Cidneo Pty Ltd v Chief Executive, Department of Transport and Main Roads [2014] QLAC 3 (2014) 35 QLCR 247; 201 LGERA 395
LAND APPEAL COURT OF QUEENSLAND
CITATION: Cidneo Pty Ltd v Chief Executive, Department of Transport
and Main Roads [2014] QLAC 3
PARTIES: Cidneo Pty Ltd
ACN 105 454 064
(appellant)
v
Chief Executive, Department of Transport and Main
Roads
(respondent)
FILE NO: LAC006–13
Land Court File No: AQL325-10
DIVISION: Land Appeal Court of Queensland
PROCEEDING: Appeal from the Land Court of Queensland
ORIGINATING
COURT: Land Court at Brisbane
DELIVERED ON: 6 June 2014
DELIVERED AT: Brisbane
HEARING DATE: 25 – 26 November 2013
THE COURT: Peter Lyons J
CAC MacDonald, President of the Land Court
WA Isdale, Member of the Land Court
CATCHWORDS: REAL PROPERTY – COMPULSORY ACQUISITION OF
LAND – COMPENSATION – ASSESSMENT –
GENERALLY – where the appellant owned a parcel of land,
part of which was resumed by the respondent in order to
upgrade the Ipswich Motorway – where the compensation
was determined by the before and after method and use of
hypothetical cash flows – where the method required
assumptions about future contributions for road works –
where the appellants submit that the contributions constituted
injurious affection – whether compensation should be
assessed under each head under s 20(1) of the Acquisition of
Land Act 1967 (Qld) or by use of the before and after method
REAL PROPERTY – COMPULSORY ACQUISITION OF
LAND – COMPENSATION – ASSESSMENT – MARKET
VALUE – BEFORE AND AFTER METHOD – where the
compensation to be paid to the appellant was determined by
-- 1 of 32 --
2
application of the before and after method and cash flow
analyses – where the valuer for the respondent assessed the
compensation to be $6,877,800, with a period of 62 months
for the development and sale of the land post-resumption,
which was ultimately adopted by the Land Court – where the
valuer for the appellant assessed the compensation to be
$25,000,000, with 76 months for the development and sale of
the land to take into account redesign, further traffic analysis,
and slower rates of sale – where the valuers for the appellant
and respondent used different assumptions about the time to
commence development, the rate of sale and the construction
program – whether the Land Court Member erred in not
adopting the approach of the appellant’s valuer – whether the
Land Court Member gave sufficient reasons for his findings
REAL PROPERTY – COMPULSORY ACQUISITION OF
LAND – COMPENSATION – ASSESSMENT – MARKET
VALUE – BEFORE AND AFTER METHOD – where the
valuers for both parties agreed that the best method to assess
compensation payable to the appellant for the resumption of
part of its land was by application of the before and after
method – where valuers for both parties used cash flow
analyses and internal rates of return to determine the value of
the retained land after resumption – where the valuer for the
respondent derived an internal rate of return from the cash
flow analysis rather than adopting the rate as input for the
analysis, which was the approach of the valuer for the
appellant – where the internal rate of return adopted by the
valuer for the respondent was significantly lower than that
adopted by the valuer for the appellant – whether the Land
Court Member failed to address the question – whether the
Land Court Member erred in adopting the approach of the
valuer for the respondent
REAL PROPERTY – COMPULSORY ACQUISITION OF
LAND – COMPENSATION – INJURIOUS AFFECTION
OF ADJOINING PROPERTY – where the assumptions to be
used for the cash flow analyses were to be determined by
reference to knowledge available to the hypothetical vendor
and purchaser at the date of resumption – where the
respondent submits that contribution is an element of
injurious affection under s 20(1) of the Acquisition of Land
Act 1967 (Qld) and therefore the contribution agreed upon
some years after resumption could be considered in
determining the value of land at the date of resumption –
where the respondent submits that fair compensation for the
impacts of injurious affection should be assessed by reference
to the contribution actually required – whether contribution
for external road works constitutes injurious affection for the
purposes of s 20(1) of the Acquisition of Land Act 1967 (Qld)
– whether the Land Court Member erred in refusing to take
into account the final contribution
-- 2 of 32 --
3
HIGHWAYS - CONSTRUCTION, MAINTENANCE AND
REPAIR - LEVYING CONTRIBUTIONS FOR
PARTICULAR WORKS OR EFFECTING AT
INDIVIDUAL'S EXPENSE – where prior to resumption the
land was the subject of a development application – where
the respondent was a concurrence agency under the
Integrated Planning Act 1997 (Qld) for that application –
where the respondent gave notice of conditions to be imposed
on that development application, one of which was a
$30,000,000 contribution to upgrade the major roads – where
that application was not approved – where the respondent
submitted that in the current case $3,000,000 should be
assumed as the contribution for external road works because
of the reduced size of the development – where the appellant
submitted that a contribution of $16,550,000 should be
assumed – whether the Land Court Member erred in adopting
the respondent’s assumption – whether the Land Court
Member overlooked evidence
APPEAL AND NEW TRIAL - APPEAL - GENERAL
PRINCIPLES - RIGHT OF APPEAL - WHEN APPEAL
LIES - ERROR OF LAW - PARTICULAR CASES
INVOLVING ERROR OF LAW – FAILURE TO GIVE
REASONS FOR DECISION – ADEQUACY OF REASONS
- where the Land Court Member favoured the evidence
presented by the respondent in regards to contribution, time
for the development and sale of the land, the internal rate of
return, and compensation - where the appellant submits that
the Land Court Member overlooked evidence and did not
provide adequate reasons for his conclusions - whether the
Land Court Member failed to give adequate reasons for
decision
Acquisition of Land Act 1967 (Qld), s 20(1)
Integrated Planning Act 1997 (Qld)
Adelaide Fruit & Produce Exchange Co Ltd v Adelaide
Corporation (1961) 106 CLR 85; [1961] HCA 20
Barnes v Department of Transport (1997) 16 QLCR 22
Beale v Government Insurance Office (NSW) (1997) 48
NSWLR 430
Brisbane City Council v Mio Art Pty Ltd [2012] 2 Qd R 1;
[2011] QCA 234
Drew v Makita (Australia) Pty Ltd [2009] 2 Qd R 219; [2009]
QCA 66
Kenny & Good Pty Ltd v MGICA (1992) Ltd (1999) 199 CLR
413; [1999] HCA 25
Metroplex Management Pty Ltd v Brisbane City Council &
Ors [2009] QPELR 270
-- 3 of 32 --
4
Mifsud v Campbell (1991) 21 NSWLR 725
Mitchell v Cullingral Pty Ltd [2012] NSWCA 389
Pettitt v Dunkley [1971] 1 NSWLR 376
Soulemezis v Dudley (Holdings) Pty Ltd (1987) 10 NSWLR
247
Spencer v Commonwealth of Australia (1907) 5 CLR 418;
[1907] HCA 82
Suntown Pty Ltd v Gold Coast City Council (1979) 6 QLCR
196
COUNSEL: M D Hinson QC for the appellant
D R Gore QC, with J Brien, for the respondent
SOLICITORS: Anderssen Lawyers for the appellant
Clayton Utz for the respondent
THE COURT:
[1] The Land Court determined compensation payable to the appellant (Cidneo) for the
resumption for part of a parcel of land, in the sum of $6,900,000. The
compensation was assessed under all heads (save for disturbance) as the difference
between the value of Cidneo's land before and after the resumption (before and after
method).
[2] As was apparent from its outline of argument, Cidneo's appeal relates to a number
of matters relevant to determining the value of its retained land after the resumption
(after value), derived from a cash flow analysis. One is, the contribution which
would have been payable in respect of the development of Cidneo's retained land, as
a consequence of a requirement imposed by the respondent (DTMR) for a
development approval for the land. Two others relate to periods of time, one being
for the approval of the development; and the other being for carrying it out, and
selling the resulting lots. The fourth related to the internal rate of return used in the
cash flow analysis adopted by the Member.
[3] In his determination, the learned Member held that, as a matter of law, he was not
entitled to take into account the contribution ultimately payable to DTMR in respect
of the development of the retained land. DTMR has cross-appealed, on the basis
that the learned Member was wrong to take that approach; and contending that the
compensation should be less than was determined in the Land Court. At the hearing
it added by leave a ground to its cross-appeal, alleging that the Land Court erred by
assessing compensation by the before and after method, rather than assessing
separately compensation under each of the heads provided for in s 20 of the
Acquisition of Land Act 1967 (Qld) (AL Act).
Background
[4] Before the resumption, Cidneo owned three parcels of land (site) having a total area
of 100.477 hectares. The site had in times gone by been the location of the
-- 4 of 32 --
5
Sananander Army Barracks (sometimes referred to as the Wacol Army Barracks). It
lay on what might be described as the southern side of the Ipswich Motorway, a
short distance outbound, or west, of the intersection between the Motorway and the
Centenary Highway. Further outbound from the land was the intersection of
Progress Road and the Motorway. The land may be described as generally
rectangular in shape, with its long axis roughly parallel to the Motorway; and with a
rectangular extrusion on its southern (or south eastern) side. Boundary Road, which
was generally parallel to the Motorway, ran along part of the southern boundary of
the site, separating what has been referred to as the extrusion from the balance of
the site. Where it separated the extrusion from the balance of the site, Boundary
Road, though dedicated, was not a constructed road.
[5] Bullockhead Creek runs in a roughly northerly direction through the centre of the
site. The resumption cut off the north eastern (or possibly northern) corner of the
site, east of Bullockhead Creek, adjacent to the Motorway, and the boundary nearest
the Centenary Highway.
[6] The resumed land has an area of 8.385 hectares, Cidneo retaining 92.092 hectares
(retained land). The resumption was effected by a notice published in the
Government Gazette on 22 February 20081.
[7] The Notice of Intention to Resume stated that the land was to be resumed “for the
purpose of transport, in particular, road purposes {Cunningham Arterial Road
(Ipswich Motorway)}.
[8] There was no issue about the scope of the scheme or project for which the land was
resumed. It was the upgrading of the Ipswich Motorway, from Wacol to Darra,
extending from Argyle Parade and Acanthus Street, which are to the east of the
Centenary Highway, to the Progress Road interchange2.
[9] Prior to the resumption, the Centenary Highway interchange was grade-separated.
Essentially, traffic from the Centenary Highway entered a large loop which sat
above the Ipswich Motorway (similar, at least conceptually, to an over-sized
roundabout). The interchange then permitted a vehicle approaching it from one
direction to depart in any of the other three directions. Traffic travelling to the site
from the major road system could travel from the interchange south along the
Centenary Highway exiting at the Kelliher Road offramp, and looping back to
Boundary Road which then passed above the Centenary Highway to the site
(Boundary Road East). Traffic from the site could travel along Boundary Road East
turning north to what was referred to as the Bakery Road onramp, joining the
Centenary Highway just south of the interchange.
[10] As a result of the project, the Centenary Highway interchange was substantially
altered3. Changes of direction for traffic travelling from the south to the west, and
from the west to the south, were no longer accommodated at the interchange, but
involved the use of Progress Road between the Centenary Highway and the Ipswich
Motorway4. The Bakery Road onramp and the Kelliher Road offramp (together the
1 See s 12(5) of the AL Act.
2 Appeal Hearing Transcript (T) 1-12, lines 9-40; see also Appeal Record Book Vol 3 (AR3) p 716.
3 See Appeal Record Book Vol 5 (AR5) pp 1397-1398.
4 See AR5 p 1433.
-- 5 of 32 --
6
ramps) were no longer retained. These changes had implications for the manner of
development of Cidneo's land.
[11] The resumed land was used to accommodate a link for traffic approaching the
interchange from the north, seeking to depart west on the Motorway5.
[12] In July 2006, Metroplex Management Pty Ltd had made a development application
to Brisbane City Council for a development approval for Cidneo's land. The
principal forms of development were large format retail, residential, centre
activities, offices and industry. The application was revised as a result of an
information request under the Integrated Planning Act 1997 (Qld) (IP Act), with the
result that the anticipated development included industrial development with a gross
floor area (gfa) of 386,000 square metres; office development with 98,000 square
metres gfa; and retail and services development of 6,000 square metres gfa6. A
traffic report prepared by Mr Neil Viney predicted that this development would
generate some 3,946 traffic movements (in and out of the site) in the daily peak
hours of traffic7. Mr Viney’s projections were reviewed on behalf of DTMR, and
were considered satisfactory8.
[13] DTMR was a concurrence agency under the IP Act for the Metroplex application.
By a letter dated 11 July 20079 it gave notice of the conditions to be imposed in
respect of the Metroplex development application. They included the construction
of Boundary Road through the site; and the payment of a total of $30,000,000 by
way of monetary contributions in respect of the upgrading of interchanges on the
major roads. The amount consisted of a contribution of $12,000,000 in respect of
the Progress Road/Ipswich Motorway interchange; a contribution of $12,000,000 to
the upgrading of the Boundary Road/Logan Motorway interchange; a contribution
of $3,000,000 to the upgrading of access to the Motorway at Argyle Parade and
Acanthus Street; a contribution of $2,000,000 towards cycling infrastructure in the
Ipswich Motorway corridor; and a contribution of $1,000,000 towards the Main
Roads Intelligent Transport System (the Court was told, without objection, that this
system provided signs on major roads giving the distance and estimated travel times
to exits from the major road).
[14] On 21 September 2007, Metroplex Management appealed to the Planning and
Environment Court against a deemed refusal by Brisbane City Council of the
Metroplex development application (Metroplex appeal). DTMR participated in the
appeal, contending that, if that Court were to approve the Metroplex development
application, it should impose a condition requiring the payment of $27,000,000 in
respect of the contributions sought in its concurrence agency response; and
alternatively that Metroplex’s appeal should be refused10. The Metroplex appeal
was dismissed by the Planning and Environment Court. This decision was
overturned in the Court of Appeal. Subsequently, Metroplex further amended its
application, omitting the proposed office development. On 6 December 2011,
agreement was reached with DTMR about conditions for the approval of the
5 See AR5 p 1398.
6 See Appeal Record Book Vol 7 (AR7) p 1735.
7 AR7 p 1736.
8 AR7 pp 1739-1740.
9 AR3 pp 693-694.
10 See Metroplex Management Pty Ltd v Brisbane City Council & Ors [2009] QPELR 270, 294 [149],
[151].
-- 6 of 32 --
7
amended development application11 (2011 conditions agreement). The agreed
conditions required the completion of works on the Progress Road/Ipswich
Motorway outbound offramp and the Progress Road approach, the parties agreeing
that the cost of those works was $1,087,110.7612.
Land Court’s reasons for judgment
[15] To appreciate some of the recorded findings of the Land Court, it is necessary to
note some aspects of the valuation evidence. The valuers called by the parties
prepared joint reports. They agreed that the highest and best use of Cidneo’s land in
February 2008, both omitting the resumption from consideration (before
resumption) and taking the resumption into account (after resumption), was to
secure approval for the development of, and subsequently to subdivide, Cidneo’s
land as an industrial estate in accordance with plans identified by the valuers13. It
was agreed that the diminution in the value of Cidneo’s retained land, consequent
upon the resumption, was appropriately identified as the difference between the
values of its property immediately before (and unaffected by), and again
immediately after (and affected by), the resumption14. It was also agreed that sales
of englobo industrial properties provided a guide to the market value of Cidneo’s
land in February 2008; but that a comparison with such sales was insufficient to
properly assess the difference in value before and after resumption; and accordingly
it was appropriate to undertake cash flow feasibility analyses of the development,
“which will better account for the resumption impacts”15. It is clear that such
impact would include the effects (if any) of severance of the taken land, and what is
commonly referred to as “injurious affection”16.
[16] Mr Brett was the valuer called by DTMR. Ultimately Mr Brett concluded the value
of the land before resumption to be $60,000,00017, a figure derived by an analysis of
sales evidence18. He then adopted this value for the purpose of a cash flow exercise
to generate an internal rate of return (slightly under 15%), which he used in a
similar cash flow exercise for the purpose of identifying the after resumption value
of the retained land19. Ultimately that exercise produced a difference between the
value of Cidneo’s land before resumption, and its value immediately after, of
$6,877,80020, adopted by the Land Court as the compensation payable to Cidneo21.
His approach assumed that a contribution of $3,000,000 would be required for road
works.
[17] In broad outline, there are similarities between the approach taken by Mr Brett, and
that of Mr Hamilton, the valuer called in Cidneo’s case. Mr Hamilton adopted the
direct comparison approach as his initial methodology, resulting in a before
resumption land value of $60,000,00022. He then carried out a cash flow analysis,
11 AR7 p 1928, para 158.
12 Land Court reasons for judgment (RJ) [226]-[227].
13 Appeal Record Book Vol 4 (AR4) pp 1189, 1194.
14 AR4 p1189.
15 AR4 p 1189.
16 See s 20(1) of the AL Act.
17 AR5 p1370.
18 See AR5 pp 1368-1370, 1355; Appeal Record Book Vol 2 (AR2) pp 402-403.
19 AR2 p 403, lines 6-25.
20 AR5 p 1378.
21 RJ [405].
22 AR5 p 1284.
-- 7 of 32 --
8
with an internal rate of return of 21.7 percent, based on a land value of
$60,000,00023. The two exercises resulted in his adopting a value of $60,000,000
for Cidneo’s land, unaffected by the resumption24. Mr Hamilton then assessed the
value of Cidneo’s land after the resumption by a cash flow analysis. His internal
rate of return for this analysis was 21.46 percent25. Significant for his approach
were his assumptions that, before resumption, no transport infrastructure
contribution for road works external to the site would be required; but after
resumption, contributions of $20,000,000 would be required. His analyses resulted
in a value of the land, after resumption of $35,000,000; with an implicit assessment
of compensation of $25,000,00026. It is convenient to mention that he produced an
alternative cash flow based on transport infrastructure contributions of $3,000,000,
resulting in a market value after resumption of $42,000,00027.
[18] The learned Member recorded the agreement of the valuers about the value of
Cidneo’s land before resumption28, though he did not make an express finding
adopting it. He described the cash flow analyses as being a “modelling exercise”,
and expressed concerns about their reliability and accuracy29. He noted a number of
differences in the matters assumed by each of the valuers for the purpose of the cash
flow analyses. With reference to the rates of sale and sale prices adopted by the
valuers, he said that they were “premised upon speculation and estimation”30.
Having expressed these concerns, the learned Member said, “the best that the Court
can do is to prefer one approach over another”31. He expressed some criticism of
Mr Hamilton’s response to a suggestion in cross-examination that he had not
correctly applied evidence relating to a property described as the “Motorway
Business Park”, as he had not sufficiently recognised the difference in the sizes of
lots to be produced from that land and the sizes of the lots adopted for the cash flow
analysis for Cidneo’s land32. He then referred, somewhat critically, to Mr
Hamilton’s application of sales evidence to derive prices of lots produced by the
development of Cidneo’s land, in particular that it did not seem to reflect an
adjustment in the rate per square metre, related to the size of those allotments33.
After reference to sales evidence in one of Mr Brett’s reports, the learned Member
took the view that the sales evidence relating to developed lots seemed more
consistent with the approach taken by Mr Brett than that taken by Mr Hamilton34.
[19] The learned Member then dealt with the criticism of Mr Brett’s approach; and the
use made by Mr Brett of the internal rate of return, it being described as an output
rather than an input into Mr Brett’s cash flow analysis (apparently referring to the
exercise in relation to Cidneo’s land, before resumption). He then referred to
criticism of Mr Brett’s internal rates of return as being too low to be acceptable to
an intended purchaser, Mr Brett stating that the sale prices for englobo parcels
indicated that purchasers were expecting to make a profit because the prices would
23 AR5 p 1285.
24 AR5 p 1286.
25 AR5 p 1286.
26 AR5 p 1287.
27 AR5 p 1296.
28 RJ [17], [267].
29 RJ [270]-[280], [325], [327], [351].
30 RJ [347].
31 RJ [352].
32 RJ [370]-[373].
33 RJ [374]-[379].
34 RJ [388].
-- 8 of 32 --
9
continue to increase, rather than from the development of the land; and to Mr
Brett’s comment that, in the cash flow analysis, the assumed prices for the lots
produced by subdivision could not be raised above those shown by the sales
evidence, a view which the learned Member regarded as sensible35. He then
accepted that a prudent purchaser would assume the contribution for road works
external to the site to be $3,000,00036. He concluded that because of his
reservations previously expressed about the evidence of Mr Hamilton, his
acceptance of most of the evidence of Mr Brett, and his acceptance of Mr Brett’s
assessment of economic conditions relating to the prices of lots resulting from the
subdivision, and the rates of sale, compensation should be in accordance with the
figures which appeared in Mr Brett’s report of 23 November 201137.
[20] The learned Member had earlier considered the question of contributions to external
road works, when discussing the traffic engineering evidence. He found that
development of Cidneo’s land, whether before or after the resumption, would have a
significant impact on traffic in the adjacent road system38. He referred to the
evidence of Mr Beard, a traffic engineer called on behalf of DTMR, that
development in accordance with the highest and best use of Cidneo’s land would
generate less traffic than would the development which had been the subject of the
DTMR’s concurrence agency response; and accordingly a different concurrence
agency response would be expected for an application for approval to develop the
land in accordance with its highest and best use39. He concluded, on the basis of the
evidence of Mr Viney, a traffic engineer who gave evidence in Cidneo’s case, that a
traffic engineer would have advised the hypothetical prudent purchaser of the land
that there was no proper basis for DTMR to demand contributions for external road
works, save for the construction of Boundary Road; and that accordingly it was
unlikely that a prudent purchaser would have paid $60,000,000 for the land,
burdened by a contingency of paying $30,000,000 for road work contributions to
DTMR40.
[21] The learned Member referred to Mr Viney's evidence that a request for
contributions for road works (save relating to the construction of Boundary Road)
would be unreasonable. He also referred to Mr Viney’s evidence that DTMR's
concurrence agency response requiring the imposition of a condition for payment of
a contribution of $30,000,000, was a reason to think that DTMR was likely to seek
some contribution41. Mr Viney calculated this to be $16,550,000 by reason of the
reduced size of the development42. The learned Member also referred to Mr Viney's
evidence that he considered that no contribution (save for Boundary Road) should
be imposed in respect of development of Cidneo's land after resumption43. He also
referred to Mr Beard's evidence that in fact the developer and DTMR would have
entered into negotiations (evidence based upon what in fact occurred subsequent to
35 RJ [394]-[397].
36 RJ [403].
37 RJ [404]. The report was Ex 61 in the Land Court; because of an error in the compilation of the
appeal record, this report became Ex 1 in the appeal; see p 5.
38 RJ [163].
39 RJ [187].
40 RJ [208].
41 RJ [209].
42 RJ [210].
43 RJ [211].
-- 9 of 32 --
10
the resumption)44. He also referred to evidence, the effect of which was that Mr
Beard and Mr Viney both considered that the same requirements for external road
works contributions could reasonably be imposed for the development of Cidneo's
land before resumption, as could be imposed after resumption; the difference
between them being that, in both cases, Mr Beard considered that some contribution
could be required in respect of the upgrading of the intersections of the Motorway
with the Centenary Highway and Progress Road45.
[22] The learned Member stated that the "only truly objective evidence" of the likelihood
of a contribution was the concurrence agency response previously referred to,
though it related to a larger development46. He summarised Mr Viney's evidence as
being to the effect that if DTMR persisted in seeking the contribution for external
road works which was identified in the concurrence agency response, and that was
challenged, there was a high prospect that the challenge would be successful47. The
learned Member then stated that he preferred the approach of Mr Beard, who
proposed that a contingency of $3,000,000 be allowed, in respect of "unsustainable
demands being made" by DTMR for external road works contributions48.
[23] The learned Member then stated that he also preferred the approach of Mr Beard to
that of Mr Viney on the question of traffic generation and traffic flows, because Mr
Beard was "somewhat less pessimistic and more pragmatic"49. That preference, the
learned Member said, led him to prefer Mr Beard's approach in the context of likely
contributions for external road works (other than for works relating to Boundary
Road)50.
[24] The learned Member also stated that he was unwilling to accept "the direct
relevance" of the DTMR's concurrence agency response, which related to "a much
larger project with much higher traffic generation features"51. That led the learned
Member to regard the response as a "first offer", and somewhat speculative in view
of the uncertainty about the form of the proposed development52.
Submissions on appeal
[25] The first ground of appeal was that the learned Member erred in determining, for the
purpose of the cash flow analysis, that the appropriate figure to adopt for a
contribution for road works (other than on Boundary Road) was $3,000,000. In
relation to that ground it was submitted for Cidneo that the learned Member erred in
law by disregarding relevant evidence. That evidence was that in 2008, traffic
engineers (Mr Beard and Mr Eppell) considered that substantial contributions were
justified in respect of the development, the subject of the Metroplex appeal53;
evidence that the contribution nominated in DTMR's concurrence agency response
could be proportionately reduced to identify a likely contribution which DTMR
44 See RJ [213].
45 RJ [219]-[223].
46 RJ [243].
47 RJ [247]- [258].
48 RJ [259].
49 RJ [260]-[263].
50 RJ [264].
51 RJ [265].
52 RJ [266].
53 AR4 p 1075; see also Appeal Record Book Vol 1 (AR1) pp 209-211.
-- 10 of 32 --
11
would require for the highest and best use of the land retained by Cidneo54; the
evidence of Mr Cumming, a town planner, that in February 2008, he would have
advised a potential purchaser of the land retained by Cidneo that the contribution
nominated by DTMR in its concurrence agency response would likely be reduced
by reason of the smaller development proposed as the highest and best use, but that
there was a substantial risk that there would be no further reduction of the
contribution55; Mr Beard's evidence relating to what he would have told a potential
purchaser in February 2008 as to the likely contributions to be required for the
development of the site56; Mr Viney's evidence about the advice he would have
given a potential purchaser in February 200857; the evidence of Ms Mitchell
(contrary to the evidence of Mr Beard in the Land Court), denying that DTMR's
concurrence agency response was an instruction to negotiate58; and Mr Beard's
evidence that DTMR's concurrence agency response was technically defensible and
not outrageous, having regard to the traffic to be generated by the development then
under consideration59. It was also submitted that the learned Member failed to take
into account that there was no evidence that DTMR had reduced by negotiation
contributions notified in a concurrence agency response in any analogous case, in
contrast to the evidence in Townsville City Council v Department of Main Roads60.
Given the delay between the hearing and the delivery of the learned Member’s
reasons, it could not be assumed that this evidence was not overlooked61.
[26] It was also submitted that the learned Member erred by failing to give adequate
reasons for judgment, as they did not deal with the evidence just referred to.
[27] It was submitted that the learned Member erred in accepting Mr Beard's evidence as
to the likely contribution to be required by DTMR as establishing the contribution
to be adopted for the purpose of the cash flow analysis. Indeed it was submitted
that the learned Member erred by determining what contribution he would impose,
if he were sitting in the Planning and Environment Court hearing an appeal in
respect of a condition relating to the payment of such a contribution; rather than by
asking what contribution should be assumed for the purpose of a valuation being
made by use of a cash flow analysis, carried out on 22 February 2008.
[28] It was also submitted that the learned Member erred in misdescribing the evidence
of Mr Beard, by referring to a requirement for a contribution of $3,000,000 for
“unsustainable” demands by DTMR, when his evidence was that the contribution
should be between $3,000,000 and $5,000,000, and in a worst case scenario, could
be between $10,000,000 and $12,000,000; by referring to an irrelevant matter,
namely, that a prudent purchaser was unlikely to pay $60,000,000 for the land,
burdened by a contingency of $30,000,000 for road contributions, said to refer to
the price to be paid for the land before resumption; and by asking on what basis the
value of the land taken might be elevated from $5,000,000 to a figure between
$6,800,000 and $25,000,000.
54 Ms Mitchell at AR1 p 272, lines 34-44; see also Mr Beard at AR1 p 219, lines 22-39.
55 AR3 p 918, para 8.
56 AR1 pp 208, lines 27-51; 226, lines 5-15, 38-43; 228, lines 20-22.
57 AR4 p 1079.
58 AR1 p 278, lines 1-8.
59 AR1 p 223, lines 25-49.
60 (2003) 24 QLCR 241.
61 The submission relied on Monie v Commonwealth (2005) 63 NSWLR 729 at [43] especially at (6).
-- 11 of 32 --
12
[29] Ground 2 of the Notice of Appeal alleged that the Land Court erred in not accepting
and acting on evidence called in Cidneo's case that, in assessing the value of its
retained land after resumption, an additional period of six months should have been
allowed for the time assumed to be taken to develop and sell lots resulting from the
subdivision of the land. The written submissions for Cidneo supported this ground.
The submissions identified the six month period as being an extra six months in part
occasioned by the need for a further traffic analysis, but also by the need to redesign
the estate in relation to the construction of Boundary Road, and the hydraulics
associated with Bullockhead Creek62. It was orally submitted that the evidence in
support of this longer period was uncontradicted, but not referred to in the reasons
of the learned Member. It was submitted that the reasons identified the issue63, but
did not resolve it. Alternatively, if the issue was taken to be implicitly resolved by
the adoption of Mr Brett's valuation, then the Land Court erred in failing to give
reasons for doing so.
[30] Ground 3 of the Notice of Appeal alleged that the Land Court erred in adopting Mr
Brett's period of 62 months for the development and sale of the land in the post-
resumption case. Mr Hamilton's cash flow analysis assumed a period of 76 months.
The submissions for Cidneo made clear that, of the 14 months' difference, six
months was accounted for by the period the subject of Ground 2. In relation to the
balance (8 months), it was submitted that the Land Court erred in particular in
accepting Mr Brett's evidence as to his rate of sale for lots produced in Stage 3,
being two sales per month. It was submitted that the Land Court Member erred in
failing to take into account evidence from Mr Whitelaw and Mr Hamilton criticizing
this rate of sale; as well as Mr Brett's own acknowledgement that in February 2008
it could be expected that credit (and, if it be different, finance) was tightening. It
was also submitted that Mr Brett in his cash flow analysis assumed an overlap in the
construction of stages of the development (thus reducing the time required for the
project); which he acknowledged might not be the approach of the prudent
purchaser; but the learned Member failed to deal with this evidence.
[31] As formulated, Ground 4 of the Notice of Appeal alleged that the Land Court erred
in accepting Mr Brett's evidence that in February 2008 a low internal rate of return
was acceptable for his cash flow analysis. The submissions for Cidneo in relation to
this ground of appeal criticised Mr Brett's approach of deriving an internal rate of
return from a cash flow analysis, rather than adopting such a rate as an input for the
analysis. It was submitted that his explanation that in February 2008 the market
was speculative, was inconsistent with the agreed highest and best use of the land
for development for industry and warehouse purposes; as this use did not include
land banking. It was submitted that these matters were not dealt with in the reasons
for judgment.
[32] With respect to Ground 1 of the appeal, for DTMR it was submitted that the
assumption made on behalf of Cidneo that, without the resumption, DTMR would
not require a contribution for transport infrastructure, but that post-resumption, a
contribution of $20,000,000 would be required, involved significant weaknesses,
and faced significant hurdles. In particular, it was submitted that the upgrade of the
Ipswich Motorway was undertaken because of significant traffic problems being
experienced generally on the Motorway, and at the Centenary Highway interchange.
62 AR5 p 1285.
63 At RJ [354].
-- 12 of 32 --
13
Mr Viney had not done a relevant assessment of the impact of traffic generated by
the development of Cidneo's land on the road network. Without the upgrade, the
traffic engineering evidence indicated that Cidneo's land could not be substantially
developed. The assumed development of Cidneo's land, without the upgrading of
the Motorway, was premature. It was submitted that it was common ground that
there was no difference between the before and after cases from a traffic
engineering perspective. It was also submitted that Mr Viney had consistently taken
the view that the contribution of $30,000,000 identified in the concurrence agency
response could not be maintained. The learned Member correctly preferred the
analysis and contentions advanced by Mr Beard, to those advanced by Mr Viney.
His conclusion was supported by Mr Hamilton's evidence that no prudent purchaser
would take $30,000,000 (or even $16,550,000) off the price of a property of the
order of $57,000,000; and by the fact that Mr Hamilton's primary assessment of
compensation of over $25,000,000 significantly exceeded the uncontested
assessment of Mr Brett of the value of the resumed land at $4,535,000. It was
submitted that the reasons of the learned Member sufficiently referred to relevant
evidence, and appraised the parties of the broad outline and constituent facts of the
reasons upon which he had acted.
[33] For DTMR it was also submitted that Mr Beard's evidence about the likely
contribution was not to be characterised as hindsight, but was rather a forensic
exercise to determine the advice which would have been given to a prudent
purchaser at the date of resumption64. It was submitted that it was relevant that the
concurrence agency response did not include a contribution for the upgrading of the
Centenary Highway interchange. It was also submitted that that response related to
a development more than twice the size of the development representing the agreed
highest and best use of Cidneo's retained land after the resumption. It was
submitted that the Land Court had in truth focused on the advice which a prudent
purchaser would have received as at the date of the resumption, about the likely
contribution to be required in respect of the development of the retained land. It
was submitted that the learned Member correctly regarded as more relevant, the fact
that the traffic engineers would have advised that the same contribution would have
been imposed whether one was considering the development of the land before
resumption, or its development after resumption; than the concurrence agency
response itself65. It was submitted that, although the valuers might have come to the
same conclusion about the value of Cidneo's land in the before resumption case, it
was not correct to say that it was only necessary to focus on the post-resumption
value, when a cash flow analysis was used to determine the difference between the
value of Cidneo's land in the before resumption and after resumption cases. It was
submitted that Mr Beard had (no doubt correctly) pointed out that DTMR would
rely on its manual for the generation rates of traffic resulting from the development
of Cidneo's land, and not just on the generation rates relied upon by Mr Viney at the
time of the Metroplex application66. It was submitted that when it is appreciated
that the monetary contributions for the external road network would be the same in
the before resumption case and the after resumption case, that demonstrates that the
value adopted by the learned Member for the retained land was correct67. It was
submitted that it was not possible to determine the correct value for the land
64 T 2-12, lines 24-32.
65 T 2-13, lines 39-45.
66 T 2-24, lines 18-20.
67 T 2-27, lines 14-17.
-- 13 of 32 --
14
retained by Cidneo after resumption, without appreciating the evidence relating to
its value before the resumption. It was submitted that (most of) the compensation
claimed by Cidneo was either severance or injurious affection; and that if the
contributions were the same before and after resumption, then no compensation was
payable under these heads.
[34] It was submitted that Mr Beard (like Mr Viney) considered that, in the before
resumption case (i.e., without the upgrading of the Motorway), development of
Cidneo's land was premature. The difference between his current evidence and that
which he gave in the Planning and Environment Court should not be held against
him, as in the Land Court he was asked to assume that Cidneo's land could be
developed without the upgrading of the Motorway. It was submitted that, if the
learned Member incorrectly decided the likely contribution to be taken into account
by a prudent purchaser in February 2008, then that would throw doubt on the
determined value of Cidneo's land before resumption.
[35] It was submitted that the learned Member should have adopted a piecemeal
approach to the assessment of compensation (a point more directly relevant to
DTMR's ground of cross-appeal, added by leave).
[36] Reliance was placed on Mr Brett's evidence that the value attributed to the land by
Mr Hamilton after resumption was too low, when compared with the englobo
sales68.
[37] It was submitted that Mr Hamilton gave no explanation for his 20 per cent risk
margin, and in particular its application to the likely contribution payable to DTMR
for external road works69. It was submitted that Mr Brett did not say that the market
had fallen away by February 200870 (relevant to the time allowed for completing the
hypothetical development of the land); nor did he say that the highest and best use
of the land was land banking71.
[38] It was submitted, by reference to the tests formulated in Drew v Makita (Australia)
Pty Ltd 72 and Mitchell v Cullingral Pty Ltd73, that it was not necessary for the
learned Member to refer more fully to the evidence of Mr Viney, nor to the earlier
views expressed by Mr Beard. The learned Member's preferences for the evidence
of Mr Beard and Mr Brett was adequately explained.
[39] It was also submitted that, if Ground 1 of the appeal was upheld, then the matter
should be remitted to the Land Court for further determination.
[40] With respect to Ground 2, it was submitted for DTMR that the proposition that an
additional six months would be required for a traffic analysis report and other
approval related issues had been challenged. That appears to have been on the basis
that no more time would be required for these matters in the after resumption case
than in the before resumption case74. The correct assumption was said to be that the
68 T 2-38, lines 1-23.
69 T 2-39, lines 40-42.
70 T 2-40, lines 42-46.
71 T 2-41, lines 1-2.
72 [2009] 2 Qd R 219 (Drew).
73 [2012] NSWCA 389 (Mitchell).
74 See Respondent’s Outline of Argument on the Appeal filed 11 November 2013 (ROAA) paras 23-24;
T 1-76 to 1-78. See also AR2 p 454, lines 20-29.
-- 14 of 32 --
15
parties, at the date of resumption, knew all the relevant facts; and accordingly there
was no question of a need to carry out a redesign for the development75. Further,
Mr Hamilton's evidence was based on the evidence of Mr Viney; and the learned
Member had preferred the evidence of Mr Beard to that of Mr Viney. To the extent
that Mr Hamilton's evidence might have been based on the evidence of Mr
Cumming, Mr Cumming’s evidence in this area was "marginalised"76, and the
learned Member concluded that it was "unconvincing"77.
[41] With respect to Ground 3 of the appeal, it was submitted for DTMR that Mr
Hamilton's evidence "looked wrong", because in the after case there were fewer
allotments to develop and sell than in the before case; he was wrong in respect of
the six month period, the subject of Ground 2; and he left substantial gaps between
the end of Stage 2 and the release of Stage 3; and the end of Stage 3 and the release
of Stage 4. Although it was submitted that Mr Whitelaw's evidence was not truly
independent, reliance was placed on the fact that he accepted that Mr Hamilton's
gap between Stages 3 and 4 was too long; and on his acceptance of a quicker rate of
sale for lots in Stage 3 than was adopted by Mr Hamilton. It was submitted that Mr
Brett's rate of sale for lots in Stage 3 was justified by the fact that the lots were
smaller. It was also submitted that, in a number of places, the learned Member
explained his preference for the evidence of Mr Brett.
[42] With respect to Ground 4, it was submitted that the learned Member was correct in
accepting Mr Brett's approach to the internal rate of return, and that he adequately
explained his reasons for doing so.
[43] Overall, it was submitted that an appellate court should not lightly interfere with a
determination at first instance, particularly in a valuation case.
Submissions on cross-appeal
[44] With respect to the ground stated in the unamended Notice of Cross-Appeal, DTMR
submitted that, in the after resumption situation, the contribution likely to be
required for external road works was an element of injurious affection; and
accordingly, by reference to Adelaide Fruit & Produce Exchange Co Ltd v Adelaide
Corporation78 compensation in respect of it could be determined with the benefit of
hindsight. It was not accepted that the description of injurious affection found in
Suntown Pty Ltd v Gold Coast City Council79 was an exhaustive definition of that
term. It was submitted also that, in its pleadings in the Land Court, Cidneo had
alleged the likely contribution to be an element of injurious affection; and its
departure from that position in contesting the cross-appeal would be prejudicial to
DTMR.
[45] In relation to the added ground for the cross-appeal, DTMR pointed to the
significant discrepancy between the value of the land taken of $4,535,000; and the
amount claimed by Cidneo as compensation. It was submitted that the difference
could only properly be explained as compensation for injurious affection; and
accordingly it was necessary to assess what damage in truth was suffered by Cidneo
75 T 1-79, lines 18-24.
76 ROAA para 23.
77 At RJ [118].
78 (1961) 106 CLR 85 (Adelaide Fruit), 90.
79 (1979) 6 QLCR 196 (Suntown), 207-208.
-- 15 of 32 --
16
under this head. Accordingly the learned Member erred in assessing compensation
by using the before and after approach, rather than by assessing separately
compensation under each of the heads identified in the AL Act.
[46] For Cidneo, it was submitted that a consideration of the likely contribution to be
required by DTMR was an element of the determination of the value of its land at
the date of compensation, and for that purpose facts must be determined as at that
date, and without the benefit of hindsight80. Cases where the use of hindsight was
permitted for the determination of injurious affection or severance damage were
cases where compensation under these heads was assessed separately from the value
of the land. Barnes v Department of Transport81 was a case where compensation
for injurious affection was allowed in respect of stock losses and the remediation of
water quality in a dam, the damage being suffered after the resumption, and
independently of the value of the retained land. Similarly, in Adelaide Fruit,
compensation for severance was assessed by reference to the cost of building a wall
to replace a wall on the resumed land; and to build toilets. That compensation had
nothing to do with land value. These cases did not support the ground originally
raised by DTMR's cross-appeal.
Some principles relating to a court’s duty to give reasons
[47] As Muir JA held in Drew82, a court from which an appeal lies must state adequate
reasons for its decision; and its failure to do so constitutes an error of law. His
Honour then went on to identify additional bases for the requirement to state
reasons, beyond the need to give effect to a right of appeal83.
[48] The requirement to give reasons has been described as an incident of the judicial
process84. It may be obvious, but it is the duty of a judicial officer deciding a
proceeding at first instance to determine the relevant issues presented for
determination by the parties85. A judicial officer accordingly is required to
determine those issues of fact and law which it is necessary to decide in order to
determine whether any, and if so what, relief is to be granted. Each issue of fact is
to be determined by reference to so much of the evidence as is potentially
significant for the determination of that issue. The legal issues are to be determined
by the identification and application of the relevant legal principles. While it will
not always be necessary for reasons to demonstrate that each of these steps has been
taken, perhaps because that will be evident from other sources, a failure to give
reasons showing the taking of these steps may lead to a conclusion that justice has
not been seen to be done; and accordingly that there has been an error of law on the
part of the judicial officer86.
[49] The duty to give reasons, and whether it has been fully complied with, has been
more fully examined in a number of cases, which form the basis of the following
80 Relying on Brisbane City Council v Mio Art Pty Ltd [2012] 2 Qd R 1 (Mio Art), 12 [33], 18 [53], 23
[68] and 26 [77].
81 (1997) 16 QLCR 22 (Barnes).
82 At 237 [57].
83 At 237 [58].
84 Housing Commission (NSW) v Tatmar Pastoral Co Pty Ltd [1983] 3 NSWLR 378, 386; Public
Service Board (NSW) v Osmond (1986) 159 CLR 656, 667.
85 Compare Soulemezis v Dudley (Holdings) Pty Ltd (1987) 10 NSWLR 247 (Soulemezis), 278.
86 Beale v Government Insurance Office (NSW) (1997) 48 NSWLR 430 (Beale), 431, 441, 446;
Soulemezis, 281; Mifsud v Campbell (1991) 21 NSWLR 725 (Mifsud), 728.
-- 16 of 32 --
17
statements. Since issues which depend on questions of fact are determined on the
basis of evidence, a judicial officer must consider all evidence relevant to an issue,
though it will not be necessary to refer to all the evidence in the reasons for
judgment; but a failure to deal with evidence potentially critical to an important
issue in the case tends to deny the fact and the appearance of justice having been
done, and indicates that the evidence was excluded from consideration87. The duty
to state reasons requires a judicial officer to record the steps taken to arrive at the
result, including the examination of relevant material; so that a failure to refer to
material evidence can properly be taken as showing that the judicial officer has
erroneously overlooked or discarded it88. Where the reasons for judgment do not
refer to evidence which is important or critical to the proper determination of an
issue, an appellate court may infer that the judicial officer overlooked the evidence
or failed to give consideration to it89. Where one set of evidence is accepted over a
conflicting set of significant evidence, the reasons should refer to the existence of
both sets of evidence, and make it apparent how the judicial officer came to prefer
one over the other90. Where the evidence is expert evidence, which amounts to a
coherent reasoned opinion, then its rejection should be explained by coherent
reasoned rebuttal, or discounted for another good reason91. The reasons for
judgment should make apparent the process of reasoning by which the judicial
officer has reached his or her conclusions92. Overall, the reasons are to demonstrate
that the judicial officer has grappled with the case as presented by each party93.
[50] It is well established that a judicial officer is required to give reasons, so that the
parties, and an appellate tribunal, can identify how the issues have been determined,
and how, ultimately, the judicial officer has determined whether any, and if so what,
relief is to be granted94. That would support the conclusion that, where a full right
of appeal lies, the reasons for judgment must demonstrate a consideration of
potentially significant evidence.
Appeal ground 1: the contribution for road works
[51] As has been mentioned, compensation was determined by reference to the value of
Cidneo's land before and after resumption; and the value after resumption was
determined by reference to cash flow analyses carried out by the valuers. In each of
these analyses, the value of the land was to be determined at the date of the
resumption. Subject to the ground stated in the Notice of Cross-Appeal, it was
common ground that the assumptions to be used for the cash flow analyses were to
be determined by reference to knowledge available to the hypothetical vendor and
purchaser at the date of resumption; including advice they might receive from
87 See Mifsud, 728.
88 See Waterways Authority v Fitzgibbon (2005) 79 ALJR 1816, 1835 [130] (per Hayne J); 1821 [26]
(per McHugh J); 1821 [28] (per Gummow J); see also 1819 [11] (per Gleeson CJ); Mitchell, [2] (per
Allsop P); [3] (per McColl JA); [116] (per Campbell JA).
89 See Beale, 443, cited with approval in Drew at [63].
90 Beale, 443, cited with approval in Drew at [63]; see also Camden v McKenzie [2008] 1 Qd R 39 at 48
[32]-[33].
91 Eckersley v Vinnie (1988) 18 Con LR 1, 77-78 cited by Ipp JA in Wiki v Atlantis Relocations (NSW)
Pty Ltd (2004) 60 NSWLR 127, 137; in turn cited with approval in Drew at 239 [65].
92 Soulemezis, 273; Strebak v Newton (Unreported; New South Wales Court of Appeal; Gleeson CJ,
Samuels and Priestley JJA, 18 July 1989) (see BC8901946 at p 7 per Samuels JA); Ansett Transport
Industries (Operations) v Wraith (1983) 48 ALR 500 at 507; Beale at 443-444.
93 Mitchell, [116].
94 See Pettitt v Dunkley [1971] 1 NSWLR 376, 380-382. 386-388.
-- 17 of 32 --
18
appropriately qualified experts about likely conditions to be imposed on the
potential development of Cidneo's land.
[52] The task which had to be undertaken was to determine the value of the land at 22
February 2008. That is to be done by reference to the approach formulated in
Spencer v Commonwealth of Australia95 for the determination of market value. In
that context, McHugh J said in Kenny & Good Pty Ltd v MGICA (1992) Ltd96
“In determining that value, there must be attributed to the parties a
knowledge of all matters that affect its value. Those matters will
include the predicted impact of future events as well as the
experience of the past…”
[53] At the date of resumption, no application had been made for the development of the
land in accordance with its highest and best use; and the contribution for external
road works to be required in respect of the development of the land for that use was
unknown. However the likelihood of such a requirement, known at the date of the
resumption, to these hypothetical parties, or to appropriate experts they might
reasonably be expected to have engaged, and the weight prudently to be given to the
possibility of such a requirement, are plainly relevant to the determination of the
value of the land97. Where regard is to be had to expert evidence on these matters, it
follows that the focus must be on the likely state of mind of the expert at the date of
the resumption, rather than on the expert’s view at the time of the hearing.
Subsequent events may provide evidence of a state of affairs in existence at the date
of the resumption; but that state of affairs will only be relevant if knowledge of it
was available to the hypothetical vendor and purchaser at that date98.
[54] The approach of Mr Beard adopted by the learned Member was described by him as
“a figure of $3,000,000 being contemplated by way of contingency to allow for
additional but unsustainable demands being made by (DTMR) for external
roadworks contributions”99. This was further described as Mr Beards’ approach “in
the context of likely contributions that might be required apart from the Boundary
Road works”100. That appears to have led to the finding by the learned Member that
“the appropriate figure to apply to a prudent purchaser contemplating a likely
demand by (DTMR) for a contribution for road works external to the site and apart
from the completion of the Boundary Road link would be $3,000,000”101. This in
turn was relevant to the cash flow analyses relied upon for determining the value of
the retained land102. A lack of precision in the language used by the learned
Member provided a basis for a submission by Cidneo that he approached the matter
as if he were sitting in the Planning and Environment Court to determine what the
appropriate condition for a road works contribution should be. However, a
consideration of the reasons for judgment as a whole indicates that the learned
Member correctly appreciated that the question to be determined was what
allowance the hypothetical vendor and purchaser would have made for a
contribution for road works, if carrying out a cash flow analysis at the time of
95 (1907) 5 CLR 418 (Spencer).
96 (1999) 199 CLR 413, 436 [49].
97 Mio Art, 12 [33], 26 [78].
98 Mio Art, 26-27 [79].
99 RJ [259].
100 RJ [264].
101 RJ [403]; as to the question considered by the learned Member see also RJ [184], [208].
102 See RJ [281]-[282].
-- 18 of 32 --
19
resumption. A question remains whether the reasons for judgment were directed to
answering that question.
[55] One submission made by Cidneo was that the learned Member failed to consider Mr
Viney's evidence that in February 2008 he would have advised an intending
purchaser that DTMR could be expected to seek a contribution of $16,550,000 for
external road works; and that there was a real risk that such a purchaser would have
to pay a substantial contribution to DTMR in respect of the development of the land
retained by Cidneo for its highest and best use.
[56] The reasons for judgment refer to the evidence of Mr Viney on the contribution
likely to be required by DTMR103. Later, the reasons for judgment refer extensively
to Mr Viney's view, that, in truth, a requirement for a contribution to external road
works, similar to that sought in the concurrence agency response, could not be
maintained104. Immediately after that, the learned Member expressed his preference
for the approach of Mr Beard, whose evidence was that a contribution of $3,000,000
should be contemplated as the amount likely to be required to be paid for such
contributions105. The expressed preference for the approach of Mr Beard,
immediately following a discussion of Mr Viney's evidence, implicitly recognises a
difference between them. It is sufficiently clear that in expressing this conclusion,
the learned Member had in mind his earlier reference to the evidence of Mr Viney
about the contribution for external road works, likely to be sought by DTMR.
Further, it is difficult to see the discussion of Mr Viney's evidence about the
unsustainability of a contribution requirement, other than as directed to a rejection
of his view about the contribution to be taken into account by a hypothetical
purchaser.
[57] However, the learned Member referred to Mr Viney's evidence only insofar as Mr
Viney expressed a view about the likely contribution which DTMR would seek to
impose, and whether its position was maintainable. He did not refer to Mr Viney's
further evidence that he would have advised an intending purchaser in February
2008 that if the purchaser were to enter into an unconditional contract for the land,
then the purchaser should make an allowance for a contribution to which might be
required by DTMR of $16,550,000 (and perhaps something more for risk); nor his
evidence that he would have advised the purchaser, based on his experience of
difficulties in negotiating a settlement with DTMR, that there was a real risk that a
substantial contribution for external road works would have to be paid in respect of
the development of the land; nor his evidence that the contribution would have been
determined with reference to traffic engineering advice.
[58] That evidence of Mr Viney was plainly of significance for determining the weight
to be given to the possibility that a contribution would be required, if determining
the value of the land in February 2008. The reasons for judgment do not
demonstrate that it was considered by the learned Member. Rather, they support the
contrary conclusion.
[59] Of the concurrence agency response, the learned Member stated that he was
unwilling to accept its direct relevance, because the application to which it related
103 See in particular RJ [209]-[210].
104 RJ [244]-[258].
105 RJ [259].
-- 19 of 32 --
20
was "later largely abandoned", that application relating to a "much larger project
with much higher traffic generation features"106. He considered it to be "somewhat
speculative", because of the absence of "substantial detail about what final form of
the proposed development would have taken [sic]"107.
[60] Earlier the learned Member had referred to the concurrence agency response as the
"only truly objective evidence of the likelihood of a contribution" to be imposed in
respect of the development of Cidneo's land108. Although it related to what might
be described as a subsidiary issue, its relevance was nevertheless a matter of
considerable significance in the case. The learned Member's reasons for not
accepting the direct relevance of the concurrence agency response indicate that he
did so because of the size and traffic generation characteristics of a development to
which it related. The stated reasons support the view that he did not take into
account the evidence of Ms Mitchell and Mr Beard referred to in the submissions
for Cidneo that the response could be used to identify a proportionate contribution
likely to be required by DTMR for development of the land in accordance with the
agreed highest and best use. The absence of any reference to this evidence again
tends to indicate that it was not considered.
[61] Mr Beard's evidence as to the likely level of contribution (at least so far as it was to
be taken into account in the cash flow analysis) was plainly contentious. At face
value there was a very marked discrepancy between that evidence, and the evidence
which Mr Beard gave (both by way of a joint report and orally) in the Planning and
Environment Court in 2008 that a contribution of $88,000,000 was justified; and the
amount of the contribution nominated in the concurrence agency response
represented a significant discount, notwithstanding the difference in size and traffic
generation rates for the development the subject of the response, and the
development to which the cash flow analysis related. That evidence is quite
relevant in determining what advice he might have given in February 2008. To
accept the evidence which Mr Beard gave in the Land Court, and adopt the amount
of $3,000,000 as the contribution relevant for the cash flow analysis, without
reference to his evidence in the Planning and Environment Court, rather strongly
suggests that the latter evidence was not considered. Likewise, Mr Beard's evidence
that in February 2008 he would not have advised a purchaser that the likely
contribution was $3,000,000; and that he would have advised that a higher
contribution would have been required, which in the worst case might be between
$12,000,000 and $15,000,000, was highly relevant to the question the learned
Member had to determine. The fact that the learned Member did not refer to this
evidence rather strongly indicates that it was not taken into account.
[62] The evidence given by Mr Eppell in the Planning and Environment Court in 2008 is
also indicative of the state of mind of a relevant expert, and the advice which a
prudent purchaser was likely to receive, in February 2008. Although less significant
than Mr Beard's evidence from the same period, the fact that it was not referred to
by the learned Member tends to suggest it was not considered; a conclusion which is
more easily reached in light of the failure to refer to the evidence of Mr Beard
which has just been discussed.
106 RJ [265].
107 See RJ [266].
108 RJ [243].
-- 20 of 32 --
21
[63] The learned Member concluded that the concurrence agency response should be
regarded as "first offer" and "somewhat speculative"109, because of the lack of
substantial detail about the ultimate form of development. The learned Member
made no reference to the evidence of Ms Mitchell referred to in Cidneo’s
submissions; nor, indeed, to the fact that the response was based on generation rates
provided by Mr Viney and reviewed on behalf of DTMR by another traffic
engineer, Mr Dunne, who regarded them as "generally satisfactory"110. The DTMR
memorandum of 1 August 2007 also indicated the reasoning which led to the
concurrence agency response. Again, this evidence was relevant to the question
whether the response should have been treated as a position DTMR was likely to
maintain; or simply a first offer, made on a highly speculative basis. The fact that
the evidence was not referred to again suggests that it was not considered.
[64] Like the evidence of Mr Eppell, the evidence of Mr Cumming about the risk that
DTMR would require a significant contribution might not, in isolation, be regarded
as particularly significant; so that an absence of reference to it might by inference
reflect the view that this evidence was of little weight. However, having regard to
other, more significant, evidence of a similar character which was not referred to, it
is easier to conclude that this evidence too, was not taken into account.
[65] It is convenient to summarise the considerations set out above in relation to Ground
1. The learned Member appeared correctly to identify the question as being what
advice the hypothetical prudent parties would adopt for road contributions, for the
purpose of carrying out a cash flow analysis, in February 2008, to be determined by
reference to advice they would then have been likely to receive from a traffic
engineer. The adoption of the figure of $3,000,000 from Mr Beard’s evidence in
the Land Court is inconsistent with his own evidence about the advice he would
have given in February 2008; and sits uncomfortably with his evidence in the
Planning and Environment Court given later that year. It is also inconsistent with
the evidence of Mr Viney and Mr Cumming as to what advice they would then have
given. The evidence given by Mr Eppell in the Planning and Environment Court in
2008 also rather strongly suggests that, had he been asked to advise on the likely
contribution, he would not have accepted that a figure as low as $3,000,000 was
correct. The adoption of that amount by the learned Member, and his approach to
the concurrence agency response, are inconsistent with the evidence of Ms Mitchell.
The reasons for judgment do not reveal that these matters were considered.
Alternatively, they do not provide an adequate explanation for the learned
Member’s conclusion, in light of these matters. It follows that the learned Member
erred in law.
[66] For DTMR it was submitted that the valuation which the learned Member adopted
of the land retained by Cidneo was correct, because the road works contributions
payable to DTMR were likely to be the same in the before and after cases. A
number of its other submissions seem to have been directed to supporting this
proposition. The point of the submission appears to have been that, on that basis,
since neither party suggested a significant contribution for external road works in
the before case, the learned Member was right to reach the conclusion he reached
for the after case. That does not address the question whether the learned Member
considered relevant evidence, and gave adequate explanations for his reasons. Nor
109 RJ [266].
110 AR7 p 1740.
-- 21 of 32 --
22
does it address the question whether he erred in the conclusion he reached about the
value of the retained land. Cidneo’s submissions may cast doubt on the correctness
of the assumptions about contributions, and on the value of the land, in the before
resumption case; but these matters were not in issue in the appeal.
[67] Cidneo should succeed on Ground 1.
Appeal Ground 2: assumed period prior to commencement of works
[68] The cash flow analyses presented by Mr Brett assumed a period of 12 months from
the commencement of the project, until the commencement of development works,
in both the previous resumption and post-resumption cases111. The cash flow
analyses put forward by Mr Hamilton made the same assumption in the before
resumption case, but assumed the period was 18 months in the after resumption
case112. Mr Hamilton explained that the periods were allowed for obtaining
necessary pre-construction approvals; and the additional six months was to allow
for a comprehensive traffic analysis and a redesign of the estate, particularly relating
to the construction of Boundary Road and the hydraulics on Bullockhead Creek113.
Mr Cumming gave evidence that he advised Mr Hamilton that a period of 12
months would be required in the before resumption case, and 18 months in the after
resumption case, before work could commence, and of his reasons for the longer
period in the latter case114. Essentially, his evidence depended on the proposition
that at the date of resumption some investigation and design work had been carried
out, the benefit of which would be available to a potential purchaser in February
2008; but in the after resumption case, some of this work would have to be
redone115. That was because the original work assumed development from east to
west; whereas with the project which led to the resumption, the development would
be carried out logically from west to east. There would also be the need to
reconsider hydraulic work, and the treatment of cut and fill; and, as a result of the
road resumption, there would be a new road alignment. Mr Viney also gave
evidence that the longer period would be required in the after resumption case,
because negotiations with DTMR about road access would be more complex, the
final form of the Centenary Highway interchange not having yet been
determined116.
[69] Although the civil engineers retained by the parties for the Land Court proceedings
had agreed that 12 months would be sufficient for the design and approval process,
the uncontroverted oral submissions for Cidneo pointed out that that agreement was
based on civil engineering considerations only, and did not take into account
planning and traffic issues117.
[70] Mr Brett's adoption of a 12 month period in each case, and no more, was ultimately
based on advice he had from Mr Beard118; although Mr Beard's evidence was that
111 See Appeal Ex 1 pp 8, 12.
112 AR5 pp 1290, 1293.
113 AR5 p 1285.
114 AR1 p 10.
115 See AR1 p 10, lines 20-27.
116 AR1 p 89, lines 5-28.
117 Appeal Record Book Vol 9 (AR9) pp 2168 para 32; 2169 para 38.
118 See AR2 pp 454, line 20 to 455, line 9.
-- 22 of 32 --
23
more time would be required for the traffic impact assessment process in the before
resumption case than in the after resumption case119.
[71] The reasons for judgment in the Land Court made reference to the evidence of Mr
Hamilton and Mr Cumming in support of the longer period in the after resumption
case120. The learned Member adopted the cash flow analyses of Mr Brett, that
adoption carrying with it the acceptance of the shorter time frame for the period
before the commencement of works in the after resumption case. However the
reasons do not set out any analysis of the evidence in support of the longer period,
or any explanation for the rejection of that evidence.
[72] The submissions for DTMR sought to glean an explanation for the implicit rejection
of the evidence of Mr Viney and Mr Cumming on this point. Thus it was said that
the evidence of Mr Cumming "was marginalised"121 and that his evidence was
found to be "unconvincing", by reference to passages in the reasons for judgment122.
It is apparent from a reading of those paragraphs that the learned Member was
referring to the evidence of Mr Cumming so far as it dealt with matters which are
particularly the province of a traffic engineer, namely, traffic generation and flow,
and queue lengths and degrees of saturation predicted for particular intersections.
The learned Member was not considering his evidence on the time likely to be
required prior to the commencement of development work.
[73] The implicit finding of the learned Member as to the length of this period was also
supported, it was submitted on behalf of DTMR, by the learned Member's
preference for the evidence of Mr Beard over the evidence of Mr Viney123. Apart
from a problem which arises because the learned Member has not referred to a
substantial body of evidence which supported Mr Viney's approach to the
appropriate assumption about a contribution for external road works, the preference
for Mr Viney's evidence over Mr Beard's evidence occurred in relation to questions
other than the question now under consideration. It could not be said that in
expressing that preference, the learned Member was addressing the question
whether 12 months or 18 months was the appropriate period to allow before the
commencement of development work, in the after resumption case.
[74] There was a real issue between the parties on this question. It was raised by the
differences in the cash flow analyses, and was the subject of submissions on behalf
of Cidneo in the Land Court124. The matters raised by Mr Viney and Mr Cumming
in support of the longer period are not obviously without substance, so that a failure
to discuss them might be explained on that basis. The reasons for judgment provide
no basis for thinking that the learned Member considered this issue, and decided to
accept the approach taken by Mr Brett on the basis of such a consideration. So far
as is apparent from the reasons, the opposite is true.
[75] The submission made on behalf of DTMR that the matter is covered by the
assumption, apparently derived from Spencer, that the parties are aware of all
relevant facts, is novel. No authority was cited in support of it. It is difficult to see
119 AR4 p 1061.
120 RJ [103]-[104].
121 ROAA para 23.
122 See RJ [105]-[116], [118].
123 RJ [167], [205], [206], [259], [261], [264].
124 See AR9 p 2169.
-- 23 of 32 --
24
how the assumption would account for the existence of a traffic study, no doubt to
be presented in support of a development application. The submission should not
be accepted.
[76] It follows that Ground 2 should be upheld.
Appeal Ground 3: balance of period for completion of project
[77] There was a further difference of some eight months in the time assumed by Mr
Brett for the completion of the development and sale of lots resulting from the
project, and the period assumed by Mr Hamilton. Some explanation for this
difference is found in the difference in the rates of sale of lots in Stage 3. Leaving
aside what were described as "presales", there were 15 lots to be sold from this
stage, Mr Brett assuming a sale rate of two per month, and Mr Hamilton one per
month. The basis for this difference was explained in Cidneo's written submissions
as being that Mr Brett's approach was "stock driven", while Mr Hamilton's approach
was "cost driven"125.
[78] Another factor affecting when sales in Stage 3 might be completed is the
construction program assumed for the cash flow exercise. The submissions for
Cidneo pointed out that Mr Brett's approach involved overlapping construction
periods for stages. The relationship between this aspect of his approach, and the
difference in the rates of sale in Stage 3, was not explained.
[79] The written submissions for Cidneo contended, in effect, that Mr Hamilton's
approach should have been preferred. However, it is also submitted that the learned
Member failed to resolve these differences in the approaches of the valuers; or
alternatively he did not give adequate reasons for preferring the approach of Mr
Brett.
[80] The learned Member expressly identified the grounds on which he adopted Mr
Brett's approach in relation to the rate of sales in preference to that of Mr
Hamilton126. They were the reservations he earlier expressed with respect to the
evidence of Mr Hamilton; his acceptance of most of the evidence of Mr Brett; and
in particular his acceptance "that Mr Brett's assessment of economic conditions
relevant to the setting of prices and the uptake of developed land is to be preferred
to Mr Hamilton's"127.
[81] The reservations of the learned Member about Mr Hamilton's evidence were not
better identified. A reading of the reasons for judgment would suggest that he
considered that Mr Hamilton's approach "was driven by an internal rate of return";
while Mr Brett's approach attempted to reflect the reality of the market place, both
in relation to costs and revenue from the sale of land128; Mr Hamilton’s response to
criticism about the application of an analysis of what was referred to as the
125 By reference to AB2 pp 405, lines 36-45; 461, line 33 to 462, line 57; 465, lines 41-55; Appellant’s
Outline of Argument on the Appeal filed 15 November 2013 (AOAA) para 34.
126 RJ [404].
127 RJ [404].
128 RJ [335].
-- 24 of 32 --
25
Motorway Business Park129; and tension between the application of sales evidence
by Mr Hamilton, and his comments on that evidence130.
[82] It follows that the reasons for judgment indicate that the learned Member recognised
the need to determine which rate of sales should be preferred; he expressed a
preference for that adopted by Mr Brett; and he gave brief reasons for doing so. It
cannot be said that he failed to determine the issue. Although brief, his reasons
provide some explanation for his conclusion on this question. However the
adequacy of these reasons requires further consideration.
[83] Mr Brett's cash flow analysis for the after resumption case assumed a rate of sale
(ignoring presales) of one lot per calendar month for the first stages to be developed
(Stages 1 and 2); but adopted a rate of sale of two lots per calendar month for Stage
3, reverting to a rate of one sale per calendar month for Stage 4. The submissions
for Cidneo pointed out that Mr Brett had identified that, by comparison with 2007,
conditions had changed as a result of increasing interest rates and tightening credit,
and an awareness of difficult economic conditions, both in Australia and elsewhere.
These matters had the consequence that by February 2008 "both the cost of finance
and its availability had become more difficult than was previously the case"131. He
therefore considered that "at least a levelling of market demand and values was a
reasonable anticipation at this time"132. The potential significance of this evidence
in the context of his cash flow analysis is apparent from his oral evidence, where he
made it clear that he was proceeding "on the basis of the kind of market that
prevailed in 2007"133.
[84] The other matter raised by Ground 3 related to the construction program. This
matter (and the rate of sales) had been raised before the Land Court134. On Mr
Brett's approach the construction of Stage 3 commenced before the completion of
the construction of Stage 2, and before any income was received135. Mr Whitelaw is
a chartered accountant who has specialised in property development financing with
experience using cash flow modelling as a tool for seeking, gaining or providing
finance in respect of development projects136. He gave evidence that the early
commencement of Stage 3 assumed by Mr Brett was uncommercial, and not the
action of a prudent developer137. In cross-examination, Mr Brett said that there was
"a degree of realism" in Mr Whitelaw's review138.
[85] It is not particularly easy to discern how the learned Member dealt with these
matters. He made a number of comments pointing out that the results from a cash
flow analysis might be significantly affected by the assumptions made, and the
results might be "wild guesses"139. He also said that sales rates are based on
129 RJ [370]-[373].
130 RJ [374]-[378].
131 AR5 p1367.
132 AR5 p 1367.
133 AR2 p 466, lines 1-24; see also pp 464, lines 30-43; 405, lines 55-57; 461, lines 34-37; 462, lines 22-
26.
134 AR9 pp 2201-2203.
135 AR1 pp 316-317, especially p 317, lines 27-32.
136 AR7 p 1780, para 5.
137 AR7 p 1782, paras 19-21.
138 AR2 p 418, lines 36-37.
139 RJ [279], [280], [283], [325].
-- 25 of 32 --
26
"speculation and estimation"140; and was sceptical about the utility of attempting to
determine the appropriate assumption about staging, amongst other things141. He
expressed the view that the best that could be done was "to prefer one approach over
another"142. Nevertheless, he recorded that both matters relied upon by Cidneo were
in issue143. After an analysis of sales, and their application by Mr Hamilton, a
matter about which he was critical144, the learned Member expressed the view that
the sales rates and rates of development had "no great impact on the overall
result"145. Nevertheless he expressly accepted Mr Brett's "assessment of economic
conditions relevant to … the uptake of developed land"146; but made no express
finding about Mr Brett's approach to construction.
[86] The learned Member’s observations about the difficulties with the use of a cash
flow analysis only emphasised the importance of the assumptions on which each
analysis was based. There was a real dispute about whether Mr Brett erred in his
approach to the commencement of the construction work for Stage 3, in the after
resumption case. It was therefore necessary for the learned Member to determine
whether or not Mr Brett's approach, particularly to the construction program, was
correct. Indeed, Mr Brett described the "primary difference" between his analysis
and that of Mr Hamilton as being "the gaps between the release of stages"147, which
appears to be a consequence of the differences in relation to this program. However
the reasons for judgment do not indicate that the learned Member applied his mind
to deciding this issue. It may be said that the issue was implicitly decided by the
learned Member's adoption of the analysis undertaken by Mr Brett. If so, the
reasons do not reveal any evaluation of the evidence of Mr Whitelaw and Mr
Hamilton, critical of Mr Brett's approach. If, in fact, that evidence were evaluated
and rejected, the reasons failed to disclose the basis on which that was done.
[87] The learned Member's acceptance of Mr Brett's assessment of economic conditions
relevant to the uptake of developed land148 appears to amount to a finding that he
accepted Mr Brett's evidence on the rate of sale of lots in Stage 3. However, the
reasons do not explain the learned Member’s approach, in light of Mr Brett's views
about economic conditions in February 2008, on which Cidneo had relied.
Acceptance of his evidence of economic conditions would include an acceptance of
his view about them in February 2008.
[88] These conclusions provide a sufficient basis on which to uphold the appeal on
Ground 3. It should, however, be said that there must be a real doubt about the
validity of Mr Brett's approach to the rate of sales. As has been mentioned, he
proceeded on the basis that the speculative market of 2007 would continue,
notwithstanding the increases in interest rates up to February 2008, and the
increased difficulty in obtaining finance. Particularly against that background, there
is a very real question whether the hypothetical prudent vendor and purchaser would
assume the continuation of a speculative market for a further period approaching
140 RJ [347].
141 RJ [350]-[351].
142 RJ [352].
143 RJ [353].
144 RJ [356]-[388].
145 RJ [389].
146 RJ [404].
147 AR2 p 460, lines 5-9.
148 RJ [404].
-- 26 of 32 --
27
four years149. If Mr Brett’s rate of sales were not adopted, that could well have
implications for the assumed construction program. With slower sales, a developer
might be more inclined to delay construction for Stage 3, to reduce its risk and its
interest liabilities.
Ground 4: internal rate of return
[89] Cidneo's submissions criticised Mr Brett's approach to the internal rate of return in
his cash flow analyses on two bases. The first was that he adopted a value to
generate an internal rate of return, when, it was submitted, the correct approach was
to adopt an internal rate of return, and then generate a value for the land. The
second was that his internal rate of return was unrealistically low. It was submitted
that the learned Member failed to deal with this question.
[90] As the submissions for DTMR point out, the learned Member in fact did consider
the question, and addressed the criticisms of Mr Brett's approach150. The learned
Member recorded that Mr Brett accepted that, in the ordinary course, an internal rate
of return should be adopted, and a land value then arrived at, by the use of the cash
flow analysis. However, it is apparent from the evidence referred to by the learned
Member that Mr Brett formed the view that on this approach, a value would be
attributed to the land which was not consistent with market evidence151. That led
him to adjust his internal rate of return to produce an outcome consistent with the
market value attributed to the land based on sales evidence. It is clear that the
learned Member accepted the explanation, and the appropriateness of Mr Brett's
approach. The learned Member's reasons on this issue, though brief, are adequate.
[91] In Cidneo's oral submissions on the appeal, an explanation was given of Mr Brett's
approach152. As has been mentioned, it commenced with the derivation of an
internal rate of return from an adopted value for Cidneo's land of $60,000,000 in the
before resumption case. This rate was then used to determine the value of the
retained land. It might be observed that the internal rate of return adopted by Mr
Hamilton for his after resumption cash flow analyses was also derived in a similar
fashion153.
[92] Once it is assumed that the market evidence showed the value of the land in the
before resumption case to be $60,000,000, the cash flow analysis, based on the
balance of Mr Brett's assumptions, inevitably resulted in the internal rate of return
which he adopted post-resumption. Cidneo's case was that the rate of return in both
cases was unreasonably low154. The correctness of its case would throw doubt on
the assumptions, including the assumed value of the land before resumption.
However, if the assumptions were correct, the internal rate of return must be low. If
Mr Brett's assumptions are accepted, then no error has been shown in his approach
to internal rates of return. To the extent that there has been, or may be, successful
challenges to some of his assumptions, that provides a basis for upholding the
appeal on other grounds. However Cidneo has not established that the appeal
should succeed on Ground 4.
149 That is, until the finalisation of sales in Stage 3: see AR5 p 1420.
150 RJ [391]-[400].
151 RJ [393]-[394].
152 See T 1-71.
153 See AR5 p 1285.
154 AR2 p 473, lines 2-4.
-- 27 of 32 --
28
Cross-appeal Ground 1: use of hindsight to determine road works contribution
[93] The learned Member rejected DTMR's submission that the contribution ultimately
imposed by DTMR in respect of the development of Cidneo's land could be
considered, to determine the contribution which should be assumed for the purposes
of the cash flow analyses155. DTMR submitted on the appeal that the contribution is
in truth an element of injurious affection or severance damage, for the assessment of
which the Court may take into account facts known at the time of assessment156.
DTMR's submissions referred to the language in s 20(1)(a) of the AL Act,
submitting that the contribution was in fact an element of one of the two heads of
damage as described in that paragraph.
[94] The submissions for Cidneo point out that, what the Land Court determined was the
value of Cidneo's land at the date of resumption, assuming first that no resumption
were to occur; and secondly on the basis that part of the land was then resumed.
The determination of the value of the land on each basis required a consideration of
the likely contribution for external road works. That was an element of the
assessment of its value, in each case. Cases where subsequent events were taken
into account to determine compensation were cases where there were separate
claims for severance or injurious affection157.
[95] The imposition of a requirement to pay contributions for external road works cannot
sensibly be said to be (in the language of s 20(1) of the AL Act) "damage … caused
by … the severing of the land taken from other land of the claimant".
[96] It is arguable that such a contribution might satisfy the description from s 20 of
"damage … caused by … the exercise of any statutory powers by the constructing
authority otherwise injuriously affecting the claimant's other land (from which the
resumed land is taken)". The words reproduced in parentheses are an attempt to
state the effect of the words "mentioned in subparagraph (i)" which appear at the
end of s 20(1)(a)(ii).
[97] However, the question then arises whether the imposition of a contribution for
external road works, as part of an approval for development of the land retained by
the land owner, in truth comes within s 20(1)(a)(ii) of the AL Act. In character, a
requirement for such a contribution is not different from a requirement which some
other authority might require for some other form of external works, for example
relating to water supply, drainage, or the supply of electricity. On DTMR’s own
case on the appeal, it has to be taken into account to determine the value of the land,
before resumption, when no question of severance or injurious affection can arise.
Further, the imposition of the contribution is not an act of DTMR as constructing
authority, that is, when carrying out the project which led to the resumption158.
Rather, it is a consequence of its role in the approval process, as part of the planning
regime which, at the time of the resumption of the land, regulated development in
this State159. Nor does a decision of DTMR as a concurrence agency, requiring a
155 RJ [224]-[235].
156 Relying in particular on Adelaide Fruit, 90; see also Mio Art Ltd, 10-11 [30], 26 [75].
157 For example Barnes; Adelaide Fruit.
158 Compare Suntown, 207-208; Marshall v Director-General, Department of Transport (2001) 205
CLR 603, 616 [20], 617-619 [25], 625 [45].
159 See in particular s 3.5.11(1) of the IP Act; together with the definition of "concurrence agency" in
Schedule 10 of that Act, and the provisions of Part 3 of Chapter 3, particularly ss 3.3.16, s 3.3.18.
-- 28 of 32 --
29
contribution as a condition of a development approval, amount to the exercise by it
of a statutory power "injuriously affecting the claimant’s (retained) land … ". Such
a condition is simply part of the price for carrying out a particular form of
development of the land, but does not affect the land itself. It might also be
observed that the contribution identified in the concurrence agency response
appeared to relate in part to works beyond the project (in particular, the upgrading
of the Boundary Road/Logan Road interchange).
[98] Moreover, the question of the likely road works contribution did not arise in the
context of determining compensation for injurious affection under s 20(1)(a)(ii) of
the AL Act. Rather, it arose in the context of determining the value of the land
retained by Cidneo, at the date of resumption. That value must be determined by
reference to the approach adopted in Mio Art. While it is commonly accepted that
the approach described as the "before and after" approach will identify a sum
representing both the value of land lost, and compensation for severance and
injurious affection, it nevertheless requires the determination of the value of the
retained land at the date of the resumption. The fact that the separate determination
of compensation for injurious affection might take into account events which occur
after the resumption is of no assistance in determining the value of the retained land,
at the date of resumption.
[99] It follows that the Land Court Member correctly refused to take into account a
contribution agreed upon in 2011.
[100] DTMR submitted that, in the Land Court, Cidneo's case was that the contribution
likely to be imposed on the development of the land by DTMR caused either
severance damage or injurious affection to its retained land, for the purposes of s
20(1)(a) of the AL Act; and accordingly it should not be permitted, in the cross-
appeal, to assert that the contribution was an element of the value of the land, rather
than an aspect of severance damage, or damage resulting from injurious affection.
Particular reliance was placed on paragraph 14(e) of Cidneo's Statement of Facts
and Contentions in the Land Court160. DTMR submitted that, had Cidneo pleaded
that the contribution was an element of the value of the land, it might have
conducted a further challenge to Cidneo’s pleading.
[101] It might be noted that in paragraph 14(e) of the Statement of Facts and Contentions,
Cidneo alleged that the imposition of the contribution both caused severance
damage or injurious affection to its retained land; and reduced its value. At least on
one reading, the latter assertion would justify Cidneo's reliance on the road works
contribution as a matter relevant to determining the value of the retained land, in the
after resumption case. That in fact is how the case was conducted by Cidneo in the
Land Court. It was a case which DTMR sought to meet, by leading evidence from
Mr Beard as to the amount to be taken into account in respect of the likely
contribution, for the purposes of the cash flow analyses. Mr Beard suggested an
amount of $3,000,000161; which differed from the amount of $1,087,110.76, the cost
of what was ultimately agreed to in 2011162.
160 AR3 p 748.
161 See RJ [259].
162 RJ [225]-[227].
-- 29 of 32 --
30
[102] DTMR therefore was, in the Land Court, in a position to meet a case where Cidneo
alleged that the likely contribution for external road works was to be taken into
account in determining the value of its land at the date of resumption. On one view,
that was consistent with Cidneo's pleaded case. Cidneo's submissions on the cross-
appeal as to the character of this contribution are consistent with the cases
conducted by the parties in the Land Court (although DTMR also contended for the
determination of each head of compensation separately)163. There is no difficulty in
the case Cidneo advanced on the appeal.
Cross-appeal Ground 2: compensation should be determined separately under each
of the heads in s 20(1) of AL Act
[103] For DTMR it was submitted that the fair assessment of compensation meant that
Cidneo should not recover more for the impact of injurious affection and severance
on its land than was fair164, and accordingly that compensation for these should be
assessed by reference to the contribution actually required by DTMR. That would
carry with it a separate assessment for the value of the land taken. Depending upon
the value adopted, that would result in compensation of either $5,622,110, or
$5,877,800. DTMR's oral submissions have pointed to the difference between the
only evidence of the value of land taken ($4,535,000) and the amount claimed by
Cidneo, apparently to demonstrate that most of the compensation was not referrable
to the value of the land taken, and accordingly fell under one of the other heads of
compensation identified in s 20(1) of the AL Act.
[104] The submissions for Cidneo referred to the fact that the valuers recognised that their
role was to assist the Land Court to determine compensation for diminution in the
value of Cidneo's land resulting from "the scheme of the resumption". They agreed
that the appropriate methodology was to determine the value of the land
immediately before, and unaffected by the resumption, and its value immediately
after the resumption. They agreed that cash flow analyses provided the best method
of carrying out this purpose165. The learned Member referred to the agreement of
the valuers about the correct approach in his reasons for judgment166. The learned
Member recorded judicial support for the approach167. Implicit in the submission is
the proposition that the valuers agreed that the “before and after” method would
capture compensation under all heads.
[105] The “before and after” method is often regarded as appropriate for the determination
of compensation, when only part of a landowner’s land is resumed168. It captures all
heads of compensation, as well as any enhancing effect of the project169; and avoids
163 See, for example, AR9 p 2223 para 60.
164 By reference to Director of Buildings and Lands v Shun Fung Iron Works Ltd [1995] 2 AC 111, 125;
see CMB No 1 Pty Ltd v Cairns City Council [1999] 1 Qd R 1, 15-16; Transport For London v
Spirerose Ltd [2009] 1 WLR 1797, 1822.
165 AR4 p 1189.
166 RJ [273].
167 RJ [275].
168 See the discussion of the topic in Alan Hyam, The Law Affecting Valuation of Land in Australia
(Federation Press, 4th ed, 2009), 174-178; Marcus Jacobs, Law of Compulsory Land Acquisition
(Lawbook Co, 2010) (Jacobs), 454-456 [24.100].
169 Section 20(3) of the AL Act; see Mir Bros Unit Constructions Pty Ltd v Roads and Traffic Authority
(NSW) [2006] NSWCA 314 at [11], cited in Jacobs at 454 [24.100].
-- 30 of 32 --
31
the risk of double counting170. One author, after a survey of such cases where the
method was not used, concluded that they demonstrated special circumstances; and
were not authority for the proposition that the method could be rejected in the
absence of such circumstances171. Whether or not that be correct, a proper basis
must be shown for concluding that a court erred in using this method in such a case.
[106] DTMR's submission appeared to be that the use of the before and after method
would result in an unfair assessment of compensation. If the appeal is to be
allowed, the submission is, at least to some extent, speculative. Moreover, the
matters referred to in relation to Ground 1 of the cross-appeal show that the
contribution for external road works expected to be imposed in respect of a
particular development proposal is a matter relevant to the value of the land at the
date of resumption. As was held in Mio Art, that may not be determined by
reference to the knowledge of subsequent facts (save where those facts demonstrate
the existence of facts at the date of resumption, known to the parties)172. It would
follow that where events subsequently turn out to be different from those known, or
taken to be likely, at the date of resumption, that does not have the consequence that
the assessment of compensation is unfair.
[107] DTMR has not identified the basis on which Ground 2 of the cross-appeal should be
upheld.
Disposition of appeal and cross-appeal
[108] The appeal should be allowed, and the cross-appeal dismissed. At the hearing, the
parties indicated that, should the appeal be upheld, they wished to make further
submissions about the disposition of the case. It is therefore appropriate to hear
further submissions from the parties about the orders to be made.
PETER LYONS J
CAC MacDONALD
PRESIDENT OF THE LAND COURT
WA ISDALE
MEMBER OF THE LAND COURT
170 Parramatta City Council v Gestetner Pty Ltd (1978) 37 LGRA 246, 254; cited in Jacobs at 458
[24.120].
171 Jacobs at 458 [24.120] – 460 [24.130].
172 Mio Art, 6-27 [79].
-- 31 of 32 --
32
IN THE LAND APPEAL COURT
OF QUEENSLAND
LAC006-13
BETWEEN
Cidneo Pty Ltd
Appellant
and
Chief Executive, Department of Transport and Main Roads
Respondent
Before The Honourable Justice P Lyons,
Mrs CAC MacDonald and Mr WA Isdale
BRISBANE
The Seventeenth day of June 2014
The Court ORDERED that:
1. The appeal is allowed.
2. The cross-appeal is dismissed.
3. The matter is remitted to the Land Court for the determination of compensation.
4. The Chief Executive, Department of Transport and Main Roads pay the costs of the
appeal and the cross-appeal, including reserved costs, if any, on the standard basis.
By the Court
Registrar
-- 32 of 32 --
Official source: https://www.sclqld.org.au/caselaw/QLAC/2014/003