Bullfrog Constructions Pty Ltd v Crowther [2014] QCAT 189
CITATION: Bullfrog Constructions Pty Ltd v Crowther
[2014] QCAT 189
PARTIES: Bullfrog Constructions Pty Ltd
(Applicant)
v
Ronald Crowther
Gwendoline Crowther
(Respondents)
APPLICATION NUMBER: BDL008-13
MATTER TYPE: Building matters
HEARING DATE: 18, 19 September 2014
HEARD AT: Brisbane
DECISION OF: Member McLean Williams
DELIVERED ON: 15 May 2014
DELIVERED AT: Brisbane
ORDERS MADE: The Tribunal Orders:
(a) The respondents are to pay the applicant
the sum of $96,214.02, together with
interest in the amount of $26,294.10
within 28 days of the date of these orders;
(b) The applicant is to arrange rectification of
the defective building works specified in
paragraphs [65] and [66] of the Tribunal’s
reasons (‘the rectification works’), within
four (4) months of the date of these
orders, or such longer period, as may be
agreed;
(c) The rectification works are to be at the
expense of the applicant, and are to be
performed by sub-contractors arranged
by the applicant;
(d) Mr Nathan Parker is not permitted to
attend the site at 259-265 Ney Road at
Capalaba during the rectification works;
(e) All necessary communication between
the applicant and the respondent
regarding the rectification works is to be
in writing, and is to be exchanged by e-
mail between the applicant and the
-- 1 of 25 --
2
respondent’s solicitor, or other nominee;
(f) Any dispute regarding the standard of
any rectification works is to be
determined by a building inspector
appointed by the Queensland Building
and Construction Commission, whose
view on the issue in contention is to be
determinative. The costs of any such
inspection are to be born equally by the
applicant and the respondent.
(g) The applicant is to provide the
respondents with any outstanding
construction certificates or other contract
documentation within 28 days of the date
of these orders.
(h) The parties are given leave to make
written submissions within 14 days on
the question of the appropriate orders
regarding the costs of these proceedings,
and that matter will be determined by the
Tribunal on the papers.
CATCHWORDS: Residential building dispute – Where applicant
builder seeks payment of outstanding sums
pursuant to written contract, plus undocumented
variations – Where respondent owners allege
the written contract to be a sham, and the
agreement to be an unlawful antecedent oral
“cost plus” agreement – Effect of Parol evidence
rule – evidence necessary to overcome
presumptive effect of the written agreement –
Inferences to be drawn from consequential
conduct several months after date of alleged
agreement – Whether family relationship
between building owners and wife of builder
sufficient to constitute an “exceptional
circumstance” within s 84(4)(a)(i) of the
Domestic Building Contracts Act 2000 – Factors
giving rise to appropriate circumstances for the
making of rectification orders pursuant to
s 77(2)(g) of the Queensland Building and
Construction Commission Act 1991.
Domestic Building Contracts Act 2000 (Qld)
s 84
Queensland Building and Construction
Commission Act 1991 (Qld) s 77(2)
Queensland Building Services Authority v
McGrath Corporation Pty Ltd (unreported, QBT,
-- 2 of 25 --
3
13 April 1994)
KD Properties Pty Ltd v Leda Design &
Construction (Qld) Pty Ltd [2003] QCCTB 26;
Rainbow v Nelson [2009] QCCTB 264;
Codelfa Constructions Pty Ltd v State Rail
Authority of New South Wales (1982) 149 CLR
337;
Allaro Homes Pty Ltd v O’Reilly & Anor [2012]
QCA 286;
Weier v Pugh [2008] CCT BD486-06
APPEARANCES and REPRESENTATION (If any):
APPLICANT: Mr Simon Taylor of counsel, instructed by
Crouch & Lyndon Lawyers
RESPONDENT: Mr Timothy Mitchell, Solicitor, Hemming & Hart
Lawyers.
REASONS FOR DECISION
[1] The applicant in this matter is a residential construction company, Bullfrog
Constructions Pty Ltd (ABN 801 581 725 51), (“the applicant”). Mr Nathan
Parker is the sole director of Bullfrog Constructions. The applicant
conducts operations from an office in a converted double car garage at
Mr Parker’s home, at Ormiston.
[2] The respondents are Mr Ronald Victor Crowther, and Mrs Gwendoline
Dale Crowther (“the owners”). It is relevant to record that the owners are
the aunt and uncle of Mr Parker’s wife, and came to use the applicant as
their builder as a result of that family connection.
[3] The dispute relates to the construction of a new home by the applicant at
420 Mt Cotton Road, Capalaba. Although that was the address specified
on the building contract signed by the parties on 24th November 2011, the
property has since undergone a subdivision, and it is now known as 259-
265 Ney Road, Capalaba. In these reasons the house construction will be
referred to via its current Ney Road address.
[4] This matter was heard over 2 days on 18 and 19 September 2013.
Because the time allowed for the hearing of the matter proved to be
inadequate, the parties were directed to provide extensive written
submissions. The last of these (the applicant’s submissions given in reply
to those of the respondent) were not filed until 4 November 2013.
The Applicant’s Case:
[5] By an application filed before QCAT on 14 January 2013, the applicant
seeks the sum of $104,699.20, which the applicant says remains
outstanding, together with interest and costs.
-- 3 of 25 --
4
[6] The applicant says that Bullfrog Constructions and the owners entered into
a Queensland Master Builders contract (August 2010 edition) on
24th November 2011 for the construction of a low-set residential dwelling,
for the amount of $297,300.00 (inclusive of GST). Pursuant to that
contract, the applicant says that the owners were required to pay for the
construction in accordance with the following stage payments:
CONTRACT STAGE CONTRACT AMOUNT
Deposit $ 14,865
Slab $ 29,730
Frame $ 59,460
Enclosed stage $104,055
Fixing stage $ 59,460
Practical completion $ 29,730
Total: $297,300
[7] Expressed in the simplest terms, the applicant’s case is that Bullfrog
Constructions brought the house all the way to practical completion, and
then delivered the finished house to the owners; such that any sums still
outstanding under the contract are due and owing.
[8] In relation to practical completion and the process of effectuating
handover, the applicant says that Mr Parker, together with one of his staff
and the owners, undertook a practical completion inspection (as required
by Clause 17 of the general conditions of the contract), on 27th June 2012.
The parties were unable to agree in relation to all of the defects. Despite
this, 15 items were still recorded in a defects document, and the parties
signed that document, after that inspection as comprising ‘the’ list of
defects.
[9] The applicant contends that it has since rectified 10 of the 15 listed defect
items and says that the respondents took complete possession of their
property (by moving into it), on 4th July 2012. In the premises, the
applicant says that the contracted works are deemed to have attained
practical completion, in accordance with Clause 17.9 of the contract.
[10] Although the contract made provision for several prime cost and
provisional sum items, the applicant says that the owners did not use up
all of their allowances in that regard; such that the applicant acknowledges
that it is required to give the owners a credit (a negative variation), in the
sum of $9,349.12. By agreement between the parties, the applicant also
did not undertake some of the building works that were meant to be
performed by the builder; such that a further sum, $11,858.04, also needs
to be given back to the owners, in the form of another negative variation.
In total therefore, the applicant says that it gave credits of $21,557.16 back
to the owners, against the original contract price, as negative variations.
[11] Because Mr Parker was broadly aware that an amount for credits was
going to have to be paid to the owners at the end of the project, he paid
the sum of $15,000.00 to Mr and Mrs Crowther, even before a final
-- 4 of 25 --
5
accounting of expenditures on the project had been undertaken. Because
of this advance payment, the applicant says that the net credit required to
be given back to the owners was only for $6,207.16. Deducting this sum
from the contract price, so the applicant says, results in the amended
contract price becoming $291,092.84.
[12] In addition to these negative variations, the applicant also says that there
were a number of positive variations, in the manner of extra matters
beyond the original scope of works that were also agreed between the
parties during the course of the construction. These are specified by the
builder to be as follows:
No VARIATION DESCRIPTION COST
1 Site cut $929.28
2 Bored piers to under slab $5,762.40
3 Additional underground cabling $1,881.00
4 Provision of a full set of working drawings $1,512.00
5 Upgrade of site classification, from ‘M’ to ‘P’ $3,600.00
6 Supply and install slab for owners’ shed $6,000.00
7 Alteration to plans regarding rumpus room $600.00
8 Upgrade of entry door furniture $90.00
9 Upgrade of windows (tint) $1,365.60
10 Electrical upgrades $6,978.67
11 Upgrade of cornice (square set) $300.00
12 Upgrade of cabinetry $9,236.04
13 Upgrade of shower screens $703.64
14 Upgrade of bathroom $1,227.59
15 Rectification of owners’ rendering $144.00
19 Upgrade of roof sisalation $1,036.14
TOTAL: $41,365.76
[13] Although the applicant says that there were these positive variations, it
admits that not all of these were reduced into writing and signed by the
owners, in the manner required by Part 7 of the Domestic Buildings
Contract Act 2000 (Qld) (‘the DBCA’). In point of fact, only the first three
variations were documented in writing and then agreed by the owners, by
means of their signature on a variation document.
[14] The Applicant says that written variations were generated for all of the
variations, and those for which signatures from the owners were not
obtained had been placed by the builder inside a plastic sleeve that had
been affixed to the inside wall of the on-site toilet (for use as an on-site
document exchange), for collection by the owners. However, Mr and
Mrs Crowther strongly deny that any written variation documents were
ever left for them in a plastic sleeve inside the site toilet. Although
Mr Parker is equally adamant that written variation documents were left for
the owners in the manner described, Mr Parker does however concede
that he was totally remiss in not then following up with Mr and
Mrs Crowther in order to ensure that these variation documents were
returned to him, signed by the owners. Mr Parker’s explanation for this
oversight was that he approached this construction job in a more informal
-- 5 of 25 --
6
manner than would be the case had this been an ordinary, “arms length”
business transaction. In this instance things were different because he
was dealing with members of his wife’s immediate family, and he trusted
that they would be good for the money, because they were family.
[15] Because of the fact of these unwritten variations, the applicant applies
pursuant to s 84 of the Domestic Buildings Contract Act 2000 (Qld) for the
approval of this Tribunal for it to be paid for the variations. In the final
wash up, the applicant says that it is owed monies by the owners in
accordance with the following:
Amended contract price $291,092.84
Plus variations: $41,365.76
Final contract sum: $332,459.20
Less payments already made by the owners to
date:
($228,110.00)
Outstanding amount: $104,699.20
[16] The applicant also claims an entitlement to interest at the rate of 15% per
annum, pursuant to Item 19 of the contract. The applicant says that the
owners were required to make payment of the full contract price by no
later than 13th July 2012, such that the applicant claims interest at 15%
from 14th July 2012 until the date of its filing of this application
(14th January 2013),1 and accruing thereafter on a daily basis.
The Owner’s Case:
[17] As indicated at the commencement of these reasons, Ronald and
Gwendoline Crowther are the uncle and aunt of Mr Parker’s wife.
The owners give a radically different account of the agreement between
themselves and their niece’s husband.
[18] Although Mr and Mrs Crowther readily admit to their having signed the
building contract, as well as the builder’s written quote at the office of
Bullfrog Constructions at Ormiston on 24th November 2011, it is their case
that these documents do not represent the true arrangement between
themselves and their builder. Indeed, the owners say that the written
contract is a complete sham, designed to do no more than afford a veneer
of respectability to their real agreement: which they say was an unlawful
(and now unenforceable) “cost plus” agreement. The owners say that the
arrangement was one by which Bullfrog Constructions had agreed to build
their home for the cost of construction, plus a fixed fee to the builder of
$20,000.
[19] Mr and Mrs Crowther say that they were initially introduced to Bullfrog
Constructions by Mr Crowther’s brother, who had assured them that his
son-in-law could build their intended house at a price that was
considerably below the sum that Mr and Mrs Crowther had already been
1 185 days.
-- 6 of 25 --
7
quoted, by another building company. As a consequence of that
assurance the owners arranged to meet with Mr Parker, at Ormiston, on
20 October 2011. During that initial meeting Mr and Mrs Parker produced
some sketch diagrams showing a house that they wished to construct with
a gross floor area of approximately 247 square metres.2
[20] The owners claim that when Mr Parker was shown this sketch they were
assured that such a house could be had for a build cost of somewhere
between $180,000 and $210,000, and the price would be based on a ‘cost
plus’ agreement, where they would merely pay Bullfrog Constructions for
the actual costs of the construction (whatever these ultimately worked out
to be), “plus a $20,000 fee”; and that Bullfrog Constructions oftentimes
priced jobs in this manner. The owners say that an oral agreement was
struck between themselves and Mr Parker that day, and on that basis; with
Mr Parker also clearly understanding that their total budget for the
construction could not exceed $220,000, as that was all that Mr and
Mrs Crowther could afford.
[21] Subsequently, the owners admit that on 20th October 2011, they entered
into a preliminary (written) agreement with Bullfrog Constructions to
enable the applicant to undertake a soil test. They also admit that they
were sent by Mr Parker to see the applicant’s preferred draftsman, so that
detailed plans could be drawn up for the intended construction.
[22] During the process of preparing detailed working drawings, Mr and
Mrs Crowther gave the draftsman instructions for - and obviously
approved - a final design for a significantly larger house than the sketch
first shown to Mr Parker – one of approximately 320 square metres. Given
that the house had increased in size, the applicant says that he sent to
Mr and Mrs Parker a written quote for $297,300.00 (based on the enlarged
drawings), together with a set of detailed building specifications.
[23] On 24th November 2011 Mr and Mrs Crowther went back to Ormiston to
see Mr Parker. The owners admit that on this occasion they also signed a
written contract in the amount of $297,300, inclusive of GST, as well as a
copy of the quotation document referred to in paragraph [22], above.
[24] Although it is the case that the owners admit to having signed both the
contract and the quotation, they say that they were assured by Mr Parker
at the time of their signing the documentation that these were only being
signed so as to give their antecedent oral agreement (that made on
20th November 2011) an appearance of complying with the requirements
of the Domestic Buildings Contract Act 2000 (Qld), and so that insurance
could be obtained under the statutory home warranty scheme. They also
claim that Mr Parker told them on 24th November 2011 that their oral
agreement would still govern the relationship between themselves and
Bullfrog Constructions.
2 Yet only 207 square meters, according to the builder. At the end of it, nothing really
turns on this conflict in the evidence.
-- 7 of 25 --
8
[25] The owners also admit that a defects inspection was undertaken on
27th June 2012, yet they say that the inspection on that day was only ever
a partial inspection, as it was cut short when Mr Parker had to leave, quite
suddenly. Although some defects had been noted by the parties before
Mr Parker’s sudden departure, and were also signed off by them, Mr and
Mrs Crowther say that there was no agreement regarding the extent of the
defects and those that were signed were only signed on an express
understanding that Mr Parker would be returning, to complete the
inspection on a later occasion. Clearly therefore it is the owners’ case that
the list of defects is far more extensive than simply those matters recorded
and signed by the parties, on 27th June 2012.
[26] There is also a dispute in relation to credits that the owners say they
should receive from the builder for prime cost and provisional sum items.
The owners say that the total deduction (in the form of a credit to them) for
prime cost and provisional sum items should be more in the order of
$10,915.00, and that the value of the works omitted (for which they should
also receive a credit) should be $17,974.00, rather than the $11,858.04
allowed by the applicant.
[27] In addition, the owners contend that there were still other omitted works,
for which they should receive further credit. These additional items
include:
ITEM DESCRIPTION VALUE OF
FURTHER
WORKS NOT
CONDUCTED
Clothesline Standard wall-mounted
included
$150.00
Shelving Custom wood included as
per drawings
$2,500.00
Insect screens Standard insect screens
included to aluminium
windows
$3,500.00
Blinds (window
dressings)
Vertical blinds from standard
builder’s range to all
aluminium windows and
doors, venetians to
bathrooms/wc/ensuite/wc
$5,500.00
Ceiling fans 8 included (one in each
bedroom, two to
dining/family, two to patio.
$2,550.00
Telecom: pre-
wire
2 points $80.00
Exhaust fans Standard 3-light tactics to
bathroom and ensuite
$280.00
Downpipe PVC 90ml $50.00
-- 8 of 25 --
9
ITEM DESCRIPTION VALUE OF
FURTHER
WORKS NOT
CONDUCTED
Rubbish
removal
3 x rubbish removal $1,450.00
Site clean 1 x site clean $675.00
House clean Final house clean done by
respondent
$650.00
Range hood
ducting
Supply and fit $400.00
TOTAL: $17,785.00
[28] Although the owners also agree that in September 2012 the applicant paid
to them $15,000.00, they deny that this was ever paid by the builder as an
advance on the credits for negative variations owed to them at practical
completion, as has been contended by the builder. Instead, Mr and
Mrs Crowther say that the refund of $15,000 is merely consistent with their
oral agreement wherein they were only required to pay Bullfrog
Constructions on a ‘cost plus’ $20,000 basis, as they had, by that stage,
already paid too much to the builder, and Mr Parker was acknowledging
this fact, by making a refund. Indeed, they say that at the time of making
the $15,000 payment Mr Parker also informed them that they would be
receiving another refund, of $4,902.45, to be paid to them by
14th September 2012, at the latest.
[29] In relation to the applicant’s claimed variations, the owners say that all of
these are a sham, as well. Although they agree that they received and
signed the first three written variation documents, they deny that the
builder produced any more variation documents; or that these were then
left for their collection, in a plastic sleeve, inside the on-site toilet.
[30] In relation to written variations 1 – 3 (which were signed as having been
agreed by the owners), Mr Crowther says that he queried Mr Parker at the
time as to why these were now being produced for his signature. He says
that he was told by Mr Parker at that time that these were being created in
order to provide at least some evidence of compliance with the
requirements of the Domestic Buildings Contract Act 2000 (Qld), just in
case Bullfrog Constructions were ever audited. The owners say that no
other written variations were produced (and indeed none were necessary
given the nature of their agreement), and the notion that variation
documents were produced and then left for their collection in the plastic
sleeve inside the site toilet is just an elaborate fiction.
[31] Rather than their owing $41,366.36 to the builder as contended by the
applicant, the respondents say that they do not owe the builder anything,
as they have already paid the builder for everything done by it, including
any variations.
-- 9 of 25 --
10
[32] Pursuant to their oral agreement, the owners say that they were required
to make stage payments to the applicant (which they did) in accordance
with the following:
PAYMENT
DATE
RATIONALE FOR PAYMENT AMOUNT
20.10.11 Soil test $400.00
29.11.11 Deposit $14,865.00
19.2.12 Slab stage $29,730.00
2.3.12 Site cut $929.28
2.3.12 Bored piers to under slab $5,762.40
2.3.12 Underground cabling $1,881.00
4.3.12 Frame stage $59,460.00
26.4.12 Enclosed stage $104,055.00
17.5.12 Fixing stage $20,000.00
Sub-total $237,082.68
Less, refund in September 2012 -$15,000.00
TOTAL: $222,082.68
[33] Although the fixing stage in the written contract appeared to require that
they pay to the builder the sum of $59,460.00, the owners say that they
were told by Mr Parker to only pay Bullfrog Constructions the sum of
$20,000; and in fact they never received a written fixing stage invoice from
the builder, at least not until after the commencement of these QCAT
proceedings. The Crowthers say that they only paid $20,000 because
Mr Parker had told them at the fixing stage that $20,000 would be more
than enough to cover any outstanding sum still owing under their oral
agreement, given that the agreement was that they would only be paying
‘cost plus’ a fixed fee of $20,000 for the entire job. The owners say that
the whole arrangement and the amount ultimately paid by them
($222,082.68) is consistent with the fact that they had advised Mr Parker
that they only had a maximum of $220,000 to spend on the construction
project, although it is also their case that the Applicant still now owes to
them further refunds and compensation for defective building works.
[34] The owners say that on or about 11th October 2012, and completely out of
the blue, Mr Parker reneged on their cost plus agreement, and demanded
an additional payment, of $33,162. When they asked Mr Parker to
substantiate why it was that he was now claiming that they owed that sum,
they received what they regarded as being an unsatisfactory answer.
Mr Parker is alleged to have informed them he had made a mistake on his
MYOB accounts, which had only just been detected. At that time
Mr Parker is said to have refused to provide them with invoices and
receipts substantiating the claim, and instead merely showed to them a
copy of his computer spreadsheet, which purported to set out the builder’s
costs for the project. When they refused to pay this sum, the owners say
that Mr Parker only then indicated that he would take steps to enforce the
-- 10 of 25 --
11
‘sham’ written agreement, which they say he now has, by commencing
these QCAT proceedings.
[35] As well as contending that no further sums are owed to the applicant, the
owners contend that the builder is liable for the costs of rectifying various
defective works. For these purposes the owners have produced a list of
defects that is far more extensive than those listed in the defects
document signed by them and the builder on 27th June 2012.
[36] Mr and Mrs Crowther also say that the builder has changed various
aspects of the construction without their prior approval, and this has
resulted in their home having been devalued by an estimated $100,000.
Because of delays in the construction, they also say that they have been
caused additional expenses (additional rent, and so on), of about $9,000.
In relation to the alleged devaluation, the owners have however produced
no evidence.
The Applicant’s response to the Owners’ claims:
[37] The builder agrees that there had been an initial meeting in mid-October
2011, and at that time the owners had indicated that they wished to build a
home with a gross floor area of what Mr Parker says was about 207
square metres, based on a sketch diagram brought to the meeting by
Mr and Mrs Crowther. Mr Parker says that as part of that, there had been
discussion about the ‘ballpark’ construction costs for a home of about that
size. However, beyond this, the builder says that no agreement was
reached with the owners at that time, other than for the Crowther’s to
indicate that they did wish to proceed and have their house built by
Bullfrog Constructions. Mr Parker says that this is the reason that the
owners agreed to sign the preliminary agreement on that day (20th October
2011) that enabled him to get a soil test done on the house site.
[38] Once the owners had been sent by Mr Parker to see his draftsman,
Mr Parker says that the owners enlarged their proposed house, to one
now of approximately 320 square metres, and it was this fully detailed
(and obviously much larger) plan that formed the basis of the builder’s
subsequent written quote to the owners.
[39] On 24th November 2011 Mr Parker says that Mr & Mrs Crowther accepted
his written quote to construct their proposed home for $297,300.00 in
accordance with the detailed plans and the specifications that comprised
part of his written quote. The applicant completely denies that the quote
and the written agreement were put in place only in order to afford a
“veneer of respectability” to an oral agreement, and says that the contract
signed by him and the owners on 24th November 2011 embodies their
entire agreement. In this regard, the applicant points to the evidence
given before the Tribunal by Mr John Rutter, an employee of the applicant,
who happened to be present in the same room when the contract was
signed by the parties, on 24th November 2011. Mr Rutter’s evidence
suggests that the written document was the only agreement within the
contemplation of the parties at the time when it was signed.
-- 11 of 25 --
12
[40] The applicant also says that the list of defects containing the 15 items is
the only list of defects in existence, and that although it is the case that the
owners disputed many items, this list was nonetheless still signed by
them. Moreover, at no time on 27th June 2012 did Mr Parker ever suggest
to the owners that he would be returning on the next day (or on any other
day) so as to complete the defects inspection; and nor did the owners ever
say that they were only signing the list of defects he had presented to
them on the basis that Mr Parker would be returning to do another defects
inspection, later.
[41] Although the owners contend that some $17,785 of items were not
supplied by the applicant, the builder says that upon perusal of the new list
of items presented by the owners that only $3,998 of these items
(principally the insect screens and the window dressings) might be
legitimately claimed by the owners, as additional items that were not
supplied by the applicant, yet that should have been.
[42] In relation to the owner’s key contention that the applicant only required a
payment of $20,000 at the fixing stage, in lieu of the contract sum of
$59,460, the applicant says that this is simply untrue. The applicant says
that he received $20,000 from the owners against the $59,460 specified in
the invoice at the time that payment was required for the fixing stage, yet
he did not pursue the owners for the full outstanding sum at that time,
because the owners were relatives by marriage, and Mr Parker felt
somewhat awkward about raising the matter. He also chose not to raise
the issue because he did not have any cash flow difficulties at that point,
and instead merely assumed – naively as it has turned out - that the
owners would not forget to honour their obligation to pay the remainder of
the fixing stage invoice. Mr Parker also says that he arranged for the
applicant to refund $15,000 to Mr and Mrs Crowther earlier than the
practical completion stage as an act of good faith (even notwithstanding
that a greater sum than that was already owed by the owners to the
applicant), because he was conscious that there were certain prime costs
and provisional sum items that the owners had not used and for which
they would eventually be entitled to a credit, because he wished to repay
this sum as an expedient means by which to keep a “neat ledger”.
[43] The applicant also denies demanding an additional $33,162 on
11th October 2012. Mr Parker says that the parties were, by now, in open
dispute about outstanding payments, and this was causing him a great
deal of difficulty and stress at home, because of the family connection
between his own wife, and the owners. Mr Parker says that at that time he
offered to resolve the dispute on the basis of a payment to the applicant of
only $33,162; yet this is not the same as concluding that the applicant was
only therefore owed that sum.
Issues for Determination
[44] By the end of the hearing, the parties were in general agreement
regarding the matters that need to be determined by QCAT:
-- 12 of 25 --
13
(i) The Nature of the Contract: Is the agreement embodied in the
signed contract dated 24th November 2011, or is this an (unlawful)
oral ‘cost plus’ agreement?
(ii) Related to (i), above, is the written contract dated 24th November
2011 a sham agreement, or did the applicant otherwise misrepresent
the nature of the contractual arrangement in order to induce the
owners to sign that document?
(iii) In the absence of variations agreed in writing, is the builder entitled to
payment of an amount for variations, pursuant to s 84(4) of the
DBCA?
(iv) What are the items of defective building work, and what is the most
appropriate order for their rectification?
(v) Quantum meruit: in the event of my finding the agreement to be an
unenforceable contract, what then is the reasonable value of the
building works?
[45] Ultimately, and for reasons that will be further elaborated, it becomes
unnecessary for me to make any quantum meruit assessment (item (v),
above).
(i) The Nature of the Contract:
[46] Although the owners admit that they signed the written contract on
24th November 2011, it is their case that, in reality, the agreement between
the parties is an antecedent verbal agreement made on 20th October 2012.
The owners also state that when they signed the written contract,
Mr Parker had assured them that it would not be enforced, and that
Bullfrog Constructions would carry out all of the building works in
accordance with the oral agreement. Accordingly, it is the respondent’s
case that the parties never intended to be bound by the written document,
as its purpose was never to record their agreement. The respondents say
that the written contract is a “sham”, as that concept has come to be
understood in cases such as Queensland Building Services Authority v
McGrath Corporation Pty Ltd,3 and Rainbow v Nelson.4
[47] One obvious hurdle for the owners is the very fact of the signed
agreement. The prospect for successfully vaulting that hurdle becomes all
the more challenging when the fact of it is coupled with the eyewitness
evidence of Mr Rutter, who was present when the contract was signed, by
both the owners and Mr Parker. Mr Rutter’s evidence was that the owners
gave every appearance of understanding the document that they were
signing, and that no reference was made by any of the signatories at that
time to any antecedent oral arrangement as the “real” agreement.
That evidence is obviously quite at odds with that given by Mr and
Mrs Crowther. Mr Rutter’s credibility was not impugned during cross-
examination. In the final analysis nothing said by Mr Rutter lends any
3 Unreported QBT, 13 April 1994; see also KD Properties Pty Ltd v Leda Design &
Construction (Qld) Pty Ltd, [2003] QCCTB 26 (28 August 2003).
4 Rainbow v Nelson [2009] QCCTB 264 (16 September 2009).
-- 13 of 25 --
14
benefit to the case theory that the owners now seek to advance before the
Tribunal.
[48] Ordinarily, given the operation of the Parol evidence rule, the very fact that
the parties have recorded an agreement in writing excludes evidence of
antecedent negotiations for the purposes of adding to, varying, or
otherwise contradicting the language of the written agreement.5 By their
final written submissions the owner’s solicitor concedes as much,6 yet
goes on to submit that other evidence heard by the Tribunal – that being
evidence in relation to events between the contracting parties from 17 May
20127 onwards - is enough to enable the Tribunal to discern the real truth
of their arrangement. The submission is developed that if the correct
interpretation is placed by the Tribunal on this evidence then that will
suffice to so comprehensively impugn the credibility of Mr Parker that the
evidence of Mr and Mrs Crowther will be seen to be the more preferable.
[49] The evidence relied upon by the owners in support of their contention is:
Primarily, of course, the testimonial and statement evidence of
Mr and Mrs Crowther, as regards the oral agreement made on
20 November 2011, and their evidence regarding the further
assurances allegedly given to them by Mr Parker when they signed
the contract on 24 November 2011;
A submission8 that the applicant had sufficient motive to create the
artifice of the sham contract, in order to appear not to be in breach of
s 55 of the DBCA, that prohibits cost plus contracts; and
Various events since 17 May 2012 that are said to reveal the true
nature of the sham. Specifically, these things are claimed to be:
- When paid only $20,000 against the fixing stage invoice of
$59,460 (17 May 2012), the applicant did not bother to pursue
the owners for the balance owing under that invoice, despite
already claiming to be owed $11,873.59 for variations 4 – 11 by
that point in time;
- The delivery of a gift basket by the builder to the owners on
24 June 2012 to mark the occasion of Mr and Mrs Crowther
moving into their new home, despite the builder being owed, by
that date, a much more substantial sum;
- The builder being owed (on its own case) $100,803.54 by the
date of delivery of the practical completion invoice (4 July 2012),
yet there still being no evidence of any demand for payment
emanating from the builder;
5 See: Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982)
149 CLR 337 at 347.
6 Respondent’s submissions, filed on 28 October 2013, at [21].
7 The date of the fixing stage invoice.
8 That is, a bare submission, rather than evidence, per se. As the Applicant correctly
submits in its reply submissions, these matters were never put to Mr Parker during his
cross-examination.
-- 14 of 25 --
15
- The builder then refunding the sum of $15,000 on 5 September
2012 for negative variations (rather than deducting this from the
balance claimed to be owing), and also promising that a further
refund, of $4,902.45 would be made by no later than
14 September 2012;
- Mr Parker telling Mr Crowther in a telephone call on 11 October
2012 that a payment of only $33,000 would see the builder
“break even”.
[50] At the end of it, the Respondent’s case theory is analogous to a house of
cards. I am entirely unpersuaded by the evidence that the respondent
submits might enable a finding that the written contract was a sham, and
the agreement between the parties was, in reality, an oral one reached on
20th October 2011. Not by any stretch does the owners’ assembly9 of
evidence enable that. Critical to a finding in favour of the Respondents
must be a finding that Mr and Mrs Crowther are creditable witnesses and
that Mr Parker’s evidence was untruthful. However I am not persuaded to
draw that conclusion. Indeed, quite to the contrary, I do not accept the
testimony or other evidence of Mr Crowther insofar as it is conflicts with
that of Mr Parker. Having observed Mr Crowther’s demeanour during his
testimony and the responses given by him under cross-examination,
I conclude his evidence to be unreliable, and I do not accept his version of
events. Nor do I accept the accuracy of any of the allegedly
contemporaneous notes that have been made by Mr Crowther in an effort
to self-corroborate.
[51] I am left similarly unpersuaded by any of the evidence given by
Mrs Crowther. Mrs Crowther was a generally poor historian, who had no
useful recollection of any of the matters now under examination.
Her primary statement of evidence is hardly illuminating, given that she
does no more than adopt that of her husband. Her adoption of evidence
that has already been assessed by as unreliable does not serve to make it
any more compelling.
[52] In contrast, Mr Nathan Parker gave better evidence and was, on the whole
I think, a far more creditable witness as regards the competing factual
claims. Mr Parker’s explanation for making the $15,000.00 refund is an
acceptable one. His explanation was that he desired to keep a neat
ledger, and in that regard he elected to quickly refund sums that he knew
would need to be eventually credited to the home owners, notwithstanding
that greater sums than those refunded were, by that stage, already owed
to the builder. Given the family relationship, I do not regard this approach
to bookkeeping as unusual. In respect of the lack of demand by Bullfrog
Constructions for timely payment of amounts outstanding, Mr Parker’s
evidence was equally plausible. He informed the Tribunal that, initially, he
did not have any cash flow pressure, and thus felt little imperative to raise
the outstanding payments with Mr and Mrs Crowther, and then later, when
their non-payment had become more of an issue for the builder, the
prospect of raising the issue was still complicated by the fact of that same
9 See paragraph [49].
-- 15 of 25 --
16
close family connection. I accept the submission in reply by Counsel for
the applicant: that the lack of demand for outstanding monies does not
afford evidence of the sham contract alleged by the respondents,
particularly in circumstances where other, more benign interpretations, are
open on that same body of evidence. Here, the conclusion I am asked to
draw by the respondents in relation to these pieces of evidence requires
an enormous leap in logic - from benign to sinister – yet is one that cannot
reasonably be made on this evidence. It follows that I am satisfied that the
only agreement between the parties is that which is reflected in the written
contract, that dated 24th November 2011.
(ii) Is the written contract dated 24th November 2001 a sham agreement?
Did the Builder misrepresent the nature of the contract, in order to
induce the owners to sign it?
[53] In consequence to (i) above, the contract dated 24th November 2011 is not
a sham. Mr Rutter’s evidence, which I have indicated already that
I accept, was that Mr and Mrs Crowther gave every indication of
understanding the nature of that agreement, when they signed it. In my
view there is just no acceptable evidence that the builder ever
misrepresented the nature of the contract to the owners.
(iii) Is the builder entitled to payment for variations pursuant to s 84(4) of
the DBCA?
[54] Given that there are variations that do not, on the builder’s own admission,
comply with the requirements of Part 7 of the DBCA, the applicant’s right
to recover an amount for any of those variations is a matter that is subject
to s 84 of the DBCA, which provides:
84 Right of building contractor to recover amount for variation
(1) This section applies if-
(a) the building contractor under a regulated contract gives effect to
a variation of the contract; and
(b) the variation consists of –
(i) an addition to the subject work; or
(ii) an omission from the subject work that results in the
building contractor incurring additional costs.
(2) If the variation was originally sought by the building owner, the
building contractor may recover an amount for the variation –
(a) only if the building contractor has complied with sections 79, 80,
82 and 83; or
(b) only with the tribunal’s approval given on an application
made, as provided under the QCAT Act, to the tribunal by
the building contractor.
(3) If the variation is not a variation that was originally sought by the
building owner, the building contractor may recover an amount for the
variation –
-- 16 of 25 --
17
(a) only if –
(i) the building contractor has complied with sections 79, 80,
82 and 83; and
(ii) the ground of unforeseen circumstances applies; or
(b) only with the tribunal’s approval given on an application made,
as provided under the QVAT Act, to the tribunal by the building
contractor.
(4) The tribunal may approve the recovery of an amount by a
building contractor for a variation only if the tribunal is satisfied
that-
(a) either of the following applies –
(i) there are exceptional circumstances to warrant the
conferring of an entitlement on the building contractor
for recovery of an amount for the variation;
(ii) the building contractor would suffer unreasonable hardship
by the operation of subsection (2)(a) or 3(a); and
(b) it would not be unfair to the building owner for the building
contractor to recover an amount.
(5) For subsection (3)(a)(ii), the ground of unforeseen circumstances
applies if the variation became necessary because of circumstances
that could not have been reasonably foreseen by the building
contractor when the contract was entered into.
(6) If the building contractor is entitled to recover an amount for the
variation of a fixed price contract, the amount is –
(a) the increase in the contract price stated, or worked out in the
way stated, in the appropriate variation document for the
variation; or
(b) if paragraph (a) does not apply – the most of carrying out the
variation plus a reasonable profit.
(7) If the building contractor is entitled to recover an amount for the
variation of a cost plus contract, the amount is the amount worked out
in the way stated in the contract.
[emphasis has been included here]
[55] The applicant seeks to rely on the fact of an “exceptional circumstances”
under s 84(4)(a)(i) of the DBCA, contending that one arises because of the
family relationship between the applicant and the respondents that
resulted in a level of trust, communication and cooperation between the
parties that led to a departure from conformity with the strict requirements
of Part 7 of the Act. The applicant also says that it would “not be unfair to
the building owners” (per s 84(4)(b)), for the builder to recover an amount
as:
(i) the owners requested all the variations and knew that these were
being undertaken;
(ii) some of the variations provide for the owner to receive a credit on the
contract price;
-- 17 of 25 --
18
(iii) the builder has expended money and/or has incurred a cost in
completing the variations as requested;
(iv) the owners knew (even on their own case), they were liable to pay
the cost of the variations; and
(v) in the premises of each of the above, the only reasonable
expectation for the homeowners could be that the builder will be paid
a reasonable amount for the variations.
[56] The respondents submit that a family relationship between the builder and
the owners is insufficient to justify departure from the requirements of
Part 7 of the Act, and cite Allaro Homes Pty Ltd v O’Reilly & Anor10 as
authority for that proposition. Yet, it would not appear to me that the
question whether a family relationship might enliven s 84(4)(a)(i) of the
DBCA was even considered by the Court of Appeal in that case.
[57] In contrast, in Weier v Pugh11, the predecessor of this Tribunal, the
Commercial and Consumer Tribunal held that a personal relationship
between the builder and the home owner was a factor that could give rise
to an exceptional circumstance within the meaning of s 84 of the Act.
In that case it was said, in part:
[64] “Another feature of this case is the personal friendship of the
applicant and his wife with Mr Neville’s parents. This personal element had
a clear bearing on the relationship between the applicant and the
respondents. At all times the parties did not comply with the strict terms of
the contract as there was this close family connection. The applicant
maintained that he could have terminated the contract in May 2005
following the late payment of the progress claimed [sic], at a time when he
was concerned about the ability of the respondents to pay for the works, but
did not terminate the contract because of the personal relationship between
himself and Mr Neville’s parents. Furthermore, the failure to comply with
the requirements in Clause 20.1 [of the contract] was also influenced by this
personal relationship….
…/
[66] Taking all these matters into account, I am satisfied that these
circumstances are exceptional … “.
[58] The applicant submits that in light of Weier v Pugh the fact that the
Crowther’s’ are the aunt and uncle of Mr Parker’s wife – is sufficient to
establish an exceptional circumstance within the meaning in s 84(4).
Each case falls to be determined on its own unique circumstances. Yet, in
light of what has happened here I do concur with that submission.
Equally, I am satisfied that it would not now be unfair to the building owner
for the building contractor to recover an amount for each of the claimed
variations, particularly in circumstances where these variations have been
requested by the owners, or they have otherwise received the benefit of
them.
10 [2012] QCA 286.
11 [2008] CCT BD 486-06.
-- 18 of 25 --
19
[59] The question next pertains as to what amount the applicant builder should
be allowed to recover for the variations12
[60] Before proceeding I pause to note that I accept Mr Parker’s evidence that
written variation documents were left for the owners’ collection in the
plastic sleeve affixed inside the site toilet. Having now also examined the
invoices that underpin each of the positive variations I am satisfied that the
builder should be entitled to payment of an amount for each unsigned
variation.
[61] The contract dated 24th November 2011 notes builder’s margin is payable
on variations at the rate of 20%. Although that is a rate that is amply
consistent with industry practice and is in the written agreement, I here
allow only 10% for builder’s margin on variations, given that the right to
recover any amount is now only in consequence of relief pursuant to
s 84(4) of the DBCA. Accordingly, I allow the applicant the sum of
$37,229.18 for the positive variations, in lieu of the claimed amount
($41,365.76).
[62] Pursuant to the contract the amount to be paid by the owners is assessed
by me pursuant to s 77(2) of the Queensland Building and Construction
Commission Act 1991 (Qld) as follows:
Amended contract price: $291,092.84
Additional negative variations conceded by the applicant: ($3,998.00)
s 84(4) allowance for variations: $37,229.18
Sub-total: $324,324.02
Less payments already made under the contract (228,110)
Sum outstanding $96,214.02
(iv) The Defective Building Works
[63] There are a number of items of defective building works, yet also
considerable disagreement in relation to the extent of any defects.
The relationship between the builder and the owners ended acrimoniously,
and that acrimony prevented even minor defects (of the type usually
arising at the end of any construction project), being addressed by the
builder, within the six-month post construction defect rectification period.
[64] Now, the most objective framework within which to assess the defects is
that provided by the QBSA report, prepared by Mr Geoffrey Barrett.
However the applicant submits that Mr Barrett’s report must be
approached with caution, because Mr Barrett had little regard for the terms
of the contract (particularly any variations); did not inspect some important
elements of the house (for example the dip in the roof); and in some
12 Variations 1, 2 & 3 conform to the requirements of the Act. Here the inquiry turns to
variations 4 – 25, some of which are negative variations in favour of the owners.
-- 19 of 25 --
20
instances did not refer to the relevant Australian Building Standards,
before pronouncing that an element was defective. I accept that
submission, yet still regard Mr Barrett’s report as affording the best
evidence available to the Tribunal on the issue of defects.
[65] Having heard evidence from those witnesses called in the proceedings in
relation to the defects, and in particular light of exhibit 5, only the following
items from those listed in Mr Barrett’s report dated 2 September 2013 are
now found by me to constitute defects requiring amelioration by an order
of this Tribunal, pursuant to s 77(2):
2 The window has been positioned against the RHS of room, not
centred, as per Council Approved Plan
3 Privacy latch does not disengage by handle from inside room
4 Wall between architrave and corner has not been painted
5 The striker plate required adjusting to stop door rattling
6 The strike plate required adjusting to stop door from rattling
7 Poor finish to paint near shower where waterproofing was not sanded
8 The exhaust fan vents straight to roof cavity. Not meeting Australian
Building Codes
9 Gap between architrave and vanity requires sealing
10 panel - right side of vanity left unpainted and un-sanded
12 Rumpus Room – Manufacturing fault in cornice
13 Rumpus Room – Scratches in paint on sliding door, does not slide in
cavity properly
17 Family Room – Large sliding door RHS has been installed out of
level and as a result the bottom rail bows 7-10mm making the door
hard to slide in certain positions
19 Family Room – There is poor finish to paintwork around the 4 top
windows and above sliding doors
20 Family Room – There is poor finish to paintwork around the 4 top
windows and above sliding doors
22 Family Room – Painting and sanding of skirting between the sliding
doors has not been completed
23 Family Room – Cracks in wall between the room and kitchen require
expansion joints to be fitted
24 Kitchen – Sanding and painting around range hood has not been
completed
25 Kitchen – There is a crack in cornice where cabinetry meets wall
above refrigerator
26 Kitchen – Ceiling requires sanding finish coat over nails are
pronounced
-- 20 of 25 --
21
27 Bedroom 3 – There is a manufacturing fault in cornice
28 Bedroom 3 – There are cracks in architraves at corners of both
windows
29 Bedroom 2 – There are cracks in architraves at corners of both
windows
30 Southern Hallway – Dent in wall approximately 200mm from light
switch
31 Southern Hallway – Crack in architrave top left side of sliding door
33 Broom closet – Poor finish on door (needs re-painting)
34 Broom closet – Door edge requires planning back has rough finish
35 Study – Crack in architrave and door jamb
37 Bedroom 1 – Poor finish on gloss paint RHS of door
39 Bedroom 1 – There is a crack in skirting north side of room
41 Ensuite – Exhaust fan vents straight to roof cavity. Not meeting
Australian Building Codes.
43 Ensuite – Towel rail is loose
47 Garage – Deadbolt has been installed upside down
52 South Elevation – Roof over entry is easily moved and can be heard
thumping in windy conditions
53 North Elevation – Wall northern side of fixed panel in sliding door is
out of square
54 North Elevation – Joins in alfresco ceiling have been poorly finished.
Gyprock joins visible as they have not been sanded properly.
55 North elevation – Flashing N/W corner is loose and requires
resealing
61 Exterior west – Soffit is not level
65 Toilet roll holder is loose.
[66] In addition to those matters drawn from Mr Barrett’s report, the owner’s
have prepared an additional list of defects (matters not addressed by
Mr Barrett), now appearing as ‘Schedule B’ to the owner’s final
submissions, dated 28th October 2013. In relation to that supplementary
list, it is my determination that the following items also constitute defective
building works:
2 Outside Front – Gap in wall
3 Outside Entry Soffit out of level in entry doorway
8 Entry – Feature wall bowed/poor finish gyprock seam visible
16 Rumpus- 2 holes behind air-conditioner (still not fixed)
-- 21 of 25 --
22
17 Rumpus – Crack in skirting board near window/join visible
21 Kitchen – Crack in cornice where cabinetry meets pantry
24 Bed 1 – Back of feature wall gyprock seam visible (not painted
properly). Allowance to repaint inside walls, architraves and skirtings,
as there is too many areas to patch up. Will not be able to match
paint.
25 Ensuite – Poor paint finish near shower (fibreglass not sanded)
27 Laundry door – Laundry door is binding on the sill
28 Garage – Fault in gyprock cornice
31 Garage – Door seals missing (not refitted)
[67] How the rectifications are to be undertaken, and the likely cost of these
works is another contentious issue. On the one hand the Applicant
submits that the most appropriate order is for the Tribunal to order that the
builder rectify these defects via its sub-contractors. The applicant notes
that because it was precluded from the site when the relationship with the
owners became acrimonious it was not afforded its contractual right to
rectify minor works within the six-month period provided under the
contract. Equally, the builder says that damages are not an appropriate
remedy: because the quantum of the owners’ loss has not crystallised,
because the defects have not yet been rectified. The builder says that in
these circumstances it becomes more practical and cost effective to order
that the builder rectify the defective works, particularly given that the sub-
contractors who performed most of these works are contractually obligated
to the builder to rectify, in all events. The applicant also makes the point
that rectification performed by these same sub-contractors is likely to be
the most expedient means for fixing the outstanding problems.
[68] Meanwhile, the owners submit that the most appropriate order for
rectification is to award a sum of money as damages to the owners (or to
offset that amount against any sum owing by the owners to the
applicants). The respondents submit that it is not appropriate to make an
order under s 77(2)(g) of the Queensland Building and Construction
Commission Act 1991 (Qld) because of:
(a) The level of animosity between the parties;
(b) The fact that the respondents do not wish to have any further
involvement with the applicants;
(c) The respondents objecting to the making of any order under
s 77(2)(g); and
(d) The risk that such an order is unlikely to achieve a final resolution of
this dispute.
[69] Determining whether to award damages or to order rectification is
confounded by the enormous disparity in the competing evidence
-- 22 of 25 --
23
regarding the likely cost of rectification. In yachting parlance, there is
“blue water” between the estimates provided by the owners, and those
submitted by the applicant.
[70] In the final analysis, I do not accept the estimates for the cost of
rectification provided by Mr Morris of Goodwood Building and Carpentry,13
prepared on behalf the owners. These appear to be implausibly high.
Much of the inaccuracy in those estimates appears to have arisen
because Mr Morris has quoted on the basis of applying a call out fee to
each rectification task – thus taking no account that the majority of these
are very minor and several remediation tasks could easily be performed
during one site visit by a competent tradesman. Equally, Mr Morris
conceded during his cross-examination that some items could be rectified
in far less time than he has estimated. The rectification estimates
obtained by the owners from Alliance Builders14 also seem implausibly
high, such that I reject them, as well.15
[71] The Applicant relies on evidence from its own sub-contractors,
Messrs Ahern, Levers and Rasmussen, to formulate the applicant’s far
lower estimated costs for rectification and submits that the most
appropriate order as regards any defects found by the Tribunal is one
pursuant to s 77(2)(g) of the Queensland Building and Construction
Commission Act 1991 (Qld), requiring the applicant to return to site and
rectify the defects.
[72] The owners submit that the evidence from Messrs Ahern, Levers and
Rasmussen should be rejected because of their business relationship with
the applicant, and submit that, in the event that the Tribunal is dissatisfied
with the quality of the evidence on the costs of rectification presently
available to the Tribunal (and I am dissatisfied) then the matter should be
set down for another hearing, in order for the Tribunal to determine the
costs of rectification. In my view, far too much shot and powder has been
expended, already. For the sake of finality and the avoidance of further
legal costs, I will not be ordering another hearing.
[73] Ultimately, it is my determination that the most appropriate order is one
pursuant to s 77(2)(g) of the Queensland Building and Construction
Commission Act 1991 (Qld). I do not accept the submission regarding the
applicant’s sub-contractors lacking impartiality. Even if these gentleman
have worked for Bullfrog Constructions before (or will do so again in the
future), this affords no useful basis for any complaint about their estimates
of the costs of rectification, particularly when the owners’ primary interest
is best served by having these defects rectified, at no cost to them.
If these gentlemen can achieve rectification at that price, then all the
better.
13 Exhibit RC-20 to the supplementary statement of Mr Crowther dated 13 September
2013.
14 Exhibit RC-21 to Mr Crowther’s supplementary statement.
15 The owners’ final submissions concede difficulties with Mr Morris’ approach to
estimation, at [159], yet my assessment is that even a 50% reduction, as proposed by
the Respondent results in an estimated cost for rectification that remains too high.
-- 23 of 25 --
24
[74] The applicant will be required to arrange for rectification of the defects
specified in paragraphs [65] and [66] of these reasons in a proper and
tradesman-like manner, at its own expense. Given prior acrimony
between Mr Crowther and Mr Parker, it is a term of the Tribunal’s order
that Mr Parker not be permitted to attend the Ney Road property
personally and all rectification works are to be performed by sub-
contractors, arranged by the applicant. Any necessary liaison between the
applicant and the owners is to be communicated by e-mail between the
applicant and the owner’s solicitor, or other nominee. Rectification works
are to be completed within 4 months of the date of these reasons, or any
longer period, as may come to be agreed by the parties. Any dispute that
arises regarding the standard of workmanship in any of the rectification
works required by these orders is to be determined by an inspector
appointed by the Queensland Building and Construction Commission,
whose assessment is to be determinative of the issue. If such an
inspection becomes necessary, then the costs of it are to be borne equally
by the parties.
[75] The Applicant seeks interest on the outstanding sums ordered by the
Tribunal, assessed at 15%. The Respondents are ordered to pay interest
at that rate on the judgement sum of $96,214.02 from 14 July 2012 until
9 May 2014 (665 days).
[76] In conclusion, I order:
(a) The respondents are to pay the applicant the sum of $96,214.02,
together with interest in the amount of $26,294.10 within 28 days of
the date of these orders;
(b) The applicant is to arrange rectification of the defective building
works specified in paragraphs [65] and [66] of these reasons, within
4 months of the date of these orders (“rectification works”);
(c) The rectification works are to be at the expense of the applicant, and
are to be performed by sub-contractors arranged by the applicant;
(d) Mr Nathan Parker is not permitted to attend 259-265 Ney Road at
Capalaba during the rectification of the defective works;
(e) All necessary communication between the applicant and the
respondent regarding the rectification of the defective works is to be
in writing, exchanged by e-mail between the applicant and the
respondent’s solicitor, or other nominee;
(f) Any dispute regarding the standard of any rectification works is to be
determined by a building inspector appointed by the Queensland
Building and Construction Commission, whose view on the issue in
contention is to be determinative. The costs of any such inspection
are to be born equally by the applicant and the respondent.
(g) The applicant is to provide to the respondents any outstanding
construction certificates or other contract documentation within
28 days of the date of these orders.
-- 24 of 25 --
25
(h) The parties are given leave to make written submissions within
14 days on the question of the appropriate orders regarding the costs
of these proceedings, and that matter will be determined by the
Tribunal on the papers.
-- 25 of 25 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/189