Allan Thompson Building and Development v Mecca Bah (Gold Coast) Pty Ltd [2014] QCAT 300
CITATION: Allan Thompson Building and Development v
Mecca Bah (Gold Coast) Pty Ltd [2014] QCAT
300
PARTIES: Allan Thompson t/as Allan Thompson Building
and Development
(Applicant)
v
Mecca Bah (Gold Coast) Pty Ltd
(Respondent)
APPLICATION NUMBER: MCDO742-13
MATTER TYPE: Other minor civil dispute matters
HEARING DATE: 20 May 2014
HEARD AT: Southport
DECISION OF: Adjudicator Bertelsen
DELIVERED ON: 24 June 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The respondent pay to the applicant the
sum of $6,792.32.
CATCHWORDS: Cost plus contract for installation and repair –
authority to source and arrange appliances and
services – obligation to source on best terms –
obligation to supervise – margin applicable to
cost plus contract
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Allan Thompson, Proprietor
RESPONDENT: Stan Kravchenko, General Manager by authority
REASONS FOR DECISION
Application
[1] By application filed 12 September 2013 the applicant Allan Thompson
seeks the sum of $7,514.67 which he says is the balance of his invoice of
$11,014.67 owing for repair and replacement construction work at the
Mecca Bah Gold Coast together with $1,100 costs incurred in respect of
-- 1 of 7 --
2
an adjudication pursuant to the Building and Construction Industry
Payments Act 2004 (Qld) and $900 in respect of document preparation to
pursue his claim.
Background and Evidence
[2] During a severe storm event which occurred in the period 25-28 January
2013 the Mecca Bah alfresco dining area was damaged. The motorised
blinds/awnings were torn from their mountings causing damage to the
blinds/awnings, motors, brackets and ceiling areas.
[3] At about the end of January 2013 Mr Thompson met with Mr Kravchenko
the manager of Mecca Bah onsite. According to Mr Thompson he
provided a verbal estimate of around $10,000 on a ‘cost plus’ basis ie the
total cost was to be calculated based on cost of materials and labour,
Mr Thompson’s hourly rate (supervision) and an 18 per cent builders
margin which Mr Thompson asserted was below industry standard.
The scope of works according to him was to replace the motors, supply
materials and labour to install the motors and repair peripheral damage.
[4] According to Mr Kravchenko, Mr Thompson was asked to quote for repairs
to the alfresco area, roof cladding and motorised blinds/awnings shortly
after the storm period 25-28 January 2013; that Mr Thompson quoted for
the job at under $10,000; that he Mr Kravchenko accepted such quote on
condition that Mr Thompson be responsible for the whole project; that the
job was to be undertaken immediately.
[5] Mr Thompson said he urgently approached supplier/installer Pauls
Screens and Blinds (‘Pauls’) on 31 January 2013 to reinstall four café style
awnings/blinds at Mecca Bah; that it became apparent the originally
installed Italian brand motors were not available in Australia; that another
supplier of motors, Somfy, was approached by Pauls; that, though
available, motors were problematic in that there were issues with the
supply of adaptors and brackets. He said that Pauls then approached
Uniline a local supplier. Uniline, after site inspection, was able to source
suitable motors, crown adaptors and brackets out of Sydney. An urgent
order was placed for four motors. According to Mr Thompson this process
of sourcing and arranging for Pauls to install four motors took to the
middle of February 2013. During the same period Mr Kravchenko
asserted he was eagerly awaiting commencement of works.
Mr Kravchenko paid a deposit of $3,500 on 13 February 2013.
[6] According to Pauls chronology of events produced to the Tribunal by
Mr Thompson a purchase order was placed with Pauls on 14 February
2013; that on 21 February 2013 Pauls collected the motors from Uniline;
that on 22 February 2013 Pauls installation team attended site; that
between Friday 22 February 2013 and Tuesday 26 February 2013
installation of all four awnings/blinds was effected by Pauls.
[7] According to Mr Kravchenko he waited an excessively long time for the
awnings to be installed; that by 26 February 2013 he was desparate to get
-- 2 of 7 --
3
the job finished (it was costing him business); that Mr Thompson’s
electrician who turned up onsite to programme the ‘blinds’ had no idea
what he was doing and was simply unable to set any programme; that on
27 February 2013 he enquired of Mr Thompson by text regarding
completion of the job; that on 27 February 2013 he was informed by
Mr Thompson that the electrician would be ‘completing the tensioning
today after which the steel frame and blue board will be fitted after which
the painting will be done’. On 28 February 2013 Mr Kravchenko asked if
plastering would take place that day. Mr Kravchenko stated that on
1 March 2013 plasterers turned up onsite with no safety equipment; that
after repeated attempts to contact Mr Thompson by phone that day he
finally sent a text to Mr Thompson stating his patience had run out; that he
did not want Mr Thompson or his people back onsite; that he would get
someone else to finish the job.
[8] Mr Kravchenko said he retained a builder Darren Michels to complete
plastering, rendering, painting and some metal framing at a cost of some
$3,900. Despite opportunity particularly after the first hearing on 6 May
2014 Mr Kravchenko did not produce any invoice for that work.
[9] Mr Thompson argued that any such work and any invoice for such was
irrelevant as his invoice of 5 March 2013 was only ever for works
completed to 1 March 2013 (the day his people were put offsite) pursuant
to his cost plus oral contract.
[10] Mr Thompson’s invoice dated 5 March 2013 charged for seven items as
follows:
1. Screens and motors - $6,321;
2. Vinyl welding - $60;
3. Electrical work Robina Electrical - $456.50;
4. Metal frame repairs - $231;
5. Materials for framing and re-sheeting - $468;
6. Mr Thompson’s supervision - $1,530;
7. Mr Thompson’s builders margin - $1,631.97.
[11] Items 2, 4 and 5 were agreed at hearing not to be in contention.
[12] Mr Kravchenko said he agreed to 80 per cent of item 1; that items 3, 6 and
7 were otherwise in contention.
Item 1 Motors and Blinds
[13] Mr Thompson asserted that after a lot of time and effort particularly
dealing with Pauls he was satisfied that suitable motors had been sourced
and were available for installation by Pauls; that Pauls quote for supply of
four motors was as invoiced by Pauls on 28 February 2013 the only
addition being that this invoice included the labour charge at $1,800; that
he paid Pauls $2,000 in good faith for Pauls to install the four motors and
-- 3 of 7 --
4
ancillary fittings; that Pauls tax invoice was properly and reasonably
$6,321. Mr Thompson said he was required then in terms of his cost plus
contract and in terms of his relationship with Pauls to pay Pauls the
outstanding $4,321 ($6,321 minus $2,000).
[14] Mr Kravchenko stated that whilst Pauls had done their job not to his
complete satisfaction that in due course the job had been completed.
He said that after terminating Mr Thompson there were numerous
attendances with Pauls and that Uniline were called in twice to fix the
installed awnings. He said that all of this had nothing to do with
Mr Thompson. Mr Kravchenko said he was prepared to honour
Mr Thompson’s invoice item 1 to 80 per cent of $6,321.
Whilst Mr Kravchenko suggested Pauls was primarily a domestic installer
Mr Thompson said this installation was within Pauls scope of works and
that Mr Kravchenko was not qualified to pass opinions a long time after
the event.
[15] Mr Kravchenko suggested the cost of motors as quoted by Pauls was
excessive but Mr Thompson said it was a commercially acceptable quote
and that in any event the contract between himself and Mecca Bah was a
cost plus contract. Mr Thompson contended that it was part of his cost
plus contract for him to source the motors at a reasonable cost which he
said he had done.
Conclusion
[16] Pauls as a third party commercially independent entity effected the
installation at a commercially acceptable charge. That accorded with
Mr Thompson’s cost plus oral contract brief. After installation of the
motors and blinds/awnings by Pauls there were some initial operating
problems. Mr Kravchenko having dismissed Mr Thompson on 1 March
2013 dealt directly with Pauls and Uniline. Those initial problems were
attended to and the motors and blinds/awnings then functioned
adequately. There was no evidence produced to the Tribunal supportive
of the contention that Pauls quote was excessive. With the motors and
blinds/awnings installed and functional the Tribunal finds Pauls invoice
payable in full.
Item 3 Electrical work Robina Electrical
[17] Robina Electrical charged Mr Thompson $456.50 inclusive of GST for
electrical work conducted onsite. Its invoice of 5 March 2013 charged for
‘connected motorised awnings, programmed controller and motors’.
Labour consisted of five hours for an electrician and two hours for a trades
assistant.
[18] Mr Kravchenko asserted that he observed four powerpoints to have been
connected; that the electrician who attended was unable to or was
incapable of programming the blinds/awnings; that Nice (the
manufacturer) and Uniline eventually programmed the blinds.
-- 4 of 7 --
5
[19] Mr Thompson argued that with the electrician charging five hours only that
he had not ever charged for programming; that the electrician attended
site on some three occasions; that travelling time, rewiring and connecting
powerpoints would have taken at least five hours in any event; that there
was never any charge in reality for programming.
Conclusion
[20] Though charged for it is was not prosecuted with credibility that the
electrician ever programmed anything. Rather it was contended that the
installation of four power points warranted payment of $456.50. But that is
not what the electrician’s own invoice says. It would appear the electrician
has included a charge for at least attempting programming. There is no
individual monetary itemisation in the invoice just the recitation of
connecting and programming. It is reasonable to conclude that half of this
invoice only ought to be allowed ie $228.25.
Item 6 Supervision
[21] Mr Thompson asserted his supervision of the job in the period end
January 2013 through 1 March 2013 was in fact more than 18 hours; that
supervision was not restricted to onsite supervision but included telephone
calls, correspondence and attendances with Pauls particularly in the first
few weeks of February when sourcing suitable motors was a priority.
He contended there were real difficulties in sourcing motors and relied on
Pauls letter of 20 March 2013 to himself confirming a substantial amount
of time spent by both himself and Pauls on phone calls and enquiries; that
in any event he claimed supervision only to the date he was dismissed by
Mr Kravchenko.
[22] Mr Kravchenko estimated that Mr Thompson had spent no more than two
hours onsite; that it was he Mr Kravchenko who repeatedly had to manage
various contractors onsite; that there was no supervision of contractors
using scaffolding; that Mr Thompson’s inattention to the job at hand meant
that to the time he dismissed Mr Thompson the job had already taken a
month; that there was a complete disregard for OH & S factors.
Conclusion
[23] There was no written record of onsite supervision only Mr Thompson’s
assertion that he spent 18 hours plus onsite. Mr Kravchenko was the
restaurant manager present onsite and would have been better placed to
remember when Mr Thompson visited and supervised the site particularly
so given his eagerness to have the job completed quickly. There was no
evidence to the effect that nor was it asserted that Mr Thompson attended
the site on 22 February 2013 and 26 February 2013 in a supervisory
capacity when the installation of motors and blinds/awnings took place.
[24] Mr Thompson’s assertion of offsite supervision is not supported by any
reference to time. If it was agreed that an hourly rate be charged for
supervision and the Tribunal finds that it was, then it was encumbant on
-- 5 of 7 --
6
Mr Thompson to maintain some reasonable record of dates and times.
It is not enough to assess the degree of supervision by reference to the
size of the job. The Tribunal accepts that some supervision would have
taken place for the job to get as far as it did by 1 March 2013. Based on
all the evidence the Tribunal allows an estimate of 9 hours supervision ie
$765.
Item 7 Margin
[25] Mr Thompson stated that he was a licensed builder of many years
standing and a person familiar with industry margin standards.
He asserted that his margin at 18 per cent was less than industry
standard; that a margin of 20 per cent was usually applicable to a job over
$200,000; but a job less than $100,000 was usually subject to a margin of
between 25 per cent and 27.5 per cent; that in hindsight his margin here
was too low; that his margin included his administration; that it was agreed
that the contract being a cost plus contract included a builders margin.
Mr Kravchenko pointed to a lack of proof of industry standards.
Conclusion
[26] That the contract between the parties was always a cost price contract
was not disputed. Rather Mr Kravchenko sought proof of the percentage
margin that ought to apply. There is no regulation or schedule setting out
what builders margin ought to apply in this particular instance.
The Tribunal accepts Mr Thompson’s evidence that 18 per cent is
reasonable in the circumstances. The Tribunal allows a builders margin at
$1.453.18 being 18 per cent of the adjusted total of items 1 to 6
($8,073.25) of Mr Thompson’s invoice of 5 March 2013.
In Finality
[27] The Tribunal accepts Mr Thompson’s assertion that he provided an oral
estimate of around $10,000 rather than guaranteeing his invoice would be
less than $10,000. Given his years of experience the Tribunal finds it is
unlikely he would have subjected himself to such a constraint.
[28] Items 1 to 7 of the invoice of 5 March 2013 are allowed at $9,526.43. GST
is allowed on items 6 and 7, being the two charges not already subject to
GST in terms of the cost plus contract, at $221.81. $3,500 was paid on
the 19 February 2013 leaving $6,248.24 as properly payable.
Mr Thompson’s costs claim of $1,100 is not allowed. It is not for the
Tribunal to make orders for costs incurred in what is effectively another
jurisdiction quite apart from the fact that there is no authority to award
costs in the context of a minor civil dispute. Document preparation falls
within the ambit of costs and is disallowed. Interest at the QCAT
calculator rate is allowed for the period 30 April 2013 to 20 May 2014 on
$6,248.24 in the sum of $442.68 together with the filing fee of $101.40.
The total allowed therefore is $6,792.32.
-- 6 of 7 --
7
Order
1. The respondent pay to the applicant the sum of $6,792.32.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/300