Crawford v Doug Thoms & Son Master Painters [2014] QCAT 404
CITATION: Crawford v Doug Thoms & Son Master Painters
[2014] QCAT 404
PARTIES: Neville Crawford
(Applicant)
v
Doug Thoms & Son Master Painters
(Respondent)
APPLICATION NUMBER: BDL302-13
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member McLean Williams
DELIVERED ON: 21 August 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Applicant is relieved from the
requirement to pay the Respondent the
sum of $2,000 pursuant to the contract
between the Applicant and the
Respondent dated 12 August 2013.
2. The Respondent is ordered to pay the
Applicant the sum of $3,413.24 within
twenty-eight (28) days of the date of
these orders.
CATCHWORDS: DOMESTIC BUILDING DISPUTE – application
for final payment by builder, homeowner alleges
work is defective, expert report supports finding
by Tribunal that work was defective, costs of
rectification awarded to homeowner
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
[1] Mr Neville Crawford (‘the Applicant’), has commenced a claim before
QCAT seeking an order that he now be relieved from a contractual
-- 1 of 4 --
2
requirement to pay $2,000 to Doug Thoms & Son Master Painters (‘the
Respondent’), representing the final instalment sum due pursuant to a
contract for house painting entered into between the Applicant and the
Respondent.
[2] In addition, the Applicant also seeks the costs for rectifying defective and
incomplete painting works ($2,500); as well as some costs that are
referable to his bringing this claim before QCAT ($913.24).
[3] On 12 August 2013 the Applicant and the Respondent entered into a
Master Painters’ Australia contract for the Respondent to paint the
Applicant’s newly constructed home, at Biggera Waters. The contract
price was for $18,975, and the Applicant paid a deposit of $5,693 to the
Respondent.
[4] The Applicant has paid the Respondent all the various progress
payments, bar the final progress payment. The Respondent has claimed
payment of the final progress payment ($2,000), contending that the job is
now complete. Yet, the Applicant contends that the job is still far from
complete, and he has identified many aspects of the job that are not of an
acceptable quality. In this regard, the Applicant says:
Raked ceilings have been painted the wrong colour;
Bath tubs were scratched by the Respondent’s workers using ladders
in the bath tubs without adequate surface protection;
Roofing sheets have been damaged;
In many instances the Respondent has failed to use masking tape,
and that has resulted in poor cutting-in around various glass doors
and other fixtures;
In many areas timber staining was not undertaken satisfactorily by
the Respondent particularly on the side edges, tops and bottoms of
architraves;
The Respondent has failed to paint inside wardrobes;
Drop sheets have not been used in all areas, such that tiles and other
surfaces have become marked by paint drips and paint over-spray;
The Respondent has not properly supervised his workers on the job
and in consequence final coats on exterior walls were applied even
before other trades had completed their works, and in other areas
painting has been left incomplete; and
The Respondent has failed to respond to the Applicant’s request to
confirm the brand of external paint that was used to paint the house
and the process to be followed by the Applicant in order to obtain a
15-year written warrantee from the paint manufacturer.
-- 2 of 4 --
3
[5] In correspondence filed before QCAT by the Applicant the Respondent
has acknowledged that some works do require rectification, yet has
insisted that he be paid in full before these rectification works are
undertaken. Those discussions did not result in any resolution.
[6] The Respondent has not filed any materials before the Tribunal.
[7] The Applicant has obtained a report from Building Survey Australia Pty Ltd
and the author of that report, Mr Bruce Moore, concludes that painting
throughout the home at Biggera Waters has been conducted in a sub-
standard manner. A series of photographs included as part of Mr Moore’s
report clearly demonstrate a range of obvious defects and poor
workmanship, including:
Numerous instances of over-paint to painted surfaces, fixtures and
fittings;
Insufficient paint coverage;
Poor finishes;
Areas of no paint coverage at all;
Seal joints having not been installed;
Insufficient preparation prior to painting; and
Damage to roof sheeting.
[8] I accept the report from Building Survey Australia Pty Ltd as clearly
evidencing substandard works. This report also demonstrates that the job
has not been completed. The Applicant has obtained a quote from
another painter, Colour Elegance Painting & Decorating Pty Ltd.
This quote reveals that it will now cost $2,500 (inclusive of GST) to
complete the job started by the Respondent.
[9] In my view, the Respondent was not entitled to make claim to the final
instalment sum and there would now be very little utility in the Tribunal
ordering that the Respondent return to the site in order to perform
rectification works, or complete the job. In all the circumstances I regard it
as being more preferable that another painter perform these rectification
works instead. The quoted costs of rectification are reasonable, such that
I will allow the Applicant that sum as compensation.
[10] The Applicant also seeks the $550 cost of the building report that he
obtained from Building Survey Australia Pty Ltd in order to demonstrate
the nature of the problem, and his court costs ($285) and postage and
photocopying fees ($78.24). These costs are also reasonable, such that I
will allow them.
-- 3 of 4 --
4
[11] The order of the Tribunal is as follows:
1. The Applicant is relieved from the requirement to pay the
Respondent the sum of $2,000 pursuant to the contract between the
applicant and the respondent dated 12 August 2013.
2. The Respondent will pay to the Applicant the sum of $3,413.24 within
twenty-eight (28) days of the date of these orders.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/404