Bigby v Queensland Building and Construction Commission [2014] QCAT 169
CITATION: Bigby v Queensland Building and Construction
Commission [2014] QCAT 169
PARTIES: Graham Bigby
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: GAR076-14
MATTER TYPE: General administrative review matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Gardiner
DELIVERED ON: 1 May 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application to extend a time limit is
dismissed.
CATCHWORDS: PROCEDURE – Extension of time to lodge a
review – where applicant sought extension of
time to file a review application – whether
extension should be granted
Queensland Civil and Administrative Tribunal
Act 2009 (Qld) s 61
Cardillo v Queensland Building Services
Authority [2011] QCAT 574 followed
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
[1] On 26 February 2014 Mr Graham Bigby filed an application to review a
decision of the Queensland Building Services Authority (as it then was) to
refuse an insurance claim made by Mr and Mrs Bigby under the statutory
insurance scheme.
-- 1 of 8 --
2
[2] In the rejection letter to Mr and Mrs Bigby, the Commission says that the
work was performed by the builder Daniel Kondra at their property at the
Gap. This work was performed in 2003 and completed, on the
Commission’s reckoning, on 6 August 2004.
[3] In 2008 a damaging storm swept through the Gap and the Bigbys’ house
suffered critical damage. A complaint form was lodged with the then
Authority on 7 August 2013.
[4] The Commission says that it could not have issued a direction to rectify to
Mr Kondra as more than six years and three months has passed.
The Commission says that Mr and Mrs Bigby are unable to claim under
the insurance policy for the work as the time for rectification expired.
[5] The solicitors for Mr Bigby have filed an application to extend time to
within which to file a review of the denial.
[6] The original letter to Mr Bigby was dated 28 August 2013 and it is
common ground that the letter was sent to the wrong address for
Mr Bigby.
[7] However Mr Bigby’s original application also had an email address on it
which was the solicitors for the Bigbys.
[8] It is conceded by the solicitors for Mr Bigby that the denial letter was also
sent to the email account of Mr Heath, the solicitor having conduct of this
matter on 18 September 2013.
[9] Mr Heath says he was travelling interstate at the time and due to a clerical
error within his office, the denial letter was not downloaded and placed on
file for Mr Heath’s attention.
[10] Mr Heath says he was not aware that the Commission had made a
decision in respect of Mr Bigby’s claim and in fact wrote to the
Commission on 15 January 2014 asking for information. After the
Commission’s response to the 15 January letter, Mr Heath reviewed his
email inbox and became aware that he received the email.
[11] Mr Heath says that Mr Bigby should have the advantage of having the
28 days run for the filing of a review application from when he became
aware of the email on 31 January 2014.
[12] The Commission says while they agree that they sent the original letter to
the wrong address, they sent the email to the email address given in the
application.
Issue
[13] The matter for determination by the Tribunal is whether the Tribunal
should grant an extension of time in the circumstances of this particular
matter.
-- 2 of 8 --
3
[14] The application is pursuant to s 61 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld).
[15] The factors that are to be considered in respect of an application to extend
time have been summarised in the leading case of Cardillo v Queensland
Building Services Authority.1 They are:
1. Has a satisfactory explanation been given to account for the delay;
2. The strength of the case the applicant will bring if allowed to proceed;
3. Will other parties be prejudiced;
4. Has the delay been short or long; and
5. Is it in the interests of justice to grant the extension.
Has a satisfactory explanation been given?
[16] The solicitors for Mr Bigby submit that the sending of the letter of denial to
the wrong postal address caused some delay through the conduct of the
Commission.
[17] Notwithstanding Mr Heath’s concession that he received the email on
18 September 2013, Mr Heath seems to be highlighting a difference
between the non-reception of the denial letter by Mr Bigby by post and the
letter being sent to Mr Heath’s email address, although not read by him at
the time.
[18] The Commission says that even if the original posting was not proper
notification (and it appears that this is the case because the address was
incorrect) the insurance decision notice was sent to the nominated email
address on 18 September 2013. It is, the Commission submits, not
effectively their responsibility to ensure that somebody reads the email.
The email was sent to the address nominated and says the Commission
that is the end of the matter (my paraphrasing).
[19] The Commission says the applicant has effectively received notice of the
insurance decision on 18 September 2013. The application for review was
not filed until 26 February 2014 over five months the Commission says
after the applicant was notified.
[20] The Commission has a point. It is not the Commission’s responsibility nor
this Tribunal’s, to ensure that where a nominated email address is
provided, emails to that address (when properly sent) are read and
actioned.
[21] Mr Heath says that this was a clerical error while he was interstate.
[22] I am not satisfied that this adequately explains the overlooking of this
email. I am assuming that even if Mr Heath does not himself open all of
1 [2011] QCAT 574; subsequently affirmed in Molier v The Body Corporate for Q1 CTS
34498 [2012] QCATA 8.
-- 3 of 8 --
4
the emails in his inbox, then someone with appropriate responsibility and
ability to identify the importance of communications received would be
acting on his behalf in that regard.
[23] The Commission points particularly to the comments of the learned
Member in Cardillo2
It has been said that it is the prima facie rule that proceedings commenced
outside the prescribed period will not be entertained. Further it has also
been said that it is a precondition to the exercise of discretion in the
applicant's favour that the applicant for extension show an acceptable
explanation of the delay. …3
[24] The Commission submits that the applicant has failed to provide an
explanation for a delay and accordingly the prima facie rule should apply.
[25] I am satisfied that no satisfactory explanation has been given for the
clerical error arising in Mr Heath’s office as the reason for the late reading
of the email and the inability of it to come to Mr Heath’s attention.
Strength of the case the applicant will bring
[26] Mr Heath’s submissions say that the Commission’s reasons for denying
Mr Bigby’s claim can be summarised as follows:
a) The claim was not submitted during the currency of the policy
insurance held by Mr Kondra which expired on 6 August 2010;
b) The statutory insurance policy does not respond in circumstances
where there is another insurance policy and Mr and Mrs Bigby held a
home insurance policy at the time of the storm;
c) The insurance policy does not respond in circumstances where the
rectification work was undertaken without the prior approval of the
Commission; and
d) The policy does not respond in circumstances where damage was
caused by or contributed to by an excluded storm event.
[27] Mr Heath submits that the Commission was engaged at an early juncture
in the investigation of the damage caused following the storm and of the
allegedly defective work performed by Mr Kondra. Evidence of this can be
seen in the disciplinary proceedings before this Tribunal against
Mr Kondra himself. Mr Heath submits the Commission was aware of the
alleged defects in the construction of the dwelling prior to the expiry of the
policy because of the disciplinary action.
[28] Mr Heath concedes that Mr and Mrs Bigby did hold an insurance policy at
the time of the storm but says that the risk insured under that insurance
policy was not the same risk as that insured under the statutory insurance
policy held by the Commission. He says that the double insurance
2 At [33].
3 Lucic v Nolan [1982] FCA 217; Hunter Valley Developments Pty Ltd v Barry Cohen
Minister for Home Affairs [1984] FCA 176 at [18].
-- 4 of 8 --
5
exclusion clause in the statutory policy is not triggered so as to exclude
the applicant’s claim.
[29] Mr Heath submits that the Commission was aware in its investigations of
Mr Kondra that the dwelling had been demolished and was in the process
of being reconstructed prior to the expiry of the insurance policy.
Mr Heath seems to infer this meant the Commission had given some form
of prior approval to that process.
[30] Finally, Mr Heath says that it is arguable the damage was not caused by
the storm but rather by the alleged defective construction of the dwelling
by Mr Kondra, with the storm simply being a triggering event. The policy is
therefore not excluded because of a storm event.
[31] The Commission submits that Mr Bigby has no real prospects of success if
allowed to proceed.
[32] The Commission says that the claim was not submitted until three years
after the insurance policy had expired and that the home had a higher
insurance policy that was in place at the time of the loss. The dwelling was
demolished and reconstructed without the Commission’s approval and the
storm was a contributor, which is specifically excluded under the policy.
[33] The Commission points to clause 5.1 of the insurance policy which
requires written approval of the Authority prior to work being completed or
rectified. The Commission says no such written approval was given,
particularly as the house was completely demolished and rebuilt.
[34] Clause 5.4 of the insurance policy says that the insured is not entitled to
pay for loss where the loss is caused by or contributed to by a storm.
[35] Referring to clause 5.5.4 of the insurance policy, the Commission asserts
that the loss was contributed to (my emphasis added) by an excluded
event (the storm). The Commission says that contributed to by the storm
requires a lesser causal link then a loss that must be caused or
occasioned by the excluded event. In this regard, the Commission says
the loss was contributed by the storm and therefore the exclusion in
paragraph 5.4 is enlivened.
[36] The Commission further says that in any event, the applicant has no
prospects of success because there was another insurance policy in place
at the time as is contemplated by clause 4.6 of the Commission’s
insurance policy.
[37] The Commission says while this home insurance policy was in place at the
time of the loss, the applicants failed to notify the Commission in writing of
the home insurance policy and also failed to identify that there was any
excess payable in breach of clause 4.6 of the statutory policy.
-- 5 of 8 --
6
Discussion
[38] I accept there was another insurance policy over the home. I also accept
that the home was demolished and rebuilt without the Commission’s
approval in writing in breach of clause 5.1 of the insurance policy.
[39] I accept that the Commission was aware of the alleged defects in the
construction of the dwelling prior to the expiry of the policy because of the
disciplinary action against Mr Kondra but I also accept that the storm
contributed to the loss by the homeowners which appears to enliven the
exclusion in paragraph 5.4 of the policy.
[40] It also appears that the home owners have substantial difficulties with the
terms of clause 4.6 of the policy where other insurance policies exist and
the Commission is only required to pay the amount in excess of any
amount payable under that policy.
[41] On balance, I am not satisfied the homeowners have a strong case in
these circumstances.
Will other parties be prejudiced
[42] The Commission says it will be prejudiced should the extension of time
application be granted because:
i) the Bigbys’ insurance policy was in place at the time of the loss;
ii) the rectification of the dwelling has already occurred; and
iii) the Bigbys have commenced proceedings in the Supreme Court to
cover a substantial amount of money from the builder whilst
simultaneously attempting to recover under the statutory insurance
fund.
[43] So far as the Commission is concerned, the applicant had been notified
for a significant period and took no steps.
[44] Mr Heath on behalf of Mr Bigby said that the Commission has suffered no
prejudice as a result of the delay in these circumstances due to its
involvement with the prosecution of Mr Kondra and the information it
gained from that process.
[45] Mr Heath says that the Commission has an intimate knowledge of the
manner of construction and the alleged deficiencies in the construction of
the dwelling by Mr Kondra.
Discussion
[46] I am not satisfied the Commission suffers loss if time is extended. I agree
that the Commission had knowledge of the circumstances surrounding this
house because of the prosecution of Mr Kondra and would not have been
taken by surprise by the claim.
-- 6 of 8 --
7
The length of the delay
[47] Depending on the version of events the delay in filing the review was
between three and five months. In the greater scheme of things, this is not
a lengthy delay.
[48] I am not in these circumstances, satisfied that three to five months is such
a long time as to prejudice either party. I consider it to be a relatively short
delay in the nature of these proceedings and I give no importance to this
particular factor other than to note that the delay between notification and
the filing of the extension application was somewhere between three and
five months (depending on the view of the party concerned).
Interests of justice
[49] The Commission submits that it is not in the interests of justice to grant the
extension. The Commission says:
i) the applicant had the opportunity to review the decision and failed to
do so within the prescribed time limits;
ii) the Commission is now unfairly prejudiced; and
iii) the applicant cannot now say he is unfairly prejudiced if he is unable
to challenge the decision.
[50] The Commission says Mr Bigby has not provided an adequate explanation
for the delay not only in regard to the application for review but also for the
application to extend time and has limited prospects of success if allowed
to proceed.
[51] Mr Bigby’s solicitors submit that it is in the interests of justice that the
Commission’s decision should be reviewed in circumstances where the
Commission has considered it appropriate to bring disciplinary action
against Mr Kondra the builder, especially given that these proceedings
were successful.
[52] Mr Heath points out that the delay in making this application in excess of
three months was caused by a clerical error and contributed to by the
Commission.
[53] Mr Heath also says that continued correspondence with the Commission
and a request for policy terms on 7 August 2013 demonstrate that
Mr Bigby was motivated to receive the Commission’s decision and to
consider any potential denial of his application. The Commission, the
applicant says, was essentially put on notice that Mr Bigby would carefully
consider the reasons for any denial with reference to the policy terms
delivered to Mr Heath and that the finality of any decision might be
contested.
-- 7 of 8 --
8
Discussion
[54] Overall, I do not consider the applicant has provided a satisfactory
explanation for the delay arising for the clerical error in Mr Heath’s office.
[55] More importantly, I am not satisfied Mr Bigby has a strong case under the
terms of the insurance policy. There was a second policy, the storm
contributed to the damage of the home and the dwelling was completely
demolished and reconstructed without the Commission’s written approval.
[56] I am not satisfied the Commission suffers loss if time is extended and I
give no importance to be a relatively short delay in the general nature of
these proceedings.
[57] Because in particular I am not satisfied Mr Bigby has a strong case under
the terms of the insurance policy, I do not propose to exercise my
discretion to extend time. Instead I rely on the prima facie rule as
enunciated in Cardillo that proceedings commenced outside the
prescribed period will not be entertained.
[58] Mr Bigby’s application to extend a time limit is dismissed.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/169