Clarke v Prime Building & Pest Consultants Pty Ltd [2014] QCAT 325
CITATION: Clarke & Clarke v Prime Building & Pest
Consultants Pty Ltd [2014] QCAT 325
PARTIES: Alexander John Clarke
Amanda Heidi Clarke
(Applicants)
v
Prime Building & Pest Consultants Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL314-13
MATTER TYPE: Building Matters
HEARING DATE: 19 June 2014
HEARD AT: Brisbane
DECISION OF: Member Hughes
DELIVERED ON: 7 July 2014
DELIVERED AT: Brisbane
ORDERS MADE: Prime Building & Pest Consultants Pty Ltd
pays to Alexander Clarke and Heidi Clarke
the sum of $5,695.00 by 21 July 2014.
CATCHWORDS: BUILDING INSPECTION REPORT – whether
breach of Agreement – whether report failed to
comply with Australian Standards – where
report purports to be structural only – where
report failed to report certain issues – whether
failure to report caused loss – where buyer
failed to enquire – where measure of loss is loss
of chance to negotiate reduction in purchase
price
Queensland Building and Construction
Commission Act 1991, ss 75, 77, Schedule 2
Queensland Civil and Administrative Tribunal
Act 2009, s 102
Aldridge v JHA 09 Pty Ltd [2012] QCAT 440
Castlemaine Tooheys Ltd v Carlton & United
Breweries Ltd (1987) 10 NSWLR 468
Codelfa Construction Pty Ltd v State Rail
Authority of NSW (1982) 149 CLR 337
-- 1 of 14 --
2
Lewis v Jeffrey Hills & Associates Pty Ltd [2011]
QCATA 241
Liverpool City Council v Irwin & Anor [1976] 2
All ER 39
Miller v Hancock [1893] 2 QB 177
O’Connell v JHA No. 11 Pty Ltd [2013] QCAT
710
Robinson v Harman [1848] EngR 135
Spargo v Katz [2010] QCATA 94
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Alexander John Clarke and Mrs Amanda
Heidi Clarke in person
RESPONDENT: Mr Mark Rentoul, Director for Prime Building &
Pest Consultants Pty Ltd
REASONS FOR DECISION
What is this Application about?
[1] Home buyers often engage building and pest inspectors to report on
building and pest issues before completing their purchase.
[2] Mr Alexander Clarke and Mrs Heidi Clarke paid $410 to Prime Building &
Pest Consultants Pty Ltd to report on building and pest issues for
139 Kent Road, Wooloowin.1
[3] Mr and Mrs Clarke then completed their purchase of the property.
Mr and Mrs Clarke have since discovered issues not identified in Prime’s
building and pest reports. They claim that had Prime identified these
issues, they would not have completed the purchase.
[4] Mr and Mrs Clarke limited their claim to $50,000 to ensure it is within the
Tribunal’s jurisdiction.2
[5] The Tribunal may therefore award damages, interest thereon, restitution
and costs.3
What was the Agreement?
[6] Prime’s Report comprised a building report4 and pest report5.
Prime claims that the parties agreed that the building report was limited to
a structural report only.
1 Tax Invoice 42531 of Prime Building & Pest Consultants Pty Ltd dated 19 October
2012.
2 Queensland Building and Construction Commission Act 1991, ss 75(1)(g), 77 and
Schedule 2 definitions of “building dispute”, “minor commercial building dispute”,
“commercial building dispute”, “reviewable commercial work” and “tribunal work”.
3 Ibid s 77.
-- 2 of 14 --
3
[7] I do not accept this was the Agreement because of the below
considerations.
Agreement with structural limitation not signed
The Agreement and Report Definition purporting to limit the inspection and
report to ‘readily visible structural defects’ is not signed or dated by any of
the parties – this in itself is a breach of the Australian Standard
AS4349.1.6 An inference can therefore be drawn that this does not reflect
the Agreement between the parties.
Tax Invoice without limitation
The Tax Invoice7 refers to ‘Building and Pest + free Ultrascan House 4’
without fetter or qualification.
Post-Contract limitation only
Although the Prime Report purports to limit the inspection to ‘any
significant and obvious structural defects’8, the Prime Report is provided
after the inspection. It therefore cannot form part of the pre-contractual
negotiations between the parties or contractual terms agreed upon
between the parties. Mr and Mrs Clarke did not know of the purported
limitation until they received the report from Prime. They therefore could
not have agreed to the limitation.
Report content beyond structural only
A structural report is limited in its scope to identifying major defects of the
building structure9 and should not contain any assessment or opinion of
any non-structural element including roof plumbing and roof covering,
cabinetry, windows, doors, trims, fencing, non-structural damp issues,
ceiling linings, floor coverings and decorative finishes such as plastering,
painting and tiling.10
Yet the Report extends to and comments on items including ‘Cladding’,
‘Eaves’, ‘Fascia’, ‘Gutters & Valleys’, ‘Downpipes’, ‘Site Drainage’, ‘Hot
Water System’, ‘Kitchen’, ‘Laundry’, ‘Bathroom’, ‘Ensuite’, ‘Doors’, ‘Door
Furniture’, ‘Windows’, ‘Paintwork’ and ‘Plaster / Sheeting’. The Report
specifically notes the cabinets in the kitchen, bathroom and ensuite are
‘generally in good condition’.
4 Prime Building & Pest Consultants Pty Ltd Building Inspection Report of Marc Ellis
dated 19 October 2012.
5 Prime Building & Pest Consultants Pty Ltd Visual Timber Pest Inspection Report of
Marc Ellis dated 19 October 2012.
6 AS4349.1 – 2007 at paragraph 2.1.
7 Tax Invoice 42531 of Prime Building & Pest Consultants Pty Ltd dated 19 October
2012.
8 Prime Building & Pest Consultants Pty Ltd Building Inspection Report of Marc Ellis
dated 19 October 2012 at page 3.
9 AS4349.1 – 2007 at paragraphs 2.2 and 2.3.1 and Appendix A, Paragraph A3.
10 Ibid Appendix A, paragraph A3.
-- 3 of 14 --
4
These items are not consistent with a mere structural report but are
consistent with items to be inspected and commented on in a full building
inspection report11:
There is a difference between a structural inspection report and a building
inspection report. The difference is set out in AS4349.1. A structural
inspection report should not contain any assessment or opinion regarding
any non-structural element, any component that cannot be seen or requires
testing, general maintenance or serviceability issues, or damp defects
unless there is a structural change. A structural report is… a very basic
report.12
[8] I therefore find that Mr and Mrs Clarke engaged Prime to conduct a pre-
purchase building and pest inspection that was not limited to structural
defects.
Did Prime breach the Agreement?
[9] Mr and Mrs Clarke claim that the Prime Report failed to identify a number
of issues as required by the Australian Standard. During the hearing,
Mr and Mrs Clarke conceded the following items were not supported by
the Building Service Authority Reports13 or any quantum evidence or were
beyond the scope of the Prime Reports: Brisbane City Council Approvals
($791.00), Electrical ($836.90), Engineer Drawings ($962.50), Plumber
($929.50), Fences ($1,800) and Floor to Main Bedroom ($1,700). Mr and
Mrs Clarke therefore did not proceed with those claims.
[10] The Australian Standards prescribe the minimum requirements for a pre-
purchase building and pest inspection report. The Report incorporates
references to those Standards in its title.14 The purpose of engaging a
licensed builder to inspect the property is to identify defects in the
property.15 The types of defects to be identified are prescribed in the
Standards. I am therefore satisfied that compliance with the Standards is
an implied term of the Agreement:
Terms can be implied by law (as a legal incident to a particular class of
contract, regardless of the intention of the parties) or by necessity to give
business efficacy to a particular contract. Those implied by law are deemed
necessary by implication; otherwise the whole of the transaction would be
futile.16
11 Ibid at Appendix C.
12 Aldridge v JHA 09 Pty Ltd [2012] QCAT 440 at [10].
13 Building Services Authority Pre-Purchase Inspection Investigation Report of Michael
Hulme dated 5 April 2013 and Building Services Authority Pre-Purchase Pest
Inspection Investigation Report / Statement Of Reasons of Michael Hulme dated 30
August 2013.
14 The Building Report is entitled “Building Inspection Report Special Purpose Report –
Australian Standards (AS4349.1)”. The Pest Report is entitled “Visual Timber Pest
Inspection Report Visual Timber Pest Inspection – Australian Standards (AS4349.3)”.
15 Lewis v Jeffrey Hills & Associates Pty Ltd [2011] QCATA 241 at [16].
16 Spargo v Katz [2010] QCATA 94 at [13], per Wilson J applying Castlemaine Tooheys
Ltd v Carlton & United Breweries Ltd (1987) 10 NSWLR 468 at 487-489, Codelfa
Construction Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337 at 345-346
-- 4 of 14 --
5
[11] The Prime Report purports to limit its scope to ‘significant and obvious
structural defects’.17 Contrary to this purported limitation, the Prime
Report then reports on items18 that are beyond the scope of a structural
inspection19 but within the scope of a building inspection20, consistent with
the Agreement. Purporting to limit the scope of the report to a structural
report is a breach of the Agreement.21
[12] It was not until the hearing that Mr and Mrs Clarke verbally correlated their
claim with an amount for each issue with the property. The below table
itemises these issues with the corresponding Prime Report description,
BSA Report finding and quantum evidence.
Area Prime Report
Description22 BSA Report
Finding23 Cost to rectify24 Invoice /
Quote
Carport Not applicable /
Not reported
AS4349.1
does not
require Prime
Report to
identify
unauthorised
building work
or work not
compliant with
building
regulations
Boxed out
section with
damp proof
course fixed to
wall cladding
to prevent
water ingress
is installation
defect
(AS4349.1 –
Table F1 Item
F)
Cut back to
legal size
($957.00)
Replace
leaking roof to
conform with
code
($2,420.00)
Install down
pipes and
gutter to meet
code
($1,083.50)
Josh Olsen
Carpentry Pty
Ltd Quote 534
of dated 24
July 2013
(per Mason J), Liverpool City Council v Irwin & Anor [1976] 2 All ER 39 and Miller v
Hancock [1893] 2 QB 177 at 180 and 181 (per Bowen LJ).
17 Prime Building & Pest Consultants Pty Ltd Building Inspection Report of Marc Ellis
dated 19 October 2012 at page 3.
18 Ibid at pages 4B (Cladding), 7 (Eaves, Fascia), 12 (Gutters & Valleys, Downpipes),
13 (Site Drainage, Hot Water System), 15 (Kitchen, Laundry), 16 (Bathroom, Ensuite),
17 (Doors, Door Furniture, Windows), 18 (Paintwork, Plaster / Sheeting).
19 AS4349.1 – 2007 at paragraphs 2.2 and 2.3.1 and Appendix A, Paragraph A3.
20 Ibid at Appendix A, paragraph A3.
21 A similar finding was made in Aldridge v. JHA 09 Pty Ltd [2012] QCAT 440 at [18] to
[20].
22 Prime Building & Pest Consultants Pty Ltd Building Inspection Report of Marc Ellis
dated 19 October 2012 and Prime Building & Pest Consultants Pty Ltd Visual Timber
Pest Inspection Report dated 19 October 2012.
23 Building Services Authority Pre-Purchase Inspection Investigation Report of Michael
Hulme dated 5 April 2013 and Building Services Authority Pre-Purchase Pest
Inspection Investigation Report / Statement Of Reasons of Michael Hulme dated
30 August 2013.
24 Including GST.
-- 5 of 14 --
6
Area Prime Report
Description22 BSA Report
Finding23 Cost to rectify24 Invoice /
Quote
Prime Report
does not note
defective
guttering
system
evident at time
of inspection
Front Awning / Pergola Timber beam to
roof is bowed
Maintenance
recommended
Good ground
clearance to
timber post is
recommended
Good to fair
condition
Prime Report
clearly
advises timber
beam is
bowed
Damp proof
course fixed to
timber fascia
to prevent
water ingress
is installation
defect
Prime Report
does not note
defective
installation of
damp proof
course evident
at time of
inspection
Pull down
entire pergola
rebuild using
correct tie
down and
construction
and install
flashings and
replace
warped head
($4,059)
Remove soil
to below base
of posts as
per code –
paint and
finish
($3,146)
Josh Olsen
Carpentry Pty
Ltd Quote 534
of dated 24
July 2013
Back Awning /
Veranda
Not applicable /
not reported - but
generally in good
to fair condition
Sealant to
timber support
posts through
tiled and metal
roof to prevent
water ingress
is installation
defect
Timber
support post is
out of plumb
Prime Report
does not note
sealant and
support post
being out of
plumb evident
at time of
inspection
Replace
support posts
to conform
with code
($3,173.50)
Install roof
flashings
($698.50)
Install
beadings to
suffits ($308)
Install tie
down to
rafters and
head ($561)
Paint & Finish
($726)
Josh Olsen
Carpentry Pty
Ltd Quote 534
of dated 24
July 2013
Front Low Deck No access to
under decking /
veranda
Property
considered to
have no termite
Over-sized for
council
regulations
and possible
white ant
threat with
proximity to
Remove
illegal
structure as
requested by
council
($1,001)
Install
Josh Olsen
Carpentry Pty
Ltd Quote 534
dated 24 July
2013
Qld Termite
Reports
-- 6 of 14 --
7
Area Prime Report
Description22 BSA Report
Finding23 Cost to rectify24 Invoice /
Quote
protection ground
AS4349.1
does not
require Prime
Report to
identify
unauthorised
building work
or work not
compliant with
building
regulations
Prime Report
does not note
breaching of
visual physical
barrier from
ground being
in close
proximity to
timber deck
and deck
connection to
garage /
carport /
dwelling
concealing
access to
building
suitable
landscaping
as per plan
($1,650)
Subterranean
termite
treatment to
house and
decks
($1,331)
Australia Pty
Ltd Tax
Invoice C123
dated 5
December
2012
Ensuite Generally in good
condition
Weather boards
cladding –
paintwork is in
good condition
Damp proof
course fixed to
wall cladding
to prevent
water ingress
is installation
defect
Polycarbonate
cladding
wrapped from
roof onto wall
to form wall
cladding to
prevent water
ingress is
installation
defect
Prime Report
does not note
defective
installation of
damp proof
course and
polycarbonate
cladding
evident at time
of inspection
Repair wall
cladding
($1809.50)
Remove and
replace roof
to key into
existing roof
($20,086)
Connect into
existing
guttering
($696)
Josh Olsen
Carpentry Pty
Ltd Quote 534
dated 24 July
2013
-- 7 of 14 --
8
Area Prime Report
Description22 BSA Report
Finding23 Cost to rectify24 Invoice /
Quote
Side wall outside
kitchen
Weather boards
cladding –
paintwork is in
good condition
Damp proof
course fixed to
wall cladding
to prevent
water ingress
is installation
defect
Prime Report
does not note
defective
installation of
damp proof
course evident
at time of
inspection
Remove
damp-course
covering
holes, install
weather
boards to
match house
($385)
Josh Olsen
Carpentry Pty
Ltd Quote 534
dated 24 July
2013
Brick sub-floor Sub-floor was
inspected –
access was fair
Conditions which
can increase the
likelihood of
timber infestation
include poor
ventilation and
inadequate
drainage in
subfloor area
Areas which are
susceptible to
termite activity -
Subfloor
Prime Report
does not note
enclosed sub-
floor under
kitchen and
main bedroom
where no
access is
available and
does not note
that area not
inspected and
provide
reason for
exclusion from
inspection
Subterranean
termite
treatment to
house and
decks
($1,331)
Qld Termite
Reports
Australia Pty
Ltd Tax
Invoice C123
dated 5
December
2012
Timber boxing for
concrete pathway
Property
considered to
have no termite
protection
Prime Report
does not note
breaching of
visual barriers
between
ground and
dwelling on
right side and
rear of
dwelling
where boxing
used for
concrete
pathway and
rear timber
support post
in contact with
concrete
concealing
access to
building
Remove
timbers in
contact with
soil to stop
termites
($3575)
Josh Olsen
Carpentry Pty
Ltd Quote 534
dated 24 July
2013
-- 8 of 14 --
9
[13] Based on the findings of the independent expert evidence25, I accept that
the Prime Report fails to comply with the Australian Standard where noted
in the above Table, in breach of the Agreement.
Did Prime’s breach of the Agreement cause Mr and Mrs Clarke’s loss?
[14] Mr and Mrs Clarke claim that had they known of these issues, they would
have terminated the Contract to buy the property and not proceeded with
the purchase.
[15] Prime claims that Mr and Mrs Clarke could not have terminated the
Contract in any event. This is because Mr and Mrs Clarke did not pay for
the Prime Report until after business hours on 19 October 2012 and
therefore did not receive the Report until 22 October 2012, after the date
of inspection in the Contract of Sale26.
[16] The Contract of Sale is dated 13 October 2012 with an Inspection date of
‘7 days from date of Contract’. Although terms of the Contract relating to
calculation of time were not submitted in evidence, it is a usual condition
that if an inspection date falls on a day that is not a business day, then it
falls on the next business day. Seven days from 13 October 2012 is
20 October 2012. 20 October 2012 fell on a Saturday. The next business
day was Monday 22 October 2012. This means that Mr and Mrs Clarke
had until 22 October 2012 to terminate the Contract.
[17] Mr and Mrs Clarke had the Prime Report on that day. The Prime Report
had sufficient detail that should have at least raised questions for Mr and
Mrs Clarke:
The scope of the Prime Report purports to be limited to ‘significant
and obvious structural defects… apparent at the time of inspection’;
The Prime Report ‘relates only to that which is readily viewable.
No opinion or warranty is made on that which cannot be readily
seen’;
The Prime Report notes ‘No inspection available under floor
coverings – infrared thermal imaging is recommended for concealed
areas or areas of no access’;
The Prime Report notes ‘Gutters and Valleys – where there is no
access to the roof the related comments are from the ground only.
Joints to all valleys on the roof structure should be maintained with
waterproofing material such as silicone’;
The Prime Report notes ‘Downpipes – visual inspection not possible
due to height restrictions. Recommendations: maintain silicone to
joins’;
The Prime Report notes ‘Visual inspection of gutters, eves and
fascia, viewed from ground due to height restrictions’;
25 BSA Report of Mr Michael Hulme dated 5 April 2013.
26 Contract of Sale dated 13 October 2012.
-- 9 of 14 --
10
The Prime Report notes ‘Internal – high moisture was found;
Recommend to improve ventilation to subfloor’;
The Prime Report notes ‘Front Low Deck - No access to under
decking / verandah – High Risk Area to which access should be
gained, or fully gained, since they may show evidence of Timber
Pests or Damage’;
The Prime Report notes ‘Interior inspected but with some restrictions
- High Risk Area to which access should be gained, or fully gained,
since they may show evidence of Timber Pests or Damage’;
The Prime Report notes ‘Furnishings in dwelling have restricted
inspection – of walls and timber finishings of doors and windows -
High Risk Area to which access should be gained, or fully gained,
since they may show evidence of Timber Pests or Damage’;
The Prime Report notes ‘No access to roof due to OH&S height
restrictions’;
The Prime Report notes ‘No inspection was made, and no report is
submitted, of inaccessible areas. These include, but may not be
limited to, cavity walls, concealed frame timbers, eaves, flat roofs,
fully enclosed patio subfloors, soil concealed by concrete floors,
fireplace hearths, wall linings, landscaping, rubbish, floor coverings,
furniture, pictures, appliances, stored items, insulation, hollow
block/posts etc.’;
The Prime Report states that the property is ‘considered to have no
termite protection’;
The Prime Report recommends ‘a TermiteScan – Infrared Thermal
Imaging to find relative thermal patterns associated with termite
nesting in concealed areas ie inside walls that can not be visually
accessed by the inspector’;
The Prime Report notes under ‘Areas Which Are Susceptible To
Termite Activity’: ‘Conditions which can increase the likelihood of
timber infestation include poor ventilation and inadequate drainage in
subfloor area’; ‘Air conditioning leaking next to dwelling’; ‘Good
clearance between ground level and bottom of weep holes is
recommended for unrestricted visual inspection of termite entry into
dwelling. Australian standards recommends 75mm clearance’;
‘Subfloor’; ‘High moisture areas’; and
The Prime Report notes the carport as ‘Not applicable / Not reported’.
[18] Mr and Mrs Clarke did not explore these caveats within the Prime Report
with Prime, did not enquire about access to, or attempt to arrange more
intrusive inspections such as infrared thermal imaging of, restricted areas
as recommended, or revisit the property to clarify these caveats.
[19] The Prime Report’s content makes it clear that it is not comprehensive.
I therefore do not accept that it was reasonable for Mr and Mrs Clarke to
-- 10 of 14 --
11
rely upon the Prime Report to proceed to completion of the purchase of
the property without further enquiries or inspections.27
[20] Specifically, I do not accept the Prime Report is causative of the below
items.
Carport
The Prime Report is clear that this is not reported.
Front Awning / Pergola
That the Prime Report fails to note the defective installation of damp proof
course does not warrant the entire rebuilding of the pergola or removing
the soil to below base as claimed. The costs of rebuilding the pergola are
attributable to the need for correct construction and not any failure of the
Prime Report – the Prime Report specifically notes the timber beam is
bowed. The cost of removing the soil is not attributable to any failure of
the Prime Report – the Prime Report specifically recommends good
ground clearance and maintenance.
Back Awning / Verandah
The defective sealant referred to in the BSA Report appears not clearly
visible from ground height. This suggests it was “not readily viewable” and
“cannot readily be seen” due to height restrictions. These cannot be
attributed to any failure of the Prime Report.
Front Low Deck
The Prime Report clearly notes no access and that the property has no
termite protection. The costs of termite protection cannot be attributed to
any failure of the Prime Report.
Ensuite
The defective cladding referred to in the BSA Report is visible only from
the roof. The Prime Report clearly notes no access to roof due to
occupational health and safety (OH&S) restrictions. The costs of repairing
the cladding and removing and replacing the roof to key into the existing
roof and connecting into existing guttering cannot be attributed to any
failure of the Prime Report.
Brick sub-floor
The Prime Report clearly notes the subfloor as susceptible to termite
activity. The costs of treatment cannot be attributable to any failure of the
Prime Report.
27 Similar reasoning was applied in Aldridge v JHA 09 Pty Ltd [2012] QCAT 440 at [33].
-- 11 of 14 --
12
[21] This means that the only inaccurate items in the Prime Report reasonably
relied upon by Mr and Mrs Clarke were as follows:
Back Awning / Verandah – the Prime Report failed to note the timber
support post out of plumb (replacement cost - $3,173.50);
Side wall outside kitchen – the Prime Report failed to note the
defective installation of the damp proof course (rectification cost -
$385.00); and
Timber boxing for concrete pathway – the Prime Report failed to note
the breaching of visual barriers (removal cost - $3,575.00).
[22] I am satisfied that Mr and Mrs Clarke suffered loss because of Prime’s
failure to properly identify these issues.
What is the measure of Mr and Mrs Clarke’s loss?
[23] Mr and Mrs Clarke’s loss is not the cost of rectifying these three issues.28
This is because the purpose of damages is to restore Mr and Mrs Clarke
to the position they would have been in had the wrongful act not
occurred.29 This means assessing the true measure of loss flowing from
Prime’s negligence or breach of contract.30
[24] Mr and Mrs Clarke claim that the measure of their loss is the difference
between the amount they paid for the property of $585,00031 and the
amount it was worth, with a proper building and pest inspection, of
$525,000 as noted in the valuation report32, plus a refund for the cost of
the Prime Report ($410).
[25] The Tribunal has previously refused to accept this method where the loss
is not solely attributable to the failure to report:
In my view it is not appropriate to adopt the diminution in value… some of
the costs assumed in the valuation are costs in respect of work found to be
other than because of a failure to properly report.33
[26] The valuation is assessed ‘as at the date of purchase … as if all those
faults were known to a potential purchaser’.34 This refers to all the faults
forming Mr and Mrs Clarke’s claim. However, Mr and Mrs Clarke would or
should reasonably have known of most of these faults had they
undertaken further enquiries or inspections. Mr and Mrs Clarke elected
28 See for example Lewis v Jeffrey Hills & Associates Pty Ltd [2011] QCAT 241 at [20] to
[22] and Aldridge v JHA 09 Pty Ltd [2012] QCAT 440 at [41].
29 Robinson v Harman [1848] EngR 135.
30 Lewis v Jeffrey Hills & Associates Pty Ltd [2011] QCATA 241 at [20].
31 Contract of Sale dated 13 October 2012. The purchase price is amended from
$585,000 to $600,000. However, Mr and Mrs Clarke stated they negotiated a reduction
to $585,000 because of issues from searches of the property. Regardless, the
Tribunal’s jurisdiction is limited to $50,000.
32 Valuation Report of Herron Todd White dated 11 February 2014 at pages 5 and 6.
33 O’Connell v JHA No. 11 Pty Ltd [2013] QCAT 710 at [156].
34 Valuation Report of Herron Todd White dated 11 February 2014 at page 5 under
“General Comments”.
-- 12 of 14 --
13
not to attempt further inquiries or inspections or to terminate the Contract
but continued with the purchase. Most of these faults are therefore not
attributable to a failure by Prime to properly report.
[27] I therefore do not accept the difference between the actual purchase price
and valuation of the property as noted in the valuation report to be a true
reflection of Mr and Mrs Clarke’s loss.
[28] It was reasonable for Mr and Mrs Clarke to rely upon the Prime Report to
the extent that it failed to identify the out of plumb timber post on the back
awning and verandah, the damp proof course on the kitchen wall and the
breaching of visual barriers. However, there is no evidence of what
Mr and Mrs Clarke would have done had they known of these three issues
alone.
[29] Mr and Mrs Clarke essentially had three options:
… if the buyer is not satisfied with the building report (the applicant) could
have elected to terminate. Secondly, she would have been in a position to
negotiate a reduction in price… Thirdly, if the vendor was resistant to any
further negotiation, she could have completed and waived reliance on the
building inspection report.
There is no evidence from (the applicant) as to what she would have done
had she known the pool did not comply because she was never in a
position to consider her options. However, she was clearly placed in a
position of disadvantage due to the inaccuracy of the report. One therefore
has to assess damages having regard to all of the above factors and apply
a discount on the basis that she may have completed the transaction in any
event without a discount on the purchase price.35
[30] I am not satisfied that Mr and Mrs Clarke could have terminated the
Contract of Sale had Prime reported on these three issues. A buyer must
act reasonably.36 The cost of rectifying these items represents a small
portion of the purchase price. I therefore do not consider these items to
be sufficiently serious for a buyer acting reasonably to terminate a
Contract of Sale.
[31] Instead, Mr and Mrs Clarke could have attempted to negotiate a reduction
in the purchase price because of these issues. There is no way of knowing
whether and the extent to which this might have succeeded.
Effectively, the measure of their loss is the loss of chance for Mr and
Mrs Clarke to negotiate a discount for these three issues.
[32] Mr and Mrs Clarke’s purchase was subject to finance. This suggests that
the property was appropriately valued and unlikely to be discounted:
I note that (the applicant’s) purchase was subject to finance. Presumably,
the property came up to valuation, otherwise finance would have been
declined. If the bank valuer inspected the property and it came up to
35 Lewis v Jeffrey Hills & Associates Pty Ltd [2011] QCATA 241 at [21] and [22].
36 Contract of Sale dated 13 October 2012, Condition 4.2(a).
-- 13 of 14 --
14
valuation, then without further evidence, I find it unlikely that the seller
would have renegotiated the purchase price.37
[33] However, there is evidence here that at the time of sale, market conditions
did not favour the seller. The valuation report relevantly notes:
2011 was typified by relatively slow market conditions resulting in
historically low sale volumes… some improvement in market conditions was
experienced over the first quarter of 2012, with increased interest and
enquiry reported, however there was no significant increase in market
values. Market sentiment remained subdued.38
[34] This suggests that Mr and Mrs Clarke may have had some success in
negotiating a reduction in the purchase price had they brought to the
seller’s attention the out of plumb timber post on the back awning and
verandah, the damp proof course on the kitchen wall, and the breaching of
visual barriers. However, I am not satisfied that this would extend to a
discount equating to the full cost of rectifying these issues.
[35] The cost to rectify these issues exceeds $7,000.00.39 Mr and Mrs Clarke
gave evidence during the hearing that the seller agreed to a $15,000.00
discount from $600,000.00 to $585,000.00 three days before settlement
due to compliance issues. There is therefore evidence that the seller was
willing to negotiate.
[36] Applying all these factors, I consider an award of $5,000.00 damages is
appropriate. Mr and Mrs Clarke are also entitled to a refund for the cost of
the Prime Report of $410.00 plus their filing fee of $285.0040.
What are the appropriate orders?
[37] The appropriate order is that Prime Building & Pest Consultants Pty Ltd
pays to Alexander Clarke and Heidi Clarke the sum of $5,695.00 by
21 July 2014.
37 Aldridge v JHA 09 Pty Ltd [2012] QCAT 440 at [40].
38 Valuation Report of Herron Todd White dated 11 February 2014 at page 5 under
“Market Commentary”.
39 I do not accept that the breaching of visual barriers is remedied simply by a termite
management plan recommended by the Prime Report. Removing the visual barriers
themselves is integral to the success of any termite management plan, equating to a
cost of $3,575.00 as noted in the Josh Olsen Carpentry Pty Ltd Quote 534 dated
24 July 2013.
40 Queensland Civil and Administrative Tribunal Act 2009, s 102.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/325