Barry Pitt Constructions Pty Ltd v Smith & Anor [2014] QCATA 339
CITATION: Barry Pitt Constructions Pty Ltd v Smith & Anor
[2014] QCATA 339
PARTIES: Barry Pitt Constructions Pty Ltd
(Applicant/Appellant)
v
Shane Harold Smith
Agnieska Smith
(Respondents)
APPLICATION NUMBER: APL085-14
MATTER TYPE: Appeals
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Senior Member Stilgoe OAM
Member Deane
DELIVERED ON: 9 December 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application for leave to appeal or
appeal is allowed.
2. Order 2 of the orders of the Tribunal
dated 23 January 2014 is set aside.
3. The matter is remitted to the Tribunal for
determination according to law.
4. The proceeding, BDL037-13, is listed for a
directions hearing on a date to be fixed.
5. Shane Harold Smith and Agnieska Smith
are to pay to Barry Pitt Constructions Pty
Ltd, within 14 days of agreement or
assessment as applicable, its costs of
and incidental to:
a) this application for leave to appeal or
appeal on an indemnity basis and
certified fit for counsel, to be agreed,
or absent agreement within 28 days of
the date of this order, to be assessed
by Hickey & Garrett Legal Costs
Assessors, Level 21, 141 Queen
Street, Brisbane.
b) any assessment as also assessed.
-- 1 of 8 --
2
CATCHWORDS: APPEALS – DOMESTIC BUILDING DISPUTE –
failure to award costs – whether inadequate
reasons – failure to award interest – failure to
give reasons – error of law
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 107, s 121, s 142, s 146,
s 147
Queensland Building and Construction
Commission Act 1991 (Qld), s 77
Pickering v McArthur [2005] QCA 294
Lyons v Dreamstarter Pty Ltd [2011] QCATA
142
Commissioner for Children and Young People
and Child Guardian v FGC [2011] QCATA 291
Ricchetti v Lanbuilt Pty Ltd [2011] QCATA 266
Commissioner for Children and Young People
and Child Guardian v Eales [2013] QCATA 303
Better Homes Queensland Pty Limited v
O’Reilly & Anor [2012] QCATA 37
Ericson v Queensland Building Services
Authority [2013] QCA 391
Lida Build Pty Ltd v Miller & Anor [2013] QCATA
139
Campbell v Telford & Anor [2013] QCAT 620
Baque v Rivergum Homes Pty Ltd [2013]
QCATA 200
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REPRESENTATIVES:
APPLICANT: Barry Pitt Constructions Pty Ltd represented by
Mr Mark Williams of Counsel, instructed by Bill
Cooper & Associates
RESPONDENT: Shane Smith and Agnieska Smith represented
by Mr Smith, assisted by McKays Solicitors
REASONS FOR DECISION
[1] Barry Pitt Constructions brought an application for a domestic building
dispute against Mr and Mrs Smith, claiming $74,431.50 due under a
building contract. Mr and Mrs Smith filed a counterclaim for defective work.
The learned Member ordered Mr and Mrs Smith to pay Barry Pitt
Construction’s claim but refused its application for costs and interest.
-- 2 of 8 --
3
[2] Barry Pitt Constructions seeks leave to appeal or to appeal the decision
on the grounds that the learned Member erred in refusing the costs claim
and by failing to award interest. It contends that leave is not required
because the entitlement to costs is derived from the contract and,
therefore, the learned Member erred at law.
[3] Where grounds of appeal consist of an error of fact or mixed law and fact
leave to appeal is necessary.1 Leave to appeal will usually be granted
where there is a reasonable argument that the decision is attended by
error, and an appeal is necessary to correct a substantial injustice to the
applicant caused by that error.2
[4] Barry Pitt Constructions also seeks to appeal against the failure to award
interest and contends that as this only involves a question of law, the
appeal is as of right and that leave is not required.3
Failure to award costs and interest
[5] The appeal is allowed.
[6] Barry Pitt Constructions contends that the reasons given were not
supported by the substantive decision.
[7] We do not accept that the reasons are not consistent with the decision.
Mr and Mrs Smith’s counterclaim was based, at least in part, on an
allegation that the residence was not built in accordance with the plans.
The learned Member found that ‘both parties agree upon the position of
the house’4 and that ‘the residence does not conform to the original
plans’.5 She accepted that this was a breach of Barry Pitt Constructions’
contractual obligations6 but found that there was no expert evidence which
quantified the diminution of the property’s value by the non-compliances7
and that:
… the costs of rectification ...would be wholly unreasonable as a method to
compensate the Respondent for the variations to the building plan.8
[8] Barry Pitt Constructions submits there was ‘no basis for the learned
Member to decide that the usual principle, that costs should follow the
event, not to apply’.
[9] It is well established that the ‘usual principle’ which applies to costs
decisions in the courts does not apply to costs decisions in the Tribunal.
This is because the ‘usual principle’ is found in the Uniform Civil
Procedure Rules (UCPR). The UCPR is not applicable to the Tribunal.
1 QCAT Act s 142(3)(b).
2 Pickering v McArthur [2005] QCA 294 at [3].
3 QCAT Act s 142.
4 Reasons at [21].
5 Ibid at [40].
6 Ibid at [42].
7 Ibid at [49].
8 Ibid at [46].
-- 3 of 8 --
4
Barry Pitt Constructions acknowledges, in its submissions in reply9, there
is no automatic rule in the Tribunal that costs follow the event. The Appeal
Tribunal has acknowledged that there is no certainty ‘even considering the
broad general discretion conferred by the QBSA Act’10 that a successful
party will be awarded costs of the proceedings.11
[10] The originating application made a claim for costs and interest. It did not
specify the basis for those claims. Claims for costs and interest did not
form part of the issues lists tendered at the hearing. However in the written
submissions tendered at the hearing Barry Pitt Constructions did assert an
entitlement to interest under the terms of the contract and sought a costs
award both on ‘general principles and pursuant to the express terms of the
contract’.12
[11] Barry Pitt Constructions contends that the learned Member failed to take
into account the terms of the contract which provided a separate right to
costs ‘on a solicitor and own client basis associated with recovery ...of an
amount under this contract’.13
[12] The learned Member’s reasons do not refer to the terms of the contract as
regards any entitlement to costs. Reasons for final decisions are required
to be given.14 The Appeal Tribunal15 has recognised that:
… they must contain three essential elements: appropriate and sufficient
reference to the relevant evidence; the material findings of fact that were
made (and the reasons for making those findings); and, the applicable law
and the reasons for applying it.....the crucial requirement is for the Tribunal
to give reasons which disclose what has been taken into account in a way
that means that any error is revealed.
[13] It has also been accepted by the Appeal Tribunal that the adequacy of the
Tribunal’s reasons is to be considered ‘in light of the simpler, expedited
procedures it is obliged to adopt under the QCAT Act’.16
[14] The learned Member gave very brief reasons for the refusal to award
costs. These were:
..on the grounds that the Respondents were able to prove their case at
least in part, even though this did not result in an award of damages in their
favour.
[15] The learned Member did not refer in her reasons to the claim for interest.
9 Dated 13 May 2014 [25].
10 As it was then called, now Queensland Building and Construction Commission Act
1991 (Qld).
11 Lyons v Dreamstarter Pty Ltd [2011] QCATA 142 at [38].
12 Written submissions dated 14 November 2013 at [36].
13 Clause 33 of the General Conditions.
14 QCAT Act s 121.
15 Commissioner for Children and Young People and Child Guardian v FGC [2011]
QCATA 291 at [47].
16 Ricchetti v Lanbuilt Pty Ltd [2011] QCATA 266 at [3]; Commissioner for Children and
Young People and Child Guardian v Eales [2013] QCATA 303 at [44].
-- 4 of 8 --
5
[16] Even considering the simpler and expedited procedures of the Tribunal,
we find that the reasons are inadequate, as they do not disclose why the
claim for costs and the claim for interest under the terms of the contract
were not allowed.
[17] We also find that the reasons are inadequate as they do not clearly
disclose the ‘three essential elements’ as referred to earlier in these
reasons as to why the broad general discretion to award costs was
refused.
[18] A failure to provide sufficient or adequate reasons for a decision is an
error of law.17 Leave is not therefore required. The appeal is allowed.
[19] Mr and Mrs Smith raise a number of matters in their submissions relating
to the conduct of Barry Pitt Constructions during the course of the
performance of the work, after the dispute arose and after the decision of
the learned Member was made.18 These matters are not relevant to
whether there is any error of law in the learned Member’s findings.
Consequences
[20] Section 146 of the QCAT Act sets out the Appeal Tribunal’s powers on
appeal where the appeal is on a question of law. It does not provide for
rehearing as compared to section 147, which relates to appeals on
questions of fact or mixed law and fact.19 If the question of law resolves
the matter as a whole then the Appeal Tribunal may substitute its own
decision, otherwise it is to remit the matter for further consideration.
[21] Barry Pitt Constructions submits that:
a) there was evidence before the learned Member that the fixing stage
payment in the sum of $50,000 was due on 7 December 2012 and so
claims interest on and from 8 December 2012;
b) it is entitled to interest on $20,000, the practical completion payment
claim on and from 17 February 2013, the date the Tribunal
application was commenced;
c) it is entitled to interest on the additional amounts found payable in the
sum of $4,431.50 on and from 23 January 2014 being the date of the
learned Member’s decision;
d) the amount of $74,431.50 was paid on 29 January 2014 so that
interest ceased to accrue on that date.
[22] It is not possible for the Appeal Tribunal to substitute its own decision as it
is not possible to calculate interest payable as the learned Member’s
reasons do not set out findings of fact in respect of:
17 Better Homes Queensland Pty Limited v O’Reilly & Anor [2012] QCATA 37 at [22].
18 E.g. Failure to negotiate the defects identified and accepted by the learned Member;
breaches of the Domestic Building Contracts Act 2000 (Qld) including a failure to
provide written variations.
19 Ericson v Queensland Building Services Authority [2013] QCA 391 at [13].
-- 5 of 8 --
6
a) whether each amount found to be payable were due and payable
under the contract as distinct from under a statutory entitlement20.
If the entitlement to payment arose under a statutory entitlement and
not under the contract then the contractual entitlement to interest on
that amount does not arise;
b) when the amounts found to be payable under the contract were due
under the contract e.g. when the progress claims were received by
the owners and the consequential due dates having regard to the
terms of the contract;
c) the interest rates applicable and whether they varied across the
relevant periods.21
[23] The Appeal Tribunal has previously accepted that where the contract
remained on foot the stage claim payments are liquidated claims pursuant
to the contract and therefore enlivened an entitlement to ‘recover the cost
to recover that sum [under the relevant clause of] the contract’.22
[24] Mr and Mrs Smith contend that the reasons in Lida Build23 do not clearly
identify the type of costs that were allowed as ‘debt collection costs’ and
the reasons make no reference to costs of the proceeding so that debt
collection costs only refers to costs incurred prior to the proceedings
commencing.
[25] The Tribunal has accepted that costs available under the contract are not
subject to s 100 of the QCAT Act and has previously awarded legal costs
from the date of initial instructions.24 The Appeal Tribunal has clearly
recognised claims for legal costs of building dispute proceedings and a
successful appeal under equivalent contractual terms by awarding
$95,260.42 as the solicitor and own client costs billed by the builder’s
solicitors.25
[26] It is not possible for the Appeal Tribunal to substitute its own decision, as it
is not possible to calculate costs payable under clause 33 in respect of the
original proceedings. The learned Member’s reasons do not set out
findings of fact in respect of whether each amount found to be payable
was due and payable under the contract as distinct from under a statutory
entitlement and whether those claims were for liquidated claims as distinct
from damages.
20 The claims for adjustments/variations and in particular the additional costs of air-
conditioning may have been founded under the Domestic Building Contracts Act 2000
rather than the contract.
21 Barry Pitt Constructions submits that interest was sought at 5% in the absence of
evidence before the learned Member as to the applicable Commonwealth Bank rate
during the relevant period – Submission dated 19 February 2014.
22 Lida Build Pty Ltd v Miller & Anor [2013] QCATA 139 at [44] – [46].
23 Ibid.
24 Campbell v Telford & Anor [2013] QCAT 620.
25 Baque v Rivergum Homes Pty Ltd [2013] QCATA 200.
-- 6 of 8 --
7
[27] Mr and Mrs Smith refuted the claim for $4,431.50 but did not deny that the
stage claims were due under the contract other than asserting a set off by
way of damages as set out in their counterclaim.
[28] If the entitlement to payment of $4,431.50 arose under a statutory
entitlement or as an assessment of damages as distinct from a liquidated
amount under the contract then the contractual entitlement to debt
collection costs does not arise in respect of that amount and there would
need to be a quantification or apportionment of costs incurred in respect of
the relevant part of the claim.
[29] We have no alternative but to allow the appeal and set aside the decision
and return the matter to the learned Member for a fresh determination to
be made according to law.
Costs of the Appeal
[30] Barry Pitt Constructions seek an order that Mr and Mrs Smith pay:
a) the costs of the appeal on an indemnity basis and ‘certified fit for
counsel’, to be agreed, or absent agreement to be assessed’ or in the
alternative on ‘a standard basis in accordance with the District Court
Scale of Costs’.
b) its costs and the costs generally of such assessment, as assessed.
c) the costs within 14 days of agreement or assessment.
[31] As outlined earlier in these reasons there are no findings in relation to
whether all of the successful claims are properly characterised as debt
collection under the contract. There was no assertion by either party that
the contract had been terminated so there appears no reason why the
claim in respect of the two progress claims ($70,000) ought not to be
characterised as collection of debts under the contract. As noted earlier in
these reasons they are claims for liquidated amounts and not for
damages.
[32] As a matter of law a contractual entitlement to recover debt collection
costs arose at least in respect of the two progress claims and these
appeal proceedings are associated with recovering or attempting to
recover an amount under the contract i.e. debt recovery costs.
[33] We allow the claim for costs of the appeal having regard to the broad
general discretion to award costs in domestic building disputes26 and
having regard to the contractual entitlement in clause 33 of the contract
which allows recovery of costs on a solicitor and own client basis. The
Appeal Tribunal has previously accepted that this is ‘virtually the same as
indemnity costs’.27
26 Queensland Building and Construction Commission Act 1991 (Qld) s 77.
27 Baque v Rivergum Homes Pty Ltd [2013] QCATA 200 at [9].
-- 7 of 8 --
8
[34] We are to fix costs if possible.28 There is no evidence before us to allow us
to fix the costs of the appeal. Given the nature of the proceedings and the
technical nature of applications for leave to appeal and appeal it was
reasonable for counsel to have been retained. If the parties are unable to
agree on costs, they ought to be assessed by a costs assessor.
28 QCAT Act s 107.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2014/339