Davies v Amazing Decks Pty Ltd [2014] QCAT 316
CITATION: Davies v Amazing Decks Pty Ltd [2014] QCAT
316
PARTIES: John Paul Davies
(Applicant)
v
Amazing Decks Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL346-12
MATTER TYPE: Building matters
HEARING DATE: 18 March 2014
HEARD AT: Brisbane
DECISION OF: Member A Fitzpatrick
DELIVERED ON: 2 July 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. Amazing Decks Pty Ltd pay to John Paul
Davies the sum of $611.60 within 21 days
of the date of this Order.
CATCHWORDS: Building dispute – defective work – damages for
breach – liquidated damages.
APPEARANCES and REPRESENTATION (if any):
APPLICANT: John Paul Davies, self represented
RESPONDENT: Amazing Decks Pty Ltd represented by Simon
Ramke, Director.
REASONS FOR DECISION
Background
[1] The applicant Mr Davies entered into a contract with the respondent
Amazing Decks Pty Ltd for the construction of a landscape deck abutting
his residence and extending over a septic tank on the property.
[2] Mr Davies signed a Master Builders Minor Works Contract Schedule on
18 October, 2011. The Contract Schedule provides that a quotation forms
part of the contract. The quotation is dated 17 October, 2011 and
-- 1 of 6 --
2
comprises a description of the work by reference to an attached Plan
dated 13 September, 2011. Also attached to the Contract Schedule and
initialled by Mr Davies is a document headed “Conditions of Sale and
Quotations”. The Contract Schedule expressly provides at Item 14 that no
Contract Information Statement was provided to the home owner.
[3] The contract price was $44,301.40 inclusive of GST, payable in stages,
with the bulk of the sum payable by the time of commencement of
installation of posts, battens and decking.
[4] The commencement date was said to be 31 October, 2011. The Contract
Schedule provides for a date for practical completion of 20 December,
2011.
[5] During the course of construction, the nominee of Amazing Decks Pty Ltd,
Mr Ramke encountered personal difficulties which resulted in delays to
completion of the deck. The deck was completed on 22 June, 2012, a
delay in completion of 185 days.
[6] Mr Davies made certain complaints to the Queensland Building Services
Authority (QBSA), which directed Mr Ramke to rectify aspects of the work.
This was completed to the satisfaction of the QBSA.
[7] Mr Davies has brought this claim in relation to other matters.
Claim
[8] Mr Davies claims:
a) liquidated damages of $50.00 per day for a period of 185 days in the
sum of $9,250.00;
b) re-imbursement of $556.00 plus GST paid as part of the contract
price for materials not supplied as part of the completed work:
316 Stainless steel wire rope at $10 per metre, 14 metres -
$140.00
Jaw/Jaw rigging screw and lag screws, 6 at $24/piece - $144.00
Flat Bar 316 Stainless Steel Spreader at $5.25/metre, 8 metres -
$42.00
Protectadeck Impervious Joist Protection at $25/25 metre roll,
12 rolls - $300.00
3 step Galvanised steel stair stringer at $130.00.
[9] As first formulated Mr Davies, claimed an unspecified amount for “Septic
tank top rework of hatch”. He also claimed labour charges of $3,000.00
plus GST, estimated at 10 six hour days (60 hours) at $50.00/ hour for
rectification work carried out by another contractor to alleged defects to
the support structure of the deck.
-- 2 of 6 --
3
[10] Mr Davies tendered a report from Steven Drury Builder, dated 18 October,
2012, which set out a list of defects in the work performed by Amazing
Decks Pty Ltd. Mr Drury was engaged to rectify this work, however, there
is no discrete supporting evidence as to his costs in undertaking that
rectification work. Mr Davies said at the hearing that rectification of non-
tradesman like work did not form part of the claim against Amazing Decks
Pty Ltd.
[11] Mr Davies subsequently claimed the sum of $5,963.79 for labour
performed and materials supplied by Steven M Drury, Builder who
installed further hatches above the septic tank and who dismantled and
reconstructed parts of the deck. Mr Davies tendered a list of costs from
Mr Drury in relation to this work. Mr Drury was not called to give evidence
or to be cross examined.
[12] Mr Davies’ evidence was that leaving the battens exposed for a long
period of time caused excessive weathering, creating cracks and that lack
of Protectadeck joist protection resulted in boards lifting at regular
intervals. He also gave evidence that it was not possible to paint the deck
to give it protection until the defective work had been rectified including the
work directed to be performed by the QBSA which was performed in
October, 2012.
[13] Mr Davies also tendered a number of photographs of the allegedly
defective work and photographs evidencing work and materials omitted
from the deck.
[14] Mr Davies relied upon a paragraph in relation to “Liquidated Damages” set
out at page 3 of the Master Builders 06/11 Contract Information Statement
which he obtained from Master Builders Queensland, in support of his
claim for liquidated damages of $50.00 per day. He submitted that the
Domestic Building Contracts Act 2000 requires the contract information
document to be provided to him. The Contract Information Statement
explains that the contract provides for a default rate for liquidated
damages of $50 per day where nothing is stated in the contract schedule.
[15] Finally, Mr Davies pointed to the drawing attached to the quotation in the
contract documents which referred to “access hatches” to support his
contention that Amazing Decks Pty Ltd had only installed one hatch to
access the septic tank, when 3 were required.
Response
[16] Mr Ramke on behalf of Amazing Decks Pty Ltd gave evidence that there
was no contractual term between the parties which entitled Mr Davies to
liquidated damages for delay. His evidence was that he informed
Mr Davies during the course of the project of the reasons for delay and
that Mr Davies expressed understanding. He does not otherwise deny the
delay.
-- 3 of 6 --
4
[17] Mr Ramke did not deny that an 11th row of wires around the deck
balustrade was omitted, nor that 2 rather than 3 steps were installed.
Nor did he submit that there had been an adjustment to the contract price
to take account of these omissions.
[18] In relation to application of the Protectadeck product, Mr Ramke said that
a product ‘H4” was used which meant that there was no need for
Protectadeck.
[19] Mr Ramke pointed to the description of works in the quotation which
referred to construction of an “access hatch”, singular. He says that he
was not told at any time during the course of construction that 3 hatches
were required.
[20] Mr Ramke submitted at the hearing that Mr Drury was unqualified to say
what work needed to be rectified and that in any event the installation of a
steel floor frame was unnecessarily expensive. The original floor frame
was timber.
[21] Mr Ramke submitted that none of the costs paid to Mr Drury need to have
been incurred and that the QBSA would have required rectification works
to be performed if necessary. That did not occur. He said that he offered
to rectify any defective work, however that offer was declined by
Mr Davies.
Findings
[22] I find that the documents comprising the contract between the parties are;
a) the Master Builders Minor Works Contract Schedule dated
18 October, 2011;
b) quotation, dated 17 October, 2011 together with an attached drawing
dated 13 September, 2011 and
c) “Conditions of Sale and Quotations” document initialled and dated
18 October, 2011.
[23] It is apparent that Amazing Decks Pty Ltd has used part, but not all, of the
Master Builders’ standard form contract. The standard form usually
includes a set of general conditions to accompany the Schedule.
Amazing Decks Pty Ltd has added its own set of general conditions to be
read in conjunction with the Schedule. The question is whether the
Master Builders’ general conditions which are said to contain a default
provision in relation to liquidated damages can be taken to be
incorporated as terms of the contract.
[24] Provision of its own detailed general conditions and failure to provide the
Master Builders general conditions to Mr Davies, suggests that Amazing
Decks Pty Ltd had no intention of incorporating the general conditions as
terms of the contract. It appears that Mr Davies had no knowledge of the
existence of general conditions until he pursued a copy of the Contract
-- 4 of 6 --
5
Information Statement after the dispute with Amazing Decks Pty Ltd arose.
The general conditions are not in evidence.
[25] This is not a case where there is a liquidated damages item in the
schedule which has been left blank so that there might be the opportunity
for a default provision to operate. In this case there is no reference at all
to liquidated damages in the schedule, to which a default provision might
attach, even if the general conditions were found to form part of the terms
of the contract in question.
[26] I also note that it is not apparent on the face of the Contract Information
Statement forming part of Mr Davies evidence that it is the Contract
Information Statement which accompanies a minor works contract or
whether it is relevant to a different contract in the suite of Master Builders
documents. The Contract Information Statement does not purport of itself
to constitute terms and conditions of any contract, it is merely provided for
information purposes to aid understanding of a contract entered into by a
home owner. Mr Davies has not provided a copy of the term from the
standard terms and conditions on which he relies in order for it to be
interpreted by this Tribunal or considered by Amazing Decks Pty Ltd.
[27] For these reasons I find that there was no term of the contract between
the parties that liquidated damages of $50.00 per day apply. Mr Davies
claim for liquidated damages must fail.
[28] In relation to the claim for recovery of moneys not expended by Amazing
Decks Pty Ltd on works omitted from the contract I find on the basis of
Mr Ramke’s evidence that the work was not performed, the materials were
not supplied and there was no consequent adjustment to the contract
price. On that basis Mr Davies is entitled to recover the sum of $556.00
plus GST ($611.60) for the items set out at paragraph [8](b) above.
In relation to the Protectadeck claim, I find that application of H4 was in
any event part of the contract work and that the contract specifically
provided for “all battening and joists to have Protectadeck impervious joist
protection installed”. H4 was not a substitute for the Protectadeck product.
[29] In relation to the claim for recovery of the sum of $5,963.79 I accept the
submissions of Mr Ramke that there is no evidence of defective work
which necessitated rectification in the manner effected by Mr Drury.
Mr Drury did not give evidence and was not able to be cross examined in
relation to the work he performed. I am not satisfied on the evidence that
there has been any breach of contract by Amazing Decks which required
dismantling of the sub floor frame and replacement with a steel floor
frame. I am not prepared to order that Amazing Decks meet those costs.
[30] In relation to the instalment of 3 access hatches over the septic tank, there
is no evidence before me of any local authority requirement in relation to
the extent of access required. The contract itself is not clear in relation to
how many hatches should be installed. In any event, even if I were to find
that Amazing Decks Pty Ltd was in breach of contract for failing to install
more than one access hatch, I cannot discern from Mr Drury’s list of costs
-- 5 of 6 --
6
what labour and materials relates to construction of the additional access
hatches apart from the other reconstruction work carried out by him.
For these reasons I refuse the claim by Mr Davies relating to construction
of further access hatches.
Order
[31] I order that Amazing Decks Pty Ltd pay to Mr Davies the sum of $611.60
within 21 days of the date of this Order.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/316