Davey v Allblack Central [2014] QCATA 75
CITATION: Davey v Allblack Central [2014] QCATA 075
PARTIES: Peter Davey
Amanda Davey
(Applicants/Appellants)
v
Nicholas Fallbrown t/as Allblack Central
(Respondent)
APPLICATION NUMBER: APL545 -13; APL577 -13
MATTER TYPE: Appeals
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Senior Member Stilgoe, OAM
DELIVERED ON: 7 April 2014
DELIVERED AT: Brisbane
ORDERS MADE: APL545 -13
1. Leave to appeal granted.
2. Appeal allowed
3. The decision of 14 November 2013 is set
aside.
4. Nicholas Fallbrown t/as Allblack Central
shall pay Peter Davey and Amanda Davey
$16,500.00 [within 28 days of today’s
order].
APL577 -13
5. Leave to appeal refused.
CATCHWORDS: APPEAL – LEAVE TO APPEAL – MINOR CIVIL
DISPUTE – TRADER CLAIM – where defective
asphalt paving – where tribunal found paving
contractor liable for defective paving – whether
evidence supported tribunal’s finding – where
tribunal assessed damages on diminution in
value of property – whether assessment of
damages appropriate – whether alternative
assessment of damages appropriate – whether
grounds for leave to appeal
-- 1 of 4 --
2
Dearman v Dearman (1908) 7 CLR 549
Fox v Percy (2003) 214 CLR 118
Pickering v McArthur [2005] QCA 294
Chambers v Jobling (1986) 7 NSWLR 1
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
[1] Mr and Mrs Davey have a long asphalt driveway leading to their home in
semi-rural Samford. In 2010, they engaged Mr Fallbrown to extend areas
of asphalt paving. Mr Fallbrown completed the paving. Mr and Mrs Davey
paid him $17,000.
[2] The paving started to fail. Mr Fallbrown refused to rectify the paving so
Mr and Mrs Davey filed a claim for a refund of the $17,000. Eventually,
after three separate days of hearing over an extended period, an
Adjudicator found that Mr Fallbrown’s paving was defective. He ordered
Mr Fallbrown pay Mr and Mrs Davey $5,110.
[3] Both sides want to appeal the learned Adjudicator’s decision.
Mr Fallbrown says the learned Adjudicator erred in finding he was
responsible for the failure of the paving. Mr and Mrs Davey say the
learned Adjudicator erred in assessing the appropriate compensation.
[4] Because this is an appeal from a decision of the tribunal in its minor civil
disputes jurisdiction, leave is necessary. The principles the appeals
tribunal applies when considering an application for leave to appeal are as
summarised by Keane JA (as His Honour then was) in Pickering v
McArthur1:
There are numerous authorities, in varying language but with unvarying
emphasis, that leave to appeal will usually be granted where there is a
reasonable argument that the decision is attended by error, and an appeal
is necessary to correct a substantial injustice to the applicant caused by
that error.
Mr Fallbrown’s appeal
[5] Mr Fallbrown says his agreement with Mr and Mrs Davey was to supply,
deliver and lay 10 mm asphalt 30 mm thick in the pre-existing base and
that is what he did. He says that the paving failed because of a defect in
the base, not because of his work. He says he should not be liable to pay
Mr and Mrs Davey anything.
[6] The learned Adjudicator considered these arguments when coming to his
decision. He accepted the conclusions from independent experts that the
1 [2005] QCA 294 at [3].
-- 2 of 4 --
3
paving failed because of the way it was laid, not because of the condition
of the base.
[7] The appeal tribunal will not usually disturb findings of fact on appeal if the
evidence is capable of supporting the conclusions.2 An appellate tribunal
may interfere if the conclusion is ‘contrary to compelling inferences’ in the
case.3
[8] Although there is some evidence from a core sample that the base was
the problem, that evidence was not accepted. There was only one core
sample taken in a very large area. Mr Fallbrown had the technical results
of the core sample but he did not have the benefit of an expert
interpretation of those results. The core sample is the only evidence of a
base failure and the experts took a different view. The learned Adjudicator
chose to accept the experts’ view. The evidence can support the learned
Adjudicator’s finding. There is nothing in the material that persuades me
the learned Adjudicator should have taken a different view of the facts.
[9] There is no reasonably arguable case that the learned Adjudicator was in
error. Mr Fallbrown’s application for leave to appeal should be refused.
Mr and Mrs Davey’s appeal
[10] The learned Adjudicator accepted4 that the proper measure of damages
was the amount required to put Mr and Mrs Davey into the position they
would have been in had Mr Fallbrown performed the contract correctly.
Mr and Mrs Davey presented three quotes for rectification, ranging from
$16,500 to $35,538.67.
[11] The learned Adjudicator rejected all quotes because he found that they
included work on the base that was not part of Mr Fallbrown’s original
specification. He also found that, if any of the quotes was accepted,
Mr and Mrs Davey would have a better driveway than if Mr Fallbrown had
completed his work properly.
[12] It is true that the quote from Austek Asphalt Services, which is the most
expensive, contemplates rectification work to the base. Mr and Mrs Davey
admitted that this quote was “overkill”5. It does suggest an improved result
and the learned Adjudicator was right to discount it.
[13] Mr Fallbrown pointed out that the quote from Australian Asphalt
Specialists contemplated two layers of asphalt, not one6. It also
contemplates 40 mm of asphalt whereas Mr Fallbrown quoted for 30 mm
of asphalt. If that quote was accepted, Mr and Mrs Davey would have a
2 Dearman v Dearman (1908) 7 CLR 549 at 561; Fox v Percy (2003) 214 CLR 118 at
125-126.
3 Chambers v Jobling (1986) 7 NSWLR 1 at 10.
4 Reasons for decision at [16].
5 Transcript Day 3, page 2-23, lines 37-39.
6 Transcript Day 3, page 2-22, lines 29-38.
-- 3 of 4 --
4
better result than Mr Fallbrown’s quoted work. Again, the learned
Adjudicator was right to reject that quote.
[14] However, the quote from Asphalt Concepts does appear to be limited to
rectification of the defective work. Indeed, Mr and Mrs Davey say that it
does not address all of the defective work7. It appears that Mr Fallbrown’s
submissions – that the quotes all included work on the sub base - led the
learned Adjudicator into error. The learned Adjudicator erred in failing to
accept the quote from as Asphalt Concepts evidence of the true measure
of damages.
[15] The learned Adjudicator assessed the measure of damages on the
diminution of the value of Mr and Mrs Davey’s property because of the
defective driveway. The learned Adjudicator had no evidence to assist him
in that assessment. He then proceeded to assess the value of the work
that was not defective. Again, he had no evidence to assist him in that
task. In an effort to produce what he saw as a fair result, the learned
Adjudicator fell into error.
[16] Leave to appeal should be granted and the appeal allowed. The decision
of 14 November 2013 is set aside. Nicholas Fallbrown t/as Allblack Central
shall pay Peter Davey and Amanda Davey $16,500.00 [within 28 days of
today’s order].
7 Transcript Day 3, page 2-23, lines 26-28.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2014/075