Board of Professional Engineers v Hart [2013] QCAT 689
CITATION: Board of Professional Engineers v Hart [2013]
QCAT 689
PARTIES: Board of Professional Engineers
(Applicant)
v
John Hart
(Respondent)
APPLICATION NUMBER: OCR176-11
MATTER TYPE: Occupational regulation matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member McLennan
DELIVERED ON: 20 December 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. Mr Hart is reprimanded;
2. The penalty of $5,000 is imposed upon
Mr Hart such amount to be paid in three
equal monthly instalments of $1,666.66
with:
a. the first instalment is to be paid within
3 business days of this order; and
b. the second instalment is to be paid
within 30 days of this order; and
c. the third instalment is to be paid
within 60 days of this order;
3. Should the penalty or any part thereof not
be paid by the dates stated in this order,
Mr Hart’s registration is suspended until
the earlier of the date the amount is paid
or the day registration expires; and
4. Each party bears its own costs.
CATCHWORDS: Occupational regulation matter – Disciplinary
proceedings – civil and structural engineering –
unsatisfactory professional conduct – reprimand
Professional Engineers Act 2002
Adamson v Queensland Law Society Inc. [1990]
-- 1 of 26 --
2
1 Qd R 498
Board of Professional Engineers of Queensland
v Zaranis [2009] CCT ED001-09
Board of Professional Engineers of Queensland
v Matiukevitch [2006] CCT K002-05
Board of Professional Engineers of Queensland
v Enzo Bartilomo [2006] CCT ED008-05
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s.32 of the
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] This is a disciplinary proceeding brought in the Queensland Civil and
Administrative Tribunal (Tribunal) by the Board of Professional Engineers
of Queensland (the Applicant) against Mr John Hart (the Respondent) who
at all material times was a registered professional engineer in Queensland
under the Professional Engineers Act 2002 (the Act) and principal of
Acame Pty Ltd (Acame).
[2] The Applicant is established under s 77 of the Act and relied upon the
following material filed in the Tribunal:
a) Application or referral – disciplinary proceeding filed 9 August 2011;
b) Affidavit of Katherine Clare Murray filed 9 August 2011;
c) Affidavit of Katherine Clare Murray filed 19 April 2013; and
d) Statement of Agreed Facts dated 23 October 2013.
[3] The Respondent relied upon the affidavit of John Hart sworn on 29 July
2013.1
[4] The Respondent was registered as a professional engineer (RPEQ 7021),
under the Act on 17 August 2004 and has continuously held registration
since that date. At the relevant times the Respondent was practising as a
registered professional engineer in the area described as ‗civil and
structural engineering’ – being areas recognised under s 7A of the Act.
[5] The Respondent‘s work, to which this proceeding relates, was work of the
kind expected to be performed by a registered professional engineer
practising in that area.
[6] For the purpose of this proceeding, the parties filed a Statement of Agreed
Facts2 which constitutes the factual matrix. Joint Submissions of the
1 Appendix A Statement of Agreed Facts attached to this decision: signed by the
Applicant on 23 October 2013 and by the Respondent on 24 October 2013.
2 Appendix A Statement of Agreed Facts attached to this decision: signed by the
Applicant on 23 October 2013 and by the Respondent on 24 October 2013.
-- 2 of 26 --
3
Applicant and the Respondent3 in relation to penalty were filed.
By consent and in reliance on these documents, the parties sought orders
of the Tribunal. The parties consented to this matter being determined on
the papers.
Facts
[7] On the basis of the Statement of Agreed Facts I find that:
[8] On or about 18 June 2009, the Respondent performed professional
engineering services by issuing a Compliance Certificate for Building
Design or Specification (First Design Certificate) in relation to the
structural design drawings (sheets) 1 – 9 of the Building (First Drawings)
for the purposes of s 10 of the Building Act 1975 (BAct) and/or s 46 of the
Building Regulation 2006 (Regulation).
[9] On a date unknown, but understood to be in June 2009, Ms Vickie
Williams engaged an unnamed Builder to erect a steel framed kit house
supplied by Stone Homes at 31 Duffey Street, Burnett Heads, near
Bundaberg in Queensland (Building).
[10] The Respondent asserted that in or about October 2009, he was asked by
Stone Homes to upgrade the design of the Building to achieve compliance
with terrain category 2 region C loading conditions. He was further
informed by Stone Homes that urgent remedial action needed to be
considered and that Stone Homes would supply additional trusses and
hold downs at a later date. The Respondent undertook the certification of
the Building to facilitate the owner of the property pending completion of
proper remediation works.
[11] A review of the Building and design was undertaken and, as a result of the
review, the Respondent wrote a letter relating to the Building dated
23 September 2009 addressed ―To Whom It May Concern‖. In that letter,
the Respondent advised methods to improve the purlin capacity to a
structurally acceptable level to support the calculated loads.
[12] On about 22 October 2009, the Respondent performed professional
engineering services by issuing a Compliance Certificate for Building
Design or Specification (Second Design Certificate) in relation to the
structural design drawings (sheets 1 – 20) (Second Drawings) for the
purposes of s 10 of the BAct and/or s 46 of the Regulation.
[13] By issuing the First Design Certificate and pursuant to s 46 of the
Regulation, the Respondent certified that the Building Design or
Specification set out in the Certificate, if installed or carried out under the
Certificate, would comply with the Building Assessment provisions
including the BAct.
3 Appendix B Joint Submissions of the Applicant and the Respondent attached to this
decision: signed by the Applicant on 23 October 2013 and by the Respondent on
24 October 2013.
-- 3 of 26 --
4
[14] The Respondent recognises and accepts that the aforesaid certification
and letter were not appropriate.
[15] On about 14 May 2010 the Applicant:
a) received a complaint about the Respondent‘s professional conduct
from Ms Vickie Williams comprising a Form 6 Complaint regarding
unsatisfactory professional conduct dated 13 May 2010 with its
various attachments; and
b) gave the Respondent notice of the complaint pursuant to s 41(3) of
the Act.
[16] By email received on 17 June 2010 the Applicant received from the
Respondent, in response to the notice given pursuant to s 41(3), a letter
dated 8 June 2010 attaching handwritten calculations and truss analysis
results (together with the Respondent‘s letter ―To Whom It May Concern‖
dated 23 September 2009 defined as the Respondent‘s Material).
[17] By letter dated 5 October 2010 the Applicant gave the Respondent a
Notice of Investigation pursuant to s 44 of the Act.
[18] On 6 October 2010, John Van de Hoef of NJA Consulting Pty Limited,
Consulting Engineers, RPQ 4733 (Investigator), was appointed by the
Applicant to carry out the investigation.
[19] The Investigator prepared and provided to the Applicant, a report dated
21 January 2011 (Investigator‘s Report).
FIRST DESIGN CERTIFICATE
[20] The Respondent accepted that a competent engineer, exercising proper
skill, knowledge and judgement, would not have issued the First Design
Certificate for the First Drawings because they included the defects (First
Design Defects) where, broadly stated, elements of the building lacked
specified reinforcements; were significantly underspecified for a residential
dwelling in a cyclonic location; overstressed for the loading conditions;
criteria specified were incorrect and did not correlate with the design
certificate.4
[21] The Applicant maintained however the Respondent did not accept, that
the certain matters identified by the Applicant‘s engineer were of a
material nature. These included reinforcement specifications for the slab
and footings of the Building referenced superseded reinforcement grades.5
4 Appendix A Statement of Agreed Facts pages 2-3.
5 Appendix A Statement of Agreed Facts pages 3-4.
-- 4 of 26 --
5
SECOND DESIGN CERTIFICATE
[22] A competent engineer, exercising proper skill, knowledge and judgement,
would not have issued the Second Design Certificate for the Second
Drawings because, broadly stated, the defects (Second Design Defects)
included roof sheeting fixings which were significantly underspecified for a
residential dwelling in a cyclonic location and specified roof purlins which
were overstressed for site design loading conditions.6
Respondent’s material
[23] A competent engineer, exercising proper skill, knowledge and judgement,
would not have issued or produced correspondence or design calculations
including the defects, errors or omissions which were included in the
Respondent‘s Material (Defects in the Respondent‘s Material).7 These
defects and omissions, broadly stated, included incorrect calculations;
incorrect assumption and incorrect explanations.8
[24] Notwithstanding the certain concessions made by the Respondent,9 the
Respondent now concedes, and the Tribunal finds, that the production of
certificates without documenting those matters specified in the Statement
of Agreed Facts was unjustifiable having regard to proper engineering
practices and principles.
Unsatisfactory professional conduct
[25] The Tribunal finds that the Respondent demonstrated a fundamental lack
of understanding of, or regard for, proper engineering practices and
principles required to safely design the Building and similar structures as
defined in the Act because it is:
a) conduct that is of a lesser standard than that which might reasonably
be expected of a registered professional engineer by the public or the
engineer‘s professional peers; and
b) conduct that demonstrates a lack of adequate judgement or care in
the practice of engineering; and/or
c) misconduct in a professional respect.
[26] The Act‘s objects are defined in s 3 and the means of achieving them are
contained in s 4.
3. Main objects of Act
The main objects of this Act are —
(a) to protect the public by ensuring professional engineering services are
provided by a registered professional engineer in a professional and
competent way; and
6 Appendix A Statement of Agreed Facts pages 4-5.
7 Appendix A Statement of Agreed Facts pages 5-6.
8 Appendix A Statement of Agreed Facts pages 5-6.
9 Appendix A Statement of Agreed Facts page 6 paragraph 17.
-- 5 of 26 --
6
(b) to maintain public confidence in the standard of services provided by
registered professional engineers; and
(c) to uphold the standards of practice of registered professional engineers.
[27] In furtherance of those objects, the Applicant is effectively charged with
the regulation of registered professional engineers and its functions are
set out in s 80 of the Act. The functions include registration, investigation
of professional conduct of registered engineers and contraventions.
[28] If grounds are established for disciplining a registered professional
engineer pursuant to s 36 of the Act, the Applicant has disciplinary powers
pursuant to s 131 of the Act. The grounds are provided as follows:
36 Grounds for disciplining a registered professional Engineer
Each of the following is a ground (a disciplinary ground) for disciplining a registered
professional engineer—
(a) the engineer has, whether before or after the commencement of this Act,
behaved in a way that constitutes unsatisfactory professional conduct;
(b) the engineer has failed to comply with a provision of this Act or the repealed
Act;
(c) the engineer has been convicted of an offence against an Act of the State,
the Commonwealth or another State related to the practice of engineering;
(d) the engineer has contravened an undertaking entered into by the engineer
and the board under section 73(2)(b);
(e) the engineer has contravened a condition of the engineer‘s registration.
[29] The term ―unsatisfactory professional conduct‖ is defined in relation to a
registered professional engineer in Schedule 2 of the Act as including:
(a) conduct that is of a lesser standard than that which might reasonably be
expected of the registered professional engineer by the public or the
engineer‘s professional peers;
(b) conduct that demonstrates incompetence, or a lack of adequate knowledge,
skill, judgement or care, in the practice of engineering;
(c) misconduct in a professional respect;
(d) fraudulent or dishonest behaviour in the practice of engineering;
(e) other improper or unethical conduct.
[30] The term ―misconduct in a professional respect‖ has been defined in case
law in the following terms ‗conduct that violates or falls short of, to a
substantial degree, the standard of professional conduct observed or
approved by members of the profession of good repute and
competency’.10
[31] The Applicant alleged, and the Respondent accepted, that the facts
disclose that he engaged in unsatisfactory professional conduct, namely:
a) conduct that is of a lesser standard than that which might reasonably
be expected of a registered professional engineer by the public or the
engineer‘s professional peers; and
10 Adamson v Queensland Law Society Inc. [1990] 1 Qd R 498.
-- 6 of 26 --
7
b) conduct that demonstrates a lack of adequate judgement or care in
the practice of engineering; and
c) misconduct in a professional respect.11
[32] The Applicant‘s evidence in support of the assertion is contained in the
investigation report of Mr Jon Van Der Hoeff.12 Examples, broadly stated,
include: the original issued Form 15 Certificate noted loading and
conditions that did not match the loading conditions provided on the
design documentation; upgraded roof purlins provided little benefit in
increasing the capacity of the purlins and not based on logical engineering
assessment; a significant proportion of the ―as-designed‖ components of
the building were unsuitable for their intended application and a number of
―as-designed‖ building inadequacies are demonstrated.13
[33] The Respondent submitted that the following factors set out in his affidavit
are relevant.14 The Applicant did not concede the accuracy or relevance
of these matters. The Respondent stated that:
a) he had not been the subject of disciplinary proceedings prior to this
one;
b) the design originally completed by the Respondent was based on
information provided by Stone Homes; and
i. that such information did not include the precise location of the
property upon which the relevant design was to apply;
ii. the Respondent was originally directed, by his client, to
complete a design suitable for Terrain Category 1 Region B;
iii. the design completed was suitable for Terrain Category 1
Region B as the Respondent was originally directed and there is
no evidence from the Applicant to the contrary;
iv. the Respondent accepts that his reliance upon the information
provided to him by his client was imprudent.
c) Whilst the Respondent accepted that the Second Design Certificate
was inappropriate he submitted that the following are mitigating
factors:
i. he understood and accepted that the structural integrity of the
building was inadequate for Terrain Category 2 Region C;
ii. he had discussed interim measures to improve the structural
integrity of the building with his client, Stone Homes, and
understood and was assured by Stone Homes that the interim
11 Appendix B Joint Submissions of the Applicant and the Respondent page 3.
12 Appendix B Joint Submissions of the Applicant and the Respondent pages 3-4:
Annexure KCM-11 to the Affidavit of Katherine Clare Murray filed 19 April 2013.
13 Appendix B Joint Submissions of the Applicant and the Respondent page 4. The
Applicant relies upon the investigation report of Jon Van Der Hoeff dated January 2011
in full and without detraction from its detail.
14 Appendix B Joint Submissions of the Applicant and the Respondent page 4. The
Respondent relies upon his affidavit sworn on 29 July 2013 and filed in the proceeding.
-- 7 of 26 --
8
measures would be put in place and that a proper solution will
ultimately be implemented;
iii. he was not in a contractual relationship with the owner of the
subject property and consequently was not in a position to
manage the implementation of strengthening method measures;
iv. he accepted that he should have taken further steps to assure
the integrity of the structure; and
v. he has modified his practices to ensure that a repeat of the
circumstances in which the structure was inadequate for the
loading specified in the design certificate is not repeated.15
[34] The Applicant did not concede: the evidence of the Respondent as to an
agreement with his client, Stone Homes, for appropriate remediation at a
later date; that he issued inappropriate certifications upon the strength of
his understanding; that the Respondent‘s reliance upon Stone Homes
implementing appropriate rectification was, whilst objectively
inappropriate, consistent with a longstanding business relationship.
The Applicant did not concede that the final form of the building structure
was intended to be compliant notwithstanding the interim non-
compliance.16
[35] The Tribunal accepts that the Respondent now understands the
inappropriateness of the conduct in which he engaged and has
implemented procedures to avoid re-occurrence of similar events.
[36] The Respondent has recognised the error in his conduct and has
implemented steps to avoid a repeat of that error so as to eliminate the
risk a repeat of such conduct would impose upon the community.
Penalty
[37] Where the Tribunal is satisfied that a disciplinary ground is established
against a registered professional engineer it has power, under section 131
of the Act, to make various orders:
131 Orders relating to registered professional engineer
(1) If the tribunal decides that a disciplinary ground is established, the tribunal
may—
(a) make 1 or more of the orders mentioned in subsections (2) to (4); or
(b) take no action against the registered professional engineer.
(2) The tribunal may order the registered professional engineer to pay a stated
amount of not more than the equivalent of 200 penalty units.
(3) Also, the tribunal may make an order—
(a) reprimanding the registered professional engineer; or
15 Appendix B Joint Submissions of the Applicant and the Respondent pages 4-5.
16 Appendix B Joint Submissions of the Applicant and the Respondent page 5.
-- 8 of 26 --
9
(b) imposing a condition on the registered professional engineer‘s
registration including, for example, to submit to an audit of the
engineer‘s practice of engineering; or
(c) suspending the registered professional engineer‘s registration for a
stated period; or
(d) cancelling the registered professional engineer‘s registration; or
(e) disqualifying, indefinitely or for a stated period, the registered
professional engineer from obtaining registration as a registered
professional engineer.
(4) An order for payment of an amount under subsection (2) may direct that, if
the registered professional engineer does not pay the amount within the
period stated in the order, the registered professional engineer‘s registration
be suspended until the amount is paid.
(5) If the registered professional engineer does not pay the amount within the
stated period, the registration is suspended until the earlier of the following—
(a) the day the amount is paid;
(b) the day the registration expires.
(6) The suspension under subsection (5) takes effect immediately after the end
of the stated period.
[38] The Tribunal is satisfied that the conduct the subject of the charges and
the risk posed to life and property which it caused, justifies significant
penalty in order to protect the public and to provide a meaningful deterrent
against similar conduct by other registered professional engineers.
[39] The Applicant accepts the statement of principle which applies to the
exercise of discretion in disciplining an engineer under the Act is that set
out in Adamson v Queensland Law Society Inc at 504:
….The power of the court to discipline a barrister is ‗entirely protective and,
notwithstanding that its exercise may involve a great deprivation to the person
disciplined, there is no element of punishment involved‘. (New South Wales Bar
Association v Evatt (1968) 117 CLR 177 at 183-184; Clyne v New South Wales Bar
Association (1960) 104 CLR 186, 201, 202.) The same view has been taken in
relation to disciplinary proceedings against solicitors (Southern Law Society v
Westbrook (1910) 10 CLR 609, 619, 625-626, 627; Re Meagher (1896) 17 LR
(NSW)157,166-168 and Harvey v Law Society of New South Wales (1975) 49
ALJR 362,364). At least since Lord Mansfield‘s time the striking of a solicitor from
the rolls has been regarded as ‗not in the nature of a new trial or a second
punishment‘ but as involving whether he should remain ‗a member of a profession
which should stand free of all suspicion.‘ (Ex parte Brounsall (1778) 2 Cowp. 829;
98 ER 1385 per Lord Mansfield CJ.
[40] Accordingly, in considering an order under s 131 of the Act, the overriding
principle for the Tribunal to apply is what is necessary to protect the
community in Queensland from any repeat of the conduct by the
Respondent.
[41] The Applicant, with the agreement of the Respondent, has submitted the
proposed penalty and seeks orders of the Tribunal in terms of the Joint
Submissions pursuant to s 131(1) of the Act.17
17 Appendix B Joint Submissions of the Applicant and the Respondent pages 6 – 7.
-- 9 of 26 --
10
[42] The Respondent has accepted in principle that the proposed penalty and
orders are appropriate in the circumstances of the relevant conduct and
will consent to orders on those terms being made by the Tribunal. 18
Tribunal’s discretion
[43] The Tribunal retains the ultimate discretion as to whether or not it is
satisfied that the Respondent‘s conduct amounts to unsatisfactory
professional conduct for the purposes of the Act and, if so, whether the
proposed penalty is, in the circumstances, justified (from the Respondent‘s
perspective) and adequate (from the Applicant‘s and the public‘s
perspective) given the objects and requirements of the Act.
[44] The Applicant submits that the Tribunal should give weight to the fact that
the Applicant, as the professional regulator, has formed a view as to the
nature and seriousness of the Respondent‘s conduct and the penalty
which should follow, and to the fact that the Respondent accepts that
penalty and has been agreed it should be recommended to the Tribunal.19
[45] In consideration of the Agreed Statement of Facts and the Joint
Submissions of the parties it is important that weight be given to the
submissions of the Applicant as well as the concessions of the
Respondent.
[46] The objects of the Act as set out in s 3 above emphasise the protection of
the public; the maintenance of public confidence in the professional
standards of registered engineers and the upholding of the standards of
registered professional engineers. These objectives are all protective in
focus. It is appropriate that the deterrent effect of any orders or penalty
should tend to uphold the objects of the Act.20 The penalty should be
commensurate to the level of unsatisfactory professional conduct without
being oppressive21 as well as reflective of the disciplinary powers of the
Applicant. The tribunal is satisfied that the penalty proposed by the parties is
appropriate in the circumstances as outlined.
[47] The level of unsatisfactory professional conduct is established.
18 Board of Professional Engineers of Queensland v Zaranis [2009] CCT ED001-09 at
[17] to [21]; Board of Professional Engineers of Queensland v Matiukevitch [2006] CCT
K002-05 at [38] to [41]; Board of Professional Engineers of Queensland v Enzo
Bartilomo [2006] CCT ED008-05 at [12] and [13].
19 Board of Professional Engineers v Khatri t/as Umesh C Khatri Civil and Structural
Engineers [2013] QCAT 106 at [11] and [12].
20 Board of Professional Engineers of Queensland v Zaranis [2009] CCT ED001-09 at
[14].
21 Board of Professional Engineers of Queensland v Zaranis [2009] CCT ED001-09 at
[14].
-- 10 of 26 --
11
Orders
[48] The Tribunal orders that:
a) the Respondent is reprimanded pursuant to s131(3)(a) of the Act;
b) a penalty in the sum of $5,000 is imposed upon the Respondent
pursuant to section 131(2) of the Act such amount is to be paid in
three equal monthly instalments of $1,666.66 with:
i. the first instalment is to be paid within 3 business days of
this order; and
ii. the second instalment is to be paid within 30 days of this
order; and
iii. the third instalment is to be paid within 60 days of this
order;
c) should the penalty or any part thereof not be paid by the dates stated
in this order, the Respondent‘s registration is suspended under
section 131(4) of the Act until the earlier of the date the amount is
paid or the day registration expires unless otherwise suspended by
reason of clause (c) herein; and
d) there is no order as to costs.
-- 11 of 26 --
-- 12 of 26 --
-- 13 of 26 --
-- 14 of 26 --
-- 15 of 26 --
-- 16 of 26 --
-- 17 of 26 --
-- 18 of 26 --
-- 19 of 26 --
-- 20 of 26 --
-- 21 of 26 --
-- 22 of 26 --
-- 23 of 26 --
-- 24 of 26 --
-- 25 of 26 --
-- 26 of 26 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/689