Correnti v Queensland Building and Construction Commission [2014] QCAT 501
CITATION: Correnti v Queensland Building and
Construction Commission [2014] QCAT 501
PARTIES: John Correnti t/as Correnti Homes Pty Ltd
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: GAR282-13
MATTER TYPE: General administrative review matters
HEARING DATE: 9 September 2014
HEARD AT: Brisbane
DECISION OF: Member Browne
DELIVERED ON: 8 October 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The decision made by the Queensland
Building and Construction Commission
on 24 July 2013 to direct John Correnti
t/as Correnti Homes Pty Ltd to rectify the
defective footing and slab system of the
property at 1 Hakea Court, Plainland,
Queensland is confirmed.
CATCHWORDS: GENERAL ADMINISTRATIVE REVIEW –
RECTIFICATION OF BUILDING WORK –
where complaint lodged by home owner –
where decision made to direct builder to rectify
building work – whether work performed by
builder is defective – whether discretion to issue
a direction to rectify should be made
Queensland Building and Construction
Commission Act 1991 (Qld), s 72, s 87
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 18, s 24
Taok v Queensland Building Services Authority
[2013] QCAT 508, cited
-- 1 of 13 --
2
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Correnti, self-represented
RESPONDENT: Mr Seefeld of counsel instructed by Holding
Redlich Lawyers
REASONS FOR DECISION
[1] Mr Correnti has been a builder since 1981 and has built approximately
1,100 homes. He was engaged by owners of land at Lot 117 Hakea Court,
Plainland, Queensland to build a low-set brick veneer house in about 2006
for the contract price of $169,340.00. The house at Lot 117 Hakea Court,
Plainland (the property) was completed in about May 2007.
[2] Mr Correnti was the builder responsible for building the property in
accordance with the design prepared by FMG Koukourou Engineers.
[3] The property was constructed on what is commonly referred to amongst
professionals and trades in the building industry as a ‘waffle raft footing
system’.
[4] On 25 October 2012 and 26 October 2012, the Queensland Building and
Construction Commission (QBCC) received complaints from the owners of
the property about issues with the building work allegedly completed by Mr
Correnti. The complaints identified issues, amongst others, relating to
cracks in the ceiling and ‘new plasterwork cracks are reopening’.1
[5] The QBCC, after receiving the complaint and requesting further
information, inspected the property on 17 December 2012 and prepared
an inspection report dated 20 December 2012.2 The report prepared by
Arnold Fisher, building inspector for the QBCC, identified issues in relation
to alleged ‘cracking and movement’ in the walls and floor in certain parts
of the property.
[6] The QBCC obtained independent evidence from an engineer, Booth
Engineers & Associates Pty Ltd, to report on the alleged movement and
damage to the property.
[7] After receiving information and making further enquiries, the QBCC
determined on 24 July 2013 to issue a direction to rectify to Mr Correnti in
relation to rectification of alleged defective work at the property.3 The
direction to rectify refers to the design and construction of the footing and
1 Complaint form received 25 October 2012, material filed by the QBCC under s 21 of
the Queensland Civil and Administrative Tribunal 2009 (Qld), p 79.
2 BSA Resolution Services subsidence report dated 17 December 2012, s 21 material,
attachment marked ‘SOR-12’, p 224.
3 An earlier direction to rectify was issued to Mr Correnti by the QBCC on 15 May 2013
referred to as the ‘first direction to rectify’ in the s 21 material. The direction to rectify
issued on 24 July 2014 is referred to as the ‘second direction to rectify’ in the s 21
material.
-- 2 of 13 --
3
slab system of the property as not being constructed in accordance with
‘the Building Code of Australia Volume 2 – 2006 P2.1 Structural Stability
and Resistance to Actions (a), (b) and (c)’.
[8] Mr Correnti exercised his rights under the Queensland Civil and
Administrative Tribunal Act 2009 (QCAT Act) to review the decision made
by the QBCC. The Tribunal on review has the same powers as the QBCC
decision maker under the Queensland Building and Construction
Commission Act 1991 (Qld) (QBCC Act) in determining whether the
discretion to issue a direction to rectify under s 72 should be exercised.
[9] The Tribunal on review effectively stands in the shoes of the QBCC
decision maker and must make the correct and preferable decision
following a fresh hearing on the merits.
[10] Mr Correnti seeks an order from the Tribunal that the decision made by
the QBCC to issue a direction to rectify be set aside and that he not be
directed to rectify the alleged defective work in relation to the footing and
slab system.
[11] The application proceeded to a hearing in Brisbane and Mr Correnti and
the QBCC were given an opportunity to present evidence including expert
evidence. Directions were made by the Tribunal, by consent, at the end of
the hearing for the filing and exchange of written closing submissions.4
[12] Mr Correnti relies on his own evidence and the expert evidence of David
Hardy, structural engineer, from Queensland Soil Testing. The QBCC rely
on the evidence of Arnold Fisher, building inspector, and the expert
evidence of Stephane Rebibou, civil engineer, from Booth Engineers &
Associates Pty Ltd.
[13] The expert witnesses, Mr Hardy and Mr Rebibou attended an experts'
conclave prior to the hearing following a direction made by the Tribunal
and a joint report was prepared dated 24 July 2014.5
The QBCC’s Power to Issue a Direction to Rectify
[14] There is discretionary power under s 72 of the QBCC Act for the QBCC
and the Tribunal on review to issue a direction to rectify to the person who
has carried out defective or incomplete building work to rectify the building
work. The meaning of ‘defective’ building work is as defined under
Schedule 2 of the QBCC Act to mean ‘faulty or unsatisfactory’.
[15] There are certain matters that the QBCC decision maker and the Tribunal
on review can take into consideration in determining whether to issue a
direction to rectify.6 Relevantly, s 72(14) of the QBCC Act provides that the
4 Directions made on 9 September 2014 required the QBCC to file and deliver written
submissions by 15 September 2014 and Mr Correnti to file and deliver written
submissions by 22 September 2014.
5 Exhibit marked ‘6’.
6 QBCC Act s 72(2).
-- 3 of 13 --
4
QBCC is not required to give a direction if it is satisfied that, in the
circumstances, ‘it would be unfair to the person to give the direction'.
[16] It was previously determined by the Tribunal in the decision of Taouk v
Queensland Building Services Authority7 that the QBCC (formerly known
as the QBSA) has responsibilities under the relevant legislation, the
QBCC Act, to ‘ensure proper standards in the industry and rectification of
building work’. The power to issue a direction to rectify is not for the
‘benefit’ of the homeowner but rather a ‘discharge’ of the QBCC’s
responsibilities under the Act.8
[17] At the time the QBCC made the decision to direct Mr Correnti to rectify the
alleged defective work, there was in place a policy applicable to
rectification of building work.9 The QBCC policy identified as the
Queensland Building Services Board Policy for rectification of building
work made on 18 March 2004 refers to residential construction work that
has ‘caused footing or slab movement as a result of’ amongst others,
‘location of proposed cut and fill’. There is a further QBCC policy relevant
to ‘subsidence/settlement – responsibility for rectification’.10 The QBCC
policies are for the purposes of s 10 of the QBCC Act legislative
instruments that provide guidelines relevant to the QBCC’s exercise of
discretion under s 72 in determining whether a direction to rectify should
be issued.
What was the building work performed by Mr Correnti?
[18] It is non contentious that the design or plan for the property prepared by
FMG Koukourou Engineers (the engineers) called for a cut and fill
procedure. It is also accepted by the parties that the founding material for
a waffle raft system is firm natural soil or piers that sit on top of
uncontrolled fill - a waffle raft system must not sit on uncontrolled soil or fill
unless piers support it.
[19] Mr Correnti gave evidence at the hearing that prior to the slab being
poured, as required by the design or plan, the natural soil was cut on the
right hand side of the block and soil or natural fill was pushed to the left
hand side of the block. Mr Correnti stated that piers were placed on top of
the fill on the left hand side and rear perimeter of the slab. Mr Correnti was
adamant in giving his evidence at the hearing that fill was not placed on
the right hand side of the block and there was only natural or ‘virgin’ soil
on the right hand side of the block after the cut and fill procedure.
7 [2013] QCAT 508.
8 Taouk v Queensland Building Services Authority, ibid, at [38].
9 Queensland Building Services Board Policy, rectification of building work, s 21 material,
p 30.
10 Section 21 material, p 503.
-- 4 of 13 --
5
[20] Mr Correnti also relies, in giving his evidence at the hearing, on ‘aerial
photographs’ of the block that he states show the ‘unaltered terrain of the
site’ before and after works were commenced.11
[21] Mr Correnti also gave evidence about a ‘blinding layer’ that he says was
placed on top of the finished soil (after the cut and fill procedure). A
blinding layer was described by Mr Correnti as a stabilising material in the
form of sand or gravel that is placed on top of the soil (under the slab). Mr
Correnti relies on the engineer’s design or plan that he says calls for a
blinding layer to be placed (effectively) under the slab prior to the concrete
being poured.
[22] Mr Correnti was not present at the site when the cut and fill procedure
took place. Mr Correnti was also not present at the site when the engineer
inspected the site prior to the slab being poured and prior to the certificate
of inspection dated 23 October 2006 being issued.
Evidence of defective building work
[23] Mr Correnti in giving his evidence describes the defects or damage to the
property as ‘minimal’.
[24] Mr Correnti gave evidence at the hearing about the damage to the
property stating that it is attributable to the owner not taking steps to
prevent water penetrating under the slab. Mr Correnti states that
maintenance to the property should have been done to ensure the
perimeter of the property deflects water away so no water permeates the
blinding layer and the slab. Mr Correnti contends that any damage to the
property is the result of water permeating the blinding layer and slab; and
as a result of the water penetration there is ‘heave’ at the centre of the
property.
[25] Both expert witnesses, Mr Hardy and Mr Rebibou gave evidence at the
hearing about the damage to the property being issues identified by the
property owner in the complaints made to the QBCC.
[26] Mr Hardy did not personally inspect the damage to the inside of the
property. Mr Hardy relied on photographs taken by the QBCC contained in
the inspection report prepared by Mr Fisher. Mr Hardy did however inspect
the outside perimeter of the property and considered the results of soil test
samples taken under the slab of the property prior to preparing his report
and the joint experts’ report.
[27] Mr Hardy gave evidence at the hearing that he had seen the photographs
of the damage to the property contained in the QBCC inspection report
and the report of Booth Engineers & Associates Pty Ltd dated 24 January
2013. Mr Hardy stated that some of the cracks would be within the
11 Written submissions filed by the applicant on 22 September 2014, para 2.
-- 5 of 13 --
6
guidelines of the Australian Standard that has a damage category
system.12
[28] During cross-examination, Mr Hardy was questioned about the Australian
Standard in relation to the categories of defects for the purposes of
drawing the conclusion that the footing system is not performing. Mr Hardy
stated that the engineer assessing the damage, for example Mr Rebibou,
would look at obvious changes in floor levels. Mr Hardy stated that based
on those findings as to whether damage falls within the particular
categories under the Australian Standard it would be open to the engineer
(Mr Rebibou) to reach a conclusion about the cause of any damage.
[29] Mr Hardy was not conclusive in his evidence about the cause of the
damage to the property stating in giving his evidence that he could only
‘speculate’. When questioned at the hearing about the cause of the
damage to the property Mr Hardy stated that he would need to do further
investigation like Mr Rebibou had done. Mr Hardy gave evidence at the
hearing about the design of the footing system stating that it was his
understanding that the design under the most recent Australian Standards
may provide for additional requirements such as ‘ribs’ to be installed. Mr
Hardy did not state however in giving his evidence the extent to which the
design of the footing system may or may not have contributed to the
damage to the property. Mr Hardy stated that moisture is the main cause
of movement and he did observe ‘free moisture’ on site so he would, as
stated by him at the hearing, ‘put that forward’. Mr Hardy also stated that
he was not engaged to investigate possible causes of damage and that Mr
Rebibou had done a more thorough investigation.
[30] Mr Rebibou did inspect the inside and outside of the property. Mr Rebibou
gave evidence at the hearing about the cracks to the walls and floor of the
property. Mr Rebibou also gave evidence at the hearing and in his report
dated 11 March 2013 about the design of the footing and slab system.13
[31] Mr Rebibou in his report dated 11 March 2013 states that the footing and
slab system that has been designed for the property is ‘generally in
accordance with Figure 3.4 of AS2870 – Standard Designs’.
[32] Mr Rebibou in his report dated 24 January 2013 took photographs and
prepared an assessment of the levels and contour plan to identity data
classification for the damage to the walls and floors. The various
photographs taken and included in the report show gaps and cracks in
parts of the ceiling and the brickwork. Mr Rebibou determined in his report
dated 24 January 2013 that there has been movement and damage to the
property and states that an ‘assessment of the levels and contour plan’
identified data relevant to the classification of damage to the walls and
floor.
12 Exhibit marked ‘7’, AS 2870-1996, Appendix C.
13 Exhibit marked ‘11’, para 6.00.
-- 6 of 13 --
7
[33] Mr Rebibou classified the damage to walls as ‘Category 2 to 3, cracks and
gaps varying from 1 to 15mm in width’. In relation to the floor, Mr Rebibou
reported the damage as ‘Category 2 to 3, slab noticeably curved or
changed in level’. Mr Rebibou states:
In this case, the local deviation of slope [for the floor] exceeds the allowable
acceptable performance criteria as required pursuant AS 2870 and some
Category 2 to 3 defects were also identified.14
[34] In the report dated 24 January 2013 Mr Rebibou concludes that the
footing and slab system and movement as being a relevant issue to the
‘expected performance and functional use of the building’. The report
states:
In summary, the footing and slab system and movements that have
occurred adversely affect the structural adequacy and serviceability of the
building and the expected performance and functional use of the building
when compared to the performance criteria for footings and slabs pursuant
to AS2870.15
[35] Arnold Fisher for the QBCC also inspected the damage to property. In the
report dated 20 December 2012, Mr Fisher made findings in relation to the
damage to the property, in particular cracking and movement consistent
with the findings made by Mr Rebibou that there was evidence of
movement and damage. Mr Fisher states in his report:
Due to the cracking and movement and the slope value recorded, it was
deemed necessary to engage an independent engineer to investigate and
report on the noted movement and damage to the dwelling and recommend
remedial rectification advice.16
[36] The Tribunal is satisfied based on the evidence of Mr Rebibou that there is
evidence of damage to the property and the likely cause of the damage is
subsidence or movement resulting from the footing and slab system not
complying with the relevant Australian Standard AS2870-1996.
Is there evidence of ‘fill’ from soil test samples taken?
[37] After the complaint was made to the QBCC by the owners various
inspections were undertaken by Booth Engineers through external
consultants Geotest Engineering; and by Queensland Soil Testing. The
investigations included excavations around the property to enable soil
samples to be taken from under the slab. This was necessary to
determine the cause of the damage to the property, in particular whether
there was presence of uncontrolled fill under the slab (in the absence of
piers).
[38] Mr Correnti in giving his evidence does not accept that the soil samples
taken were adequate in that there was uncertainty about where the
14 Exhibit marked ‘11’, report dated 24 January 2013, p 3.
15 Exhibit marked ‘11’, p 7.
16 Exhibit marked ‘8’, s 21 material, p 225, investigation report dated 17 December 2012.
-- 7 of 13 --
8
excavation pits were located and whether the soil samples were in fact
samples taken from under the block.
[39] Mr Correnti was given an opportunity at the hearing to cross examine the
expert witnesses Mr Hardy and Mr Rebibou in relation to the location of
soil test samples taken at the property. Mr Hardy stated at the hearing that
the test pit samples referenced in his report dated 4 April 2014 were taken
by a technician and the location of the pits were referenced in the report
dated 4 April 2014. The pits referenced are depicted as being excavations
from the under the slab of the property. The report states:
The depth of fill material detected in all three pits is indicated on the
attached drawing number ‘SK1’ with the footing cross-sections being
provided on drawing “SK2”. A summary of the findings has been provided
below….17
[40] The soil test samples taken by Geotest Engineering Services Pty Ltd that
Mr Rebibou relied upon in preparing his report were also taken from under
the slab.
[41] Mr Rebibou produced at the hearing a copy of his instructions to Geotest
Engineering Services Pty Ltd in relation to soil test samples. The
instructions sent by Booth Engineering to Geotest Engineering identify 3
excavation sites at the property on the right hand side, far back right hand
side and far back left hand side. There is a map depicted on the
instructions to show the areas where excavation and samples should be
taken. The instructions state:
We require a soil test report for the following work for the BSA investigation:
All soil tests require three (3) boreholes, moisture contents at 500mm
intervals over 1500mm, D.C.P’s if fill or soft material encountered and
Estimate of footing depths/part footing excavations.18
[42] I am satisfied that the testing conducted by Geotech relied upon by Mr
Rebibou and the test samples taken by Queensland Soil Testing relied
upon by Mr Hardy are test samples as referenced in their respective
reports taken from under the slab of the property. I am satisfied that the
test samples of soil taken by Geotech and Queensland Soil Testing were
not corrupted by other material that was also present around the perimeter
of the property, as contended by Mr Correnti.
What is the cause of the damage to the property?
[43] It is non contentious that there was moisture present around the perimeter
of the property during some of the inspections and this was the result of
owner maintenance in that the owner had failed to properly maintain the
property necessary to prevent water entry. Mr Correnti contends that
because of the owner’s failure to properly maintain the property, water has
as stated by him: ‘gotten under the house and this is creating “heave”
because water is getting under the house’.
17 Exhibit marked ‘5’, p 1.
18 Exhibit marked ‘14’.
-- 8 of 13 --
9
[44] I have considered the submissions made and the evidence given by Mr
Correnti and his expert witness Mr Hardy in relation to the damage to the
property and the possible causes of the damage to the property. I prefer
the expert evidence of Mr Rebibou. Mr Hardy stated that he did observe
‘free moisture’ on site but conceded when giving his evidence at the
hearing that Mr Rebibou had conducted a more thorough investigation and
he could only ‘speculate’ as to possible cause or causes of the damage to
the property.
[45] I found Mr Rebibou to be reliable in giving his evidence. For example,
when questioned at the hearing about the damage to the property Mr
Rebibou did not exaggerate the extent of the damage stating that the
defects are not affecting the overall function of the building in that the
owners can continue to reside in the property. Mr Rebibou did state
however that there is evidence of damage to the property that is the result
of stressors or forces that satisfy the definition of defects under the
Australian Standard.
[46] I accept the evidence of Mr Rebibou in relation to the damage to the
property that includes the results of investigations carried out by Booth
Engineering and Geotest. Mr Rebibou in giving his evidence at the hearing
stated that there is a combination of a number of defects including the
curvature of the floor that led him to draw the conclusion that the footing
system is not performing to the Australian Standard AS 2870-1996. Mr
Rebibou states in his report dated 11 March 2013:
In summary, the footing and slab system and movements that have
occurred adversely affect the structural adequacy and serviceability of the
building and the expected performance and functional use of the building
when compared to the performance criteria for footings and slabs pursuant
to AS2870.19
[47] Mr Rebibou also considered the results of the soil testing and determined
that ‘fill is indeed present under the footing system across the entire
building platform and this has now been confirmed by both Geotest in
2013 and QST in 2014’.20
[48] Mr Rebibou determined in his report dated 30 May 2014 that there is
‘some fill settlement [sic] taking place towards the right of the building’. At
the hearing, Mr Rebibou stated that the fill settlement to the right hand
side of the building is sinking and this is effectively causing the damage to
the property. When questioned at the hearing about the cause of the
damage Mr Rebibou stated that he considered the results that show
where the damage is occurring. Mr Rebibou stated at the hearing: ‘when
you look at where the damage is occurring and combine it with where the
sharpest amount of movement occurring coincides with [sic] where there
is evidence of fill and no piers”.
19 Exhibit marked ‘11’, p 7.
20 Exhibit marked ‘12’, p 4.
-- 9 of 13 --
10
[49] The evidence of fill being present under the right hand side of the slab of
the property was also considered by Mr Hardy. Mr Hardy attended an
experts’ conclave with Mr Rebibou and prepared a joint report. Mr Hardy
and Mr Rebibou determined in the joint report that the fill present at the
site was not a ‘blinding layer’. The joint experts’ report dated 24 July 2014
states:
1. Both experts agree that the original soil test did not identify any fill on
the subject property.
2. Both experts agree that some fill is currently on the site varying from
700mm – 1m towards the left of the building and 250mm – 300mm
towards the right of the building [as viewed from the street].
3. Both experts agree that there is some fill material under the footing on
the right side of the building varying from 50mm – 120mm and that
this does not appear to be a blinding layer [a thin layer of non reactive
material, typically sand / fine gravel used to fill voids and prepare a
more uniform base for the foundations].
4. Both experts agree that there has been potentially some fill settlement
along the right hand side of the building, although some heave
[upwards movement] also may have affected the footing system.
David Hardy believes with hindsight in design based on current
practices that there is a potential for lack of stiffness through the
entry/BR1 area resulting in reduced effectiveness of the raft system.
Stephane Rebibou believes that the original design is based on “H”
site classification which would cater for up to 70mm of characteristic
surface movement (YS) and recent testing shows YS for the site to be
only 55mm.
5. Both experts agree that it is common building practice for fill to be
either compacted (certified) or for the footing system to be piered
through the fill.
[50] I accept the expert evidence of Mr Rebibou supported by Mr Hardy that
there is evidence of fill under the right hand side of the property that is not
a blinding layer. I accept the evidence of Mr Rebibou that there has been
settlement of the fill and this has caused the slab or footing system to sink
resulting in damage to the property such as cracks and gaps to the walls
and floor of the property.
Should Mr Correnti be directed to rectify the defective footing and slab
system?
[51] The Tribunal on review in determining whether to exercise the discretion
to direct Mr Correnti to rectify must take into consideration all of the
relevant circumstances and whether for the purposes of s 72(14) of the
QBCC Act it would be ‘unfair’ to give Mr Correnti the direction.
[52] Mr Correnti contends that the building work was performed by him as
required by the engineering design. Mr Correnti denies putting fill under
the footing system (on the right hand side) and relies on the engineer’s
certificate of inspection dated 23 October 2006.21 Mr Correnti also
21 Exhibit marked ‘1’, attachment marked ‘RSOR12’.
-- 10 of 13 --
11
contends that if there were any fill present (that he denies) the engineer
would not have issued the approval after inspecting the site.
[53] The certificate of inspection relied upon by Mr Correnti was prepared by
FMG Koukourou Engineers and provides that there are ‘no significant
changes to the site works from the design’ as being noted.22 The
certificate states:
The piers and waffle slab for the proposed residence were inspected prior
to the pouring of concrete on the above date. Approval was given for the
piers & slab to be poured subject to any site instructions issued.
This inspection was carried out to verify the structural compliance of the
pier & slab with the approved plans at the time of inspection and in
accordance with the relevant codes. It does not relate to particular
architectural details such as squareness, building dimensions, or sitting in
relation to boundaries.
No significant changes to the site works from the design were noted at the
time of the inspection, therefore the site classification should be consistent
with the design information.
[54] It is open to the Tribunal to draw the reasonable inference having
accepted the expert evidence of Mr Rebibou that the engineer’s approval
was subject to any site changes and this would include the addition of ‘fill’.
Mr Rebibou in giving his evidence at the hearing stated that during an
inspection of the footing system by the engineer it would be difficult to
distinguish fill, if in fact it was present, on the basis that, as stated by Mr
Rebibou, ‘it is a bare site [and there is] dirt everywhere’.
[55] The Tribunal has considered the ‘aerial photographs’ of the site relied
upon by Mr Correnti. The Tribunal is not satisfied having accepted the
evidence of Mr Rebibou that the photographs of the site are proof that
there was no fill ‘brought to the site’ as contended by Mr Correnti. The
Tribunal has made findings in relation to the presence of fill under the slab
and accepts the evidence of Rebibou that the site would be a ‘bare site’ at
the time of inspection by the engineer.
[56] The Tribunal has also considered the Queensland Building Services
Board policies applicable to the exercise of the discretion under s 72 of the
QBCC Act in determining whether a direction to rectify should be made.
The rectification policy dated 18 March 2004 refers to category 1 defective
building work that has been carried out by a contractor that includes a
failure to comply with requirements of the footing design or failing to
construct the footing or slab system in accordance with ‘all relevant
Australian Standards, including AS2870’.23
[57] The Queensland Building Services Board policy effective from 30 June
2000 also provides that a contractor will ‘usually not be held responsible
for the subsidence or settlement of a building where’ the contractor has
22 Ibid.
23 Section 21 material, p 33.
-- 11 of 13 --
12
taken ‘reasonable care’, including constructing the footings and slab of the
building ‘in accordance with the design’ prepared by the engineer.24
[58] There is evidence before the Tribunal of damage to the property that is as
opined by Mr Rebibou the result of the footing and slab system not
performing in accordance with the Australian Standard AS 2870-1996.
[59] The damage to the property including cracks and gaps in the walls and
floor observed by Mr Rebibou and Mr Fisher are as stated by Mr Rebibou
in his expert opinion occurring predominately to the right hand side of the
property. There is also evidence before the Tribunal that there is the
presence of uncontrolled fill that is not a blinding layer under the right
hand side of the slab of the property. Mr Correnti does not dispute that he
is the builder responsible for the cut and fill procedure and that he was not
present when the works took place at the site and was not present when
the site was inspected by the engineer.
[60] The Tribunal has made findings in relation to the cause of damage to the
property having accepted the expert evidence of Mr Rebibou. I am
satisfied that there is evidence of fill material under the right hand side of
the slab of the property that is not a blinding layer and that the
uncontrolled fill has settled causing movement resulting in damage to the
property.
[61] The Tribunal is satisfied that the footing and slab system of the property is
building work that is defective because it does not comply with the
relevant Australian Standard AS870-1996; and that the defective building
work has caused damage to the property such as cracks and gaps to the
walls and floor of the property.
[62] I do not accept that the owner’s failure to maintain the property in relation
to preventing water from penetrating the slab has caused the damage to
the property. The Tribunal has made findings in relation to Mr Hardy’s
evidence. Mr Hardy on his own admission was unable to give an
explanation that was otherwise based on speculation as to the cause of
the damage including the extent to which any moisture penetration
resulting from owner maintenance may have contributed to the damage to
the property. I am also satisfied having accepted the evidence of Mr
Rebibou that the design of the footing system is generally in accordance
with the Australian Standard and notwithstanding there is no cogent
evidence before me that the damage to the property was caused by any
defect in the design of the footing system that was prepared by FMG
Koukourou Engineers.
[63] The Tribunal has considered all of the evidence including Mr Correnti’s
evidence that he did no put fill under the slab of the property (on the right
hand side). Notwithstanding Mr Correnti’s evidence about the fill issue,
there is evidence before the Tribunal that there is fill present under the
right hand side of the slab and that the fill is not a blinding layer. There is
24 Ibid, p 503.
-- 12 of 13 --
13
also evidence before the Tribunal reflected in the reports prepared by
Booth Engineering that the damage to the property such as cracks and
gaps to the walls and floor depicts the ‘sharpest amount’ of movement as
occurring in the far right hand side of the property. Mr Rebibou gave
evidence that the movement evident by the damage occurring in the far
right hand side coincides with the location of fill that has been tested as
uncontrolled fill that is not a blinding layer.
[64] The Tribunal accepts that Mr Correnti may feel aggrieved by the evidence
and findings made by the Tribunal on the basis that he, as contended, did
not put fill under the slab on the right hand side of the property. Mr
Correnti was not, however, present at the time the works were undertaken
at the property, in particular when the cut and fill procedure took place.
The Tribunal has also considered Mr Correnti’s contention that he has
relied upon the engineer’s certificate in relation to an inspection that took
place on or about 23 October 2006. Again, Mr Correnti was not present at
the time the engineer inspected the footing system. The Tribunal has
notwithstanding accepted the evidence of Mr Rebibou that it would not be
easily identified during an inspection by the engineer at the site that there
were changes to the site such as the addition of fill on the right hand side
of the property because the foundation material would effectively all look
the same.
[65] I am satisfied that a direction to rectify should issue to Mr Correnti as the
builder responsible for construction of the footing and slab system. I am
satisfied based on all of the evidence before me including the evidence of
Mr Correnti that the correct and preferable decision is to direct Mr Correnti
to rectify the defective work identified in the decision made by the QBCC
dated 24 July 2013.
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/501