BAP Developments Pty Ltd as Nominee v South East Civil and Drainage Contractors Pty Ltd [2014] QCAT 229
CITATION: BAP Developments Pty Ltd as Nominee v South
East Civil and Drainage Contractors Pty Ltd
[2014] QCAT 229
PARTIES: BAP Developments Pty Ltd as Nominee
(Applicant)
v
South East Civil and Drainage Contractors Pty
Ltd
(Respondent)
APPLICATION NUMBER: BDL197-13
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Gardiner
DELIVERED ON: 27 May 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. BAP Developments Pty Ltd as Nominee
pay to South East Civil and Drainage
Contractors Pty Ltd costs of and
incidental to this application on a
standard basis calculated on the District
Court Scale within 28 days of agreement
or assessment.
2. South East Civil and Drainage
Contractors Pty Ltd shall deliver an
assessment of its costs to BAP
Developments Pty Ltd the by 13 June
2014.
3. BAP Developments Pty Ltd shall deliver
any response to South East Civil and
Drainage Contractors Pty Ltd’s
assessment by 13 July 2014.
4. If the parties cannot agree an amount for
costs by 13 August 2014, costs shall be
determined by an assessor appointed by
the Principal Registrar.
CATCHWORDS: BUILDING MATTER – COSTS – where no
jurisdiction found for a commercial building
-- 1 of 5 --
2
matter – where applicant did not appear at
hearing – where sufficient information on file for
matter to be determined – where no jurisdiction
found – whether costs should be awarded
Queensland Building and Construction
Commission Act 1991 (Qld), s 77
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 100, s 102
Lyons v Dreamstarter Pty Ltd [2011] QCATA
142; followed
Lyons v Dreamstarter Pty Ltd [2012] QCATA
071; followed
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
[1] This is an application that came before the Tribunal for a hearing on
18 February 2014. At the hearing there was no appearance by or on
behalf of BAP Developments Pty Ltd.
[2] The application was dismissed and directions made for South East Civil
and Drainage Contractors Pty Ltd to file any application for costs.
[3] In accordance with the directions, the parties have now filed submissions
in relation to costs. South East Civil seeks an award of costs on an
indemnity basis and has asked for a fixed amount of $10,000.
[4] These are the reasons on the determination of this cost application.
Submissions
[5] South East Civil, the applicant in this cost application, submits as follows:
The appropriate law to be applied in relation to this costs application
is s 100 of the Queensland Civil and Administrative Tribunal Act 2009
(Qld).
South East Civil seems to submit this in support of the costs
application on the basis that the Tribunal found that there was no
jurisdiction under the Queensland Building and Construction
Commission Act 1991 (Qld) (QBCC Act) to hear the commercial
building dispute application filed by BAP Developments on 12 August
2013.
[6] BAP Developments, the respondent to this costs application, agrees with
South East Civil in its submissions concerning this costs application and
-- 2 of 5 --
3
also states that the law to be applied in this costs application is contained
in s 100 and s 102 of the QCAT Act.
[7] BAP Developments opposes the costs application but ultimately says that
if costs are to be awarded against the company, it should not be on an
indemnity basis and should be on the basis of costs to be assessed on the
standard District Court scale.
[8] Both parties inherently argue that because the Tribunal found that there
was no jurisdiction under the QBCC Act to hear this matter that costs
should be argued under the QCAT Act.
Discussion
[9] The question to be answered by the Tribunal in the substantive matter was
whether s 76 of the QBCC Act classified the work done by South East Civil
for BAP Developments as Tribunal work. The conclusion reached by the
Tribunal was that the work was a road as defined under the Land Act 1994
(Qld) and therefore outside the jurisdiction of the Tribunal under the QBCC
Act.
[10] Both parties have jumped to the conclusion that therefore the costs must
be argued under the QCAT Act.
[11] I do not agree with this analysis of this costs argument. The question
before the Tribunal was jurisdiction under the QBCC Act. The decision
was that there was not jurisdiction but I do not accept that this excludes
the Tribunal from considering costs falling out from this application under
s 77(2)(h) of the QBCC Act.
[12] The effect of this section, which modifies the general position under the
QCAT Act, is to give the Tribunal a broad general power to award costs in
cases caught by these enabling provisions.1 This enabling Act allows that
while the power must be exercised judicially it is ‘in markedly different
terms from s 100 of the QCAT Act’2 which starts with party bearing its own
costs.
[13] As his Honour the President of QCAT determined in the appeal decision of
Lyons v Dreamstarter Pty Ltd3 about s 77,
The discretion to award costs starts with the proposition that it is just and
reasonable that a party who causes another to incur costs should reimburse
the other party for them. Otherwise the factors affecting the discretion will
vary in each.
[14] BAP Developments brought an application in a commercial dispute
against South East Civil for the work done on a road in a land
development undertaken by BAP Developments which involved the
creation of roads within a subdivision.
1 Lyons v Dreamstarter Pty Ltd [2011] QCATA 142 at [33].
2 Lyons v Dreamstarter Pty Ltd [2012] QCATA 071 at [10].
3 Ibid at [11].
-- 3 of 5 --
4
[15] BAP Developments did not appear at the hearing but this Tribunal found
sufficient information on the file to proceed with the hearing in any event.
[16] An examination of the QBCC Act and the very Act under which roads are
defined points to an exclusion of roads. An examination of the extensive
case law defining a road should have made it apparent to BAP
Developments that the likely outcome of any hearing before the Tribunal
was that the work complained of would be excluded as Tribunal work
under s 77 of the QBCC Act.
[17] Despite this fairly straight forward examination of the statutory
requirements of Tribunal work and the longstanding case law defining a
road, the matter went to a hearing.
[18] BAP Developments did not appear at that hearing.
[19] BAP Developments submit that South East Civil did not succeed on the
merits but rather succeeded on a technicality.
[20] I do not accept this argument for the reasons given above.
An examination of the law in this area would have shown BAP
Developments that, in all likelihood, the work complained of was excluded
from the QBCC Act.
[21] BAP Developments were wholly unsuccessful in this matter. Not only did
it not appear at the hearing but on the legal argument before the Tribunal,
the substantive matter was also lost by it as no jurisdiction was found.
[22] I am satisfied that in the circumstances it is appropriate that BAP
Developments pay the costs of South East Civil in this action.
[23] South East Civil asked for these costs on an indemnity basis. The reason
that they give for this is that the interests of justice would favour such an
order because of the nature and complexity of the dispute; the relative
strengths of the matter; and the financial circumstances of the parties.
[24] I do not accept that the matter to be determined was particularly complex
although I do accept in the final analysis South East Civil did have a strong
case. I have no evidence concerning the financial circumstances of the
parties apart from the submission by South East Civil that they are a small
company and that BAP Developments is a property developer.
[25] Further I have no way of knowing why an amount of $10,000 has been
fixed by the applicant, there being no evidence provided to me of a
breakdown of costs incurred by South East Civil.
[26] In the circumstances I find it is appropriate for a costs order to be awarded
the scale is generally the District Court Scale and it is appropriate that
costs be assessed on the basis of that standard scale, not on an indemnity
basis. I will make orders in those terms.
-- 4 of 5 --
5
Costs under the QCAT Act
[27] If I am wrong about the application of s 77 of the QBCC Act and as
submitted by both parties the costs should be considered under s 100 and
s 102 of the QCAT Act I would make the following findings.
[28] Section 100 of the QCAT Act requires that each party usually bear their
own costs, other than as provided under this Act or an enabling Act.
[29] Section 102 of the QCAT Act allows a Tribunal to make an order requiring
a party to pay all or a stated part of costs of another to the proceedings if
the Tribunal considers the interests of justice require the making of this
order.
[30] Section 102(3) sets out the matters the Tribunal may have regard to in
making this award. I have (under s 77 discussed above) considered the
nature and complexity of dispute; the relative strengths of the matter; and
the financial circumstances of the parties. BAP Developments submits
that the question of jurisdiction is a basic matter and that indemnity costs
should not be awarded.
[31] South East Civil was given leave to be legally represented in this matter
on 9 December 2013.
[32] I am satisfied under s 102 of the QCAT Act, having taken into account the
matters contained s 102(3) that it is in the interests of justice to make the
order as proposed above and under this legislation, I would make the
same order as I have concluded under s 77 of the QBCC Act.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/229