the laying of the blue tiles arose from the method of laying the tiles or the
tiles themselves. The Applicant says that Mintstone Pty Ltd, as agent for
the Respondents, directed the Applicant to carry out testing of the tiles.
8 Powell v Braun [1954] 1 WLR 401.
-- 10 of 15 --
11
See letters 13/10/2011 and 26/10/2011 from the Applicant to the
Respondents.
[62] In the first letter, Mr Neville says:
In accordance with your directions to undertake our investigations, Albion
Projects engaged the services of NATA Accredited Laboratory, Stone
Initiatives and Materials Testing Group Pty Ltd to undertake tests of the
bluestone tiles and three tiles were forwarded to that testing facility in South
Australia for testing.
[63] The cost of testing was $1,500. Legal costs of $2,520 were also incurred
in obtaining legal advice on the allegations of poor workmanship.
The nature of the advice sought and the party liable was not explored.
The total sum of $4,020 the Applicant says is recoverable from the
Respondents under the General Conditions of the Contract, particularly
clause 29.2(II) which refers to legal and other professional charges
reasonably incurred in connection with the Works; or clause 29.2(mm)
which refers to losses, expenses and damages to the extent not
recoverable from insurances; and clause 29.2(oo) any loss and damages
that relates to or arises out of the Works occasioned through no fault or
omission of the Contract.
[64] Mr Simpson in his statement at paragraph 13 said:
In or about September 2011, Paul Neville indicated to me an intention to
obtain expert evidence to support its argument that the damage to the
Bluestone tiles was due to defective material. I consented to Albion
removing a Bluestone tile for analysis but made clear to Paul Neville that I
disputed Albion’s position and expert report must be at Albion’s own
expense, as a cost of the dispute.
[65] In cross-examination, Mr Simpson said he did not use the words ‘as a cost
of the dispute’ and said it must have been a mere flourish. I do not accept
that. In my opinion, the cost of testing the tiles is a recoverable expense.
[66] The Applicant submits that “in connection with” is of wide import and
cannot be construed narrowly as meaning “for the purpose of completing
the Works”, as submitted by the Respondents. It is assumed by the
Respondents that the legal costs were incurred in a dispute with the
Respondents and the Applicant. From the material I have seen, that is far
from clear. It may involve the manufacturers or the sub-contractor tiler.
Indeed, the Applicant alleges in its submissions that the advice may be the
basis of the Respondents’ claim in the District Court against the supplier.
I am prepared to allow the legal costs.
[67] I allow the claim of $4,020.
Late Interest
[68] Under Clause 11.7 the Respondents were obliged to pay the Applicant
within 14 days of receipt of the progress claim.
-- 11 of 15 --
12
[69] Clause 11.9 of the Contract provided:
Interest payable on outstanding payments
If the Owner fails to make any payment to the Contractor within the time
for payment under this Contract, the Contractor is entitled to interest on
the outstanding amount at the rate specified in Item 24 of the Schedule,
payable from the time for payment until the date of payment.
[70] Item 24 of the Schedule provided for a 15% interest rate.
[71] The Applicant claims the sum of $12,786 as late interest. That is
contained in a calculation of interest on late payments in Attachment 4 of
its Statement of Claim which is the total of the sums less progress claim
number 26.
[72] The Respondents dispute the amounts on two bases. First, they allege
that the parties frequently agreed on variations to the amounts payable in
the progress claims. The practice was to negotiate on the progress
claims. The varied amount was then reflected in a tax invoice sent by the
Applicant, although the tax invoice did not reflect a new date.
Second, they allege that the language of the clause is open to two
interpretations. They say that one interpretation would appear to be
capricious, unreasonable, inconvenient or unjust even if it is the most
grammatically accurate construction.
[73] Mr Neville was cross-examined on the issue9. He made it very clear in his
responses that it was expected that the progress payments would be paid
within 14 days. Out of courtesy, they gave the Respondents’ agent,
Mr Butcher, an opportunity to comment. It is quite clear that they expected
the payments to be made on time.
[74] The Respondents maintain that on a proper construction of the clause,
where there was an agreed variation, interest was not payable until
14 days after that agreement. Accordingly, on recalculating the amount
owed, the Respondents admit an amount of $4,222.56 is owed.
[75] I reject their argument and I find that the sum of $12,786 is the correct
amount.
Bank guarantee
[76] On 14 September 2010, under Special Condition 7 of the Contract, the
Applicant gave the Respondents a Bank Guarantee for the sum of
$47,845. Special Condition 7 provided as follows:
In relation to Part D – Progress Payments of the Appendix, the progress
payments shall be subject to a 5% cash retention. The Contractor shall be
entitled at his sole discretion to substitute the cash retention, in part or full,
with an unconditional bank guarantee in favour of the Owner.
Upon achieving Practical Completion, the Owner shall return 2.5% of the
9 Transcript 1-28.
-- 12 of 15 --
13
cash retention (and/or retention guarantee) to the Contractor within
14 days. Upon expiry of the Defects Liability Period, the Owner shall return
the balance 2.5% cash retention (and/or retention guarantee) to the
Contractor within 14 days. In Clause 19.1, delete the second sentence “No
retention money is to be held by the Owner during the Defects Liability
Period.
[77] The Applicant claims the Defects Liability Period expired on 20 June 2012
because on that date the Owner took possession. The Respondents
refused to release the Bank Guarantee. A demand was made by letter
dated 10 May 2013 by the Applicant, over some two days after receipt of
these proceedings. The Respondents claimed they were entitled to call up
the Bank Guarantee because of three alleged defects:
the Bluestone tile defects;
the main ensuite tile defects;
plumbing defects in the main bathroom on level 2.
[78] The Respondents maintain that there is at least one acknowledged defect
that remains unrectified in the period for which interest and Bank
Guarantee maintenance costs are claimed and that the Bank Guarantee
has not been appropriately held for that period and no such liability to the
Applicant arises. The remaining alleged defect relates to 5 or so
discoloured tiles in the main ensuite area. The cost of repair of those tiles
is unlikely to approach $10,000 according to the Applicant’s submission.
[79] It is submitted there is no proper basis under the Contract for the
Guarantee to be held beyond 20 June 2012. Under the contractual
regime, the Respondents were obliged to provide a written list of any
alleged defects and upon giving them that list, the Contractor, that is the
Applicant, was obliged to rectify them within 28 days. After that period,
the Respondents were obliged to return the Bank Guarantee.
The Respondents did not pursue their rights under the Contract, therefore,
there is no contractual basis for withholding the Bank Guarantee.
[80] It is apparent from the absence of any justification by the Respondents to
have retained the Guarantee pursuant to the contractual provisions that
there is no basis for doing so. I allow the sum of $1,431.42 being the
maintenance cost of the Guarantee and the further sum of $6,480.19 for
interest on the proceeds of the Bank Guarantee.
Counterclaim for unrectified defects
[81] The Respondents submit that there was delay by the Applicant in
completing the Works caused by it having an insufficient number of
tradesmen and contractors on site during the period. They claim $2,000
per week for a total of $8,000 to $12,000.
[82] In addition there are claims for defective workmanship estimated by
Mr Butcher to be in the region of $25,000. The defects are alleged to be
as follows:
-- 13 of 15 --
14
a) LED lights fitted in the main entry;
b) Tiling to the pool deck being stained and damaged due to poor
sealing of the tiles;
c) The decision by the Applicant to relocate the water condensers had
delayed certification;
d) Water leaks above the main entry vestibule;
e) Discolouration of white marble tiles.
[83] The Respondents have reduced their claim for damages on account of
delay from $134,000 to $8,000 to $12,000.
[84] There were delays, but delays were caused by the Respondents or what
have been described as neutral delays. The Practical Completion date
was extended by agreement to 24 June 2011.10 Practical Completion was
achieved on 20 June 2011, when the owners took possession. In any
event, I find the claim for damages for delay is lacking in detail in respect
of substance and time. A claim for rental is unsupported by any evidence
of rent being incurred or the amount of rent. I disallow the claim for
damages for delay.
[85] The defects claimed other than the bluestone tiles, main ensuite tiles and
the plumbing issue were not pleaded and were raised for the first time in
Mr Butcher’s evidence. They were not mentioned by Mr Simpson when he
gave his evidence in chief earlier in the hearing. In any event again the
claim lacks detail of what was the precise cause of the defect and what
would be the reasonable costs of rectification.
[86] I disallow the claim.
[87] In summary the Applicant has succeeded in its claim as follows:
a) Balance of Progress Claim 25 exclusive of GST $50,000.00
b) Adjustment of Preliminaries exclusive of GST $42,447.24
c) Adjustment of Cost Plus fee exclusive of GST $60,750.00
d) Fee for additional duties exclusive of GST $9,318.00
e) Tile testing costs and legal costs exclusive of GST $4,020.00
f) Interest on late payment exclusive of GST $12,359.00
g) Bank Guarantee refund $47,845.00
h) Costs of continuing Bank Guarantee $1,431.42
i) Interest on Bank Guarantee $6,480.19
$234,650.85
[88] The Queensland Building Services Authority Regulation 2003 provides
that for the purposes of section 77(2)(c) of the QBSA Act interest is
10 Email Fyfe to Butcher dated 5 May 2011, statement of Neville Exhibit 1.
-- 14 of 15 --
15
payable on the amount of damages awarded at the rate specified under
the contract11 and is payable on and from the day after the day that the
amount became payable until and including the day the amount is paid.12
Item 24 of the Contract allowed for an interest rate of 15% p.a.
[89] Therefore the orders of the Tribunal will be:
a) Jonathon Simpson & Kim Simpson will pay Albion Projects Pty Ltd
the sum of $234,650.85 plus GST.
b) Jonathon Simpson & Kim Simpson will pay interest to Albion Projects
Pty Ltd on the said sum at a rate of 15% for 2.5 years.
c) The Respondents’ Counter-claim is dismissed.
[90] I will receive written submissions in respect to the calculation of damages
inclusive of GST, interest and costs. Such submissions to be filed by the
Applicant by 4:00pm on 3 November 2014 and the Respondents by
4:00pm on 10 November 2014.
11 Section 34B(1)(a).
12 Section 34B(2).
-- 15 of 15 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/515