Chinula v Advanced Asbestos Removal Qld Pty Ltd [2014] QCAT 227
CITATION: Chinula v Advanced Asbestos Removal Qld Pty
Ltd [2014] QCAT 227
PARTIES: Yamiko William Lewis Chinula
(Applicant)
v
Advanced Asbestos Removal Qld Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL 255-13
MATTER TYPE: Building matters
HEARING DATE: 20 March 2014
HEARD AT: Mackay
DECISION OF: Member Johnston
DELIVERED ON: 19 May 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Tribunal finds that Mr Chinula’s
payment of Four Thousand Three
Hundred and Fifty Five Dollars ($4355.00)
to Advanced Asbestos Removal meets
his contractual obligations for the
remediation works undertaken by the
Respondent.
2. The Tribunal dismisses the Respondent’s
Response and Counter-Application.
3. The Tribunal orders that each party bear
their own costs.
CATCHWORDS: BUILDING MATTERS - Dispute over the terms
of the contract
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Yamiko Chinula
RESPONDENT: Ms Karen Ngatai
-- 1 of 6 --
2
REASONS FOR DECISION
What is this application about?
[1] On 2 June 2013 Mr Darren Terangi the Managing Director of the
Respondent sent Mr Chinula a proposal to deal with the asbestos in the
floor of Mr Chinula’s residence. The Asbestos Remediation Proposal
provided at clause 10 the following quote:
Service Area Metre (m2) Rate per
(m2)
Total
Remove &
dispose
decontaminate
Friable vinyl
floor removal
and grind
timber finish
24.25 m² $250 $6062.50
Monitor &
Independent
Clearance
To all areas $830.00
Less
overpayment
from previous
job
Deposit
amount
overpaid
$-537
Sub Total $6355.50
GST 10% Included
Total $6355.50
[2] The Proposal provided for Mr Chinula to pay $6355.50 for the remediation
work. This included an estimate of the cost of the Independent Air
Monitoring Testing (“Testing”) of $830. Clause 12 of the Proposal provided
that the Applicant would to be responsible for any final costs of the Testing
over the estimate.
[3] On 6 June 2013 Mr Chinula rejected the quote that have been provided
and asked for a lower remediation cost in the range of $130 per square
metre.
[4] On 13 June 2013 Ms Karen Ngatai responded on behalf of Mr Terangi to
Mr Chinula’s e-mail stating that “Darren is in meetings today; and has
asked to send through the best revised price we can do is $4355..”.
[5] Mr Chinula sent an e-mail to Ms Karen Ngatai on the afternoon of 13 June
2013 thanking her for: “reviewing the cost. Please take this e-mail as
acceptance of your quote to complete these works on the 20th and 21st of
June for the below price of $4355.00”.
-- 2 of 6 --
3
[6] Mr Chinula’s told the Tribunal that his understanding was that the
Proposal that had been sent to him had been amended from $6355.50 to
$4355.00. His email of 13 June 2013 was accepting that offer.
[7] Ms Karen Ngatai’s told the Tribunal that her understanding was that the
Mr Chinula would pay $4355.00 for the remediation work and the Proposal
provided for the Applicant to reimburse the Respondent for paying the cost
of the Testing. This would mean that Mr Chinula would need to pay the
sum of $4355 plus the sum of $830 which was the estimate in the
Proposal for the cost of the Testing.
[8] The remediation work was undertaken and the Respondent has on 2 July
2013 billed Mr Chinula $5703.83. This amount was made up of the
remediation charge of $4355.30 plus $830 for the cost of the Testing plus
GST. The Tribunal notes that GST was included in the Total Sum payable
under the original Proposal.
[9] The issue for the Tribunal is whether or not Mr Chinula is liable to pay the
cost of the Testing and the cost of the GST.
The evidence of the parties
[10] Ms Karen Ngatai’s evidence was that it was only the price per square
metre that was being reduced. The Respondent’s intention was that Mr
Chinula was to pay for the remediation costs fixed at $4355 and the
estimate allowed for the Independent Air Monitoring Test namely $830.
[11] Her evidence was that the only matter which was discussed with the
Applicant was the price per metre cost for removal of the asbestos. The
Tribunal accepts that evidence.
[12] What is clear from her evidence is that she never said to Mr Chinula the
offer of $4355 was plus GST and plus the Testing allowance of $830.00.
[13] Mr Chinula’s evidence was that the Respondent had made him an offer
which he accepted. He accepted the Proposal at the lesser amount
offered and that this incorporated providing the Testing. He had paid the
Respondent and therefore had met his obligations to the Respondent and
could not be pursued for the $830.00 or GST on top.
[14] The Respondent’s failure in this case is not to be clear in relation to its
communication with the Applicant. If the Respondent had provided an
updated Proposal then the Respondent would have turned its mind to the
cost of the Independent Air Monitoring Test. The Respondent could have
made an amended offer which included this cost or alternatively could
have spelt out to the Applicant that this cost was on top of the offer that
had been made to undertake the remediation. The Respondent did neither
of these two steps and when the Applicant made his offer to make part
payments towards the cost this was on the basis that he owed the
Respondent the sum of $4355.
-- 3 of 6 --
4
[15] The Applicant is entitled to rely on the offer that has been made to him. If
the documentation does not reflect the intention of the Respondent that is
not in any way the fault of the Applicant. This is a warning to parties to
ensure proper contract documentation is prepared to reflect the
agreement that has been reached. The understanding of the agreement
must be reflected in its terms. The Tribunal cannot undo the terms of the
agreement when the writing doesn't reflect the intention of both of the
parties.
[16] The Applicant is entitled to assume that a counter offer in a global form
represents the total amount payable unless the Respondent has qualified
the counter offer. There is nothing in the e-mail from Ms Ngatai to the
Applicant to suggest that the sum of $4355 was not the total amount
payable to the Respondent. There was no query from the Respondent to
the Applicant’s e-mail where he accepts the offer of the Respondent of
$4355.00. The Respondent had the opportunity at that time to clarify the
offer that had been made namely to state that in addition to the
remediation costs of $4355 that the Applicant would also need to pay the
costs of the Testing which are the estimated $830 and would pay GST on
the final account . This did not happen and the work was undertaken on
the basis of the Applicant and Respondent having different views of the
total cost of remediation.
[17] The law around contracts is clear. There must be an offer and acceptance
of that offer. The Respondent made Mr Chinula an offer which he rejected.
The Respondent made another offer their “best offer” which Mr Chinula
accepted. If this was an offer qualified by other requirements or
stipulations this was never spelt out to the Applicant. The Respondent had
the opportunity to provide an amended Proposal but chose not to do so.
[18] This is clearly an unfortunate situation where the “best revised price” could
have more than one meaning. Did it mean as it says that the Respondent
would do the work for $4355? Or did it mean that the Proposal was being
amended just in the top line of the quote? The Respondent has the
responsibility to be clear about the terms of the offer it made to the
Applicant.
[19] The Tribunal makes one further point in relation to the Proposal. The
Proposal only provided for an estimate of the cost of Testing. The
Proposal provided for the amount payable to be adjusted in the event that
the final cost of the Testing was higher than the amount which had been
allowed. The Respondent’s evidence which is accepted by Tribunal was
that the actual cost of the Independent Air Monitoring Testing was
$1545.17.The Proposal treats the Testing like a provisional amount and
provides in clause 12 of the Proposal for the final amount to be adjusted to
reflect any variation.
[20] The cost of the Testing was much greater due to the fact that the
Respondent asked for the Testing to be done as soon as possible and that
turned out to be on a weekend. The Respondent was trying to help the
Applicant get back into his house as soon as possible.
-- 4 of 6 --
5
[21] On the basis of the Tribunal’s understanding of the agreement between
the parties the Respondent would be entitled to have claimed the
difference between the actual cost of $1545.17 and the estimate in the
Proposal of $830. This would have allowed the Respondent to claim from
the Applicant the sum of $715.70 as a variation provided for under the
Proposal.
[22] Ms Ngatai told the Tribunal that it was the practice of the Respondent only
to claim the estimate of the cost contained in proposals. The Tribunal gave
the Respondent an opportunity to reconsider its position given the
Tribunal's interpretation of the agreement between the parties. However
the Respondent chose to waive of those rights. The Respondent
confirmed that the amount which the Respondent was the pursuing was
the sum of $830.
The Tribunal's findings
[23] Mr Chinula had an asbestos problem with the flooring of his residence.
[24] The Respondent put a proposal to him to treat his floors for the sum of
$6355.
[25] Mr Chinula did not accept the Respondent’s quotation to undertake the
work.
[26] The Respondent made another offer to Mr Chinula by e-mail to undertake
the work for $4355.
[27] There were no conditions or stipulations attached to the offer to undertake
the work for $4355.
[28] Mr Chinula sent an e-mail to the Respondent accepting the Respondent’s
offer to undertake work for $4355.
[29] The work was undertaken by the Respondent and the Applicant has been
billed for the remedial work of $4355 plus the sum of $830 which was the
estimate for the cost of Testing plus GST.
[30] Mr Chinula has paid the sum of $4355 for the remedial work but has
refused to pay the sum of $830 plus GST.
Tribunal’s decision
[31] The Tribunal finds that the agreement between Mr Chinula and the
Respondent comprises: the Proposal; the e-mail from Ms Ngatai to Mr
Chinula dated 13 June 2013 with the price variation; and the e-mail to Ms
Ngatai of 13 June 2013 with Mr Chinula’s acceptance of the offer.
[32] The Tribunal finds that the agreement between Mr Chinula provided for
him to pay the sum of $4355 for the cost of the remediation work. The
agreement also provided for Mr Chinula to pay the difference between the
estimate in the proposal for Testing and that the actual cost. This means
-- 5 of 6 --
6
that the Respondent would have been entitled to have recovered the sum
of $715.17 from the Applicant. The Respondent has waived its rights to
pursue this amount from the Applicant.
[33] The Tribunal finds that Mr Chinula’s payment of $4355 to the Respondent
meet his obligations in relation to the agreement he had with the
Respondent to undertake the remediation work.
[34] The Tribunal dismisses the Respondent’s counter – application.
Legal Costs
[35] Legal costs in the Tribunal are not awarded as a matter of course.
Each party must bear their own costs1, unless the interests of justice
require the Tribunal to order a party to pay the costs of another party.2
[36] There is therefore a strong indicator against awarding costs:
Under the QCAT Act the question that will usually arise in each case in
which costs are sought is whether the circumstances relevant to the
discretion inherent in the phrase ‘the interests of justice’ point so
compellingly to a costs award that they overcome the strong contra-
indication against costs orders in s.100.3
[37] There is nothing here to justify departing from the strong indicator against
awarding costs. The parties clearly had interpreted the agreement in
different ways. The Respondent has waived rights that it has against the
Applicant.
[38] Each party is to bear their own legal costs.
1 Queensland Civil and Administrative Tribunal Act 2009 s 100.
2 Ibid s 102.
3 Ralacom Pty Ltd v Body Corporate for Paradise Island Apartments (No. 2) [2010]
QCAT 412 at [29].
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/227