AWX Constructions Pty Ltd v IDH Modular Pty Ltd & Anor [2013] QSC 218
SUPREME COURT OF QUEENSLAND
CITATION: AWX Constructions Pty Ltd v IDH Modular Pty Ltd & Anor
[2013] QSC 218
PARTIES: AWX CONSTRUCTIONS PTY LTD ACN 118 400 098
(applicant)
v
IDH MODULAR PTY LTD ACN 158 878 874
(first respondent)
BM ALLIANCE COAL OPERATIONS PTY LTD
ACN 096 412 752
(second respondent)
FILE NO: BS6137 of 2013
DIVISION: Trial Division
PROCEEDING: Originating application
DELIVERED ON: 23 August 2013
DELIVERED AT: Brisbane
HEARING DATE: 17 July 2013
JUDGE: Mullins J
ORDER: 1. The originating application is adjourned to a date to
be fixed.
2. The applicant must pay the first respondent’s costs of
and incidental to the hearing of the application
summarily on 17 July 2013 to be assessed.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
SUBCONTRACTORS’ CHARGES ACT (QLD) – where the
first respondent was engaged as subcontractor for the supply
of modular housing for the purpose of the head contract –
where the respondent claimed a charge over money payable
under the head contract pursuant to the Subcontractors’
Charges Act 1974 (Qld) – where the applicant applies
pursuant to s 21 of the Act for an order that the claim of
charge be cancelled – whether the issues may be disposed of
summarily
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS –
INTERPRETATION OF MISCELLANEOUS CONTRACTS
AND OTHER MATTERS – where the first respondent was
engaged as sub-contractor for the supply of modular housing
-- 1 of 10 --
2
for the purposes of the head contract – where s 42 of the
Queensland Building Services Authority Act 1991 (Qld)
prohibits undertaking to carry out building work without the
appropriate licence – where the respondent was licensed –
whether the subcontract required the respondent to engage in
building work
Queensland Building Services Authority Act 1991, s 42
Subcontractors’ Charges Act 1974, s 21
Dart Holdings Pty Ltd v Total Concept Group Pty Ltd [2012]
QSC 158, considered
Multiplex Constructions Pty Ltd v Abigroup Contractors Pty
Ltd [2005] 1 Qd R 610, considered
Multiplex Constructions Pty Ltd v Rapid Contracting Pty Ltd
(in liq) [1999] QCA 306, considered
COUNSEL: J K Bond QC and M Jones for the applicant
M Williams for the first respondent
SOLICITORS: Thomsons Lawyers for the applicant
Lenz Moreton for the first respondent
[1] The applicant is the contractor under the head contract with the second respondent
as the principal for the design and installation of modular housing at Barron Court
and Utah Drive, Moranbah for the principal's employees. The first respondent (the
respondent) entered into a subcontract as the subcontractor with the applicant for the
supply of modular housing for the purposes of the head contract.
[2] On 26 June 2013 the respondent took steps pursuant to the Subcontractors’ Charges
Act 1974 (the Act) to claim a charge in the sum of $5.7m over money payable or to
become payable to the applicant under the head contract.
[3] The applicant applies pursuant to s 21 of the Act for an order that the claim of
charge be cancelled. As required by s 21(2) of the Act, the application was heard
summarily on the basis of affidavits filed by the parties with no oral evidence.
[4] The basis on which the applicant applies for the cancellation of the charge is that by
the subcontract the respondent undertook to carry out work which was building
work within the meaning of the Queensland Building Services Authority Act 1991
(the QBSA Act) when it did not hold a contractor’s licence of the appropriate class
under the QBSA Act, thereby contravening s 42 of the QBSA Act, and was
therefore not entitled to a charge under the Act, in reliance on Multiplex
Constructions Pty Ltd v Rapid Contracting Pty Ltd (in liq) [1999] QCA 306 at [12]
per de Jersey CJ and Davies JA. It is sufficient for the applicant to show that any
part of the work which the respondent undertook to carry out was “building work”
for which it should have been licensed under the QBSA Act: Dart Holdings Pty Ltd
v Total Concept Group Pty Ltd [2012] QSC 158 at [39].
[5] The respondent contends that the subcontract was for the supply of chattels and did
not compel or require the respondent to carry out “building work” within the
meaning of the QBSA Act. It is argued on behalf of the respondent that it is only
-- 2 of 10 --
3
where the contract provides for the respondent to carry out its obligations in a
specified way that falls within the definition of "building work" under the QBSA
Act that the subcontract itself can be characterised as obliging the respondent to
carry out building work. In other words, where it is possible for the respondent to
fulfil any of its obligations under the subcontract in at least one way that would not
be characterised as carrying out building work, the respondent has not undertaken to
carry out building work.
[6] There is a factual dispute evident from the affidavits filed by the parties as to the
precise manner by which the respondent performed the subcontract, so that the
applicant endeavours to establish its entitlement to the cancellation of the charge
solely on the basis of the proper construction of the subcontract as to what the
respondent undertook to do.
[7] The onus is on the applicant to show that the respondent has “no arguable, or fairly
arguable” claim to a charge or “that the basis of the charge claimed was untenable”:
Multiplex Constructions Pty Ltd v Abigroup Contractors Pty Ltd [2005] 1 Qd R 610
at [6]. The respondent’s submission, that it did not undertake to carry out building
work under the subcontract, if it could fulfil an obligation imposed under the
subcontract in a way that did not amount to carrying on building work, is a fairly
arguable approach to the construction of the subcontract for the purpose of
determining whether the respondent undertook to carry out building work. In light
of the onus that the applicant bears on the application, that is the approach that I will
take to the construction of the provisions imposing an obligation on the respondent
that are relied upon by the applicant on this application.
The definition of “building work”
[8] The definition of “building work” is found in schedule 2 to the QBSA Act and
relevantly means:
“(a) the erection or construction of a building; or
…
(c) the provision of lighting, heating, ventilation,
airconditioning, water supply, sewerage or drainage in
connection with a building; or
(e) any site work (including the construction of retaining
structures) related to work of a kind referred to above; or
(f) the preparation of plans or specifications for the
performance of building work; or
… .”
[9] The definition of “building” in schedule 2 to the QBSA Act includes “any fixed
structure”. There is no definition of “site work”, but the use of “site work” in
paragraph (e) in the definition of “building work” to describe work related to work
of a kind referred to in the preceding paragraphs of the definition relevantly links
the site to the place where the erection or construction of the building in the sense of
creating a fixed structure occurs.
[10] The definition of “carry out” is also in schedule 2:
“carry out, for building work (other than for part 4A) means any of
the following-
(a) carry out the work personally;
-- 3 of 10 --
4
(b) directly or indirectly cause the work to be carried out;
(c) provide building work services for the work.”
[11] The definition of “building work services” is set out in schedule 2 as:
“building work services means 1 or more of the following for
building work-
(a) administration services;
(b) advisory services;
(c) management services;
(d) supervisory services.”
[12] The definition of “administration services” for building work is in schedule 2 and
includes:
“(d) arranging for certificates, including certificates from a local
government, to be issued;”
[13] The definition in schedule 2 of “advisory services” for building work relevantly
includes “the provision of advice or a report about building work.”
The subcontract
[14] The subcontract is based on AS4912-2002 general conditions of contract for supply
of goods (incorporating amendment No 1), as amended by the parties (the general
conditions). It includes Annexures Parts A to E to AS4912-2002, deeds of parent
company guarantee, Annexure 1 Scope of Works (the Scope of Works), Annexure 2
Programme, Annexure 3 Quotations, Annexure 4 Drawing Transmittals, Annexure
5 Acceptance Testing and Defects Forms and Annexure 6 Claim for Payment
Templates.
[15] Clause 3.0 of the Scope of Works sets out the precedence of documents (in order of
ranking) for the subcontract as:
"Lightwave architectural specification;
Lightwave architectural drawings;
BMA specification;
Nerantec Group structural drawings;
Hydraulic Design Solutions hydraulic drawings;
Special conditions of contract;
Contract conditions;
Head contract conditions;
Scope of works (this document);
Annexures not otherwise described above."
[16] The central obligations of the parties are set out in clause 2.1 of the general
conditions:
“In accordance with the requirements of the Contract:
(a) the Supplier shall manufacture, supply and deliver the goods
by not later than the date for delivery; and
(b) the Purchaser shall accept the goods and pay the contract sum
to the Supplier in the manner set out in this Contract.”
[17] The contract sum is defined in clause 1 to mean $21,045,785 excluding GST and
any additions or deductions which may be required to be made under the contract.
-- 4 of 10 --
5
[18] The central obligation of the respondent as the supplier of goods in the subcontract
reflects the quotations incorporated in Annexure 3 for the manufacture of the
modular dwellings and transport to site with installation not included. As to be
expected of the general conditions in AS4912-2002, they are directed at a supply of
goods, incorporating warranties in clause 9.2 such as the goods will upon delivery
be suitable for the purpose stated in item 5 (for use as residential dwellings for the
principal's Moranbah accommodation project), of merchantable quality, free of
design defects and new. Clause 19.1 specifies the applicant as the party responsible
for unloading the goods at the delivery place. Clause 21 concerns acceptance or
rejection of goods and the defects liability provision (Clause 22) contemplates that
the goods will still be goods for the purpose of the carrying out of rectification.
[19] Clause 34 is an amendment to the general conditions that incorporates a special
condition of supply that expresses that the applicant cannot reduce the scope of the
separable portion relating to the Barron Court stage unless the respondent is failing
to perform against the programme, but the Utah Drive stage is expressed to be
subject to the reduction of the scope relating to particular types of dwellings to the
maximum reduction of 24 dwellings. The clause then states:
“AWX will issue IDH with invoices for payment for any back
charges or negative variations resulting, except in the instance where
the scope of works is reduced. This will be a negative variation
reducing the contract value, but will not be offset against a progress
claim. Invoices issued to IDH must be paid in compliance with the
Building and Construction Industry Payments Act.”
[20] The definition of "Scope of Works" in clause 1 of the general conditions
incorporates the Scope of Works which gives content to and modifies the
application of the general conditions. Clause 1.0 of the Scope of Works specifies
that the Scope of Works document "should be read in conjunction with the other
parts of this AWX-IDH AS4912-2002 Contract For Supply Of Goods." Following
the precedence given to the general conditions over the Scope of Works by clause
3.0 of the Scope of Works (which would usually be taken into account to resolve
any ambiguities between them) would not give effect to the clear purpose of the
Scope of Works. The issue that is raised by the application is, in effect, whether the
provisions of the Scope of Works modify what was otherwise clearly a subcontract
for the supply of goods, so as to make it a contract pursuant to which the respondent
undertook building work within the meaning of s 42 of the QBSA Act.
The applicant’s four arguments
[21] The applicant developed four arguments by reference to specific parts of the
subcontract to advance its contention that the respondent undertook to carry out
“building work” as defined. In summary, these arguments are the respondent
undertook to:
(a) carry out building work within subparagraph (e) of the definition of
“building work”, because it undertook to carry out “site work … related to
work of a kind referred to above [in subparagraphs (a) and (c) of the
definition]”;
(b) provide “building work services” for building work in the form of “advisory
services” by agreeing to provide advice about building work;
(c) provide “building work services” for building work in the form of
“administrative services”; and
-- 5 of 10 --
6
(d) carry out building work within subparagraph (f) of the definition of
“building work”, because it undertook “the preparation of plans or
specifications for the performance of building work.”
Did the respondent undertake to carry out site work?
[22] The description of goods to be supplied under the subcontract is specified in clause
1.1 of the Scope of Works as 107 prefabricated modular dwellings (of seven
different types) constructed within the approved premises of the respondent (at
Murwillumbah) and delivered to the site at Moranbah. Although each modular
dwelling takes on a different character when affixed to land, the modular dwelling
in its manufactured state is simply a large chattel.
[23] For the first argument, the applicant pointed to a number of specific provisions in
the subcontract by which it submitted the respondent undertook to carry out site
work.
[24] The argument commenced with a reference to the opening paragraph of the Scope
of Works:
“The supplier shall supply and assist with the installation of
dwellings supplied by IDH Modular at the abovementioned project
over the two nominated sites at Moranbah, Queensland. The scope
of works shall include but is not limited to the following items.”
[25] By itself, that paragraph does not advance the argument, as it is the balance of the
document that needs to be considered to ascertain whether there were any
requirements for assisting with the installation of dwellings supplied by the
respondent that amounted to building work.
[26] In contrast to the applicant’s approach of analysing specific provisions in the
subcontract, the respondent considered the overall effect of the Scope of Works in
conjunction with the general conditions in the course of analysing those obligations
of the respondent that were highlighted by the applicant for the purpose of this
argument. The respondent’s conclusion taking this approach was that the parties
excised from the respondent’s obligations those which would be categorised as
building work. The respondent acknowledges that there are some indications to the
contrary in specific provisions, but contends the construction of those provisions is
at least ambiguous in the light of the clear overriding intent of the parties that the
respondent was supplying goods only to the applicant at the Moranbah site. In
order to deal with both parties’ submissions, it is necessary to consider those
specific provisions that are relied on by the applicant.
[27] Clause 1.3 of the Scope of Works expands on "acceptance testing" provided for in
clause 18 of the general conditions. Clause 1.3 of the Scope of Works provides for
acceptance testing to be undertaken by representatives of the principal and the
respondent at six specified stages. The applicant focuses on stage 6 which is the
delivery stage inspection which lists out the items to be covered for that inspection
that must be ticked off by the principal, the respondent and the applicant on the
form that applies to that inspection. The applicant argues that any work undertaken
by the respondent on the Moranbah site, even if it is inspecting the modular
dwellings before they have been unloaded from the truck or "tutelage" given by
employees of the respondent to facilitate the unloading must be characterised as
doing work on site. The respondent submits that “site work” is not defined in the
-- 6 of 10 --
7
QBSA Act and that it is arguable that inspection of the chattels on the truck for
defects while they remain in the state of being chattels is not site work. I accept that
this is arguable.
[28] Mr Reynolds, in paragraph 22 of his affidavit filed on 11 July 2013, states that
“Tutelage is the detailed instruction of tutorial on how to undertake a function or
activity, for example, the lifting and complexing of a modular building”. There is
no demur from the respondent’s deponents as to that meaning of tutelage. The
tutelage is in relation to each new type of dwelling and in the context where the
obligation to unload the truck is imposed on the applicant. The contract does not
specify where the tutelage is to take place and on that basis it is arguable that it is
not site work. Even if the tutelage took place on the site, it is arguable that it relates
to the unloading of the chattel and no more. It is not sufficiently clear from the
subcontract that this provision required the respondent to carry out site work within
the meaning of paragraph (e) of the definition of “building work” to resolve the
issue summarily in the applicant’s favour.
[29] Clause 1.6.16 provides:
“IDH will provide a business representative upon delivery of each
new building type to provide knowledge transfer and assistance in
the unloading and complexing process.”
[30] First, clause 1.6.16 does not say where the business representative of the respondent
provides the “knowledge transfer” and “assistance”. Second, to the extent that
knowledge transfer and assistance are provided in the unloading and complexing of
each new building type, it is provided on delivery and that is arguably undertaken in
relation to the modular dwelling in its state as a chattel, and not as site work even
though the applicant may then have used it for the complexing process.
[31] It is common ground the term "complexing" has acquired an industry meaning. Mr
Reynolds on behalf of the applicant explains in paragraph 12 of his affidavit filed on
11 July 2013:
"The term 'complexing' is a term used in relation to modular building
construction and installation. It is a reference to the site based
process of preparing the site and foundation systems and services in
readiness for the installation of a number of independent building
modules fabricated in a factory, and then configuring and connecting
them together into their final and permanent location to create the
finished building or buildings suitable for its/their intended
functional purpose."
[32] The meaning of "complexing" suggested by Mr Brooks on behalf of the respondent
in paragraph 7 of his affidavit filed on 16 July 2013 is similar:
"In my experience, 'complexing is a modular/transportable industry
term used to describe the supervision or the physical installation and
finishing off of the modules on-site to form a building/dwelling
which could be considered ready for habitation. This act could be
considered building works dependant (sic) on your level of
involvement in the scope and the cost associated to 'complex' the
modules."
-- 7 of 10 --
8
[33] There is an overlap between clause 1.6.16 and clause 1.6.51. To the extent that the
applicant relies on the argument it promotes for clause 1.6.51 in connection with
clause 1.6.16, I will deal with that argument in relation to clause 1.6.51.
[34] In relation to clause 1.6.19 of the Scope of Works which deals with remedying
defects, the applicant relies particularly on defects identified and recorded during
delivery stage inspection on the back of the truck prior to unloading in clause
1.6.19.2. In conjunction with clause 22 of the general conditions requiring the
respondent to carry out defect rectification within a time period which inevitably
meant that it was an obligation to carry out defect rectification on site, the applicant
argues that this was site work on the chattels that related to the installation of the
chattels as a building on the site. The parties were obviously alert to this potential,
as clause 1.6.19.2 also provides:
“IDH may opt for the repairs to be undertaken by AWX and back
charged to IDH.”
[35] The point made by the respondent is that on the construction of clauses 22 and 34 of
the general conditions and the option that was expressly conferred by clause
1.6.19.2 of the Scope of Works, there were other means for the respondent to deal
with defects which did not oblige it to carry out site work of a kind that was within
the definition of building work under the QBSA Act. Again, this is an arguable
position against the construction urged by the applicant.
[36] The critical provisions of the Scope of Works are:
“1.6.51 IDH will supply labour for knowledge transfer upon
commencement of site complexing works. The only
provision by AWX whilst IDH labour is in Moranbah will
be basic share accommodation. That includes a total labour
supply in Moranbah and all other associated costs for 25
men for four weeks (or other arrangement) 4250 man hours
in total. IDH and AWX will coordinate the timing and
volume of labour prior to site delivery commencing. A
separate subcontract agreement must be entered into relating
to the onsite works, this will be for a nil value, with the
labour allowance included within this supply contract.
1.6.52 Given the outlined labour allowance any site visits requested
by AWX to Moranbah for assistance or defects rectification
are deemed to be included as per the above clause.”
[37] Although the applicant concedes that the parties contemplated that a separate
subcontract agreement would be entered into relating to onsite works required to be
performed by the respondent’s employees, the labour allowance for that onsite work
and defects rectification is patently included in the contract price for the
subcontract. It is a significant labour component for which provision has been
made. This indicates that the parties agreed to inflate the subcontract price for the
supply of the goods by the value apportioned by them to the labour allowance for
works to be provided under a separate contract. The parties were free to calculate
the contract price of their subcontract for the supply of goods in whatever manner
they agreed upon. It is arguable that they have evinced an intention to excise from
the subcontract any works that would be characterised as building work by the
express terms of clause 1.6.51 and the other provisions relied on by the respondent
-- 8 of 10 --
9
(such as clauses 1.6.49 and 1.6.50) which show that the parties were intent to avoid
infringing s 42 of the QBSA Act.
[38] Clauses 1.6.51 and 1.6.52 of the Scope of Works are unusual provisions and to the
extent that it is arguable that there is some ambiguity about their operation, it is not
appropriate to reach a conclusion on their construction or about their effect on the
construction of other provisions of the subcontract on a summary basis. The
applicant fails to discharge its onus on its first argument in view of the existence of
these clauses.
Did the respondent undertake to provide advisory services?
[39] The applicant adopts the position that any provision under the subcontract by which
the respondent had to give advice (such as clause 1.6.16) falls within the definition
of “advisory services”, as the respondent agreed to provide advice about building
work. It is equally arguable that the advice was about the modular dwellings as
chattels. The applicant’s reliance on clause 1.6.51 of the Scope of Works in relation
to this second argument raises the same issue that applies to the first argument that
it is equally arguable that clause 1.6.51 acknowledges that the supply of labour for
providing advice was to be undertaken under a different subcontract.
[40] It is arguable that the obligation of the respondent to provide a written summary of
its preferred practice in relation to “safe and damage free lifting of the modules into
final installation locations” is caught within those functions that clause 1.6.51
anticipates will be supplied under a different subcontract. Clause 1.6.17 also deals
with provision of advice by the respondent, but in relation to a generic description
of the respondent’s preferred method of installing the dwellings “on a hypothetical
site”. This is another provision that does not relate to the particular building work,
but is arguably also indicative of the intention of the parties to avoid s 42 of the
QBSA Act.
[41] Clause 1.6.26 of the Scope of Works is another provision that can arguably be
treated as concerning the supply of labour by the respondent that will be covered by
a different subcontract as acknowledged by clause 1.6.51. The applicant fails to
discharge its onus on the basis of the second argument.
Did the respondent undertake to provide administration services?
[42] Under clause 1.6.49 of the Scope of Works, the respondent was required to procure
the Form 16 approval for the “prefabricated construction” and under clause 1.6.50
the applicant was to procure the Forms 15 and 16 approvals for the works required
to be undertaken or completed on site. It is arguable that even though the Form 16
approval relates to a building, the parties have acknowledged by these separate
provisions that the respondent’s obligation was in respect of obtaining that form for
the modular dwelling when it was still a chattel, in contrast to the applicant’s
obligations when the modular dwellings were transformed on site. The applicant
fails to discharge its onus by reference to the third argument.
Did the respondent undertake to prepare plans or specifications?
[43] Although clause 1.6.10 of the Scope of Works required the respondent to provide
detailed shop drawings and as constructed drawings “to facilitate set out and
installation of foundations and columns”, the drawings provided were in respect of
-- 9 of 10 --
10
the modular dwellings as chattels which was what the respondent was contracted to
supply. The applicant’s fourth argument does not assist in the discharge of its onus.
Orders
[44] The applicant has failed to discharge the onus to show on a summary basis that
there is no arguable claim to a charge. The procedure for seeking a summary
determination of a case for cancellation of a charge under s 21 of the Act is
generally used by an affected party in a case that is appropriate for summary
determination. The material filed by the parties shows that there is still an issue to
be determined by reference to evidence of whether the respondent performed
building work under the subcontract by the manner in which it performed its
obligations under the subcontract. In addition, I have not finally determined all the
construction arguments put forward by the applicant, as there are ambiguities in the
provisions of the subcontract that may permit recourse to evidence to assist in
finally determining the issue of construction. Although the respondent has been
successful in resisting the determination of the cancellation of the charge on a
summary basis, the application for cancellation of the charge should remain extant
to enable resolution after a full hearing involving all relevant evidence.
[45] At the conclusion of the summary hearing, the parties agreed that costs should
follow the event. The respondent was successful in resisting the summary
cancellation of its charge. Even though the formal order in relation to the
application is that it will be adjourned, the success of the respondent should be
reflected in an order for costs in its favour. I therefore make the following orders:
1. The originating application is adjourned to a date to be fixed;
2. The applicant must pay the first respondent’s costs of and incidental to the
hearing of the application summarily on 17 July 2013 to be assessed.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2013/218