De Berry v Principal Body Corporate for Hope Island Resort [2014] QCATA 19
CITATION: De Berry v Principal Body Corporate for Hope
Island Resort [2014] QCATA 19
PARTIES: Jeanette De Berry and
Duncan De Berry
(Appellants)
v
Principal Body Corporate for Hope Island Resort
(Respondent)
APPLICATION NUMBER: APL306-13
MATTER TYPE: Appeals
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Judicial Member Dodds
DELIVERED ON: 6 February 2014
DELIVERED AT: Brisbane
ORDER MADE: Application refused.
CATCHWORDS: APPEAL – LEAVE TO APPEAL – COSTS
ORDER – BUILDING DISPUTE - where leave
given to the parties to make submissions about
costs - where applicants were ordered to pay
the respondent‟s costs – whether Tribunal
erred in law
Building Units and Group Titles Act 1980 (Qld),
Part 5
Integrated Resort Development Act 1987 (Qld),
s 177
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 3, s 100, s 102, s 142
Queensland Civil and Administrative Tribunal
Rules 2009 (Qld), r 85
Ralacom Pty Ltd v Body Corporate for Paradise
Island Apartments (No 2) [2010] QCAT 412
Zachary Developments Pty Ltd v Turner & Anor
[2012] QCATA 86.
-- 1 of 10 --
2
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] In these reasons I will refer to the Queensland Civil and Administrative
Tribunal Act 2009 (Qld) as „the QCAT Act‟, a tribunal under the QCAT Act
as „the Tribunal‟ and to the respondent Principal Body Corporate for Hope
Island Resort as „PBC‟.
[2] This is an application for leave to appeal a costs order made by the
Tribunal on 18 June 2013. The applicants were ordered to pay the costs of
the respondent PBC, plus outlays fixed at $14,066 from a proceeding
commenced by PBC in the Tribunal arising out of a breach by the
applicants of a development approval.
[3] On 5 March 2013 orders had been made by the Tribunal in PBC‟s favour,
on its application, including an order the parties have leave to make
submissions regarding costs (the primary decision). PBC‟s application had
sought, along with the principal relief which it obtained, an order the
applicants pay its costs of and incidental to its application.
[4] A costs order can only be appealed against if the applicant has obtained
the Appeal Tribunal‟s leave.1
[5] When considering whether leave should be granted it is well established
an Appeal Tribunal is guided by the following considerations:
a) Is there a reasonably arguable case of error on the part of the Tribunal such
that an appeal is necessary to correct a substantial injustice to the
applicant;
b) Is there a reasonable prospect the applicant will obtain substantive relief;
c) Does the primary decision for which leave to appeal is sought expose a
question of general importance upon which a decision of the Appeal
Tribunal would be to the public advantage.
[6] It will be necessary to consider the circumstances of the primary decision
and the Tribunal‟s reasons for its costs order.
The Application for Leave
[7] Attached to the application for leave is an annexure containing
submissions under the heading „Grounds of Appeal‟. These are repeated
with some additions in written submissions of the applicants supplied to
the Tribunal.
1 QCAT Act s 142(3)(a)(iii).
-- 2 of 10 --
3
[8] There appear to be three main themes to the „Grounds of Appeal‟ in the
applicant‟s submissions:
a) Sections 100 and 102 of the QCAT Act were not correctly applied by
the Tribunal in awarding costs. This amounted to an error of law;
b) The reasons of the Tribunal for awarding costs contain a number of
inconsistencies which render the decision factually wrong;
c) The Tribunal Member erred in granting leave to the parties to make
submissions regarding costs in its decision of 5 March 2013.
Background
[9] Much of the background which follows is taken from the primary decision.
[10] The applicants Jeanette and Duncan De Berry at all material times were
residents of Riverleigh Gardens Resort, part of Hope Island Resort.
[11] Their property had been the subject of a development approval in 2007.
PBC‟s authority to regulate the development derived from the provisions of
the Integrated Resort Development Act 1987 (Qld). PBC is the Principal
Body Corporate for the Hope Island Resort. According to the applicants‟
development approval, a front masonry wall was to be positioned at an
approximate 6 metre setback from the front boundary of the property in
line with the front elevation of the house.
[12] Construction of the applicants‟ property was completed in approximately
November 2008. The front masonry wall was constructed past the front
elevation of the house at a 2.1 metre setback from the boundary. The
applicants were aware the location of the wall would not comply with the
development approval and would contravene the Hope Island
Development by-laws.
[13] On 7 June 2011 Cambridge Management Services wrote to the applicants
on behalf of PBC as follows:
We have been instructed by the PBC for the purposes of advising that the
relaxation sought to allow for the masonry fences in question to remain has
not been approved by the PBC. Prior to the matter being taken to the
Queensland Civil and Administrative Tribunal (QCAT) it is to be referred
back to Riverleigh Gardens Body Corporate as its residents are the most
affected, requesting that if Riverleigh Gardens Body Corporate Committee
wishes for a relaxation to leave the non-compliant fencing in its current
position, then a motion must be approved by ordinary resolution at a
general meeting of the Riverleigh Gardens Body Corporate. ---- The PBC
believes in the circumstances that a reasonable period in which to hold a
committee meeting to review the matter and if felt appropriate the calling
and holding of a general meeting can easily be achieved within 90 days.
The PBC therefore provides you with a 90 day period to achieve the above
noting that if confirmation of approval is not received by Riverleigh Gardens
Body Corporate within the specified time frame the matter will be referred to
QCAT for its determination.
-- 3 of 10 --
4
[14] On 15 August 2011 Riverleigh Gardens at its annual general meeting
resolved:
Moved that the residents of Riverleigh Gardens Body Corporate endorse a
minor relaxation of the development control by-laws to allow the existing
portion of masonry fence beyond the standard set-back to remain.
Riverleigh Gardens Body Corporate has no reason to not support the
principal body corporate to use its powers under Section 177 of the IRDA to
allow a minor relaxation of the DCBL.
[15] On 7 October 2011 a referee made an order under Part 5 of the Building
Units and Group Titles Act 1980 (Qld) that the resolution of the Riverleigh
Gardens Body Corporate was void and of no effect.
[16] On 18 November 2011 PBC commenced the primary proceeding under
the Integrated Resort Development Act 1987 (Qld) regarding the
contravention by the applicants of its development control by-laws. It
sought orders:
a) for relocation of the front masonry fence so that it was positioned in
accordance with the development approval;
b) authority to enter the applicant‟s property and complete the work at
the applicant‟s cost in the event the applicants did not comply with an
order to relocate the fence;
c) the applicants pay PBC‟s costs of and incidental to the application.
[17] The applicants opposed this application.
[18] On 6 March 2012 the Tribunal directed PBC file an agreed list of issues by
15 May 2012. On 17 May 2012 solicitors for PBC provided the Tribunal
with a list of issues agreed between the parties.
[19] On 18 May 2012 the Tribunal directed PBC give notice of the application,
the response, reply and list of issues to Riverleigh Gardens Body
Corporate.
[20] On 25 May 2012 the applicants adopted and relied upon the agreed
issues as contained in the list of issues as a suitable background to the
matter. They made submissions about the issues.
[21] On 8 June 2012 PBC filed its submissions in response to each of the
issues addressed by the applicants.
[22] On 10 August 2012 Riversleigh Gardens Body Corporate was joined as a
second respondent. Written submissions were filed by Riverleigh dated 14
August 2012. The application was to be determined on the papers.
[23] Following that further written submissions were filed by the applicants
dated 30 August 2012 and by PBC in response dated 7 September 2012.
[24] On 5 March 2013 the Tribunal determined the matter as set out above.
-- 4 of 10 --
5
[25] On 22 March 2013 PBC provided its submission on costs. It sought
indemnity costs, alternatively standard costs. It provided a chronology of
the proceeding before the Tribunal, commencing with the agreed list of
issues in agreement or dispute followed by the prolongation and
complication of the proceeding by the applicants. It submitted the
prolongation and complication only occurred because the applicants
engaged legal representatives resulting in a new set of submissions and
alleged that Riverleigh Gardens Body Corporate had approved the non-
compliance when it had not.
[26] On 25 March 2013 the applicants provided submissions to the effect that
an appropriate order was that each party to the proceeding bear their own
costs, or, alternatively, that the Tribunal only had jurisdiction to order they
pay PBC‟s application fee in the proceedings relying on r 85 of the
Queensland Civil and Administrative Tribunal Rules 2009 (Qld).
Costs in QCAT Proceedings
[27] The position is clear. Other than as provided under the QCAT Act or an
enabling act, each party to a proceeding must bear their own costs.2 The
QCAT Act provides that the Tribunal may order a party to pay all or a
stated part of another party‟s costs of a proceeding if it considers it is in
the interests of justice to do so.3 It sets out particular circumstances the
Tribunal may have regard to in considering whether the interests of justice
require a costs order. They include that the Tribunal may have regard to
anything else it considers relevant.4
[28] The discretion to award costs is constrained only by the legislative
presumption that in Tribunal proceedings each party meet their own costs
and the interests of justice. Alan Wilson J neatly summed it up when he
said:
the question that will usually arise in each case in which costs are sought is
whether the circumstances relevant to the discretion inherent in the phrase
”the interests of justice” point so compellingly to a costs award that they
overcome the strong contra-indication against cost orders in s 100.5
Discussion
The Primary Decision
[29] The essence of the decision may be stated briefly. The Tribunal found that
the proceeding before it was unnecessarily prolonged by the actions of the
applicants based on a misconceived interpretation of the letter of 7 June
2011. It concluded the history of the dispute revealed a wilful
determination of the part of the applicants not to comply with the
provisions of their development approval, that to continue with a case
2 QCAT Act, s 100.
3 Ibid, s 102(1).
4 Ibid, s 102(3)(a)-(f).
5 Ralacom Pty Ltd v Body Corporate for Paradise Island Apartments (No 2) [2010] QCAT
412 at [29].
-- 5 of 10 --
6
based on a “totally untenable interpretation of a letter from a person who
clearly did not have the authority to give the relief alleged was conduct
that unnecessarily disadvantaged the (respondent) by forcing it to incur
costs pointlessly”.
[30] It noted a submission by PBC in its costs submissions that both the factual
and legal issues were novel and complex. It later said it was satisfied the
matter was complex, highlighted because of the need to consider
arguments about the referee‟s decision that raised “principles of res
judicata and estoppel and the voluminous material used by (the
applicants) to challenge other alleged non-compliances within the resort”.
[31] It accepted the submission of the respondent that the relative strengths of
the claims of the parties was best demonstrated by the failure of the
applicants to achieve any findings in their favour.
[32] It recorded it was conscious of the applicants submission summarised in
paragraph 21 of its reasons that they were two individuals whereas the
respondent was a major body corporate. This was directed to the financial
circumstances of the parties. It noted there was no evidence about this,
simply the submission.
[33] It noted the applicants‟ submission that they understood and accepted the
primary decision but that they continued to assert that the letter of 7 June
2011 “was poorly drafted, ambiguous and misleading and had it not been
issued these proceedings would not have been necessary”. It found that
this claim was disingenuous.
[34] In declining to order the indemnity costs sought and instead fixing costs on
the standard basis, the Tribunal said “Mr and Mrs De Berry‟s initial
response and position were unsustainable. Their persistence with the
proceedings was unreasonable and irresponsible. As a result the Tribunal
finds it is in the interests of justice to award costs because their behaviour
qualifies as conduct warranting an order on the standard basis”.
Errors of Law and Inconsistencies
[1] The following general remark is apposite. It is not particularly helpful to
base submissions around selected passages extracted from the Tribunal‟s
reasons for its decision, which, taken alone, may be thought to source a
submission. The reasons must also be read as a whole. That will almost
inevitably add context and colour to select passages in the reasons.
Errors of Law
[2] The errors of law asserted focussed on ss 102(3)(a), 102(3)(b), 102(3)(c),
102(3)(e) and 102(3)(f) of the QCAT Act.
[35] As to s 102(3)(a), it was submitted that the applicants had not proceeded
in a way that unnecessarily disadvantaged the respondent. The Tribunal‟s
finding to the contrary, that the applicants prolonged the matter on a
-- 6 of 10 --
7
misconceived interpretation of the letter of 7 June 2011, one that was
totally untenable, thus continuing a case that had little or no hope of
success forcing the respondent to incur cost pointlessly was in error. That
was because the Tribunal found that its interpretation of the letter was the
“preferable interpretation”. As the applicants had contended in the primary
proceeding, there were other interpretations open, eg., the non-compliant
fence could remain provided Riverleigh Gardens Body Corporate
consented; they had reasonably believed from the content of the letter the
respondent had delegated its powers to Riverleigh Gardens Body
Corporate to authorise the non-compliant fence. These views were not
unreasonable in light of the fact that Riverleigh was a subsidiary of PBC.
The fact that the Tribunal preferred a different interpretation was not a
basis to conclude their interpretation was completely wrong, unreasonable
or untenable.
[36] This submission is not persuasive. In the primary proceeding the
applicants had advanced three interpretations of the letter each of which
advanced that which they wished to achieve. The interpretation the
Member found was the same as that submitted by PBC. That context
explains the use of the phrase “preferable interpretation”. The Tribunal
found the applicants‟ interpretation of the letter totally untenable, their
claim that the primary proceedings would not have been necessary but for
the 7 June 2011 letter being poorly drafted, ambiguous and misleading,
disingenuous and that the history of the dispute revealed a wilful
determination on their part not to comply with the development approval.
[37] As to s 102(3)(b) it was submitted the factual and legal issues were novel
and complex. The Tribunal had said the matter was complex but added
that was “highlighted by the need to consider arguments regarding the
earlier referee‟s decision that raised consideration of the principles of res
judicata and estoppel and the voluminous material used by the
(applicants) to challenge other alleged non-compliances within the resort”,
all matters introduced by the applicants.
[38] As to s 102(3)(c) the applicants‟ submission focussed on the Tribunal‟s
remark in its reasons: “the Tribunal accepts the submission of the
[respondent] that the relative strengths of the claims is best demonstrated
by the failure of [the applicants] to achieve any findings in their favour”. It
submitted that just because the applicants achieved no findings in their
favour was not a reason to award costs against it.
[39] As to this submission it may be remarked that what the Tribunal said is
only a part of the whole of its reasons. Its decision to award the costs was
not only based on this factor. A reading of the Tribunal‟s reasons makes it
clear, rather, its decision was based upon the applicants‟ stance in the
primary proceedings being misconceived and totally untenable; their
claims about the letter being without merit, their argument about the letter
being disingenuous; their case having little hope of success, and their
wilful determination not to comply with the development approval.
-- 7 of 10 --
8
[40] As to s 102(3)(e) the submission repeated similar submissions made to
the Tribunal in the costs proceedings, namely that the applicants were two
individuals with their own limited resources whereas the respondent was
the principal body corporate, one of the largest in Queensland. It therefore
had access to a greater pool of financial resources. This made it
unreasonable to require the applicants to pay its costs. It may be
remarked in passing that the financial resources of the body corporate is
that of its members, the property owners.
[41] It was not suggested here there is any evidence to support the
submission.
[42] The financial circumstances of the parties is one of the circumstances a
Tribunal may take into account in deciding whether and what order about
costs may be made. It may be added into the mix of circumstances before
a tribunal and any and what weight to be given to it, decided upon. The
Tribunal referred to the applicants‟ unsubstantiated submission about
relative financial worth in the process of looking at all the circumstances
relevant to the interests of justice.
[43] As to s 102(3)(f), the applicants submitted the Tribunal was in error in
“automatically” granting the parties leave to make submissions about
costs. Rather it was up to the parties to seek leave from the Tribunal. They
referred to a comment made in a decision by Charles Brabazon QC,6 “The
appellants should not be encouraged of allowed to make a submission for
further costs in its favour. Any order would cause additional expense and
delay --- the best course (of action) is one that brings litigation to an end.”
It submitted the Tribunal had gone against the intention of the QCAT Act
whereby each party bear their own costs and matters be dealt with quickly
and efficiently.
[44] It may be accepted that additional expense and delay in proceedings
should be avoided so far as reasonably and fairly possible. But the
submission overlooks the application which commenced the primary
proceeding applied for an order for costs along with the primary relief.
Having made orders about the primary relief it was necessary to deal with
the costs application one way or another. Here it was dealt with by giving
the parties leave to make submissions. That was entirely appropriate. A
costs order may be made if the interests of justice requires.
Inconsistencies
[45] It was submitted a number of inconsistencies occur in the Tribunal‟s
reasons for awarding costs. Five were set out. It was submitted these
demonstrated errors of fact which supported leave to appeal.
[46] The first focussed on paragraph 5 of the Tribunal‟s reasons where the
Tribunal said “subsequently the parties were granted leave to make
submissions regarding any application for costs”. I have already dealt with
6 Zachary Developments Pty Ltd v Turner & Anor [2012] QCATA 86.
-- 8 of 10 --
9
this in what I have said about the claimed errors of law. The submission is
misconceived. It overlooks the fact that the application which commenced
the primary proceeding sought both the primary relief granted by the
Tribunal and an order the applicants pay PBC‟s costs of the proceeding.
The Tribunal‟s order giving leave to the parties to make submissions about
costs is not shown to be incorrect.
[47] The second focussed on paragraph 22 of the reasons. I have already
dealt with this also in what I have said about the claimed errors of law.
When regard is had to the context surrounding the Tribunal‟s remarks
about being satisfied the matter was a complex matter and that its
interpretation of the letter of 7 June 2011 was the preferable interpretation,
no inconsistency arises from its conclusion about the disingenuous nature
of the applicants‟ claim that the letter was poorly drafted, ambiguous and
misleading and had it not been issued the proceedings would not have
been necessary.
[48] The third submission focussed on paragraph 23 of the Tribunal‟s reasons.
It contended it showed that the Tribunal regarded the applicant‟s
submissions about costs as limited to r 85 of the Queensland Civil and
Administrative Tribunal Rules 2009 (Qld). Examination of paragraph 23
and the reasons as a whole show that was not the case. Paragraph 23 of
the reasons simply set out the submission of the applicants that the
jurisdiction of the Tribunal to award costs was confined to r 85, a
submission rejected by the Tribunal. A reading of the whole of the reasons
reveals that was not the Tribunal‟s approach. The submission is
misconceived.
[49] The fourth and fifth claimed inconsistencies focussed on paragraphs 27
and 34 of the Tribunal‟s reasons where respectively, the Tribunal said “the
only basis that [the applicant] relied on to prolong this matter was a
misconceived interpretation of the letter dated 7 June 2011” and that the
applicant‟s “persistence with the proceedings was unreasonable and
irresponsible”.
[50] Once again the submission was that these remarks demonstrated
inconsistency with the Tribunal‟s remarks elsewhere in its reasons, that its
interpretation of the letter of 7 June 2011 was the “preferable
interpretation” and that it was “satisfied that this was a complex matter”.
[51] I have already dealt at some length with these passages elsewhere. It is
unnecessary to repeat what I have said. No inconsistency as claimed
arises. The submission is misconceived.
Decision
[52] The Tribunal‟s reasons make it plain it was conscious of the provisions of
the QCAT Act regarding costs. It will be apparent from what I have said
above that I do not think it is shown that the Tribunal‟s reasons for its
decision to award costs, nor its grant of leave to make submissions on
-- 9 of 10 --
10
costs expose any error of law. Nor am I persuaded the claimed
inconsistencies in those reasons exist or demonstrate factual errors.
[53] The Member who constituted the Tribunal in the costs proceeding was the
Member who constituted the Tribunal in the primary proceeding. He was
fully seized of the matter. There is nothing in his reasons or in the
submissions which show the discretion he had regarding cost miscarried.
There is no basis shown upon which to grant leave to appeal.
[54] Leave to appeal is refused.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2014/019