Alford v Walter Elliot Holdings Pty Ltd as trustee for The W E Van park Trust t/as Palm Lake Resort [2014] QCAT 298
CITATION: Alford v Walter Elliot Holdings Pty Ltd as trustee
for The W E Van park Trust t/as Palm Lake
Resort [2014] QCAT 298
PARTIES: Ronald James Alford
(Applicant)
v
Walter Elliot Holdings Pty Ltd as trustee for The
W E Van park Trust t/as Palm Lake Resort
(Respondent)
APPLICATION NUMBER: BDL007-14
MATTER TYPE: Building matters
HEARING DATE: 26 March 2014
HEARD AT: Brisbane
DECISION OF: Member Allen
DELIVERED ON: 30 June 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. Walter Elliot Holdings Pty Ltd have the
work set out in photographs 1 and 2 and
the site instruction report attached to
Mr Reid’s report dated 9 December 2013
performed by suitably licensed
tradespeople within 28 days of the date of
this order.
2. Mr Alford to give access to site 79, Palm
Lake Resort on 3 days notice in writing
for the purpose of having this work
carried out.
CATCHWORDS: BUILDING DISPUTE – ponding of water on
patio slab – expert evidence as to fall of slab
and soil profile.
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Alford represented himself at the hearing
RESPONDENT: Mr Garrie Love represented Walter Elliot
Holdings Pty Ltd at the hearing.
-- 1 of 4 --
2
REASONS FOR DECISION
[1] Mr Alford is the owner of a manufactured home located at site 79, Palm
Lake Resort and Walter Elliot Holdings is the owner of the Resort.
There was building work performed on the site at the time Mr Alford took
up residence on 15 May 2012 including the laying of a slab for a patio and
drainage works. Mr Alford alleges that water ponds on the patio slab and
that Walter Elliot Holdings is required to rectify the work performed and to
stop water run-off from site 80 next door. Mr Alford described the problem
at the hearing as an area of 11/2 m by 1m being covered with half an inch
of water which took 24 hours to dissipate.
[2] Walter Elliot Holdings acknowledges that the work was performed by an
associated entity with a building licence as part of the preparation of
Mr Alford’s site and is prepared to accept responsibility if any order is
made by the Tribunal for work to be performed.
[3] Following a series of complaints by Mr Alford and inspections by
representatives of Walter Elliot Holdings an offer was made on 18 July
2013 for the concreters to do a saw cut through the concrete to assist
drainage. With the issue to be monitored.
[4] Mr Alford was not happy with this proposed solution and made an
application to the Tribunal. He arranged for Mr Lindsay Reid, a structural
and geotechnical engineer to inspect the slab and provide a report in
regard to the water ponding issue. Mr Reid stated in his report dated
9 December 2013 that minor ponding occurs in the rear slab which he
stated had almost certainly developed due to soil moisture related soil
heave beneath the outside edge of the slab. In his opinion the initial
surface gradient would almost certainly have been provided to ensure that
water ran off the slab surface but this gradient was not sufficient to
compensate for the subsequent ground heave beneath the outside edge.
[5] Mr Reid considered that the ground movements which have occurred have
been greater than those which would normally have been expected, due to
poor site drainage and maintenance conditions which retain water, cause
soil soakage and consequently promote soil heave. The poor conditions
referred to were that the ground surfaces at the rear of Mr Alford’s site and
the adjoining building had been covered with a layer of gravel, which traps
free water, causes soil soakage and promotes soil swell. The tops of the
stormwater pits in Mr Alford’s and the adjoining site are too high to allow
water to drain freely which further promotes soil moisture build-ups and
ground movement. The site drainage conditions were in Mr Reid’s opinion
contrary to good practice and may if allowed to continue give rise to
greater than desirable movement in the building, though this was not
possible to predict without undertaking soil testing.
[6] Mr Reid documented in his report remedial works to provide free drainage
from the slab which required the cutting and relaying of a portion of the
patio slab to provide 40 mm of fall across the patio from the fence with the
-- 2 of 4 --
3
adjoining lot. He also stated that the effects of continuing poor site
drainage could give rise to the need for further work in the future.
[7] Mr Reid provided a further report dated 20 March 2014 following additional
work he performed. That is a limited geotechnical investigation which
involved augering one test hole, a level survey of the surface of the
external concrete paving slabs and ground surfaces and a series of
measurements to enable the general layout of the external areas to be
quantified.
[8] The geotechnical testing was said to confirm the assessments previously
documented in the report dated 9 December 2013, the soils are highly
reactive and capable of significant vertical movement due to variation in
soil moisture content, the potential ground surface movement of this site
are considered to have been increased as the result of the poor drainage
conditions, the potential ground movements due to normal seasonal
variations is assessed to be in the order of 50 mm to 60 mm assuming
good site drainage and maintenance is present which is not the case, the
soil moisture profile shows that that the soils are reaching or at saturation
levels and such levels of moisture are consistent with conditions which
would promote the heaving of slabs and buildings.
[9] The concrete slab level and ground surface survey confirmed that even
though the patio has lost surface fall, the surfaces nevertheless still drain,
although this drainage is marginal. Future soil moisture related swelling
may lead to ponding because there is no further tolerance available
through the current falls on the surface of the pavement to facilitate free
drainage. Shallow excavations through the granular fill materials which
have been placed at the rear of the unit revealed that free water is being
retained and that the free drainage which is required to comply with
normally accepted building practices has not been provided in an
adequate manner in these locations.
[10] Walter Elliot Holdings was not able to obtain its own expert report due to
Mr Alford not being prepared to allow entry to his property on the day that
their engineer was available. Mr Love did not object to Mr Reid’s evidence
being admitted and was given the opportunity to cross examine Mr Reid.
In his material Mr Love acknowledged that following inspections by their
builders and the concreter that there was an area of the slab about 900
mm in diameter which is slightly uneven with a maximum variation of less
than 5 mm and this is within tolerances and less than the maximum
variation as set by concreting standards. That the lowering of the tops of
the storm water pits would only allow an additional volume of surface run
off water to escape, whereas saturated ground water cannot drain into the
pits. He stated at the hearing that there is an agricultural drain running
next to the site which provides drainage fro water which enters the soil.
[11] Mr Love was of the view that Walter Elliott Holdings had previously been
prepared to do some work to relieve the issue in regard to the minor
ponding but that was on the basis that the matter would not proceed to
hearing. Now that it had gone to hearing Walter Elliott Holdings should not
-- 3 of 4 --
4
be expected to correct a minor issue that was within tolerances. Mr Love
had provided some standards and guidelines with his material which set
out the surface tolerances for various forms of concrete and noted that the
tolerance in respect of surface variation for a concrete slab such as this
was 12 mm and this slab varied by no more than 5mm.
[12] At the hearing Mr Reid confirmed that the fall on the slab was reasonable
for the first part from 234 to 216 and then in the second part was flat.
That this was due to the soil heave and it was in this section that water
was being marginally retained. He confirmed that there was no cracking
of the slab. Mr Love asked Mr Reid about the tolerances of the slab and
Mr Reid indicated that the slab itself was fine it was the fall of the slab that
was in issue. Quite a reasonably constructed slab and that it was
constructed in a good and workmanlike manner. That the slab currently
drains but marginally hold water. Simple task to fix not quite enough slope
minor ponding in one corner which would cost less than $1,000 in terms of
the work outlined in first report and that work is still required to correct the
issue to ensure free drainage as required under the Building code of
Australia.
[13] The Tribunal notes that both Mr Reid and Mr Love agree that there is
some water being retained on the slab. While Mr Love says that it is as a
result of allowable imperfections in the surface of the slab Mr Reid
considers that the slab has lifted. Mr Reid has produced a floor level
survey which shows that the slab is flat at one end and the Tribunal
accepts that this is adversely affecting the ability of the slab to drain.
The problem is not so much with the slab itself but the effects that the
retention of water by the soil around the slab is having on the slab.
[14] The Tribunal also accepts Mr Reid’s investigation of the soil profile which
raises the probability that if remedial work is not done in regard to site
drainage then the there is likelihood of further worsening of the drainage
issue of the slab. While the issue may be minor at the moment under
current conditions it will only worsen and to ensure that the slab drains
freely as required by the Building Code the work outlined by Mr Reid will
need to be performed.
[15] The Tribunal orders that Walter Elliot Holdings have the work set out in
photographs 1 and 2 and the site instruction report attached to Mr Reid’s
report dated 9 December 2013 performed by suitably licensed
tradespeople within 28 days of the date of this order. Mr Alford to give
access to site 79, Palm Lake Resort on 3 days notice in writing for the
purpose of having this work carried out.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/298