Blackwater Venture Pty Ltd v Mackay & Whitsunday Building Certification Pty Ltd [2014] QPEC 28
-1-
[2014] QPEC 28
PLANNING AND ENVIRONMENT COURT
JUDGE R S JONES
P & E No. 580 of 2014
BLACKWATER VENTURE PROPRIETARY
LIMITED Appellant
and
MACKAY & WHITSUNDAY BUILDING
CERTIFICATION PROPRIETARY LIMITED Respondent
BRISBANE
22 MAY 2014
EX TEMPORE ORDER
-- 1 of 4 --
__________________________________________________________________________________
-2-
HIS HONOUR: I will now deal with the question of costs. I have already made
orders dealing with the substantive matters raised in the appeal and as I noted then
those orders were not opposed by the respondent. I’d not go so far as to say that they
were orders made by consent but there was certainly no opposition to those orders
being made. That then left for resolution the question of costs. The appellant seeks 5
its costs of the appeal including those costs associated with the adjournment on 16
May 2014. The respondent in the proceedings, Mackay and Whitsunday Building
Certification Proprietary Limited, is a building certifier. Mr Reck is the managing
director of the respondent company.
10
Mr Reck was put in an unfortunate situation in that on 10 January 2014 the
Queensland Building and Construction Commission issued what is described as an
information notice pursuant to section 204 of the Building Act 1975 which relevantly
referred to an audit that had been carried out on the respondent company. Following
a review of that audit, the Commission decided that the respondent had engaged in 15
unsatisfactory conduct and as a consequence then required the respondent to carry
out a number of steps including the issuing of an enforcement notice.
Acting no doubt under the implied threat contained in that notice given by the
Commission, the respondent issued what has been referred to as the first enforcement 20
notice and, as I understand things, once a number of defects were pointed out in
respect of the first enforcement notice, a second enforcement notice, which
materially covered the same issues, was issued.
The matter came before me on 16 May 2014. On that date I adjourned proceedings 25
but made a number of orders including setting aside the first enforcement notice and
also dealing with questions of misnomers as to the correct parties. Those matters
were able to be dealt with in an efficient way and with, really, the respondent
conceding that the first enforcement notice ought to be set aside. As Mr O’Brien
pointed it out was, in effect, hopelessly defective. 30
Prior to that date, on 1 May 2014, the respondent wrote via its lawyers, Barron &
Allen Solicitors to the Commissioner pointing out a number of matters and, in
particular, drawing to the Commissioner’s attention the fact that there was a
proposed settlement in the wind which would, if finalised, as I read the letter, would 35
allow the respondent an opportunity to:
Walk away from both the proceedings as well as any wider dispute.
Quite unhelpfully, on 20 May 2014, the Commissioner wrote back to the 40
respondent’s solicitors relevantly stating:
The Commission has given due consideration to the matter and is of the view
that the building work carried out at 30 Byron Street, Mackay is non-compliant
with the Building Code of Australia for the reasons provided in the 45
Commission’s information notice dated 20 December 2013. If the said
enforcement notice for 30 Byron Street, Mackay is set aside by agreement
-- 2 of 4 --
__________________________________________________________________________________
- 3 -
and/or consent of the court, the Commission would require in writing from
Mr Reck demonstration of compliance with the information notice dated 20
December 2013, in particular items 3(a) and (b). Also, please provide written
evidence of notification to the local authority and any response by them.
5
The 3(a) and 3(b) referred to were set out in the notice of 10 January 2014 which
required the respondent to take certain steps including the issuing of an enforcement
notice. As I said I think at the outset, I have sympathy for the position of the
respondent. He found himself between a rock and a hard place. It appears
immediately clear to me that the Commissioner was wrong in his determination of 10
the alleged breaches of the relevant code. Section 37(1)(d) of the Building Act 1975
clearly applied.
Nonetheless, as I said, the attitude of the Commissioner placed the respondent in an
extremely difficult place. However, that said, as Mr O’Brien pointed out, the making 15
of cost orders is not to punish the unsuccessful party; it is, in fact, to indemnify the
successful party in respect of its costs or at least part of its costs in having to
successfully prosecute a proceeding. In this case, indemnity costs are not being
sought, quite properly, in my view, as it could not be said that the respondent has
acted in a vexatious or frivolous or other way which might enliven the power of the 20
court to order indemnity cost. However, it is sufficiently clearly to me that the
appellant has suffered significant legal costs. However, and I think, to an extent, Mr
O’Brien conceded that, at least to an extent, the respondent was entitled to some
sympathy up until 18 May 2014, but, thereafter, any such sympathy dissipated, or
any such reason for sympathy no longer existed. 25
In respect of the costs of the adjournment, as I have said earlier, the matters raised
there were able to be dealt with expeditiously, including dealing with the first
enforcement order and the misnomer of the parties. The misnomer point was a
matter which required rectification on the part of the appellant. On balance, I have 30
formed the view that it would be appropriate to order each party to bear their own
costs of the adjournment. However, as I have said, it is clear that the appellant was
required to prosecute its appeal. The respondent relied particularly on provisions of
section 457 of the Sustainable Planning Act 2009 as amended and, in particular,
argued that it could not be said that the respondent had acted in any inappropriate or 35
acted for an improper purposes. I agree. However, that is only one of the matters
addressed under section 457. Clearly, the relative success of the parties is one of the
matters to be brought into account under subsection 2 and it is also clear that the
matters set out in subsection 2 are only indicative of the matters that the court can
take into account. Here, the appellant has been entirely successful. There are no 40
public interest issues involved, in my view, which would deter or prevent the making
of any cost orders.
Reliance was also placed on subsection 14. It is true, as Mr O’Brien pointed out, that
the respondent here was not permitted to withdraw from the appeal. That had to be 45
so if for no other reason than allow this cost argument to be deal with. That said, as I
indicated at the outset, the respondent’s approach allowed this matter to be dealt with
in the space of an hour or so. On balance, I have reached the conclusion that the
appellant is entitled to an order for a costs order; such costs to be the costs incurred
by the appellant in the prosecution of the appeal from 16 May 2014 through to 50
-- 3 of 4 --
__________________________________________________________________________________
- 4 -
today’s date, 22 May 2014. However, I further order that the costs of counsel and
instructing solicitors be limited to one half of today. If the costs are unable to be
agreed, then to be assessed.
5
______________________
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2014/028