Boden v Martin & Roth [2014] QCAT 333
CITATION: Boden v Martin & Roth [2014] QCAT 333
PARTIES: Simon Boden
(Applicant)
v
Ruth Martin and Marc Roth
(Respondents)
APPLICATION NUMBER: BDL203-13
MATTER TYPE: Building matters
HEARING DATE: 9 May 2014
HEARD AT: Townsville
DECISION OF: Member Johnston
DELIVERED ON: 15 July 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Tribunal Orders the Respondents to
pay the Applicant the sum of $55.
2. The Tribunal dismisses the Respondents
claims.
CATCHWORDS: Dispute over nature of the agreement to build
Domestic Building Contracts Act 2000 (Qld) ss
7, 8, 26-30, 55
APPEARANCES and REPRESENTATION:
APPLICANT: Simon Boden
RESPONDENTS: Ruth Martin and Marc Roth
REASONS FOR DECISION
Background
[1] The Respondents were for the purposes of this decision the owners of the
dwelling situated at 266 Williams Road, Alligator Creek. They wanted to
build a patio to the rear of their existing dwelling. On 12 July 2012 the
Respondents contacted Mr Boden the Applicant in response to an
-- 1 of 8 --
2
advertisement in The Alligator Creek Times, in which Mr Boden held
himself out to be a builder.
[2] Mr Boden was a licensed carpenter and his license allowed him to
undertake building work of this nature.
[3] On 22 July 2012 the Respondents sent to Mr Boden an e-mail outlining
their requirements and attaching drawings/plans, requesting him to
provide a quote to build a patio based on this information.
[4] On 27 July 2012 Mr Boden provided a quote (‘the Quote’): “to construct a
colour bond patio roof to the rear of the existing dwelling”. The Quote
provided for a final cost of $19,247.69 [Exhibit 3].
[5] On 28 July 2012 the Respondents wrote to Mr Boden [Exhibit 4].
accepting the Quote The acceptance on its face is quite clear and
unequivocal.
[6] Mr Boden contends that rather than proceeding with the Quote the
Respondents agreed to pay the Applicant on an hourly rate. He filed an
Application for a minor civil dispute in which he claimed to be owed the
sum of $12,605.65. He also claimed filing fees of $275 and interest at the
rate of 10% totalling $562.55 at the time of filing. This came to a total
amount of $13,443.20.
[7] The Respondents contend that they accepted the Quote and did not agree
to an hourly rate. The Respondents’ Response to the minor civil dispute
asks the Tribunal to absolve the Respondents of any liability or debt
claimed by Mr Boden along with several other remedies. The crux of the
Respondents’ case is that they entered into a fixed contract and have paid
Mr Boden for the work he has undertaken.
The first decision for the Tribunal is the nature of the agreement between
the parties!
[8] Mr Boden's evidence to the Tribunal was that on 28 July 2012 the
Respondents agreed by e-mail to pay him at an hourly rate on a cost plus
basis. Mr Boden has however been unable to produce the e-mail and the
Respondents have denied that it has ever existed.
[9] Mr Boden has proceeded on the basis that he was entitled to charge on
an hourly basis.
[10] The Domestic Building Contracts Act (“the Act”) requires contracts to be in
writing and to only have effect if signed by the building contractor and the
building owner. Mr Boden conceded that this had not happened in this
case. When the Tribunal asked Mr Boden whether he was aware of the
use of contracts he told the Tribunal that he was familiar with the use of
HIA Contracts. He produced an example of a contract that he had used in
another matter (Exhibit 1). He also produced an example of a contract
-- 2 of 8 --
3
variation (Exhibit 2). Mr Boden acknowledged that he had not complied
with the requirements of the Act.
[11] Mr Boden's case is based on his hourly rate and the time he has spent on
the job as outlined in his invoices. The Respondents deny that they have
agreed to pay Mr Boden on an hourly rate. They seek a finding that they
have met their obligations under the agreement with the Applicant.
[12] Where there is a quotation in existence, which on the Respondents’ case
they had accepted, there is an evidentiary onus on the Applicant to
provide cogent evidence that this situation in relation to the agreement is
not correct. The Tribunal is of the view that if such an e-mail did exist then
it would have been produced.
[13] The Tribunal prefers the evidence of the Respondents on this point. The
Tribunal does not accept the evidence of Mr Kurt Hart who admitted that
his memory of events was “hazy”. The Tribunal does not accept the written
evidence of Mr Craig Myer as he was not called and therefore could not
be cross examined. The Tribunal does not accept that the Respondents
progress payments constituted evidence of their agreement to an hourly
rate. The Respondents did what many consumers do namely pay their
bills when presented. When the payments reached the total sum in the
Quote the Respondents stopped any further payment and queried Mr
Boden about the extra costs. The Respondents’ evidence is that they have
paid to Mr Boden the sum of $19,247.69 in part payments being the total
sum payable under the Quote. The Tribunal accepts this evidence and
finds that the Respondents have paid the sum of $19,247.69 to the
Applicant.
[14] The Tribunal also notes that when the Respondents complained to the
Building Services Authority that the BSA Inspector Mr Kevin Cameron in
his report noted that: there were no approved variations; that payments of
$19,247.69 had been made; and that no money remained outstanding. He
also pointed out that all the works completed were able to be completed
by Mr Boden who was a carpenter. He also commented on the fact that Mr
Boden had supplied invoices which had been calculated on an hourly rate
which was not as per the quote which was for a fixed price.
[15] The Tribunal also agrees with the Respondents’ submission that cost plus
contracts are prohibited under the Act (section 55), unless they meet
certain strict criteria. The Tribunal is not satisfied that the use of such a
contract is appropriate in these circumstances.
[16] The Tribunal is of the view that the Applicant has not produced any
evidence to give credence to his account of the agreement between the
parties. The Tribunal does not accept the Applicant’s account of the
agreement between the parties. The Tribunal finds that the agreement
between the parties is made up of the e-mail of 22 July 2012 from the
Respondents to Mr Boden and the attachments to that e-mail and the
Quote sent by Mr Boden to the Respondents constitute the agreement
between the parties.
-- 3 of 8 --
4
What does this mean?
[17] The Tribunal does not accept the Applicant's contention that this was a
cost plus agreement and that the Applicant was entitled to charge on an
hourly basis. The Applicant should have prepared a contract under the Act
and provided that to be Respondents. This was building work and it meets
the requirements of a regulated contract under the Act. This would have
amongst other things clarified the nature of the agreement between the
parties; provided a mechanism for the timing of payments; and set out a
process for variations.
[18] The Quote was for a total amount of $19,247.09. However it contained a
number of exclusions: BSA insurance/construction plans/facia
boards/gutters/painting. This would indicate that these amounts were extra
to the Quote. The Respondents e-mail of 22 July 2012 provided for the
Respondents to do work that would offset the work required to be done by
Mr Boden. Mr Boden conceded that this was the agreement but denied
the quantum of the Respondents claim.
[19] Mr Boden’s evidence was that once the plans had been drafted he met
with the Respondents and they were happy with the changes that have
been necessary. The plan involved changes to the sizes of materials and
increased the cost of the job. His evidence was that the Respondents
understood that the changes to the plans meant extra expenditure and
would mean the variation of the total sum in the Quote. The Respondents
dispute this allegation. They relied on the Applicant to undertake the work
and say that he never raised the issue of variations with them. The fact is
that Mr Boden did not provide a written variation of the job in relation to
the extra costs. He acknowledged when questioned by the Tribunal that
the agreement could be viewed as the Quote; the BSA Insurance, plus the
construction plans.
[20] The law in relation to variations is quite clear a builder is not entitled to
claim a variation unless it has the agreement of both parties. Further
under the Act it needs to be in writing. Mr Boden knew his obligations but
chose to ignore them in this matter. The Tribunal was not persuaded by
the Applicant that there were exceptional circumstances that might relieve
the Applicant of his obligations and entitle him on the basis of hardship or
any other reason to be relieved from the requirements of the law.
[21] The Tribunal finds that there were no agreed variations to the building
work to be undertaken. What the Applicant proposed was a fixed price
contract and this is the agreement which the Respondents entered into.
[22] Mr Boden’s evidence was that that the invoice dated 9 November 2012
[Exhibit 7] provided for: Engineers Specifications $490; Construction
Plans/Form 2/Form 1 $400; and Certifier Approval Fees/inspection $965.
The Quote provides for the payment of the Certifier as part of the total
cost. The Quote allows $1000 for this to be undertaken and the Invoice is
for $965 so there is a saving to the Respondents of $35. The Quote
should be adjusted down for this amount.
-- 4 of 8 --
5
[23] The Quote does not provide for construction plans to be included in the
Quote these are exclusions and accordingly additions to the Quote. These
are extra costs that Mr Boden is entitled to claim against the Respondents.
Mr Boden is entitled to claim these amounts as additions to be adjusted up
by $890. Ms Martin conceded in evidence that the plans were extra.
Upgrade to the roof
[24] Mr Boden’s evidence was that after the original plans were sized up,
sketched and provided to the engineer he determined as the patio
structure was quite high with a large roof area so that the sizes of posts
needed to be increased and other changes made. Mr Boden refers to the
report by Mr Kerry Adams dated 20 September 2012 as support for this
point. Mr Boden stated that the work which he undertook was an upgrade
to the roof of the existing dwelling. He told the Tribunal that the roof
needed to be attached and this involved pulling off the roof sheets and
strengthening the members to take the wind pressure on its structure
when it was attached. He told the Tribunal that none of this was part of the
Quote.
[25] Mr Boden states that Invoice 9 [Exhibit 7] is for the supply of and
installation of roof flashing and timber roof framing totalling $4,591.25.
This represents a variation to the agreement reached between the parties.
Mr Boden acknowledged that this was a variation and that he had not
drawn this to the attention of the Respondents. He accepted that there
was nothing on the face of the Tax Invoice to indicate that this was a
variation to the Quote that had been provided.
[26] What is quite clear to the Tribunal from their evidence is that the
Respondents were not aware of the variation. This was never discussed
with them. The onus is on the builder were a situation arises that the
contract needs to be varied to take into consideration a factor that was not
in existence of time the agreement was entered into by the parties. Mr
Boden did not do this he simply built it into his accounts. This is an
unacceptable practice.
[27] The Tribunal does not allow the variation. It was not in writing; never
explained to the Respondents; and therefore was undertaken without their
agreement.
Balance of the building work
[28] Mr Boden proceeded with job and his invoices outline various stages of
the project. Mr Boden says that on 27 December 2012 the Respondents
made a payment of $10,279.39. From that date the final invoices were not
paid. Mr Boden told the Tribunal that after Christmas the roof was finished
off and he undertook all the work that was necessary to have the project
certified. He told the Tribunal that the engineer had signed off regarding
the strength of the structure [Exhibit 5]. He told the Tribunal that the final
inspection certificate had been signed [Exhibit 6].
-- 5 of 8 --
6
[29] Ms Martin’s evidence was that they had provided Mr Boden with a sketch
of what they wanted and he had responded at providing the Quote [Exhibit
3] to undertake the work. She had on 28 July 2012 sent an e-mail [Exhibit
4] to Mr Boden accepting the Quote and instructing Mr Boden to proceed.
She denied sending Mr Boden an e-mail on that date agreeing to an
hourly rate. She told the Tribunal that she had quotes from other builders
and wanted the job to be completed at the price that had been quoted. Her
view was that the contract was for a fixed price. She did however accept
that the plans were extra.
[30] Ms Martin told the Tribunal that having accepted the quote that Mr Boden
needed to manage his labour so that he could complete the work in
accordance with the Quote. She told the Tribunal that Mr Boden had not
advised her that there were any variations to the contract for work outside
the Quote. She told the Tribunal that her training was as a social worker
and she was dependent on Mr Boden to explain to her any issues that
arose from constructing the patio in accordance with the plans. Mr Boden
provided her with invoices and they were paid up to the total provided by
the Quote. She refused to pay Mr Boden for any other work and
complained to the BSA about his conduct.
[31] Ms Martin told the Tribunal that they first became aware there was a
problem when on 23 December 2012 they received invoices 4 -7 totalling
$22,283.06 and were told that they had 24 hours to pay the same. They
had already paid $8,968.30 so they paid the balance due under the Quote
of $10,279.39 on 25 December 2012.They relied on Mr Boden to take
responsibility for the project. He was responsible for managing the project
to budget. The amount Mr Boden is seeking is $31,853.36 which is
substantially more than had been agreed.
[32] The Tribunal accepts the evidence of the Respondents that they engaged
Mr Boden to undertake the work on their behalf. The Tribunal accepts the
evidence of the Respondents that Mr Boden had the sole responsibility for
undertaking the work as the builder.
Do the Respondents have a set off on the basis of work that they have
undertaken to assist with the Applicant undertaking the building work?
[33] Mr Boden agreed that if the Respondents undertook certain work that the
Applicant might otherwise have to undertake in doing the building work
that he would make an adjustment to the total sum payable. An example
was that the Respondents had a bobcat that could be used to level the
area and to dig holes for the posts required in the construction.
[34] The Respondents evidence was that they had raised this in their e-mail of
22 July 2012 and that Mr Boden had agreed to them undertaking this
work. They say that they have contributed to the work to be undertaken by
the Applicant to the extent of 58 hours. They have valued that at a rate of
$42.50 per hour being an average of Mr Boden's value of labour rates.
This comes to a total of $2,465.
-- 6 of 8 --
7
[35] The Respondents state that Mr Boden agreed to the total price being
varied by $400 if the footings were excavated. The Respondents accepted
this variation and excavated the footings to Mr Boden's specifications. Mr
Boden did not dispute this arrangement. The Tribunal accepts that the
work was undertaken and allows an adjustment of $400 against a total
price.
[36] The Respondents states that Mr Boden agreed that he would reduce the
total price by $400 if the Respondents would drill holes. They referred to
the e-mail of 27 July 2012 from Mr Boden [Exhibit 4]. Mr Boden says in the
e-mail: “if your bobcat drills the holes the price would be approximately
$400 less”. Mr Boden did not dispute this arrangement. The Tribunal
accepts that the work was undertaken and allows an adjustment of $400
against the total price.
[37] The Tribunal does not accept the claim for a set off outside of these
adjustments. Whilst it was contemplated by the parties that the
Respondents might do work there was never any agreement reached
about the terms of that engagement. There is no information about what
work with the undertaken and the rates that would be paid in relation to
that work. The Respondents have calculated their claim on the basis of an
average in Mr Boden's pay rates. There is no evidence that Mr Boden
agreed to any rate. There was clearly never any agreement on the
essential terms of the engagement. This claim must fail for this reason.
[38] The Tribunal is of the view that the total price provided under the Quote
should be adjusted as follows:
Total sum payable under the Quote
$19,247.09
Basis of the adjustment
Less $35 See paragraph 22
Plus $890 See paragraph 23
Less $400 See paragraph 35
Less $400 See paragraph 36
Adjustments plus $55 Total $19,302.09
[39] This leaves a balance of $55 owing to the Applicant under the total sum
payable under the Quote.
[40] The Applicant claims interest in his application. There was clearly no
agreement between the parties to pay interest so that this part of the
application has been completed incorrectly. The Tribunal dismisses the
Applicant’s claim for interest. The Applicant has not proven his case so the
Tribunal does not allow the filing fees.
-- 7 of 8 --
8
[41] The Tribunal Orders the Respondents to pay the Applicant the sum of
$55. The Tribunal otherwise dismisses the Applicants claims.
Respondents’ relief
[42] The Tribunal has made findings in relation to the agreement between the
parties and the money payable to the Applicant which has addressed the
remedies the Respondents have sought in relation to paragraph 1 of the
Response.
[43] The Tribunal has made findings in relation to the work undertaken by the
Respondents which has addressed the remedies the Respondents have
sought in relation to paragraph 2 of the Response.
[44] The Tribunal notes in relation to paragraph 3 that a Final Inspection
Certificate has been signed off by the building certifier [Exhibit 6]. The
Tribunal notes further that the Respondents did not call any evidence to
support their claims in relation to the work being incomplete or not up to a
workmanlike state. The Respondents provided pictures showing work that
was allegedly defective or incomplete together with a quotation from
Heritage Plus to undertake work at the dwelling [Exhibits 15 & 16]. The
Tribunal does not accept that this constitutes sufficient evidence to prove
these matters. Ms Martin acknowledged that the Respondents did not
have the relevant expertise to give evidence on these matters. The usual
course is for the builder providing the quote to be called to give evidence
why the work is necessary and what is the basis of the costs claimed. This
allows the Applicant to cross-examine the witness and make submissions
to the Tribunal.
[45] The Tribunal notes in relation to relief claimed at paragraphs 4, 5 and 6
that the Respondents have complained to the Building Services Authority
about the state of the work that has completed and the BSA has issued
Directions to the Builder to Remedy [Exhibit 12]
[46] The Respondents have sought the assistance of the Building Services
Authority and have a remedy through that service in relation to defective
and incomplete building work.
[47] The Tribunal otherwise dismisses the Respondents Response.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/333