Bundaberg Regional Council v Lammi & Anor [2014] QPEC 52 [2015] QPELR 111
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Bundaberg Regional Council v Lammi & Anor [2014] QPEC
52
PARTIES: BUNDABERG REGIONAL COUNCIL
(applicant)
v
KENNETH AARRE LAMMI
(first respondent)
and
SUE-ELLEN LAMMI
(second respondent)
FILE NO/S: 2350/14
DIVISION: Planning & Environment
PROCEEDING: Application
ORIGINATING
COURT: Planning & Environment Court at Brisbane
DELIVERED ON: 5 September 2014
DELIVERED AT: Brisbane
HEARING DATE: 26 August 2014
JUDGE: Horneman-Wren SC DCJ
ORDER: 1. The respondents are jointly fined $5,000 for contempt
of the Order of his Honour Judge Andrews SC made
27 November 2013 in Planning and Environment
Court proceedings No. 2879 of 2013.
2. The fine is to be paid within three (3) months of this
order being made.
3. Paragraphs 2, 3, 4, 5 and 6 of the Order of his Honour
Judge Andrews SC made 27 November 2013 in
Planning and Environment Court proceedings No.
2879 of 2013 are vacated.
4. In lieu of the vacated paragraphs;
The first respondent by himself, his servants or agents
must:
a. undertake the relevant steps to refer the building
-- 1 of 16 --
2
development application to the applicant by 17
September 2014;
b. use his best endeavours to:
i. pursue the building development application
expeditiously; and
ii. obtain an effective building development
approval by 17 October 2014 (“development
permit for building works”);
c. within three months of obtaining the development
permit for building works, and by no later than
17 January 2015, complete the building works for
the exterior of the relocated buildings approved
by the development permit for building works;
and
d. within six months of obtaining the development
permit for building works, and by no later than
30 April 2015 complete the balance of the
building works for the relocated buildings and
obtain the final certificate of completion.
5. The respondents are to pay the applicant’s costs of the
application on the standard basis.
CATCHWORDS: PROCEDURE – CONTEMPT, ATTACHMENT AND
SEQUESTRATION – CONTEMPT - WHAT
CONSTITUTES – DISOBEDIENCE OF ORDERS OF
COURT – OTHER CASES – where an enforcement order
was made by the his Honour Judge Andrews SC in the
Planning & Environment Court on 17 November 2013 –
where the order was made by consent – where the
enforcement order required the respondents to take action
regrading their property – where the action was not taken –
whether the respondents are in contempt of the enforcement
order
PROCEDURE – CONTEMPT, ATTACHMENT AND
SEQUESTRATION – POWER OF COURT TO PUNISH
FOR CONTEMPT – OTHER COURTS – OTHER CASES –
where the respondents admit they are in contempt of a court
order – where the respondents have taken steps in attempting
to follow the enforcement order – where the applicant
submits that a sentence ought be imposed – whether
imprisonment is the appropriate remedy for the respondents’
contempt
PROCEDURE – JUDGMENTS AND ORDERS –
AMENDING, VARYING AND SETTING ASIDE –
OTHER CASES – where the applicant seeks a further
enforcement order be made – where the applicant does not
seek to vary or set aside the previous order – where the
-- 2 of 16 --
3
respondents would still be in contempt of the previous order –
whether the previous order should be varied or set aside –
where the second respondent is no longer an owner of the
property – whether a further order can be made against the
second respondent
District Court of Queensland Act 1967 (Qld), s 129(2)
Sustainable Planning Act 2009 (Qld), s 439(1), s 439(2), s
439(3), s 606
Uniform Civil Procedure Rules 1999 (Qld), r 926(4), r 930
AMIEU v Mudginberri Station Pty Ltd (1986) 161 CLR 98
Attorney General v Times News Papers Ltd [1974] AC 273
Booth v Frippery Pty Ltd & Ors [2008] QPEC 122
Booth v Yardley & Anor [2008] QPEC 100
Brisbane City Council v Bowman [2013] QPEC 62
Dubois v Rockhampton Regional Council [2014] QCA 215
Formal Wear Express Franchising Pty Ltd v Roach [2004]
QCA 339
Lade & Co Pty Ltd v Black [2006] 2 Qd R 531
Rockhampton Regional Council v Dubois [2014] QPEC 13
Sunshine Coast Regional Council v MC Property Investments
Pty Ltd (No 3) [2012] QPEC 12
COUNSEL: Mr M A Williamson for the applicant
Mr K A Lammi self representative for the first and second
respondents
SOLICITORS: Connor O’Meara for the applicant
The Proceedings
[1] The respondents, Mr and Mrs Lammi, are in the business of relocating and
demolishing homes. In or about 2008 or early 2009 they relocated two quite
historical buildings on to land situated at Bonna Road, Bundaberg with a view to
developing them into their dream home. The relocation of the buildings was
authorised by a development approval which had been granted on 31 March 2008.
The approval lapsed. An enforcement order was made. It is said that the
respondents are in contempt of the enforcement order. The Council makes
application for an order committing them, or otherwise dealing with them, for their
contempt.
-- 3 of 16 --
4
Background – The November Enforcement Order
[2] The development application had been made by “Lammi Bros”.1 The approval,
seemingly, was given to “Lammi Bros House Removals”.2 The only owner of the
property identified in the development application was the second respondent, Mrs
Lammi.3 Notwithstanding the identification of Mrs Lammi only as the owner of the
property at the time of the development application, Mr Lammi deposes to the land
having been owned at that time jointly by he and his wife.4 The land was
transferred into Mr Lammi’s name solely in December 2008.5
[3] The development approval lapsed. The Council brought proceedings for an
enforcement order against both Mr and Mrs Lammi.6 On 27 November 2013 his
Honour Judge Andrews SC, having been satisfied that a development offence had
been committed, namely the carrying out of assessable development not authorised
by any effective development approval, made an enforcement order pursuant to s
604 of the Sustainable Planning Act 2009 (Qld) (‘SPA’). The enforcement order
was made by consent. Mr and Mrs Lammi had been represented by Lawyers in
those proceedings. The order of his Honour Judge Andrews SC was:
“It is ordered pursuant to section 604 of the Sustainable Planning Act
2009 that:
1. The First and Second Respondents by themselves, their
servants or agents demolish all building works associated
with the Relocated Buildings and remove from the Land all
associated building materials, by 6 December 2013.
2. In the alternative to paragraph 1, the First and Second
Respondents, by themselves, their servants or agents are to:
(a) lodge a properly made building development
application to a private building certifier for the
building works by 29 November 2013;
(b) undertake the relevant steps to refer the building
development application to the applicant by 6
December 2013;
(c) use their best endeavours to pursue the building
development application expeditiously; and
1 Development application, Part A, at p 15 of exhibit CJL-1 to the affidavit of Cara Jade Lacey filed
15 August 2014.
2 Development application decision notice approval, 31 March 2008 at pp 10-12 of exhibit CJL-1 to
Ms Lacey’s affidavit.
3 Development application, Part B, Table F at p 54 to exhibit CJL-1 to Ms Lacey’s affidavit.
4 Affidavit of Kenneth Aarre Lammi filed 4 August 2014, para 3.
5 Ibid at para 10.
6 Planning and Environment Court proceedings No. 2879/13.
-- 4 of 16 --
5
(d) obtain an effective building development approval
by 10 January 2014 (‘Development Permit for
Building Works’).
3. Within 3 months of obtaining the Development Permit for
Building Works, and by no later than 10 April 2014, the
First and Second Respondents are to complete the building
works for the exterior of the Relocated Buildings approved
by the Development Permit for Building Works.
4. Within 6 months of obtaining the Development Permit for
Building Works, and by no later than 10 July 2014, the First
and Second Respondents are to complete the building works
for the interior of the Relocated Buildings approved by the
Development Permit for Building Works.
…
6. In the event that the Development Permit for Building
Works is not obtained by 10 January 2014, the First and
Second Respondents by themselves, their servants or agents
demolish all building works associated with the Relocated
Buildings and remove from the Land all associated building
materials by 10 April 2014.”
The Contempt
[4] The Council alleges that the respondents have wholly failed to comply with the
November order. This is not contested by the respondents. In his affidavit, said to
have been made on behalf of both himself and Mrs Lammi,7 Mr Lammi deposes to
having endeavoured to engage a private certifier. He deposes to his difficulties in
doing so. In a letter to the Council’s solicitors from their, then, solicitors on 13
January 2014,8 it had been stated that “our client has appointed an appropriately
qualified building certifier to lodge a building development application and to
advance the necessary building approval”.
[5] That letter was inaccurate. It is clear that no certifier had by then been appointed.
[6] Mr Lammi acknowledges that he caused the letter to be written. He says that he
believed that he had, at that stage, engaged a firm of certifiers. He says that he had
emailed them the relevant documents. After returning from a period of working
outside Bundaberg he says he followed them up. He says that they advised him that
7 Rule 926(4) of the UCPR provides that in an application for punishment for contempt an affidavit in
support of or opposing the application must not contain evidence which the person making it could
not give if giving evidence orally. However, the Council expressly waived the objection to any
inadmissible evidence.
8 Exhibit ACP-3 to the affidavit of Andrew Charles Perry filed 23 July 2014.
-- 5 of 16 --
6
they had not received the emailed documents and, further, that they were not able to
or interested in undertaking the certification process. Mr Lammi does not depose to
any times at which these various events were said to have occurred. He has not
placed into evidence any of the relevant email communications.9 Nonetheless, he
was not cross-examined on any of his evidence. The Council had accepted all of the
factual matters deposed to by Mr Lammi, including the listed difficulties he and his
wife face with compliance with the development approval in the past and, more
recently, with the court’s order.
[7] Mr Lammi deposes to his and his wife’s great regret that they had “been unable to
comply with the agreement reached with Council in November 2013 as to a
timetable for the final approval of the relocated buildings and the necessity for an
application by the Council generally”.10
[8] He concludes his affidavit by saying:
“The above being said, we indicate that with an appropriate
extension of time to move the matter forward along the lines as
originally agreed in November 2013 we will be in a position to
obtain the necessary approval and final certification of the building
works to bring this matter to a conclusion. This will, we anticipate,
take around 6 or 7 months from the uptake of the matter by the
certifier and provision of all information to him.”11
[9] From these statements by Mr Lammi it is apparent, beyond reasonable doubt, that
he and Mrs Lammi have contravened the enforcement order made on 27 November
2013. Section 439(3) of the SPA provides that if a person at any time contravenes
an order of the court, the person is also taken to be in contempt of the court.
Independently of the operation of s 439(3), the statements of Mr Lammi, together
with the evidence of Mr Perry that apart from the solicitor’s letter of 13 January
2014 the Council has received nothing by way of correspondence or documents
from which any intention to comply with the order could be inferred, also
establishes beyond reasonable doubt that the respondents are in contempt of the
court’s order; there have been deliberate omissions in disobedience of that order.12
9 Although Mr Lammi appeared himself at the hearing of the contempt proceedings, his affidavit was
prepared and filed by his solicitors.
10 Mr Lammi’s affidavit at para 27.
11 Ibid at para 29.
12 AMIEU v Mudginberri Station Pty Ltd (1986) 161 CLR 98 at 113 per Gibbs CJ, Mason, Wilson and
Deane JJ; Lade & Co Pty Ltd v Black [2006] 2 Qd R 531 at [65] per Keane JA.
-- 6 of 16 --
7
Appropriate Remedy for the Contempt
[10] Contempt having been established, the court has the same powers to punish for that
contempt as has the District Court for a contempt of that court.13 Section 129 of the
District Court of Queensland Act 1967 (Qld) applies.14 Section 129(2) confers upon
the District Court the same powers to punish for contempt as has the Supreme
Court. By r 930(2) of the Uniform Civil Procedure Rules 1999 (Qld) (‘UCPR’) the
court may punish an individual who is in contempt by making an order that may be
made under the Penalties and Sentences Act 1992 (Qld). However, in punishing for
contempt the court is exercising its inherent powers. The reference to the Penalties
and Sentences Act 1992 (Qld) in r 930 of the UCPR does not confine the court’s
powers to make only those orders contained in the Act.15
[11] At the outset of the contempt hearing the Council put forward a draft order. The
draft order sought that for their contempt each of the respondents be sentenced to
prison for a period of six weeks, but that those sentences be wholly suspended. The
draft order did not provide for any operational period for which the sentences would
be suspended. In the absence of any operational period being state in the order, the
reasonable construction would be that the suspension was to last until the expiration
of the six week term of the sentence, not that it would be suspended indefinitely.16 It
was clearly not the intention of the Council that the sentence would only be
suspended for six weeks.
[12] In the course of the hearing, when the absence of any operational period was raised,
the Council proposed that “the sentence be wholly suspended for as long as… the
first respondent complies with paragraph 3 of this order”. This would be an
appropriate way in which to frame the operational period of the suspension. As was
recently said by Muir JA in the Court of Appeal, “[w]here the Court imposes a
suspended sentence for contempt, it should fashion the operational period by
reference to the conduct or orders in respect of which the penalty is being
imposed.”17
13 Section 439(1) SPA.
14 Section 439(2) SPA.
15 Dubois v Rockhampton Regional Council [2014] QCA 215 at [73] – [74] per Muir JA.
16 Ibid at [87].
17 Ibid at [75].
-- 7 of 16 --
8
[13] The reference to paragraph 3 of the order is a reference to further orders which the
Council seeks which would require future compliance with the steps set out in
paragraphs 2 to 4 of the November order, but in extended time periods.
[14] The Council submits that the court is able, in these proceedings, to make such
orders as a new enforcement order pursuant to s 604 of the SPA. It submits that the
court may do so to remedy the same development offence as was found by Judge
Andrews SC to have been committed and which supported the November 2013
enforcement order. The Council submits that the court’s jurisdiction to make a
further enforcement order is invoked by paragraph 3 of the relief sought by it in the
originating application commencing these proceedings in which the Council sought
“such further or other orders as the court deems appropriate”. In the alternative, and
in the event that the court’s jurisdiction was not invoked by that part of the
originating application, it made an instanter application for such relief.
[15] Council expressly stated that it was not seeking a variation of the November order.
It intends that there would be two orders. The first, so it seems, would be one in
respect of which there would be a continuing breach, and thus contempt. The
second would be able to be observed in prospect. A breach of the second order
would activate the first respondent, Mr Lammi, serving the suspended sentence
imposed for his contempt of the November order. I say “Mr Lammi” because the
Council now concedes that, subsequent to the making of the November order, there
is no evidence to suggest that Mrs Lammi had or has any particular control of the
business which was named as the applicant in the development application, and that
her circumstances appear to be different to those of Mr Lammi as to the conduct and
the ability to comply with the order. The concession is well made.
[16] In my view, if a further enforcement order is to be made, it should either be in
variation of, or substitution for, the order made on 27 November 2013. There
should not, in my view, be two orders in place, the latter inconsistent with the
former in its requirements for the performance of the same steps. If the Council is
willing to permit Mr Lammi to purge his contempt of the November order by taking
those steps required, but according to a different timetable a failure to adhere to
which may result in him being in contempt of the latter order, then, in my opinion, it
-- 8 of 16 --
9
would not be appropriate to maintain the November order such that Mr Lammi (and
indeed Mrs Lammi) will remain in continued contempt of it.
[17] Learned counsel for the Council could not in the course of the hearing refer me to
any decision of this court in which the course proposed, of their being two extant
inconsistent enforcement orders, was followed. After the hearing, and with the
court’s leave, counsel referred me to the decision of his Honour Judge Brabazon QC
in Booth v Frippery Pty Ltd & Ors.18 That case concerned an order of the court
which had required the dismantling of a grid of electrical wires which had been
erected by the respondents to protect their lychee farm from flying foxes. The
respondents had not dismantled the grid and were found to be in contempt of court.
The respondents were jointly fined $5,000. Counsel for the respondents had sought
an order suspending the operation of the order of which they had been found to be
in contempt, effectively to allow them a period during which to purge their
contempt by dismantling the grid and during which period they would not be in
continued contempt. That was opposed by the Council which contended that whilst
the contempt would be continuing, if any further proceedings to punish for the
contempt were brought it would be a matter of discretion whether the court would
do so. In the event, the court left the order as previously made.
[18] Booth v Frippery Pty Ltd & Ors provides no support for the course proposed by the
Council of the court now making a further enforcement order whilst leaving the
original order in place. Whilst in Booth v Frippery the court did leave the order in
place, and thus the respondents in continuing contempt notwithstanding the
expectation that they would act to comply and purge their contempt, no further
order permitting them to take the same steps, but under a different timetable, was
made. The issue of there being inconsistent orders did not arise.
[19] The purpose of a court imposing a sanction upon persons in contempt of its orders is
twofold. It is both to punish for the past failure to comply, and to coerce future
compliance.19 It is apparent that, with the making of a further order, the Council
would have no interest in punishing the respondents for the continuing breach of the
November order. Nor is it interested in enforcing that order as opposed to the
18 [2008] QPEC 122.
19 AMIEU v Mudginberri Station Pty Ltd (1986) supra.
-- 9 of 16 --
10
further order. Lord Diplock observed in the context of discussing the element of
public policy in punishing contempt:
“… but no sufficient interest is served by punishing the offender if
the only person for whose benefit the order was made chooses not to
insist upon its enforcement.”20
[20] As there is apparently no longer any interest in enforcing the November order in its
terms, I can see no point in it remaining extant with the consequence of the
respondents continuing to be in contempt.
[21] Booth v Yardley & Anor21 was another case concerning the erection of, and failure
to dismantle, grids for the protection of fruit crops from flying foxes. The court had
ordered that the grids be dismantled within three months. They had not been. The
power to the grids had been disconnected. Contempt proceedings were brought.
The respondents were found to be in contempt, however, it was found that it may
have been a product of a misunderstanding as to the meaning and effect of the order.
Such misunderstanding may have been due to advice the respondents had been
given.22 A further order was made, in quite specific prescriptive terms, requiring
the Yardleys to dismantle the three grids constructed on their land by pulling down
and taking apart the horizontal wires and metal poles constituting the electric grids.
They were given a further period of about two moths within which to do that. His
Honour Judge Wilson SC, as his Honour then was, did not vary the earlier order.
He expressly noted that there had been no request to do so.23 Whilst that resulted in
there being two orders in place, it is quite apparent that what was sought to be
coerced was the enforcement of the earlier order. The second order was made in the
terms in which it was because his Honour considered that:
“The proper remedy in all the circumstances is to confirm, to the
respondents, the meaning and effect of the order while minimising
the likelihood of hardship by allowing the opportunity to affect
dismantling in the least expensive way, over sufficient time.”24
[22] His Honour was of the view that the respondents “now understand, I am sure, the
need for compliance and the way in which that is to be achieved”.
20 Attorney General v Times News Papers Ltd [1974] AC 273 at 308.
21 [2008] QPEC 100.
22 Booth v Yardley & Anor [2008] QPEC 5.
23 Ibid at [16].
24 Ibid at [21].
-- 10 of 16 --
11
[23] Those matters distinguish Booth v Yardley from this case.
[24] Whilst Mr Lammi has not consented to a further order being made, it is apparent
from the extract from his affidavit which I have set out above that a further period
of time within which to obtain development approval and perform the work is what
he desires. In the hearing, the only aspect of the further order proposed by the
Council to which Mr Lammi expressed any opposition was the requirement to
complete the balance of the building work within six months of obtaining the
development permit, and in any event by no later than 10 April 2015. He would
prefer a further two months to provide a “buffer” against such contingencies as the
unavailability of tradesman.
[25] In my opinion, if an accommodation is to be given to Mr Lammi to allow him to
complete the work, then the time periods proposed by the Council are appropriate. I
note also that those time periods are consistent with those set out in Mr Lammi’s
affidavit.
[26] I am satisfied that the court has power, under s 606 of the SPA to vary the order
previously made in November 2013. Whilst neither party has expressly sought such
a variation, and in the case the Council it is expressly not sought, such a course is
consistent with that which is sought by both parties; an extension of timeframes
within which to take the steps necessary for completion of the work. The
timeframes will essentially be those set out in the draft order proposed by the
Council although some dates have been changed slightly.
Is a sentence of imprisonment or a fine appropriate?
[27] In my opinion, this is not an appropriate case in which to impose a prison sentence
as punishment for contempt.
[28] In Rockhampton Regional Council v Dubois25 his Honour Judge Searles sentenced a
contemnor to three months imprisonment to be suspended after one month. That
matter had a considerably worse history than this matter. There had been an order
made in 1996. In 1997 Mr Dubois was convicted of contempt for having
-- 11 of 16 --
12
contravened that order. He was fined $1,000 and ordered to pay costs of $3,049.
Another order was made in 1999. In 2001 Mr Dubois was convicted for contempt
of the 1999 order. He was fined $1,500. Mr Dubois continued to use the land in
contravention of the 1999 order. In concluding that a sentence of imprisonment was
appropriate, his Honour observed that the 1999 order had been made almost 15
years earlier and that prior to that Mr Dubois had known that there were restrictions
on his rights to use the land under the 1996 order.26 His Honour concluded that a
further fine of $5,000 or more “would do little, to discourage the Respondent from
continuing his anarchistic conduct in ignoring the 1999 Order”,27 and that any
monetary penalty would not deter him from future similar conduct.28
[29] The conduct of the respondents does not approach that of Mr Dubois. Nor has the
stage been reached where a monetary penalty would not be a deterrent against
further non-compliance.
[30] In Brisbane City Council v Bowman29 the respondent was in contempt of several
orders made by consent on 10 December 2012. Because the parties jointly proposed
a sanction to the court the circumstances which gave rise to the enforcement order
do not appear in the court’s reasons in any detail. It is apparent, however, that the
respondent had been using premises and land at Bald Hills for industry which was
not supported by development approval. In observing that “the court ought to insist
that its orders be respected and visit consequences that may need to be harsh on
those who fail to comply” his Honour Judge Robin QC noted that it was not the first
occasion on which the respondent had had difficulty, although not suggesting that
he had ever been previously in contempt. In earlier proceedings in 2006 Mr
Bowman had been convicted of three offences against the Integrated Planning Act
1997 (Qld).30 It is apparent from the decision in those proceedings that Mr
Bowman had been using the Bald Hills premises for the purposes of conducting
extractive industry unlawfully and without development approval. Again, I am of
the view that the conduct of Mr Bowman was worse than that here.
25 [2014] QPEC 13. The sentence was upheld in Dubois v Rockhampton Regional Council [2014] QCA
215 (29 August 2014).
26 Ibid at [69].
27 Ibid at [71].
28 Ibid at [72].
29 [2013] QPEC 62 (16 September 2013).
30 Bowman v Brown [2004] QDC 006.
-- 12 of 16 --
13
[31] In Sunshine Coast Regional Council v MC Property Investments Pty Ltd (No. 3)31,
the respondent was in contempt of an order made by the court in November 2011
requiring it to pay $71,959.65 to the Council within 28 days. By the time the
contempt proceedings were heard on 1 March 2012 the respondent had separately
applied for a variation of the order. That application had been compromised by a
deed which provided for the future payment of the sum by instalments. Thus, the
contempt had been purged. His Honour Judge Robertson formally varied the earlier
order to reflect the compromise (a course consistent with that which I propose to
take in this case) and fined the respondent $1,000. The court allowed two months in
which to pay the fine.
[32] I have already referred to Booth v Yardley. The benefit of the doubt given to Mr
and Mrs Yardley that may they have misunderstood what was required to dismantle
the electrical grid, and the opportunity to comply by doing the particular things
spelled out in the second order of Judge Wilson SC were, in the end, not availed of
by them. They failed to dismantle the grid and came back before his Honour in
November 2008 in further contempt proceedings.32 His Honour was of the view
that the contempt did not require the court to contemplate a very large fine.33 He
considered that the point had not been reached where imprisonment was appropriate
because a fine would likely be futile.34 On that basis he distinguished Formal Wear
Express Franchising Pty Ltd v Roach35 in which the defendant had repeatedly
breached an undertaking to the District Court, which had been incorporated into an
order, not to conduct a formal menswear hire business. The defendant had been
fined $3,000 in one contempt proceedings and was sentenced to serve concurrent
sentences of six months imprisonment for three separate acts of contempt in
subsequent proceedings. On appeal, the sentences were reduced to three months
each to be served concurrently. His Honour imposed a fine of $5,000 payable
within six months.
[33] In my opinion, this is not a case in which the contempt of the respondents is such as
to make sentencing them to any term of imprisonment appropriate. In the case of
31 [2012] QPEC 12.
32 [2008] QPEC 100.
33 Ibid at [17].
34 Ibid at [19] – [20].
35 [2004] QCA 339.
-- 13 of 16 --
14
Mrs Lammi, the Council no longer seeks her imprisonment because it now
concedes, in respect of the period since the making of the order, that there is not any
evidence to suggest that she had or has any particular ability to ensure compliance.
On that basis, the Council fairly places her in a different category to Mr Lammi.
Abandoning its case for her imprisonment was entirely appropriate. It having been
effectively conceded that she was not in a position to ensure compliance with the
order, it would be entirely inappropriate that she be sentenced to imprisonment for
failing to do that which she could not. The suspension of any such sentence would
also seem entirely illusory. Whether she served the sentence would not be in her
hands, but in those of Mr Lammi as the person who could ensure future compliance.
[34] As for Mr Lammi, he did not seek to persuade me that a fine would be a more
appropriate remedy than a sentence of imprisonment. However, it was readily
apparent that he did not do so because he would, as he said, prefer to have the
money available to finish the project.36 It was only in the context of a discussion
about the recording of a conviction if there were sentences imposed that Mr Lammi
expressed any preference for a fine. But then it was dependent upon the extent of
the fine, although no evidence was placed before the court as to capacity, or
incapacity, to pay any fine imposed, other than some generalised evidence about the
difficult economic circumstances faced by the business in the past few years.
[35] It was tolerably clear that Mr Lammi, who represented himself and his wife, came
to the proceedings without any real understanding of their serious nature. It seems
that Mr Lammi had little understanding of the true nature of the order made in
November 2013. He seems to have considered it to be little more than an agreement
reached with the Council that events occur as specified, rather than an order of the
court that those events did occur; and punishable for contempt if they did not. The
difficulties faced by self represented persons in contempt proceedings have been
commented upon by others.37 The absence of any meaningful evidence about
capacity to pay any fine is, no doubt, a product of those difficulties.
36 Transcript p 28, l 25.
37 See Robin QC DCJ, Brisbane City Council v Bowman, supra and referring to Brisbane City Council
v Windshuttel [2011] QPEC 70, [2010] QPEC 106 and [2011] QPEC 89.
-- 14 of 16 --
15
[36] It is to be borne in mind that in imposing a remedy for contempt what is required is
that it be effective, no more but no less.38 In my view, a fine of $5,000 is
appropriate in the circumstances. It should be imposed upon both Mr and Mrs
Lammi. Whilst there is a concession as to Mrs Lammi’s lack of control, she
consented to the order being made against her. There is no evidence that she took
any steps to have Mr Lammi as the person who could ensure compliance, do so. In
fact, the admissions made by Mr Lammi on her behalf establish the contrary.
[37] In the absence of any evidence about capacity, three months seems a reasonable
period to allow for the payment of the fine.
Variation of the November Order
[38] As indicated earlier in these reasons, there should be a variation of the November
order. Exhibit 1 establishes that on 25 August 2014 a private certifier was engaged
as the building certifier for the project. Compliance with the substantive
requirement of paragraph 2(a) of the November order has thus been affected.
[39] Paragraphs 2, 3, 4, 5 and 6 of the November order should be vacated. In lieu of the
vacated paragraph the following order should be substituted.
[40] The first respondent by himself, his servants or agents must:
(a) undertake the relevant steps to refer the building development
application to the applicant by 17 September 2014;
(b) use his best endeavours to:
(i) pursue the building development application expeditiously;
and
(ii) obtain an effective building development approval by 17
October 2014 (“development permit for building works”);
(c) within three months of obtaining the development permit for
building works, and by no later than 17 January 2015, complete the
building works for the exterior of the relocated buildings approved
by the development permit for building works; and
38 AMIEU v Mudginberri Station Pty Ltd (1986) supra at 115.
-- 15 of 16 --
16
(d) within six months of obtaining the development permit for building
works, and by no later than 30 April 2015 complete the balance of
the building works for the relocated buildings and obtain the final
certificate of completion.
[41] The Council seeks its costs. It has established contempt against the respondents.
The respondents have admitted their guilt and sought the indulgence of having a
further period within which to complete the building works. It is appropriate that
the Council should have its costs on the standard basis.
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2014/052