Couture v Board of Professional Engineers [2014] QCAT 115
CITATION: Couture v Board of Professional Engineers
[2014] QCAT 115
PARTIES: Denis Couture
(Applicant)
v
Board of Professional Engineers
(Respondent)
APPLICATION NUMBER: GAR400-12
MATTER TYPE: General administrative review matters
HEARING DATE: 10 December 2013
HEARD AT: Brisbane
DECISION OF: Senior Member O’Callaghan
DELIVERED ON: 27 March 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The decision of the Board of Professional
Engineers is confirmed.
CATCHWORDS: GENERAL ADMINISTRATIVE REVIEW –
REGISTERED PROFESSIONAL ENGINEERS
– review of the decision not to take any action in
relation to a complaint against engineer –
consideration of engineer obligations under
Code of Practice in the context of his functions –
where found conduct not unsatisfactory
professional conduct
Professional Engineers Act 2002 (Qld), s 7,
s 36, s 37, s 41, s 71, s 73, s 122, Schedule 2
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 20, s 23
River Improvement Trust Act 1940 (Qld)
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Couture was self represented
RESPONDENT: Mr A D Scott of counsel instructed by
ClarkeKann Lawyers
-- 1 of 16 --
2
REASONS FOR DECISION
[1] Mr Couture owns properties on the Don River in North Queensland. The
river has a history of flooding. The Don River Improvement Trust (‘the
Trust’) was established under the River Improvement Trust Act (‘RITA’)1 to
undertake flood mitigation works. The works required the approval of the
Chief Executive of the then Department of Environment and Resource
Management (‘DERM’).2
[2] Certain works on the Don River were undertaken by the Trust in 2008-
2009 including the construction of a rock wall on the river (‘the Works’).
Part of the wall was constructed on the river bank opposite Mr Couture’s
properties.
[3] Mr Couture has serious concerns about what he says is a negative impact
that the Works have and will have on his property.
[4] Mr Coleman is an engineer. At the relevant time he was employed by
DERM as ‘Leader, Water Resource Management, North Region’ and was
the Chief Executive’s delegate in connection with approval of the Works.
He recommended technical approval of the Works. The recommendation
was made after they were constructed. Mr Couture lodged a complaint
with the Board of Professional Engineers (‘the Board’) about Mr Coleman’s
conduct in recommending approval.
[5] The Board undertook an investigation of Mr Coleman’s involvement in the
approval by appointing an independent investigator (Mr Parminter) to
provide a report. Upon receipt of that report the Board determined not to
take any further action against Mr Coleman.
[6] Mr Couture was not content with that decision and asked the Tribunal to
review it.
[7] When the matter came on for hearing the Board highlighted that the
Parminter Report did not detail the function which had been performed by
Mr Coleman which they said was fundamental to determining whether
Mr Coleman was carrying out professional engineering services (which
they said was a pre-requisite to a valid complaint).
[8] The Board submitted that there was inadequate evidence about the
function that Mr Coleman was undertaking and it was necessary to obtain
that evidence before the Tribunal could adequately review the merits of
the Board’s decision not to take any further action.
[9] An order was made by the Tribunal returning the matter to the Board for
reconsideration.
1 River Improvement Trust Act 1940.
2 RITA s 10(1).
-- 2 of 16 --
3
[10] The Board engaged another investigator, Mr Horton, and commissioned a
further report. Upon receipt of that report the Board confirmed its decision
to take no further action against Mr Coleman.
[11] Mr Couture’s application to review that decision continues pursuant to s 23
of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
(‘QCAT Act’).
[12] There was voluminous material filed in the Tribunal in this matter as a
consequence of its lengthy history. Neither the Board nor Mr Couture
relied on the Parminter Report. Mr Couture sought to rely on his own
affidavit material, material obtained following a freedom of information
application, the Board’s statement of reasons and his outline of argument.
[13] The Board relied on its statement of reasons, Mr Horton’s report which
was annexed to an affidavit of Clare Murray and its outline of argument.
[14] It is noted that no affidavit was received from Mr Coleman although
Mr Horton had access to submissions which had been made by him in
relation to the complaint.
[15] Mr Couture contends that Mr Coleman’s conduct in recommending the
approval of the Works amounts to unsatisfactory professional conduct and
that Mr Coleman should have been subject to disciplinary action in
accordance with the provisions of the Professional Engineers Act 2002
(Qld) (‘the Act’).
[16] The issue for the Tribunal in conducting this review is to determine is
whether the correct and preferable decision is for the Board not to take
any further action against Mr Coleman in relation to the complaint of
Mr Couture.3
The Complaint
[17] Mr Couture’s complaint was lodged with the Board on 2 June 2011 in
which he listed four grounds for the complaint:
1. Mr Coleman disregarded the environment by not making sure in his
review process that:
(a) approval from fisheries (Department of Primary Industries) was
obtained by the River Trust;
(b) approval from Coastal Management (DERM) was obtained by
the River Trust;
(c) approval from EPA (DERM) was obtained by the River Trust.
2. Mr Coleman disregarded Aboriginal Cultural Heritage by not making
sure, that the River Trust had exercised its duty of care as per the
Aboriginal Cultural Heritage Act 2003.
3 QCAT Act s 20(1).
-- 3 of 16 --
4
3. Mr Coleman recommended technical approval of a project without
making sure that appropriate design approvals, such as that provided
by an RPEQ was obtained by the River Trust.
4. Mr Coleman recommended technical approval when he knew that no
RPEQ would be involved (or had been involved) in the construction
phase of the project.
The legal framework
[18] The framework for the receipt of a complaint, the Boards powers to deal
with the complaint and the right to review the Board’s decision with
respect to the complaint are set out in the Act. Part 3 sets out the process
for the receipt of complaints and the Board’s investigations into the
conduct of professional engineers.
[19] Section 37 provides that a person who is aggrieved by a registered
professional engineer’s conduct in carrying out professional engineering
services may make a complaint about that conduct to the Board.
[20] Section 41 permits the Board to authorise an investigation into a complaint
about an engineers conduct in carrying out professional engineering
services.
[21] Section 71 requires an investigator so appointed to give the Board a
written report about their investigation.
[22] When the Board receives such a report it must decide to do one or more
of the actions provided for in s 73(2), which relevantly include:
a) Starting a disciplinary proceeding against the registered professional
engineer; and/or
…
e) Taking no further action about the matter the subject of the investigation.
[23] Section 36 provides for the grounds for disciplining a registered
professional engineer, including, where the engineer has behaved in a
way that constitutes ‘unsatisfactory professional conduct’.
[24] ‘Unsatisfactory Professional Conduct’ is defined in the Act4 as including
conduct that is of a lesser standard then that which might reasonably be
expected of the registered professional engineer by the public or the
engineers professional peers.
[25] Part 8 of the Act provides for reviews of particular decisions. Relevantly,
s 122 gives jurisdiction to the Tribunal, upon the application of a
complainant, to review a decision of the Board to take no further action
about the complaint.
[26] In this case, following Mr Couture’s complaint the Board appointed
Mr Parminter and subsequently Mr Horton to investigate the conduct the
4 The Act, Schedule 2.
-- 4 of 16 --
5
subject of the complaint. Reports were received by the Board. Following
receipt of the reports the Board determined not to take any further action
pursuant to s 73(2)(e).
Jurisdictional Issue
[27] The Board contends that the Tribunal should consider firstly whether it has
jurisdiction to review a decision of the Board not to take further action with
respect to the matters raised in Mr Couture’s complaint.
[28] They submit that the Tribunal’s jurisdiction is a jurisdiction to review a
decision by the Board to ‘take no further action about a “complaint”’. They
say the first question to be decided is whether the complaint of Mr Couture
is a ‘complaint’ within the meaning of the Act. They say if it is not then the
Tribunal does not have jurisdiction to deal with it.5
[29] The Act provides a scheme for complaints to be made about a registered
professional engineers conduct ‘in carrying out professional engineering
services’.
[30] The Board says that if the conduct of Mr Coleman which is the subject of
the complaint does not involve the carrying out of professional engineering
services then the Tribunal has no jurisdiction to conduct this review.
[31] I do not accept that argument. The Tribunal has jurisdiction under
s 122(2)(h) of the Act to review a decision to take no further action about
the complaint. It is not restricted to valid complaint.
[32] The question of whether the conduct involves the carrying out of
engineering services is still relevant. It may well be that if the complaint is
not about the engineers conduct in carrying out engineering services then
the correct and preferable decision is not to take any action in relation to
the complaint. However, the validity of the complaint or otherwise does not
oust the Tribunal’s review powers.
[33] By the same token, Mr Couture’s right to review a decision and the
Tribunal’s jurisdiction is however restricted to a review of a decision about
his complaint. It is not a general right to review the Board’s decision (if one
was made) not to take disciplinary action.
[34] Mr Couture made much in the hearing about the fact that under s 36 of the
Act the only test in considering whether a ground exists for taking
disciplinary action is whether the engineer ‘behaved in a way that
constitutes unsatisfactory professional conduct’ and that there is no
requirement that the behaviour be linked to the carrying out of particular
engineering services.
[35] This may be relevant if the Tribunal was conducting a review of a decision
not to take disciplinary action however, when the review is about the
decision on the complaint then the Tribunal (as the Board did) can only
5 Board’s Submissions dated 9 December 2013 at [11].
-- 5 of 16 --
6
have regard to the conduct the subject of the complaint and not to
allegations generally about the behaviour of a registered professional
engineer. As the Board contends, a complaint under the Act must be
about conduct in the carrying out of professional engineering services.
[36] For this reason I have disregarded certain allegations made by Mr Couture
in his written submissions and during the hearing about conduct of
Mr Coleman which was not the subject of his complaint, for example,
allegations that Mr Coleman misled investigators as to when he became
aware that the wall was built6 and Mr Coleman’s alleged failure to take any
action in relation to the actual construction of the wall when and he knew it
was being constructed without technical approval. These allegations were
not the subject of the complaint. I have considered solely whether the
correct and preferable decision was not to take any action in relation to the
conduct the subject of the complaint.
Mr Coleman’s Conduct
[37] Two issues arise for consideration:
a) Are the allegations in the complaint substantiated; and
b) If so does the conduct fall short of the standard expected of a
registered professional engineer so as to found a ground for taking
disciplinary action.
[38] The report of Mr Horton (upon which the Board’s decision is based)
including the documents referred to as the material with which he was
been briefed sets out the substantial evidence and conclusions upon
which the Tribunal is guided when determining these issues. I have also
taken into account Mr Couture’s submissions about those findings and
conclusions.
[39] Before considering each element of the complaint, it is relevant to set out
the evidence about:
a) What DERM and Mr Coleman’s function was in the process of
approval of the Works? and
b) In fulfilling this function, what conduct did Mr Coleman engage in?
[40] The role of DERM and Mr Coleman in the technical approval process is
relevant to determining whether Mr Coleman was providing professional
engineering services and as Mr Couture alleges whether Mr Coleman’s
conduct fell below an adequate standard.
[41] The Works originated in 2000 when the relevant local council
commissioned engineering company Ullman & Nolan Pty Ltd to undertake
a risk management study of proposed flood mitigation engineering works
in the Don River.
6 Mr Couture’s Outline of Argument at [42], [43] and [52].
-- 6 of 16 --
7
[42] In 2001 three revetment schemes were designed by Ullman & Nolan for
the Don River Improvement Trust.
[43] The Works concerned ‘scheme 3’ for which Noel Kidd, a registered
engineer with Ullman & Nolan signed the design drawings.7
[44] The Trust was required in execution of flood mitigation works to plan a
program of works for the forthcoming year and submit the plan to the Chief
Executive. The Chief Executive was then authorised to approve the plan.
[45] The approval process for the Works was divided into two parts:
a) Funding approval; and
b) Technical approval.8
[46] The Trust sought funding approval for scheme 3 of $480,000 in submitting
the annual works program for 2008-2009.9
[47] As referred to in Mr Horton’s report10 DERM had procedures and
guidelines applicable to the processing of applications for technical and
financial approval. Relevantly the procedures provided:
Procedure for approval of works
3. Check that the level of detail provided for the project is adequate for a
reasonable decision to be made given the cost estimate. If not seek
better information.
…
… over $50,000 in value – as above but also with technical specifications to
describe work requirement in reasonable detail. Such works should be
designed by a person with a professional indemnity cover, preferably
a registered professional engineer (my emphasis).
…
6. Check that the project is conceptually sound with regard to technical
and environmental detail. While the trust remains responsible for the
technical details of the design, we (the Department) need to be
satisfied that the broad concept is balanced and that any adverse
impacts are minimal.
[48] The ‘Guidelines for Preparation Submission and Approval of River
Improvement Trust Annual Works Programs’ are also relevant.11 They
state:
The involvement of the Department staff in the review or assessment of
planned projects/program of works of a Trust work/project does not waive a
Trust’s responsibility from undertaking formal planning, design and
construction of works, and it remains the obligation of the Trust to obtain
7 Horton Report at [27].
8 Horton Report at [52].
9 Mr Couture’s Statement dated 13 March 2013 Exhibit N5.
10 Horton Report at [55].
11 Horton Report at [56].
-- 7 of 16 --
8
development approvals and any other approvals or permits (eg vegetation,
environmental, fisheries permits) necessary for the proposed works.
…
Trusts should note that approval of an annual works program is granted
subject to all relevant and necessary approvals for individual works stated
in the program being obtained by the Trust before those individual works
commenced including, for example:
development approvals (Integrated Planning Act 1997).
permits and other approvals required under legislation administered
by the Department of Employment, Economic Development and
Innovation (Fisheries Act 1994).
approvals and authorities required by the Department, Environmental
Protection Act 1994, Coastal Protection and Management Act 1995;
Environment Protection and Biodiversity Conservation Act 1999.
other relevant authorities and permits, for example, vegetation
permits, cultural heritage management plans (Water Act 2000,
Vegetation Management Act 1999, Aboriginal Cultural Heritage Act
2003).
While a trust as a body corporate, is wholly responsible for the quality
of the design, construction and maintenance of its works, including
their structural integrity, the Department, as part of its approval of
planned works, ‘broadly assesses the proposed methods and likely
impact of the works to ensure that they are consistent with the States
interest and Riverine Management best practice for the region’. (my
emphasis)
[49] I accept Mr Horton’s finding that it was not contemplated that the
Department would be giving engineering approval in the strict sense, but
rather its function was to ensure that the Works ‘are consistent with the
States interest and Riverine Management best practice for the region’.
This does not include approval of the Works on an as constructed basis.
[50] Financial approval was given for the Works by letter dated 25 October
2008.12 The letter of approval notes that the Trust was to ensure before
commencing works that ….
A subsequent detailed technical assessment approval and
All relevant approvals for example from the Department of Primary
Industries and Fishery, the Environmental Protection Agency and other
relevant agencies … are obtained by the trust.
[51] The Trust proceeded to undertake the Works without obtaining the
technical approval.
[52] Mr Coleman in his role with DERM as ‘Leader, Water Resource
Management, North Region’ had responsibility with respect to the
technical approval process. The exact nature of Mr Coleman’s obligations
and responsibilities was part of the Board’s investigation. It was found by
12 Horton Report at [41].
-- 8 of 16 --
9
Mr Horton and accepted by Mr Coleman that in his role he was expected
to apply his engineering expertise and experience when giving
consideration to the Works.
[53] There is some dispute about when Mr Coleman became aware that the
Works had commenced without technical approval but at the latest this
was December 2008 when the Department received a complaint from
Mr Couture about the construction of the wall.13
[54] Without any direct evidence from Mr Coleman it is difficult to make findings
about what he knew and what he took into account in recommending
approval. The Tribunal has considered his written submissions regarding
the complaint.
[55] I find that the following events occurred after concerns were raised by
Mr Couture in December 2008 and brought to the attention of Coleman.
Mr Coleman became aware that Mr Couture complained that in
constructing the Works the Trust had reclaimed at least 10 metres of
land and was moving sand in the river up against his bank in a way
that would destabilise it.
He started to investigate Mr Couture’s concerns and requested
information from the Trust.
He inspected a section of the wall as constructed.
In an email of 17 December 2008 Mr Coleman said to his supervisor
Gary Jensen14 regarding Mr Couture’s request for information:
… I will be responding with something but not a lot. Don Trust did not
apply for technical approval of these works as yet from me but there is
the recent approval under the annual works program documentation
to consider plus the email correspondence that has gone to and from
recently regarding Mr Couture’s concerns …
On 14 April 2009 Mr Coleman wrote to his supervisor:
… finally I received all the information necessary to recommend
technical approval of a controversial Don River Webster-Brown stage
3 stabilization job
… please note this job was approved by the Minister in the trust
2008/2009 annual works plan but the trust overlooked obtaining
technical approval and went ahead and built it have since apologised
for the oversight, but they were slow to provide all the information
necessary to actually ask for technical approval
… Gary would you please endorse the attached technical approval
letter and forward up the line for RSD signature
On 15 April 2009 Mr Couture’s solicitors wrote to Mr Coleman in
these terms:
13 Mr Couture’s Statement dated 13 March 2013 Exhibits N2 and N9.
14 Mr Couture’s Statement dated 13 March 2013 Exhibit N9.
-- 9 of 16 --
10
As you are aware, Don River Improvement Trust has recently
constructed a rock wall on the eastern bank of the Don River. We
understand from previous discussions that you were unaware of any
assessment and/or approval of those works by the Department. We
ask that the Department provide written confirmation that it has not
assessed nor approved any works in relation to the rock wall.
Mr Coleman was involved in drafting a response to that letter. There
are email exchanges between Mr Coleman and his supervisors as to
the wording of the response, for example, on 21 April 2010 in an
email to Mr Cavicchioi referring to a draft response, he said:
… A reference to a qualified engineer would unfortunately fly in the
face of where we are headed at the moment or the Department trying
to distance itself from being the “engineer” on this job for a design
prepared in the 1980’s. I could not find Tony Larkin (DRIT’s engineer)
in the RPEQ register. What concerns me there is no RPEQ in the
picture (other than one who may or may not have been one in the
1980’s who designed the thing – Ullman & Nolan) by us even
mentioning “qualified engineer” it makes the Department responsible
and sue able which I suspect may be where Mr Couture may be
headed.
The Department Regional Services Director eventually responded to
Mr Couture’s solicitors letter on 29 May 2009 in these terms:
… prior to commencement of the annual works program, the
Department of Environment and Resource Management must
approve the detailed technical design. The location and the evaluation
of the impact of the wall with respect to your client’s property would
usually be considered at this stage.
The Department has no record of any detailed technical approval
neither requested by the trust nor granted by the Department. The
Department has contacted the trust and has been advised that
suitable drawings will be submitted by the trust for the Department’s
review in the near future. The Department will then decide if such
works as now constructed can be granted technical approval and will
consider your client’s reasonable interests in terms of its potential
impact on the opposing bank as part of this process.
… The trust has given the Department preliminary assurances that no
significant reclamation of land was undertaken as part of these
works.15
On 12 April 2010 the Trust via Tony Larkin formally sought approval
of scheme 3 saying:
Please accept our apologies that the approval is submitted after the
event … we also enclose a sketch plan of as constructed survey by a
registered surveyor showing the wall built approximately 10 metres
further back from the river centre line than originally designed. This
was done because of erosion of the bank since the time of the design
in 2001.16
15 Mr Couture’s Statement dated 13 March 2013 Exhibit N12.
16 Mr Couture’s Statement dated 13 March 2013 Exhibit N14.
-- 10 of 16 --
11
Mr Coleman in a lengthy email to Gary Jensen (Supervisor) on 4 May
201017 recommends approval. He said:
… Tony Larkin, the trust engineer advises there is one RPEQ
somewhere in WRC but that person has nothing to do with river trust
works. He advises me he is not on RPEQ because he was hired from
another state who do not have RPEQ’s and professional engineers
acts and also that RPEQ’s with river experience are hard to find these
days.
Noel Kidd’s involvement does however allay my concerns about the
involvement of an RPEQ in the design phase at least but not the
construction phase on this job.
Information submitted to me about the as built construction line by
Tony Larkin for example in order to address the Wilson Ryan Gross
concerns on behalf of Mr Denis Couture also seems amateurish, but
read in conjunction with email advice from Tony Larkin that the key
conclusions were based on information from a registered survey, I did
not have reason enough to challenge them and have proceeded to
recommend technical approval on the basis of them.
In the email he goes onto to explain the conditions he imposed on the
approval. It is apparent that he had misgivings about the fact that the
construction had not be supervised by an RPEQ. This email indicates
that he weighed up the pros and cons of recommending technical
approval in the circumstances. He commented on this in his
submission in response to the complaint18
I resolved that granting of technical approval for the final stage of a
partially built project that the Minister had already approved the earlier
stages of, and that had already been built, was therefore clearly in the
overall public interest in this instance, regardless of any concerns I
had with the trusts tardy compliance with the technical approval
process.
On 7 May 2010 DERM (via Nigel Kelley – Acting Regional Services
Director)19 granted approval of the Works.
Are the four grounds raised in the complaint substantiated – If so, should
the Board have taken action?
Grounds 1 and 2
[56] In items 1 and 2 of the complaint Mr Couture alleges that Mr Coleman
disregarded the environment and cultural heritage in not ensuring certain
approvals were obtained by the Trust.
[57] As Mr Horton finds, it is likely that some of the approvals referred to by
Mr Couture were not in fact obtained by the Trust.20
17 Mr Couture’s Statement dated 13 March 2013 Exhibit N28.
18 Horton Report at [77].
19 Mr Couture’s Statement dated 13 March 2013 Exhibit N19.
20 Horton Report at [92].
-- 11 of 16 --
12
[58] Mr Horton found that this complaint was not substantiated for a number of
reasons.
[59] He says, that it was not part of Mr Coleman’s function to ensure that the
approvals were obtained.
[60] This is correct. The Trust itself was specifically obliged to obtain such
approvals.
[61] Mr Couture’s argument is that despite this, in his capacity as an engineer
Mr Coleman had an inherent obligation to ensure that the environment
was protected.21 He says Mr Coleman failed in this obligation and as such
his conduct fell short of the appropriate standard.
[62] I do not accept that argument. The Code of Practice does require a
registered professional engineer to take ‘reasonable steps to be informed,
and to inform clients and employees of the social, environmental,
conservation and other possible consequences that might arise from
professional engineering services’.22 However, this must be read in the
context of the functions that the engineer is performing. Mr Coleman (and
DERM) had no obligation to obtain the approvals. It was the Trust’s
function. Further, as pointed out by Mr Horton ‘nothing in the Departmental
documents suggested that, even with the Trust having such an obligation,
that the Department had some role of review or assessment in relation to
whether such approvals had been obtained’.23
[63] The second point Mr Horton raises is that even if Mr Coleman did have
some role in reviewing whether the Trust had obtained the approvals,
such a function does not involve the provision of ‘professional engineering
services’.24
[64] In this regard, ‘professional engineering service’ is defined in the Act.25
[65] Mr Horton found that the elements of what was required to provide a
professional engineering service were not satisfied in respect to grounds 1
and 2 he said:26
There was no “service” that Mr Coleman was providing because
there was no “review” or like process which called for him to act as
alleged.
Even if there was a service, it did not involve the exercise of a degree
of technical (including engineering) judgment.
21 Mr Couture’s Outline of Argument at [62] - [69].
22 Mr Couture’s Outline of Argument at [66].
23 Horton Report at [92].
24 Horton Report at [95].
25 The Act, s 7, Sch 2.
26 Horton Report at [95].
-- 12 of 16 --
13
Asking whether general legislative approval had (or ought to have)
been obtained did not require and nor would it have been based
upon the application of engineering principles and data.
[66] I accept the point taken by the Board based upon Mr Horton’s finding that
any obligation associated with obtaining the approvals did not call for the
provision of ‘professional engineering services’ as contemplated by the
Act. As such a complaint in this regard was not about Mr Coleman’s
conduct in carrying out professional engineering services.
[67] Even if my findings as to the nature of any obligation is incorrect, I note in
any event that Mr Coleman when considering the recommendation for
approval did in fact turn his mind to environmental and cultural heritage
concerns.27
[68] I find that the correct and preferable decision was for the Board to take no
further action with respect to grounds 1 and 2 of Mr Couture’s complaint.
Ground 3
[69] Mr Couture says the Board should take action against Mr Coleman
because he recommended technical approval of the project without
making sure that the appropriate design approvals, such as that provided
by a RPEQ, was obtained by the Trust.
[70] Unlike grounds 1 and 2 Mr Horton finds, and Mr Coleman accepts, that in
recommending technical approval for the Works (grounds 3 and 4)
Mr Coleman was ‘providing a professional engineering service’.28
[71] In relation to the issue of whether requisite design approval was obtained,
Mr Horton finds that as a matter of fact design approvals were obtained by
the Trust. He said the designs for the Works were prepared by an
engineering firm and approved by engineer Noel Kidd in 2001.
[72] Even if that were not the case, I accept that Mr Coleman was not required
to ensure that the Works had been designed by a registered professional
engineer.
[73] Even the Trust itself was only required to check that the Works were
designed by a person with professional indemnity cover, preferably a
registered professional engineer.29
[74] Mr Couture’s apparent concern was that the design was outdated and
should have been revisited.30 If so that was a matter for the Trust and not
an obligation imposed on Mr Coleman. I agree with Mr Horton that this
complaint is unsubstantiated. No further action should have been taken by
the Board in relation to that complaint.
27 Mr Couture’s Statement dated 13 March 2013 Exhibit N25.
28 Horton Report pp 106 – 109.
29 As outlined in [47] of these reasons.
30 Mr Couture’s Outline of Argument at [48].
-- 13 of 16 --
14
Ground 4
[75] Mr Couture says that Mr Coleman engaged in unsatisfactory professional
conduct in recommending technical approval of the Works when he knew
that no RPEQ had been involved in the construction of the Works.
[76] It is accepted that there is no evidence that a RPEQ was in fact involved in
the construction of the Works. Mr Coleman himself notes in his
consideration of the approval post the construction that ‘what concerns me
there is no RPEQ in the picture other than one who may or may not have
been one in the 1980’s who designed the thing – Ullman & Nolan’.31
[77] Mr Couture says in these circumstances Mr Coleman’s conduct in
recommending technical approval was of a lesser standard than might
reasonably be expected of a professional registered engineer and the
Board should have taken action against him.
[78] In relation to this concern the Tribunal notes firstly that there is no
allegation in the complaint the Works were in anyway structurally
defective.
[79] In considering any obligation on Mr Coleman to safeguard the public, the
Board and the Tribunal should put Mr Coleman’s conduct in the context of
the services he was obligated to provide. It was never intended that
Mr Coleman or DERM provide engineering services with respect to the
construction of the Works. The Department’s role was ‘to broadly assess
the proposed methods and likely impact of the Works to ensure that they
were consistent with the State’s interest and Riverine Management best
practice for the region’.32
[80] As such, Mr Coleman had no obligation to ensure that a registered
professional engineer was involved in the construction. I would have some
difficulty in finding that he engaged in unsatisfactory professional conduct
by not providing a service he was never obligated to provide.
[81] Mr Horton considered whether Mr Coleman’s obligations changed in that
he was in fact granting approval after construction. He noted that
Mr Coleman did appear to adjust his conduct to the fact that the Works
had been completed.33
[82] If Mr Coleman’s obligations did change, I find that his email of 4 May
201034 illustrates that Mr Coleman did not ignore the fact that the wall had
been constructed and that apparently no RPEQ had been involved in the
construction.
31 Mr Couture’s Statement dated 13 March 2013 Exhibit N16.
32 As outlined in [48] of these reasons.
33 Horton Report at [64].
34 Mr Couture’s Statement dated 13 March 2013 Exhibit N28.
-- 14 of 16 --
15
[83] His email indicates he gave proper consideration to the concerns raised
by Mr Couture about the construction of the wall but he determined on
balance that it was appropriate to recommend the approval.
[84] Mr Coleman elaborated on his consideration of the application in his
written submission in response to the complaint:35
I recall the information provided by the Trust appeared to be consistent with
Tony Larkin’s claim that the wall had been built on and to match the new
eroded alignment also consistent with the erosion having advanced at an
unnatural rate during the many years that stage 2 … was delayed due to
lack of funding. I consider that delay had disadvantaged land owners on the
other side of the river from Mr Couture. I also considered that rapid
advancement of erosion of the order of 10 metres in a few years with large
washouts probably had been induced by clearing of Riparian vegetation or
poor riparian management practice on or near the banks at some time in
the past. … In my inspection of a section of the wall adjacent to
Mr Couture’s property I noted there appeared to be no rapidly advancing
erosion on Mr Couture’s side of the river.
…
I recognise that the land owners of properties and the community on the
other side of the river also have similar interest to those of Mr Couture. I
then weighted up what I saw were minor impacts on Mr Couture’s side
against the potentially major consequences for both the larger community
and environment on the other side of the river the advancing breakaway
erosion to eventually culminate in a change of course for the river in a flood.
...
I resolved that granting of technical approval for the final stage of a
practically built project that the Minister had already approved the earlier
stages of, and that had already been built, was therefore clearly in the
overall public interest in this instance, regardless of any concerns I had with
the Trust’s tardy compliance with the technical approval process.
[85] Mr Horton concludes that Mr Coleman did adopt a considered approach to
his task and did not merely give the approval to cover up or to avoid
dealing with a request for approval which should have been made earlier.
[86] Mr Couture says further that Mr Coleman’s moves to distance himself and
DERM from being the engineer on the job36 constitutes behaviour that is
unsatisfactory professional conduct. He says, his statutory obligation was
to protect the public by making sure a registered professional engineer
was involved in the construction of the Works.
[87] The fact that Mr Coleman sought to distance himself from being the
engineer on the job is not inconsistent with the position that the
Department and he were in fact not engaged to give engineering approval
to the Works. This does not make his conduct unsatisfactory. He was
simply acting according to and consistently with his obligations.
35 Horton Report at [77].
36 Mr Couture’s Statement dated 13 March 2013 Exhibit N16.
-- 15 of 16 --
16
[88] In summary, I find that in recommending approval where Mr Coleman
suspected that no RPEQ had been involved in the construction did not
equate to unsatisfactory professional conduct. The engineering services
he was providing did not require him to be satisfied an RPEQ was
involved.
[89] The engineering services he did provide and was required to provide in
recommending the approval in a difficult situation of considering whether
to grant approval after the Works were constructed do not evidence any
unsatisfactory professional conduct. I agree with Mr Horton’s conclusion
that Mr Coleman’s actions met the requirements of the guidelines and
policies.
[90] Whilst the Tribunal understands Mr Couture’s concerns with the process,
when considering Mr Coleman’s obligations, functions and the evidence of
what Mr Coleman did in the context of those matters, the correct and
preferable decision was for the Board not to take any further action
against Mr Coleman in respect of the matters the subject of the complaint.
[91] I order that the decision of the Board be confirmed.
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/115