BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors [2013] QCA 394 [2015] 1 Qd R 228
SUPREME COURT OF QUEENSLAND
CITATION: BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty
Ltd & Ors [2013] QCA 394
PARTIES: BM ALLIANCE COAL OPERATIONS PTY LTD
ABN 67 096 412 752
(appellant)
v
BGC CONTRACTING PTY LTD
ABN 88 008 766 407
(first respondent)
RUSSELL WELSH
(second respondent)
RICS DISPUTE RESOLUTION SERVICE
(third respondent)
FILE NO/S: Appeal No 3287 of 2013
SC No 4422 of 2012
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 20 December 2013
DELIVERED AT: Brisbane
HEARING DATE: 28 November 2013
JUDGES: Holmes and Muir JJA and Ann Lyons J
Separate reasons for judgment of each member of the Court,
each concurring as to the order made
ORDER: The appellant is directed to consult with the respondent
and bring in draft minutes of order reflecting these
reasons within 28 days of today’s date.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
ADJUDICATION OF PAYMENT CLAIMS – where the
appellant (BMA) entered into a contract with the first
respondent (BGC) for the construction of a dam – where
BGC served a payment claim on BMA pursuant to the
Building and Construction Industry Payments Act 2004 (Qld)
(the Act) which included claims for alleged latent conditions
and termination costs – where the payment claim was
referred to adjudication and BGC was awarded a progress
payment which included sums on account of latent conditions
and termination costs – where BMA sought a declaration that
-- 1 of 28 --
2
the adjudication decision was void as a result of three
jurisdictional errors – where the primary judge held that the
adjudicator had made a jurisdictional error in the
determination of the termination costs claim – where, on
13 November 2012, the primary judge declared the decision
of the adjudicator void – where, on 22 March 2013, the
primary judge revoked the declaration and dismissed BMA‘s
application upon BGC undertaking to repay to BMA the
portion of the adjudicated amount affected by jurisdictional
error – where BMA submits that the primary judge‘s
conclusion that a decision affected by jurisdictional error was
not necessarily invalid for all purposes and has some residual
effect was an error of law – whether the primary judge erred
in finding that the adjudication decision, which he held to be
affected by jurisdictional error, retained effect until he
exercised his discretion to grant a declaration or make an
order quashing or setting aside the decision – whether the
primary judge erred in law in withholding the relief sought by
BMA – whether the matter should be remitted to the
adjudicator for determination according to law
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
ADJUDICATION OF PAYMENT CLAIMS – where
cl 26.3(b) of the contract requires BGC to give written notice
to BMA of the encountering of latent conditions – where,
within 10 business days of notification, the parties must
―negotiate in good faith any changes to the Price and/or time
for completion of the Services as a result of Latent
Conditions‖ and, in the absence of agreement, must refer the
matter to an independent expert for determination – where the
primary judge held that cl 26.3 was predicated on the
existence of latent conditions and any dispute as to their
existence was to be resolved by the general dispute resolution
provision, cl 37 – where, contrary to BMA‘s contentions, the
primary judge held that the fact that the machinery for
assessment of value under the clause had not been advanced
did not alter BGC‘s entitlement under the contract to be paid
in respect of a latent condition – where the primary judge
held that the award by the adjudicator in respect of latent
conditions did not constitute a jurisdictional error – where
BMA contends that cl 26.3 was intended to deal with all
aspects of a dispute concerning latent conditions, including
the determination of the existence of a latent condition –
whether cl 26.3 operates subject to the determination of the
existence of latent conditions under cl 37 – whether the
adjudicator committed a jurisdictional error in awarding BGC
a progress payment which included a sum in respect of latent
conditions
-- 2 of 28 --
3
INTEREST – RATE OF INTEREST AND COMPOUND
INTEREST – RATE IN OTHER CASES – where BMA
sought interest on the sums repayable to it at the rate
prescribed in practice directions for default judgments –
where the primary judge accepted BGC‘s contentions that the
appropriate rate was that payable on term deposits with
financial institutions – where BGC‘s evidence of commercial
rates of interest awarded on investments was uncontested –
whether the primary judge erred in accepting and acting on
evidence of commercial interest rates when awarding interest
on the sum repayable to BMA
Building and Construction Industry Payments Act 2004 (Qld),
s 12, s 13, s 14, s 18, s 26, s 30, s 31
Civil Proceedings Act 2011 (Qld), s 58(3), s 59(3)
Atlantic Civil Pty Ltd v Water Administration Ministerial
Corporation (1992) 39 NSWLR 468, cited
Beaufort Developments (NI) Ltd v Gilbert-Ash NI Ltd [1999]
1 AC 266; [1998] UKHL 19, cited
BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty
Ltd & Ors [2012] QSC 346, related
Cardinal Project Services Pty Ltd v Hanave Pty Ltd (2011)
81 NSWLR 716; [2011] NSWCA 399, considered
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010)
78 NSWLR 393; [2010] NSWCA 190, cited
Clyde Bergemann v Varley Power [2011] NSWSC 1039,
considered
Craig v South Australia (1995) 184 CLR 163; [1995] HCA 58,
considered
Emergency Services Superannuation Board v Davenport
[2004] NSWSC 697, considered
Interchase Corporation Ltd (in liq) v Grosvenor Hill
(Queensland) Pty Ltd (No 3) [2003] 1 Qd R 26; [2001]
QCA 191, cited
Jackson v Purton [2011] TASSC 28, cited
Jadwan Pty Ltd v Secretary, Department of Health and Aged
Care (2003) 145 FCR 1; [2003] FCAFC 288, considered
Kirk v Industrial Court (NSW) (2010) 239 CLR 531;
[2010] HCA 1, considered
Lansen v Minister for Environment and Heritage (2008)
174 FCR 14; [2008] FCAFC 189, cited
Leung v Minister for Immigration and Multicultural Affairs
(1997) 79 FCR 400; [1997] FCA 1313, considered
Minister for Immigration and Multicultural Affairs v Bhardwaj
(2002) 209 CLR 597; [2002] HCA 11, considered
Minister for Immigration and Multicultural and Indigenous
Affairs v SGLB (2004) 78 ALJR 992; [2004] HCA 32, cited
Morris v Riverwild Management Pty Ltd (2011)
284 ALR 413; [2011] VSCA 283, cited
Plaintiff S157/2002 v The Commonwealth (2003) 211 CLR 476;
[2003] HCA 2, considered
-- 3 of 28 --
4
R v Commonwealth Court of Conciliation and Arbitration; Ex
parte Ozone Theatres (Aust) Ltd (1949) 78 CLR 389; [1949]
HCA 33, cited
Serisier Investments Pty Ltd v English [1989] 1 Qd R 678,
cited
South East Civil & Drainage Contractors P/L v AMGW P/L
& Ors [2013] 2 Qd R 189; [2013] QSC 45, cited
SZFDE v Minister for Immigration and Citizenship (2007)
232 CLR 189; [2007] HCA 35, cited
Truenergy Australia Pty Ltd v Minister for Industrial
Relations (2005) 93 SASR 393; [2005] SASC 490, cited
COUNSEL: P J Dunning QC, with G D Beacham, for the appellant
R A Holt QC, with S B Hooper, for the first respondent
No appearance for the second and third respondents
SOLICITORS: Herbert Smith Freehills for the appellant
McCullough Robertson for the first respondent
No appearance for the second and third respondents
[1] HOLMES JA: I agree with the reasons of Muir JA and the orders he proposes.
[2] MUIR JA: Introduction The appellant, BM Alliance Coal Operations Pty Ltd
(BMA), entered into a contract with the first respondent, BGC Contracting Pty Ltd
(BGC), under which BGC agreed to construct a dam at BMA‘s Goonyella Riverside
Mine in central Queensland. On 10 February 2012, BGC served a payment claim
on BMA, pursuant to the Building and Construction Industry Payments Act 2004
(Qld) (the Act), claiming a progress payment of $35,806,055.99 (excluding GST).
That amount was comprised of various components including claims for an alleged
latent condition and termination costs. BMA served a payment schedule under s 18
of the Act which contained a scheduled payment amount of nil and did not include
the great bulk of the amounts claimed by BGC for latent conditions and termination
costs. The payment claim was referred to adjudication and, on 7 May 2012, the
adjudicator awarded BGC a progress payment of $25,600,758.64 (excluding GST),
which included sums on account of latent conditions and termination costs.
[3] BMA commenced proceedings in the Supreme Court seeking a declaration that the
adjudication decision was void as a result of two jurisdictional errors allegedly
made by the adjudicator in the determination of the latent conditions claim and
another such error in the determination of the termination costs claim. The primary
judge upheld only the latter allegation but, in the exercise of his discretion, he
refused to make the declaration of invalidity sought by BMA and dismissed BMA‘s
application upon BGC undertaking to repay to BMA the portion of the adjudicated
amount in respect of which the adjudicator had made a jurisdictional error.
[4] BMA appeals against the primary judge‘s orders on the grounds discussed below.
Ground 1 – the primary judge erred in construing cl 26.3 of the contract
[5] As the arguments advanced in respect of this ground concerned the construction of
cl 26.3 and cl 37 of the contract, it is desirable to set them out.
-- 4 of 28 --
5
―26.3 Subject to clause 26.2(c), the parties agree that conditions
encountered on, in, under, near, or in connection with, the Site
which have not been disclosed to the Contractor, or of which
the Contractor could not otherwise reasonably have anticipated
or been aware (‗Latent Conditions‘), are not within the
Contractor‘s risk, and the Price does not contain allowance for
them. If Latent Conditions are encountered, the Contractor
must:
(a) use its reasonable endeavours to minimise the effect of
such Latent Conditions on the Price and time for
completion of the Services; and
(b) promptly (but no later than 28 days after encountering the
Latent Conditions) give written notice of the Latent
Conditions to the Principal, including a description of the
Latent Conditions, and their anticipated impact (if any) on
Price and time for completion of the Services.
Within 10 Business Days after receipt by the Principal of a
notice given under clause 26.3(b), the parties will meet to
negotiate in good faith any changes to the Price and/or time
for completion of the Services as a result of the Latent
Conditions. If no agreement is reached within a further 10
Business Days, the parties must refer the matter to an
independent expert for determination. If the parties cannot
agree an independent expert, the independent expert will be
nominated by the Institute of Arbitrators and Mediators
Australia. The independent expert will determine any
impact on Price by reference to the rates and prices specified
in Schedule F, and to the extent that Schedule F does not
apply, by reference to reasonable rates or prices. The parties
will share the costs of the independent expert equally, and
will use their reasonable endeavours to ensure that the
independent expert makes his or her determination promptly.
The independent expert‘s determination will be binding on
the parties.
…
37. Dispute Resolution
37.1 Until the relevant provisions of this clause 37 have been
complied with, no Party shall commence any action, bring
any proceedings or seek any relief or remedy in a court or by
arbitration, except that nothing in this clause 37 prevents
either Party from seeking interlocutory or equitable relief
from a court.
37.2 Any issue, dispute, controversy or claim (a ‗Dispute‘) arising
out of or in relation to this Agreement must be the subject of
a notice from the disputing Party to the other Party setting
out the material particulars of the Dispute (‗Notice‘), and
must immediately be referred to the Representative of each
-- 5 of 28 --
6
Party who must endeavour in good faith to resolve the
Dispute expeditiously.
37.3 If the Dispute has not been resolved within 7 days of
reference to the Representatives pursuant to clause 37.2 the
Dispute must be referred to the Dispute Resolution
Representative of each Party who must endeavour in good
faith to resolve the Dispute expeditiously.
37.4 If the Dispute has not been resolved or an alternate method
of resolving the Dispute has not been agreed within 7 days
of reference to the Dispute Resolution Representatives
pursuant to clause 37.3, or a longer period if the Parties
agree, the Dispute may be submitted by either Party to
mediation. If the Dispute is submitted to mediation and the
Parties do not, within 7 days after the Dispute is submitted to
mediation, agree on:
(a) a mediator and the mediator‘s compensation;
(b) the procedure for the mediation; or
(c) the timetable of each step of the procedure,
the mediation will be conducted in accordance with the
Australian Commercial Dispute Centre‘s Mediation
Guidelines in force at the time that the Dispute is referred.
37.5 If a Dispute is not resolved within 60 days after the date of
the Notice given in accordance with clause 37.2, either Party
who has complied with this clause 37 may terminate the
dispute resolution process undertaken and commence court
proceedings in relation to the Dispute.‖
The primary judge’s findings and BGC’s contentions in respect of the construction
argument
[6] Before the adjudicator, BMA argued that under cl 26.3 an entitlement to be paid in
respect of a latent condition could arise only by operation of the mechanism set out
in the clause – i.e. by the agreement of the parties or, failing that, the determination
of the independent expert. The adjudicator awarded an amount for which no
contractual entitlement existed rather than assessing BGC‘s contractual entitlement
as he was required to do by s 14 of the Act. Consequently, the award by the
adjudicator constituted a jurisdictional error.
[7] The primary judge held that cl 26.3 provided a mechanism for valuing an
entitlement in respect of latent conditions and that its operation was predicated on
the existence of latent conditions. His Honour reasoned as follows. Where BMA
did not acknowledge the existence of latent conditions, any dispute about their
existence was required to be resolved by ―the processes contained in the contract for
dispute resolution, in particular cl 37‖.1 That cl 26 is premised upon an entitlement
1 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors [2012] QSC 346 at [19].
-- 6 of 28 --
7
to be paid for latent conditions is reinforced by cl 26A, which provides, inter alia,
that ―the matters listed in clause 26.3, are not within the Contractors risk and the
Price does not contain adequate allowance for them‖.
[8] Clause 26, as a whole, assumes the existence of an entitlement to be paid for the
impact of latent conditions. The fact that the machinery for assessment of value
under the clause had not been advanced did not alter BGC‘s entitlement under the
contract to be paid. Consequently, BGC was able to seek payment in respect of that
entitlement in the form of an interim payment under the Act. There was, thus, no
jurisdictional error.
[9] The primary judge stated that, had he concluded that the adjudicator erred in
construing the contract and in concluding that BGC had an entitlement under cl 26
to claim for latent conditions, he would nevertheless have found that there was no
jurisdictional error. Rather, any such error would have been made in the course of
the decision making process based on what the adjudicator considered to be the true
construction of the contract and the merits of the claim.
[10] On appeal, BGC relied on the primary judge‘s reasons supplemented by the
following:
(a) Had the parties intended that the expert appointed under cl 26.3 would
determine entitlement as well as value, the language of the clause would have
been different and not simply have assumed the existence of latent conditions.
The second full paragraph of the clause requires the parties to meet to negotiate
―any changes to the Price and/or time for completion of the Services‖. It does
not require the parties to negotiate regarding the existence of latent conditions.
(b) If no agreement is reached by the parties, consequent on negotiations, the parties
must refer ―the matter to an independent expert for determination‖. The
―matter‖ plainly relates back to ―any changes to the Price and/or time for
completion of the Services‖.
(c) The reference to ―the Latent Conditions‖ in cl 26.3(b) further confirms that
cl 26.3 assumes the existence of latent conditions.
(d) Disputes about latent conditions are often complex and protracted. Recourse to
expert opinions is normally necessary. Consequently, most disputes of this
nature are not suited to determination by a single expert; a person with expertise
in the pricing and/or timing of construction work may well lack any expertise
relevant to the determination of the existence, nature and extent of a latent
condition.
BMA’s contentions on the construction question
[11] BMA‘s submissions in relation to the construction of cl 26.3 may be summarised as
follows. The analysis of cl 26.3 should commence with the appreciation that the
clause manifests an intention to protect both contractor and principal should latent
conditions be encountered or alleged. The contractor is protected by the prompt and
conclusive determination of its entitlement. The principal is protected by ensuring
that if a latent condition claim is asserted it is made and determined swiftly.
Although cl 26.3 speaks of latent conditions as if they in fact existed, the language
is simply a convenient way of referring to the condition for which the claim is made
-- 7 of 28 --
8
and in respect of which the clause will operate. A latent condition, by definition, is
something that the parties assumed did not exist when the contract was entered into
and, consequently, is something which one can assume would have to be proved
before an entitlement to be paid would arise. Even if the clause is predicated upon
the existence of a latent condition, it remains to be determined, in the event of
a dispute, whether the latent condition exists and how the dispute as to its existence
is to be determined.
[12] There are good practical reasons for the parties to have intended that all aspects of
the dispute be dealt with by cl 26.3. The matters relevant to the determination of the
existence of a latent condition would be relevant to the extent of any such condition
and therefore to the amount of money that BGC should be paid on account of it. It
is not sensible to have cl 26.3 deal with the extent but not the existence of a latent
condition.
[13] A conclusion that cl 26.3 was intended to deal with all aspects of a dispute
concerning latent conditions is consistent with commercial commonsense and with
the usual incentives underlying an expert determination clause, namely, the swift,
binding and often unchallengeable resolution of a dispute over a particular matter.
The primary judge‘s conclusion, if correct, means that the existence of a latent
condition and its value are to be determined under two different mechanisms, at
different times and by different decision makers. The emphasis on expedition
apparent in cl 26 would become largely pointless.
Consideration
[14] Plainly there are considerations which support the respective constructions of
cl 26.3 urged by the parties. Neither construction is entirely satisfactory. The
strongest points, in my view, in favour of the primary judge‘s construction are: the
implicit confining of the negotiations referred to in cl 26.3 to ―changes to the Price
and/or time for completion of the Services‖ and the implicit bestowal of only that
―matter‖ on the expert. However, in the absence of agreement, the expert will be
unable to decide ―the matter‖ without deciding the existence, nature and extent of
the latent conditions and the extent, if at all, to which BGC should have anticipated
or been aware of the latent conditions (the latent conditions issues) unless those
matters are decided under cl 37.
[15] I do not consider the argument propounded by BGC and noted in paragraph [10](d)
above to be strong. There is no cogent reason why the parties could not have
contemplated the appointment of an expert who could inform himself or herself of
matters involving particular expertise by obtaining appropriate expert opinions.
[16] If cl 37 applies, cl 26.3 is necessarily inconsistent with it. At the latest, a dispute
regarding the latent conditions issues for the purposes of cl 37.2 will have arisen, if
no agreement is reached, within 10 business days after the commencement of
negotiations under cl 26.3. The parties are then obliged to refer the matter to an
expert for determination. If cl 37 applies, the dispute must be must be referred to
the ―Representative of each Party‖.2 The cl 26.3 and cl 37 procedures would thus
progress together. If the dispute has not been resolved within seven days of
reference to the representatives, the dispute must be referred to the ―Dispute
Resolution Representative of each Party‖.3 If the dispute has not been resolved or
2 Clause 37.2.
3 Clause 37.3.
-- 8 of 28 --
9
an alternative method of resolving the dispute has not been agreed within seven
days of reference to the Dispute Resolution Representative, or an extended period as
agreed by the parties, the dispute may be submitted by either party to mediation.4 If
the dispute is not resolved within 60 days after notice is given under cl 37.2, a party
who has complied with cl 37 may terminate any dispute resolution process and
commence court proceedings.5 Within the 60 day period and during any litigation
that may result from a failure to resolve the dispute, the processes under cl 26.3
continue until the expert determination is made. That would almost invariably
occur prior to the conclusion of any litigation consequent on a failure to agree.
[17] If cl 37 is intended to operate in respect of a dispute about matters so fundamental to
the operation of cl 26.3 as the latent conditions issues, it is remarkable that cl 26.3
does not expressly or implicitly advert to cl 37, particularly as the timetable in
cl 26.3 assumes that cl 37 has no application.
[18] A plausible explanation for the absence of any reference to cl 37 in cl 26.3 is that it
was assumed that the expert, in order to determine the matters entrusted to him for
determination, would have to first determine the existence, nature and extent of the
latent conditions. The primary judge‘s construction could produce awkward results.
It requires that any dispute as to the existence of latent conditions, in the absence of
agreement, be resolved under cl 37. However, the precise nature and extent of such
latent conditions and the extent to which those conditions depart from the conditions
disclosed or known by BGC when the contract was entered into are critical to the
matters specifically entrusted to the expert for determination. Even if disputes
about these matters are to be left for determination under cl 37, the possibility that
a declaration or order by a court will not provide a satisfactory basis for the expert‘s
determination is obvious. Also, the results of the litigation may well falsify the
basis on which the expert determination was made. Furthermore, if the primary
judge‘s construction is correct, it would have made more sense for the negotiating
period in cl 26.3 to have commenced after the latent conditions issues had been
resolved by agreement or litigation.
[19] That the language of cl 26.3 appears to assume the existence of latent conditions is
not decisive. The clause could have been expressed to make the trigger for its
operation, not the encountering of latent conditions but, the making of a claim by
BGC that latent conditions existed. It is necessarily implicit in cl 26.3, however,
that it operates in respect of such a claim by BGC. The words:
―If Latent Conditions are encountered, the Contractor must:
(a) use its reasonable endeavours to minimise the effect of such
Latent Conditions … ; and
(b) promptly … give written notice of the Latent Conditions to
the Principal, including a description of the Latent
Conditions…‖
apply to a situation in which, rightly or wrongly, BGC forms the opinion that latent
conditions exist such that it should seek a consequential change in price and/or in
the time for completion. Before BGC gives notice under cl 26.3(b), BMA cannot
4 Clause 37.4.
5 Clause 37.5.
-- 9 of 28 --
10
be expected to know of, let alone accept, the existence of the latent conditions that
BGC intends to allege. Nevertheless, the operation of cl 26.3 is triggered by BGC‘s
notice even if it is subsequently determined that the alleged latent conditions do not
exist.
[20] The cl 26.3(b) notice must describe the latent conditions and ―their anticipated
impact (if any) on Price and time for completion‖. BMA, having been so informed,
must consider its position and, within 10 business days of notification, ―negotiate in
good faith any changes to the Price and/or time for completion … as a result of the
Latent Conditions‖. The ―latent conditions‖ to which reference is made are the
latent conditions described in the notice under cl 26.3.
[21] It is implicit in the words ―any changes‖ that the latent conditions notified need not
necessarily result in a change to either price or time for completion. Those words
are repeated in the description of the matter to be determined by the expert.
[22] BGC does not have the right to determine the latent conditions issues unilaterally.
If the parties are unable to agree, the mechanisms for their resolution must be found
either in cl 26.3 or cl 37. If cl 37 applies, the parties‘ intention, manifested in
cl 26.3, that changes in price and/or time for completion be resolved expeditiously
will be seen to be illusory. It would have been apparent to the parties that
agreement on the latent conditions issues was likely to be significantly more
difficult to arrive at than agreement on the price and time implications of the latent
conditions issues once determined. This is a significant consideration, as is the
objective unlikelihood that the parties, having chosen to address the issue of
changes in price and time for completion in a specific clause dealing only with that
topic, would have intended that specific clause to operate subject to a general
dispute resolution provision, the terms of which were inconsistent with the terms of
the specific clause and the application of which would tend to defeat the specific
clause‘s aim of ensuring prompt expert determination.
[23] For the above reasons, the primary judge erred in construing cl 26.3 of the contract.
The Ground that the primary judge erred in failing to find that the adjudicator
made a jurisdictional error in awarding BGC $8,662,655.17 for its latent
condition claim
[24] This ground was not raised in the notice of appeal but was the subject of written and
oral argument.
[25] BGC contended that, even if the primary judge‘s interpretation of cl 26.3 was
incorrect, the adjudicator did not make a jurisdictional error. In addition to relying
on the primary judge‘s reasons, reliance was placed on the following observations
of McDougall J in Clyde Bergemann v Varley Power:6
―… where matters are entrusted to adjudicators for decision, a
decision involving error of law is not, for that reason alone,
a decision beyond jurisdiction. Any other conclusion would be, as
I said and as Hodgson JA agreed in Brodyn, inconsistent with the
statutory scheme. In this context, I note that in Chase at [55],
Spigelman CJ observed that ‗the purpose of the legislative scheme
6 [2011] NSWSC 1039 at [43]–[44].
-- 10 of 28 --
11
[of the Act] is best served by restricting the scope of intervention by
the courts‘.
In determining the amount of a progress payment, adjudicators are
required to consider, among other things, the provisions of the
construction contract under which the claimed entitlement arises
(s 22(2)(b)). Presumably, they are required to do so so that they can
work out ‗the amount calculated in accordance with the terms of‘
that contract. In other words, their task requires them to identify the
contractual provisions that are relevant to quantification of the
amount of a progress payment, to decide (where there is a contest)
the proper construction of those provisions and to apply them to the
facts of the particular dispute. As Palmer J said in Multiplex at [58]:
‗... If determination of a disputed progress claim depends
upon resolution of a question as to what are the relevant
terms of a contract, it must necessarily be implicit in the
jurisdiction conferred on the adjudicator by the Act that
he or she have jurisdiction to decide that question.‘‖
[26] BMA‘s arguments were to the following effect.
[27] Clyde Bergemann is not authority for the proposition that all errors of law are within
the adjudicator‘s jurisdiction.7
[28] Errors of law are not non-jurisdictional merely because they arise in the course of
something that the decision maker is required to consider. In Kirk v Industrial
Court (NSW),8 the High Court held that the Industrial Court had fallen into
jurisdictional error because, in a prosecution under s 15 and s 16 of the
Occupational Health and Safety Act 1983 (NSW) (the OHS Act), it misconstrued
s 15 of the OHS Act and failed to comply with the rules of evidence by permitting
the prosecution to call the defendant as a witness. The construction of the OHS Act
and the admissibility of evidence were matters which the Industrial Court was
required to consider in the course of trying the case, but were jurisdictional errors as
they led the Court to misapprehend the nature and limits of its power.9
[29] Here the error was jurisdictional because the adjudicator disregarded a limitation on
his functions and powers. He could not award an amount for the latent condition
unless there was an entitlement to be paid for that under the contract. An
entitlement to be paid could only arise by the mechanism set out in cl 26.3. The
parties did not meet to negotiate and the matter was not referred to an independent
expert for determination. These requirements were not steps in assessing an
entitlement conferred under the contract. Compliance with cl 26.3 was
a precondition to the adjudicator having jurisdiction to award a sum at all. Also, the
extent of an adjudicator‘s jurisdiction on matters of law is, at best, limited. Bodies
other than courts do not have power to authoritatively determine questions of law or
make decisions other than in accordance with law, subject to contrary intent in the
statute creating the body.10
7 Craig v South Australia (1995) 184 CLR 163 at 179; Kirk v Industrial Court (NSW) (2010)
239 CLR 531 at 572 [67]; South East Civil & Drainage Contractors P/L v AMGW P/L & Ors [2013]
QSC 45 at [54].
8 (2010) 239 CLR 531.
9 Kirk v Industrial Court (NSW) (2010) 239 CLR 531 at 574–575 [74]–[76].
10 Craig v South Australia (1995) 184 CLR 163 at 179; Kirk v Industrial Court (NSW) (2010)
239 CLR 531 at 572–573 [68].
-- 11 of 28 --
12
[30] As BGC could have no entitlement to payment in respect of the alleged latent
condition until the requirements of cl 26.3 were fulfilled, the adjudicator committed
a jurisdictional error in making the award by disregarding a limitation on his
function and powers. The award effectively created a right, rather than assessing
a right that existed under the contract. Contrary to the findings of the primary
judge, the adjudicator‘s error was not one made ―in the course of the decision-
making process itself based on what the adjudicator considered to be the true
construction of the contract and the true merits of the claim‖11 and thus not
a jurisdictional error even if the adjudicator‘s construction was wrong. If BMA‘s
construction of cl 26.3 and cl 37 of the contract are accepted, the adjudicator
necessarily assessed the progress payment other than by reference to the terms of
the contract.
Consideration of the jurisdictional error in respect of the cl 26.3 ground
[31] The nature of a ―jurisdictional error‖ was discussed as follows by Brennan, Deane,
Toohey, Gaudron and McHugh JJ in Craig v South Australia:12
―An inferior court falls into jurisdictional error if it mistakenly
asserts or denies the existence of jurisdiction or if it misapprehends
or disregards the nature or limits of its functions or powers in a case
where it correctly recognises that jurisdiction does exist. Such
jurisdictional error can infect either a positive act or a refusal or
failure to act. Since certiorari goes only to quash a decision or order,
an inferior court will fall into jurisdictional error for the purposes of
the writ where it makes an order or decision (including an order or
decision to the effect that it lacks, or refuses to exercise, jurisdiction)
which is based upon a mistaken assumption or denial of jurisdiction
or a misconception or disregard of the nature or limits of jurisdiction.
Jurisdictional error is at its most obvious where the inferior court
purports to act wholly or partly outside the general area of its
jurisdiction in the sense of entertaining a matter or making a decision
or order of a kind which wholly or partly lies outside the theoretical
limits of its functions and powers … [A]n inferior court can, while
acting wholly within the general area of its jurisdiction, fall into
jurisdictional error by doing something which it lacks authority
to do. If, for example, it is an essential condition of the existence
of jurisdiction with respect to a particular matter that a certain
event or requirement has in fact occurred or been satisfied, as
distinct from the inferior court’s own conclusion that it has,
there will be jurisdictional error if the court or tribunal purports
to act in circumstances where that event has not in fact occurred
or that requirement has not in fact been satisfied even though the
matter is the kind of matter which the court has jurisdiction to
entertain. Similarly, jurisdictional error will occur where an
inferior court disregards or takes account of some matter in
circumstances where the statute or other instrument establishing
it and conferring its jurisdiction requires that that particular
matter be taken into account or ignored as a pre-condition of the
11 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors [2012] QSC 346 at [26].
12 (1995) 184 CLR 163 at 177–178.
-- 12 of 28 --
13
existence of any authority to make an order or decision in the
circumstances of the particular case. Again, an inferior court will
exceed its authority and fall into jurisdictional error if it misconstrues
that statute or other instrument and thereby misconceives the nature
of the function which it is performing or the extent of its powers in
the circumstances of the particular case. In the last-mentioned
category of case, the line between jurisdictional error and mere error
in the exercise of jurisdiction may be particularly difficult to
discern.‖ (citations omitted) (emphasis added)
[32] Later in their reasons, their Honours contrasted the position of an inferior court in
relation to jurisdictional error with that of an administrative tribunal:13
―The position is, of course, a fortiori in this country where
constitutional limitations arising from the doctrine of the separation
of judicial and executive powers may preclude legislative
competence to confer judicial power upon an administrative tribunal.
If such an administrative tribunal falls into an error of law which
causes it to identify a wrong issue, to ask itself a wrong question, to
ignore relevant material, to rely on irrelevant material or, at least in
some circumstances, to make an erroneous finding or to reach
a mistaken conclusion, and the tribunal‘s exercise or purported
exercise of power is thereby affected, it exceeds its authority or
powers. Such an error of law is jurisdictional error which will
invalidate any order or decision of the tribunal which reflects it.
In contrast, the ordinary jurisdiction of a court of law encompasses
authority to decide questions of law, as well as questions of fact,
involved in matters which it has jurisdiction to determine. The
identification of relevant issues, the formulation of relevant questions
and the determination of what is and what is not relevant evidence
are all routine steps in the discharge of that ordinary jurisdiction.
Demonstrable mistake in the identification of such issues or the
formulation of such questions will commonly involve error of law
which may, if an appeal is available and is pursued, be corrected by
an appellate court and, depending on the circumstances, found an
order setting aside the order or decision of the inferior court. Such
a mistake on the part of an inferior court entrusted with authority to
identify, formulate and determine such issues and questions will
not, however, ordinarily constitute jurisdictional error. Similarly,
a failure by an inferior court to take into account some matter which
it was, as a matter of law, required to take into account in
determining a question within jurisdiction or reliance by such a court
upon some irrelevant matter upon which it was, as a matter of law,
not entitled to rely in determining such a question will not ordinarily
involve jurisdictional error.‖
[33] In Kirk, the majority summarised a discussion of jurisdictional error by the Court in
Craig,14 as follows:15
13 Craig v South Australia (1995) 184 CLR 163 at 179–180.
14 Craig v South Australia (1995) 184 CLR 163 at 176–180.
15 Kirk v Industrial Court (NSW) (2010) 239 CLR 531 at 573–574.
-- 13 of 28 --
14
―The Court in Craig explained the ambit of jurisdictional error in the
case of an inferior court in reasoning that it is convenient to
summarise as follows.
First, the Court stated, as a general description of what is
jurisdictional error by an inferior court, that an inferior court falls
into jurisdictional error ‗if it mistakenly asserts or denies the
existence of jurisdiction or if it misapprehends or disregards the
nature or limits of its functions or powers in a case where it correctly
recognises that jurisdiction does exist‘ (emphasis added). Secondly,
the Court pointed out that jurisdictional error ‗is at its most obvious
where the inferior court purports to act wholly or partly outside the
general area of its jurisdiction in the sense of entertaining a matter or
making a decision or order of a kind which wholly or partly lies
outside the theoretical limits of its functions and powers‘ (emphasis
added). (The reference to ‗theoretical limits‘ should not distract
attention from the need to focus upon the limits of the body‘s
functions and powers. Those limits are real and are to be identified
from the relevant statute establishing the body and regulating its
work.) Thirdly, the Court amplified what was said about an inferior
court acting beyond jurisdiction by entertaining a matter outside the
limits of the inferior court‘s functions or powers by giving three
examples: (a) the absence of a jurisdictional fact; (b) disregard of
a matter that the relevant statute requires be taken [into] account as
a condition of jurisdiction (or the converse case of taking account of
a matter required to be ignored); and (c) misconstruction of the
relevant statute thereby misconceiving the nature of the function
which the inferior court is performing or the extent of its powers in
the circumstances of the particular case. The Court said of this last
example that ‗the line between jurisdictional error and mere error in
the exercise of jurisdiction may be particularly difficult to discern‘
and gave as examples of such difficulties R v Dunphy; Ex parte
Maynes, R v Gray; Ex parte Marsh and Public Service Association
(SA) v Federated Clerks’ Union.‖ (citations omitted)
[34] Their Honours noted that the foregoing discussion provided examples of
jurisdictional error which were ―not to be taken as marking the boundaries of the
relevant field‖.16
[35] In order to apply these principles, it is necessary to identify precisely what the
adjudicator did and how, by reference to the provisions of the Act, he exceeded his
jurisdiction.
[36] Section 12 of the Act creates an entitlement to a progress payment on the part of a
person who has carried out construction work or supplied related goods and services
under a construction contract. Section 13 provides that the amount of such payment
is the amount calculated under the contract or, if the contract does not provide for
the matter, the amount calculated on the basis of the value of construction work
carried out or undertaken to be carried out, or related goods and services supplied or
undertaken to be supplied under the contract. Section 14(1) provides that:
16 Kirk v Industrial Court (NSW) (2010) 239 CLR 531 at 574 [73].
-- 14 of 28 --
15
―Construction work carried out or undertaken to be carried out under a
construction contract is to be valued—
(a) under the contract; or
(b) if the contract does not provide for the matter, having regard
to …‖ (various matters are then listed)
[37] Section 26 of the Act provides:
―26 Adjudicator’s decision
(1) An adjudicator is to decide—
(a) the amount of the progress payment, if any, to be paid by
the respondent to the claimant (the adjudicated amount);
and
(b) the date on which any amount became or becomes
payable; and
(c) the rate of interest payable on any amount.
(2) In deciding an adjudication application, the adjudicator is to
consider the following matters only—
(a) the provisions of this Act and, to the extent they are
relevant, the provisions of the Queensland Building
Services Authority Act 1991, part 4A;
(b) the provisions of the construction contract from which
the application arose;
(c) the payment claim to which the application relates,
together with all submissions, including relevant
documentation, that have been properly made by the
claimant in support of the claim;
(d) the payment schedule, if any, to which the application
relates, together with all submissions, including relevant
documentation, that have been properly made by the
respondent in support of the schedule;
(e) the results of any inspection carried out by the
adjudicator of any matter to which the claim relates.
(3) The adjudicator‘s decision must—
(a) be in writing; and
(b) include the reasons for the decision, unless the claimant
and the respondent have both asked the adjudicator not to
include the reasons in the decision.‖
-- 15 of 28 --
16
[38] The adjudicator‘s reasons in respect of the latent conditions claim are to be found in
paragraphs [273]–[294] of his reasons. That part of the reasons may be summarised
as follows. BMA assessed the $11,685,437 claim on account of latent conditions
(claimed as a variation) at nil on the bases that:
(a) the basis of the claim was not identified;
(b) if the claim was made as a variation, the requirements of the contract had not
been complied with and neither entitlement nor quantum were established;
(c) if the claim was a latent conditions claim, there was no latent condition, no
compliance with cl 26.3 and the costs claimed were not caused by any latent
condition; and
(d) the sum claimed was not reasonable.
[39] BGC contended that the work could be claimed as a variation under cl 18, which
deals with variations of the agreement. The adjudicator found that variations to the
agreement are not limited to those made under cl 18. Clause 26.3 is an example of
another provision of the contract which ―exist[s] to vary the Agreement‖.
[40] The adjudicator did not ―necessarily agree with [BMA‘s] view that a change in the
nature of the material encountered is not a ‗variation of the Services‘‖. If ―the
ground conditions are at variance to the geotechnical report included in the
specification … and the variance results in additional work being undertaken [there
will be] a variation to the scope of the works‖. ―[T]echnically‖, BGC could seek a
variation for the alleged latent condition, but the matter ―is more appropriately dealt
with under … clause 26.3‖.
[41] If the provisions of cl 26.3 are not adhered to, neither party has a remedy, but BGC
―is not barred from entitlement under [cl 26.3] if [BMA] does not participate in the
process‖ under the clause.
[42] BGC had a valid claim for latent conditions under either cl 18 or cl 26.3.17
[43] BMA‘s assessment of BGC‘s entitlement at $1,929,525, in the alternative, was
flawed for the reasons given by BGC. BGC‘s methodology for its claim was
accepted, but not all of the claim was substantiated by the materials provided by
BGC.
[44] Although the adjudicator noted BGC‘s claim to have satisfied the notice provisions
of cl 26.3 by its notification of 6 June 2011 and its letters of 10 and 20 October
2011, there is no finding of either compliance or non-compliance with cl 26.3 by
either party.
[45] BMA‘s argument is based on the assumption that the adjudicator disregarded the
requirements of cl 26.3 and otherwise ignored the provisions of the contract in
making his adjudication. It is clear, however, that the adjudicator found that BGC
could claim either under cl 18 or cl 26.3 in respect of the alleged latent conditions.
[46] Neither party made submissions in respect of cl 18 on the hearing of the appeal. It
seems an unlikely basis for a latent condition claim. Clause 18.1 provides that the
terms of the contract ―may not be varied except in writing and signed by both
parties‖.18 BMA may vary ―the Services‖ by written notice of variation to BGC.19
17 Mistakenly referred to in para [281] as 23.6.
18 Clause 18.1.
19 Clause 18.2.
-- 16 of 28 --
17
BGC is required to vary ―the Services‖ in accordance with BMA‘s notice and
provide BMA with a written claim prepared as prescribed by cl 18.4 ―within
30 days of the effective date of variation‖.20 In cl 18.7, BGC ―acknowledges and
agrees that the remedy set out in clause 18.3(b) [the provision of the written claim
prepared as prescribed within the prescribed time] is its sole and exclusive remedy
in respect of a variation of the Services‖ by BMA.
[47] It appears that none of the requirements of cl 18 was met. That was implicitly
acknowledged by BGC in its adjudication application where it asserted:
―28.41 Accordingly, BMA‘s decision not to direct a formal
variation in respect of the extra work needed to overcome
the latent condition was reviewable, and if BMA behaved
inappropriately in withholding such a direction, then the
adjudicator may proceed as if the direction were given and
the formal requirements in clause 18 complied with.‖
[48] It is arguable that the adjudicator‘s error in not applying cl 26.3 was jurisdictional.
He was required by s 14(1) of the Act to value construction work under the contract
unless the contract did not provide for the matter. Clause 26.3 provided for the
matter. The adjudicator was required to apply its provisions. He referred to it but
ignored its terms. In particular, he ignored the fact that entitlement to any payment
in respect of latent conditions was dependent on the determination of an expert
approved under cl 26.3.21 This was so even if, contrary to the view expressed
earlier, cl 37 was also applicable. Once a latent condition, and presumably its
nature and extent, were established by agreement, mediation or litigation under
cl 37 the expert was required to determine the ―changes to the Price and/or time for
completion‖, if any. If, for some reason which did not emerge on the hearing of the
appeal, cl 18 was applicable as the adjudicator found, he also appears to have
ignored its provisions. It is unnecessary, however, to decide the jurisdictional
argument. As I have already mentioned, it was not raised in any ground of appeal
and, if the adjudication decision is of no legal effect as a result of the adjudicator‘s
jurisdictional error in respect of termination costs, the identification of further
jurisdictional errors has no utility.
Ground 2 – the primary judge erred in holding that the adjudication decision
retained effect unless and until the Court exercised its discretion to grant a
declaration or make an order quashing or setting aside the decision
Ground 3 – the primary judge erred in dismissing BMA’s application on
condition that BGC paid to BMA the portion of the adjudication decision
affected by the jurisdictional error found by the primary judge and other
consequential amounts on the basis that this course of action provided a more
convenient and satisfactory remedy than a declaration that the decision was
void coupled with consequential orders
[49] The primary judge found that the adjudicator had made a jurisdictional error in
allowing BGC‘s claim for termination costs in the sum of $4,345,377.42. The Act
gave BGC a right to progress payments based only on contractual entitlements
which accrued on or before the reference date. It was found that the adjudicator had
erred because an entitlement to payment of the sums claimed could not have arisen
20 Clause 18.3(b).
21 See e.g. Beaufort Developments (NI) Ltd v Gilbert-Ash NI Ltd [1999] 1 AC 266 at 288–289; Atlantic
Civil Pty Ltd v Water Administration Ministerial Corporation (1992) 39 NSWLR 468 at 476.
-- 17 of 28 --
18
on or before 1 January 2012, the relevant reference date. On appeal, BGC did not
contest these findings. In his reasons delivered on 13 November 2012, the primary
judge held that, ―A decision affected by jurisdictional error is void‖.22 His Honour
said:23
―[61] In conclusion, BMA has succeeded in establishing one of the
three jurisdictional errors alleged by it. It has established
an entitlement to a declaration that the decision of the
[adjudicator] dated 7 May 2012 in relation to Adjudication
Application No 1064504-831 is void.
[62] It will be necessary to consider consequential orders including
an order remitting the matter to the [adjudicator] for
reconsideration.
[63] On 16 May 2012 BMA paid to BGC the adjudicated amount
(excluding GST) together with accrued interest in accordance
with the adjudication decision and the adjudication fee. In
paragraph 3 of the originating application filed on 18 May 2012
BMA sought an order that BGC pay to it the sum of
$26,135,709.37 together with interest from 16 May 2012. I will
hear the parties in relation to the terms of orders including the
rate of interest and on the issue of costs.‖ (emphasis added)
[50] On 13 November 2012, the primary judge declared the decision of the adjudicator
void. When the matter came before the primary judge for hearing on 29 November
2012 and 8 March 2013, he revoked the declaration. On 22 March 2013, the
primary judge made the following orders:24
―Upon the undertaking of [BGC] by its counsel to pay to [BMA]
within 14 days:
(a) the sum of $4,345,377.42; and
(b) the sum of $147,992.84 (representing interest on the amount
in (a) from 16 May 2012 to 22 March 2013); and
(c) the sum of $434,537.74 (representing GST paid by [BMA] to
[BGC] in respect of the amount in (a)).
the order of the Court is that:
1. The application filed 18 May 2012 is dismissed.
2. There be no order as to costs.‖
[51] In reasons given on 22 March 2013, the primary judge stated that when he delivered
his initial reasons he anticipated making a declaration that the adjudicator‘s decision
was void and making consequential orders, including an order remitting the matter
22 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors [2012] QSC 346 at [58].
23 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors [2012] QSC 346.
24 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [69].
-- 18 of 28 --
19
to the adjudicator for reconsideration. The parties made further written and oral
submissions about the appropriate orders that should be made. BMA contended that
the adjudicator‘s decision should be declared void; that BGC should be restrained
from enforcing or otherwise relying on the decision; and that BGC should be
ordered to repay the $26,135,709.37 it had been paid by BMA on 16 May 2012
together with interest and GST. BGC contended that on its undertaking to pay to
BMA within 14 days $4,345,377.42 together interest thereon from 16 May 2012
and a further sum on account of GST paid by BMA to BGC, the application should
be dismissed.
[52] The primary judge discussed authorities concerned with the power of a court to
decline to grant prerogative remedies and to make declaratory orders on
discretionary grounds. His Honour identified as a critical issue:25
―… whether the form of conditional order proposed by BGC
represents ‗a more convenient and satisfactory remedy‘ than an order
declaring the decision void, together with an order for the repayment
of the adjudicated amount in full, along with interest. More
generally, the issue is whether the circumstances make it just to
withhold the declaratory and other relief sought by BMA in the
circumstances, which include the objectives of the Act, the nature of
the jurisdictional error, its ascertainable monetary consequences and
BGC‘s undertaking to remedy those consequences by repaying to
BMA the component of the adjudicated amount, together with
interest and GST.‖
[53] The primary judge then considered the effect of a decision such as that of the
adjudicator until set aside or declared void. His Honour referred to Emergency
Services Superannuation Board v Davenport,26 in which McDougall J upheld two of
the plaintiff‘s three challenges to the validity of the adjudicator‘s determination.
McDougall J indicated that he was prepared to grant the plaintiff relief on condition
that the plaintiff pay the contractor the unaffected amount of the determination,
together with interest thereon, in accordance with the determination. The plaintiff
accepted the imposition of the condition.
[54] In Cardinal Project Services Pty Ltd v Hanave Pty Ltd,27 Basten JA, after observing
that the amount included in the condition proposed by McDougall J in Davenport
was not ―arbitrarily selected‖ and was justified by reference to the otherwise invalid
determination, said:28
―Such an approach has much to recommend it, particularly, it might
be added, if the claimant is otherwise unable to pursue its original
payment claim to achieve a second adjudication. However, such
conditional relief can itself only be valid if it is designed to achieve a
legitimate purpose: cf Minister for Immigration and Multicultural
Affairs v Wang [2003] HCA 11; (2003) 215 CLR 518 at [15]–[16]
(Gleeson CJ); [39] (McHugh J); [68] Gummow and Hayne JJ). If the
determination is indeed legally ineffective in all respects, it would be
25 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [21].
26 [2004] NSWSC 697.
27 (2011) 81 NSWLR 716 at 730.
28 Cardinal Project Services Pty Ltd v Hanave Pty Ltd (2011) 81 NSWLR 716 at 730 [52].
-- 19 of 28 --
20
doubtful whether the court could condition declaratory relief (or an
order setting aside the decision) upon the applicant making such
payment as would be required by the determination if validity could
be determined part by part, like the curate‘s egg. Accordingly, the
underlying assumption was inconsistent with total invalidity for all
purposes.‖
[55] The primary judge noted29 that he was not invited by BGC to make an order which
conditioned the declaratory relief (or an order setting aside the decision) upon
a requirement that BMA pay the unaffected amount. He said in that regard:30
―Basten JA observes in the passage [quoted in paragraph [54]
above], an order of that kind, as made in Emergency Services
Superannuation Board v Davenport, is inconsistent with the
proposition that a determination affected by jurisdictional error
carries the consequence of ‗total invalidity for all purposes.‘
I respectfully follow his Honour‘s discussion of the concept of
nullity.‖
[56] The primary judge then discussed authorities including Minister for Immigration
and Multicultural Affairs v Bhardwaj;31 Leung v Minister for Immigration and
Multicultural Affairs;32 and Jadwan Pty Ltd v Secretary, Department of Health and
Aged Care.33
[57] Having done so, his Honour observed:34
―[29] … In a case in which the decision is challenged, and the Court
declines to declare it invalid for a discretionary reason, the
decision will remain binding. In other cases, a decision
affected by jurisdictional error, such as a denial of natural
justice, will lack validity without the need for a challenge in
proceedings as to its validity, for example, where the decision-
maker appreciates there has been a jurisdictional error and
treats the decision as no decision at all.
…
[32] The [adjudicator‘s] decision did not cease to have legal and
other consequences upon BMA challenging it for jurisdictional
error on three grounds, two of which failed, or even upon my
finding that the third ground of alleged jurisdictional error was
established. It continued to have operational effect and also
provided the legal justification for BGC to retain the money
which had been paid to it pursuant to the decision. An order
declaring the decision void might be made conditional upon the
29 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [25].
30 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [25].
31 (2002) 209 CLR 597.
32 (1997) 79 FCR 400.
33 (2003) 145 FCR 1.
34 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at
[29] and [32].
-- 20 of 28 --
21
payment of a certain amount, in the form of an order of
the kind made in Emergency Services Superannuation Board
v Davenport. As Basten JA observes, such an approach has
much to recommend it, particularly if the claimant is otherwise
unable to pursue its original payment claim to achieve a second
adjudication. However, I have yet to make a declaration that
the decision is void. As matters stand, the decision does not
lack effect notwithstanding my finding of jurisdictional
error. It retains effect unless and until I exercise my
discretion to grant a declaration or make an order quashing
or setting aside the decision.‖ (emphasis added)
[58] His Honour rejected submissions by BMA that a refusal to make the declaration it
sought would ―clothe the decision with a measure of legal validity‖, remarking,
―The decision already has a measure of validity‖.35
[59] After considering the competing arguments as to whether remittal of the matter to
the adjudicator was permissible, and/or desirable, his Honour concluded that the
most satisfactory course was to make the order he eventually made. His Honour‘s
reasons for adopting this course were:
such an order was ―best suited to correct the error which resulted in the
determination of an amount in excess of jurisdiction and to achieve a just result,
being the result that would have been achieved had the adjudication decision
been made without jurisdictional error‖;36
it would avoid the risk of further litigation and the cost and complexity in
relation to the conduct of a further adjudication;37
it would avoid BGC being deprived of approximately $24,000,000;38 and
it would avoid any doubt about whether remittal was possible.39
[60] BMA argued that the primary judge‘s conclusion that a decision affected by
jurisdictional error was not necessarily invalid for all purposes and had some
residual effect was an error of law. In particular, BMA complained about the
conclusion that the adjudicator‘s decision ―retains effect unless and until
[the primary judge] exercise[s] [his] discretion to grant a declaration or make an
order quashing or setting aside the decision‖.40 In support of its contentions,
BMA referred to Bhardwaj;41 Plaintiff S157/2002 v The Commonwealth;42 Minister
for Immigration and Multicultural and Indigenous Affairs v SGLB;43 and SZFDE
v Minister for Immigration and Citizenship.44
35 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [38].
36 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [42].
37 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [43].
38 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [43].
39 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [45].
40 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [32].
41 Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597 at 614–615
[50]–[51] per Gaudron and Gummow JJ; at 618 [63] per McHugh J; at 646–647 [152]–[153] per
Hayne J.
42 (2003) 211 CLR 476 at 506 [76] per Gaudron, McHugh, Gummow, Kirby and Hayne JJ.
43 (2004) 78 ALJR 992 at 997 [29] per Gummow and Hayne JJ.
44 (2007) 232 CLR 189 at 206 [52].
-- 21 of 28 --
22
[61] BGC sought to uphold the primary judge‘s findings under consideration, relying, in
particular, on Truenergy Australia Pty Ltd v Minister for Industrial Relations;45
Jackson v Purton;46 and Jadwan.47 It was further submitted that the provisions of
the Act did not support a conclusion that an adjudicator‘s decision affected by
jurisdictional error is necessarily of no legal effect. I will refer to the basis for this
submission later.
Consideration
[62] In Bhardwaj, Gaudron and Gummow JJ, with whose reasons McHugh J relevantly
agreed, said:48
―There is, in our view, no reason in principle why the general law
should treat administrative decisions involving jurisdictional error as
binding or having legal effect unless and until set aside. A decision
that involves jurisdictional error is a decision that lacks legal
foundation and is properly regarded, in law, as no decision at all.
Further, there is a certain illogicality in the notion that, although
a decision involves jurisdictional error, the law requires that, until the
decision is set aside, the rights of the individual to whom the
decision relates are or, perhaps, are deemed to be other than as
recognised by the law that will be applied if and when the decision is
challenged. A fortiori in a case in which the decision in question
exceeds constitutional power or infringes a constitutional
prohibition.‖
[63] To like effect, Hayne J said:49
―In general, judicial orders of superior courts of record are valid until
they are set aside on appeal, even if they are made in excess of
jurisdiction. By contrast, administrative acts and decisions are
subject to challenge in proceedings where the validity of that act or
decision is merely an incident in deciding other issues. If there is no
challenge to the validity of an administrative act or decision, whether
directly by proceedings for judicial review or collaterally in some
other proceeding in which its validity is raised incidentally, the act or
decision may be presumed to be valid. But again, that is
a presumption which operates, chiefly, in circumstances where there
is no challenge to the legal effect of what has been done. Where
there is a challenge, the presumption may serve only to identify and
emphasise the need for proof of some invalidating feature before
a conclusion of invalidity may be reached. It is not a presumption
which may be understood as affording all administrative acts and
decisions validity and binding effect until they are set aside. For that
reason, there is no useful analogy to be drawn with the decisions of
the Court concerning the effect of judgments and orders of the
45 (2005) 93 SASR 393 at 413 [107].
46 [2011] TASSC 28 at [60]–[61].
47 Jadwan Pty Ltd v Secretary, Department of Health and Aged Care (2003) 145 FCR 1 at 16 [42].
48 Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597 at 614–615 [51].
49 Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597 at 645–647
[151]–[153].
-- 22 of 28 --
23
Federal Court of Australia made in proceedings in which that Court
had no constitutionally valid jurisdiction.
This is not to adopt what has sometimes been called a ‗theory of
absolute nullity‘ or to argue from an a priori classification of what
has been done as being ‗void‘, ‗voidable‘ or a ‗nullity‘. It is to
recognise that, if a court would have set the decision aside, what was
done by the Tribunal is not to be given the same legal significance as
would be attached to a decision that was not liable to be set aside. In
particular, it is to recognise that if the decision would be set aside for
jurisdictional error, the statutory power given to the Tribunal has not
been exercised …
Nothing in the Act requires (or permits) the conclusion that despite
the jurisdictional error, some relevant legal consequence should be
attributed to the September decision. In particular, the fact that the
Federal Court had only limited jurisdiction to review the decision
does not lead to the conclusion that the September decision is to be
treated as having some effect. Once it is recognised that a court
could set it aside for jurisdictional error, the decision can be seen to
have no relevant legal consequences.‖ (citations omitted)
[64] In Plaintiff S157/2002, Gaudron, McHugh, Gummow, Kirby and Hayne JJ,
referring to passages from the reasons of Gaudron and Gummow JJ,50 McHugh J51
and Hayne J52 in Bhardwaj, said:53
―This Court has clearly held that an administrative decision which
involves jurisdictional error is ‗regarded, in law, as no decision at
all‘.‖ (citations omitted)
[65] Finkelstein J observed in Leung,54 in a passage implicitly approved of by
Gleeson CJ in Bhardwaj:55
―There is no doubt that an invalid administrative decision can have
operational effect. For example it may be necessary to treat an
invalid administrative decision as valid because no person seeks to
have it set aside or ignored. The consequence may be the same if a
court has refused to declare an administrative decision to be invalid
for a discretionary reason. In some circumstances the particular
statute in pursuance of which the purported decision was taken may
indicate that it is to have effect even though it is invalid or that it will
have effect until it is set aside.‖
[66] BGC relied on these observations and on a number of decisions of the Full Court of
the Federal Court, including Jadwan, which expressed the view that whether
jurisdictional error on the part of a tribunal or decision maker will render the
50 Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597 at 614–615 [51].
51 Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597 at 618 [63].
52 Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597 at 646–647 [152].
53 Plaintiff S157/2002 v The Commonwealth (2003) 211 CLR 476 at 506 [76].
54 Leung v Minister for Immigration and Multicultural Affairs (1997) 79 FCR 400 at 413.
55 Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597 at 604–605 [12].
-- 23 of 28 --
24
decision nugatory for all purposes may depend on the terms of the statute under
which the decision was made.56 That proposition, with respect, may be accepted
but, absent statutory provisions necessitating a contrary conclusion, the general
principle identified in paragraphs [62]–[64] above applies.57
[67] BGC identified two matters which it claimed demonstrated a legislative intention
that an adjudicator‘s decision affected by jurisdictional error not be deprived of any
legal effect:
The absence of a statement in the Act that an adjudicator‘s decision affected by
jurisdictional error lacked legal effect and the mechanism provided by s 30 and
s 31 of the Act whereby an adjudication certificate may be obtained and ―filed
as a judgement for a debt, and may be enforced, in a court of competent
jurisdiction‖.58
The ―pay now, argue later‖ nature of the scheme.
[68] The fact that the Act provides for a simple expeditious and robust mechanism for
ensuring the payment of progress claims does not, of itself, support the conclusion
for which BGC contends. The Act also provides a relatively straightforward
framework which facilitates compliance. I am unable to detect anything in the Act
which indicates a legislative intention that the benefits provided to claimants and the
corresponding detriments to respondents under the Act should exist irrespective of
whether there has been compliance with the Act‘s provisions. To the contrary,
some of the Act‘s provisions are expressed in peremptory language.59
[69] Sections 30 and 31 are merely machinery provisions to enable the enforcement of
adjudication decisions which provide for the payment of money. Without such
provisions, an adjudication decision that a sum of money was payable to a claimant
would lack practical consequences.
[70] As BMA submitted, respondents under the Act do not have the benefit of decisions
made after mature consideration based on evidence admitted under the evidentiary
rules applied in Court proceedings and tested by cross-examination. Nor do they
have any right of appeal. Respondents are afforded a measure of protection only by
strict compliance with the provisions of the Act.
[71] Whatever the position might be if the parties to an adjudication make no complaint
about the adjudication decision, the decisions of the High Court relied on by BMA
make it plain that once a court determines that a decision of the type in question is
affected by jurisdictional error, the decision cannot give rise to legal consequences.
[72] On 13 November 2012, not only did the primary judge find jurisdictional error
resulting in the invalidity of the adjudication decision, he declared the decision void.
Even without the declaration, it necessarily followed from the findings in the
13 November reasons, that the adjudication decision had no legal effect. It is
56 Jadwan Pty Ltd v Secretary, Department of Health and Aged Care (2003) 145 FCR 1 at 16 [42];
22 [64].
57 See Lansen v Minister for Environment and Heritage (2008) 174 FCR 14 at 47–50 [156]–[176];
Morris v Riverwild Management Pty Ltd (2011) 284 ALR 413 (VCA) at 423–424 [38]–[41].
58 Building and Construction Industry Payments Act 2004 (Qld), s 31(1).
59 Sections 17(2), 17(4), 18(2), 18(3), 21(2), 21(3), 21(4), 21(5), 21(6), 24(2), 24(3), 24(4), 24(5),
25(1), 25(2), 25(3), 25(5) and 26(2).
-- 24 of 28 --
25
difficult to see how the declaration that the decision was void could have been
revoked, but no issue about that was raised in the grounds of appeal or in argument.
[73] There was no suggestion at first instance or on appeal that BMA did not have a
legally enforceable right to the repayment of the sum of $26,135,709.37. The
primary judge‘s 22 March 2013 orders effectively defeated that right, except in
respect of the $4,345,377.42, and interest, relating to the termination costs claim.
[74] In order to justify the revocation of the 13 November 2012 declaration and the
making of the 22 March 2013 orders, the primary judge relied on the existence of
a discretion as to whether to grant declaratory relief even though a legal basis for the
making of the subject declaration existed. His Honour identified as a relevant
circumstance the existence of ―alternative and adequate remedies for the wrong of
which complaint is made‖.60
[75] The primary judge then, with respect, proceeded to deny BMA the remedy dictated
by the finding of jurisdictional error. In so doing, the primary judge was motivated
by a desire to allow BGC to retain the amounts which the adjudicator had allowed
and to which BGC would have been entitled had there been no jurisdictional error.
In his Honour‘s view, ―[s]uch a course advances the policy of the Act‖.61 It is not
clear what connection, if any, existed between this rationale and the existence of an
alternative and adequate remedy.
[76] As previously discussed, there is nothing in the Act which would support the denial
to a respondent to a payment claim of its rights and entitlements under the Act
except to the extent that the Act expressly or implicitly so provided. Nor is there
any principle identified which would authorise a court to deny a litigant a legal right
or remedy on the grounds that the policy of an Act would thereby be advanced. In
this case the matters discussed in respect of the latent conditions claim indicate that
a failure to permit BMA to enjoy the normal benefits of its success in the
proceeding were unlikely to assist in advancing the policy of the Act but were likely
to cause injustice. It is also relevant that the primary judge‘s refusal to grant
appropriate declaratory relief may well have left it open to BMA to bring other
proceedings to recover the monies paid by it to BGC.62
[77] The adjudication decision gave BGC no entitlement to payment of any part of the
adjudication amount as BMA had no obligation to pay it. BMA, having paid it, had
a right to recover it. The primary judge erred in law in withholding the relief sought
by BMA. His Honour also erred in finding in his 22 March 2013 reasons that the
adjudication decision, which he held to be affected by jurisdictional error, retained
effect until he exercised his discretion to grant a declaration or make an order
quashing or setting aside the decision.
[78] For the above reasons, the primary judge‘s orders of 22 March 2013 should be set
aside.
60 Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393 at 449 [284]; see also
R v Commonwealth Court of Conciliation and Arbitration; Ex parte Ozone Theatres (Aust) Ltd
(1949) 78 CLR 389 at 400.
61 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at
[48].
62 See e.g. Lansen v Minister for Environment and Heritage (2008) 174 FCR 14 at 49 [166].
-- 25 of 28 --
26
Ground 4 – the primary judge erred in accepting and acting upon evidence of
commercial interest rates when awarding interest on the sum repayable to
BMA in circumstances where no sufficient basis was made out to justify such a
course
[79] BMA sought interest on the sums repayable to it at the rate prescribed in practice
directions for default judgments. BGC contended that the appropriate rate was that
payable on term deposits with financial institutions. It adduced evidence in that
respect. BMA referred to Serisier Investments Pty Ltd v English,63 in which
Thomas J said:
―It would be undesirable to encourage the calling of accountants or
other experts to give evidence on applicable rates of interest in every
case or even frequently. This would lead to multiplicity of issues,
increase in costs and waste of human resources.‖
[80] It was submitted that the principle expressed by Thomas J accorded with the
practice of the court in awarding interest at an established rate, unless some other
rate is shown to be more appropriate. In that regard, BMA referred to
McPherson JA‘s observation in Interchase Corporation Ltd (in liq) v Grosvenor
Hill (Queensland) Pty Ltd (No 3)64 that ―In Queensland, a simple interest rate of
12 per cent p.a. has generally been applied under s. 47 [of the Supreme Court Act
1995 (Qld)] since about 1985 or earlier.‖
[81] It was submitted that the current practice in Queensland was to award interest at the
rate prescribed in practice directions from time to time65 and that a similar practice
existed in New South Wales.66
[82] According to the argument, the statement of principle in Serisier Investments Pty
Ltd and the practice of the Court reflect the undesirability of encouraging disputes
over an appropriate interest rate and are inconsistent with a departure from the
generally applied rate simply because it differs from prevailing commercial interest
rates. To entertain such departures from the norm would encourage frequent
disputation over the appropriate rate as commercial interest rates regularly differ.
Consequently, it was submitted, BGC bore the onus of demonstrating that there was
a rate of interest more appropriate than the prescribed rate. It could not discharge
the onus by merely introducing evidence of different commercial interest rates. The
primary judge gave no reason for adopting the deposit investment rate, beyond
concluding that the evidence of such was admissible.67 That finding, however, did
not demonstrate that the deposit rates were more appropriate to compensate a large
mining company for the loss of its money than interest at the rate set in a practice
direction. The primary judge reversed the onus of proof when he stated that BMA
had put on no evidence as to how the money would have been used.68
63 [1989] 1 Qd R 678 at 681.
64 [2003] 1 Qd R 26 at 55 [65].
65 See e.g. Fulcher & Ors v Knott Investments Pty Ltd & Ors [2012] QSC 232 at [173]–[174];
Cashmere Bay Pty Ltd v Hastings Deering (Australia) Ltd (No. 2) [2011] QSC 134 at [23]–[24].
66 Hexiva Pty Limited & Ors v Lederer & Ors [2007] NSWSC 49 at [16]. In Interchase Corporation
Ltd at [65], MacPherson JA considered it appropriate to consider the rates and practice in New South
Wales.
67 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [51].
68 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67
at [52]–[53].
-- 26 of 28 --
27
[83] The substance of the primary judge‘s reasons may be summarised as follows.
BGC‘s evidence of ―commercial rates of interest awarded on investments‖69 was
uncontested. BMA led no evidence as to commercial rates of interest or rates
relevant to its having been denied the use of the money. There was no reason to
suppose that the money in question would not have been held by BMA in a bank
deposit if it had not been paid to BGC. Consequently, the rate of four per cent per
annum put forward by BGC on the basis of the evidence adduced by it as the
commercial rate applicable to investments was appropriate.
[84] BGC contended that the submission in relation to the practice in New South Wales
in relation to awards of interest was not accurate.70
Consideration
[85] BMA did not contend that there was any requirement under statute or the Uniform
Civil Procedure Rules 1999 (Qld) for the primary judge to apply the interest rate
applicable to default judgments. Section 58(3) of the Civil Proceedings Act 2011
(Qld) provides for the payment of pre-judgment interest ―at the rate the court
considers appropriate‖. It was not contended that the primary judge was not entitled
to award interest nor was it submitted that the primary judge was bereft of
a discretion in that regard.
[86] The object of the award of interest was to compensate BMA for the loss of the use
of the subject monies. The approach adopted by the primary judge, having regard to
the limited evidence before him, was apt to serve that end. No error of principle
was made out. As the orders made on 22 March 2013 should be set aside, it is
appropriate that interest at the rate of 8.75 per cent per annum be awarded from
3 October 2012, the date on which the original declaration in favour of BMA was
made. That is the rate of interest prescribed by Practice Direction No 7 of 2013,
pursuant to s 59(3) of the Civil Proceedings Act 2011 (Qld), in respect of money
orders.
Conclusion
[87] BGC submitted that, in the event that BMA‘s appeal succeeded, the matter should
be remitted to the primary judge for a determination of whether the adjudication
application should be remitted to the adjudicator. Such an order would not be
desirable in my view. It would cause these proceedings to be further prolonged. In
his reasons of 22 March 2013, the primary judge explained that he had resiled from
his original intention to order that the matter be remitted to the adjudicator. That
was because of doubts raised by BMA as to whether such a course was open and, if
it was open, whether remittal was appropriate in the circumstances. This Court
heard no argument on whether remittal to the adjudicator was legally possible.
Also, it may be doubted, having regard to the above discussion on the latent
conditions question, that remittal to the adjudicator would be desirable.
[88] For the above reasons, I would order to the effect that:
69 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors (No 2) [2013] QSC 67 at [50].
70 Practice Note SC Gen 16 provides that pre-judgment interest can be expected to be included in a
judgment at a rate which is referred to a cash rate last published by the Reserve Bank prior to
commencement of the pre-judgment period. Federal Court practice note CM 16 is to like effect.
-- 27 of 28 --
28
1. The appeal be allowed.
2. The orders made on 22 March 2013 be set aside.
3. The first respondent pay to the appellant the sum of $26,135,709.37.
4. The first respondent pay to the appellant interest on such sum at the rate of
four per cent per annum from 16 May 2012 until 3 October 2013 and from
that date until today‘s date at the rate of 8.75 per cent per annum.
5. The first respondent pay to the appellant the sum of $2,613,570.94 being the
sum paid by the appellant to the respondent in respect of GST.
6. The first respondent pay to the appellant interest on the sum of
$2,613,570.94 from 16 May 2012 at the rate of four per cent per annum and
from 13 November 2012 until today‘s date at the rate of 8.75 per cent per
annum.
7. The first respondent pay the appellant‘s costs of the proceedings including
the costs of this appeal.
[89] On the hearing of the appeal, the precise terms of the order sought by BMA in the
event that it succeeded on the appeal were not identified. In particular, if there was
evidence of dates of payment and partial repayment of monies, it was not identified.
This Court should not have to scour the appeal record in an attempt to find facts
necessary for the formulation of an order. The appellant should be directed to
consult with the respondent and bring in draft minutes of order reflecting these
reasons within 28 days of today‘s date. The rather leisurely period allowed takes
the Christmas and New Year period into account.
[90] A LYONS J: I agree with his Honour‘s reasons and the orders proposed.
-- 28 of 28 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2013/394