Bellamy t/as Bellamy Plumbing Pty Ltd v Burbage [2013] QCAT 649
CITATION: Bellamy t/as Bellamy Plumbing Pty Ltd v
Burbage [2013] QCAT 649
PARTIES: Derek Bellamy t/as Bellamy Plumbing Pty Ltd
(Applicant)
v
Catherine Burbage
(Respondent)
APPLICATION NUMBER: MCDO139/13
MATTER TYPE: Other civil dispute matters
HEARING DATE: 11 November 2013
HEARD AT: Holland Park
DECISION OF: Member Favell
DELIVERED ON: 20 November 2013
DELIVERED AT: Brisbane
ORDERS MADE: Application is dismissed.
CATCHWORDS: Minor Civil Dispute – whether debt – whether
agreement for additional work
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Dereck Bellamy (Director of Bellamy Plumbing
Pty Ltd)
RESPONDENT: Catherine Burbage
REASONS FOR DECISION
[1] The applicant seeks an order that there be payment by the respondent of
$1,605 in respect claimed of extra plumbing works and electrical works
carried out at 9 Littles Road, Glasshouse Mountains, for the installation of
a sceptic and holding tank.
[2] It also seeks a filing fee of $101.40 and a service fee of $100. It also
seeks interest of 10% for 735 days.
[3] The respondent opposed the application on the basis that she had a quote
to have the work carried out and was never approached about any extra
-- 1 of 5 --
2
work or extra charges. She says that there is no agreement for any
variation.
[4] The Tribunal has been supplied with quote 974 dated 2 May 2011 which
was signed and accepted by the respondent.
[5] The quote was for $10,515.50 being for work described as follows:
Wastewater systems QLD will supply and install to Catherine Burbage at 9 Littles
Pl, Glasshouse Mountains, 3000L concrete sceptic tank and 7200L holding tank
80mm PBC outlet pipe to road with ball valve.
Price includes:
Full installation and labour, pump out and decommissioning of sceptic tank,
bedding material, excavation x 10 hours plus BSA home insurance.
Price does not include removal and spreading of soil, council application fees.
[6] The wording of the agreement included the following:
(1) I wish to purchase the items and services described above. I note that we do
not have title to the system tanks or pumps until I have fully paid the full price and
system tank, pumps or irrigation pipe work may be reclaimed at any time at our
costs, for our failure to pay any balance owing.
(2) If, for any reason the tank cannot be craned into the hole by the sewerage
system delivery truck, I agree to meet the costs in full for the hire of a mobile crane,
organised by the installer.
(3) The owner is responsible for the location and marking of underground surfaces.
Price variation may apply for costs associated with excavation of rock, underground
water or changes to irrigation design.
(4) This quote excludes electrical supply in connection to the system, plumbing
from house into the system, removal or spreading of excess soil, soil supplied or
council application fees.
(5) Responsibility for loss or damage passes to the client immediately after
installation/delivery.
(6) Deposit paid on acceptance is refundable minus any and all incurred costs.
Full payment will be made on or before the day of delivery.
[7] In the application the applicant says
Derek Belamy from Bellamy Plumping Pty Ltd is seeking payment for extra
plumbing and electrical works carried out at 9 Littles Roads, Glasshouse
Mountains, for installation of sceptic and holding tank. Our quote did not allow for
electrical works, excavation of rocks, alarm and repair of plumbing under the
house, and it clearly states that. When council requested this to be done
I immediately phoned Catherine requesting approval to do this and it was approved
over the phone.
[8] The respondent says that she was not contacted by Mr Bellamy about
extra charges. She says that a global testing report and Caloundra
Council plan was forwarded to assist Mr Bellamy prior to commencing
work so that he could cost out and provide a quote which met with the
Caloundra City Council regulations and was within her budget. She told
Mr Bellamy that she would be taking out a loan for the work and that at all
times he needed to be upfront and forthcoming with costs.
-- 2 of 5 --
3
[9] She says that Bellamy Plumbing was given all plans by the Council
inspector prior to commencing work. She says that the plans clearly
explain and state what requirements needed to be met for the installation.
She says that the plans which are provided by the Council and are now
exhibit one, show a typical holding and tank pump out installation.
That plan includes the words:
All holding tanks are to be fitted with an audio and visual alarm system. All holding
tank installations must be provided with an 80mm DIA pressure pump line
extended to the property boundary. If point of discharge is lower than the holding
tank, a gate valve must be installed. The maximum length of pipe should not
exceed 30m. The maximum vertical height allowable from the bottom of the holding
tank to the pump out point or road shall not exceed 5m. If these requirements
cannot be met a 3900L all-purpose sceptic tank and 450L pump well may be
installed to pump uphill to the holding tank. The base of the holding tank shall be
anchored with concrete to prevent lifting.
[10] The global test locality plan is exhibit two. It shows the location of the two
tanks and an 80mm suction line to be installed. It also includes the words
„existing residents (disconnect existing sceptic system and reroute to now
recommend system)‟.
[11] The applicant has not provided any receipts to support the extra claim.
I was told at the hearing that alarm posts as required along with a light and
float cost $385, electrical work for 30 metres cost $770, extra excavation
costs $300 and plumbing under the house cost $150.
[12] Mr Bellamy said that he contacted Ms Burbage about the extra work after
he says the council inspector required the work to be done and asked
Ms Burbage whether she wanted the work done then. He said that she
told him she did.
[13] Ms Burbage says she was not contacted by Mr Bellamy about extra
charges and she could not understand why there would be an extra
charge because a conduit which apparently was part of the electrical work
had already been laid.
[14] In a statement that she tended which was a letter addressed to
Mr Bellamy she said :
in a telephone conversation we had on 30 July, Friday, where you informed me that
at the final inspection the council inspector had demanded that the system was
fitted with audio and visual alarm I was distressed about this and rang to speak to a
council inspector to clarify the situation on the same day we had spoken, and
spoke to Peter Rimes with the Caloundra Council. Peter assured me of two things,
one, that he was surprised that you had informed that you had just been told that
this safety device was to be installed as there had been a council inspector there
the day before and he had noted that the conduit was being laid for this and that
the requirement of alarm system was clearly stated in the original plans sent to you
by council.
[15] In my view, the quote which was given and accepted did not include the
cost of electrical supply in connection with the system. I accept what
Ms Burbage says about her telephone conversation with Mr Bellamy on
30 July. That seems to accept that indeed there was a telephone
-- 3 of 5 --
4
conversation as asserted by Mr Bellamy about the extra work.
Ms Burbage‟s concern was that a conduit had already been laid and the
requirement for alarm system had already been identified.
[16] I accept that there was a telephone conversation with Mr Bellamy and
Ms Burbage about the extra work. I find that it is likely that Mr Bellamy did
contact Ms Burbage about the claimed extra charges. I do not however
accept that all of the work described by Mr Bellamy was extra work under
the accepted quote. In my view it is likely that Mr Bellamy did have the
council documentation and knowledge of the council requirements. In any
event as a licenced plumber operating within the council plumbing
requirements, he should have had that knowledge.
[17] In my view the quote properly construed was for the full installation and
supply of the 3000L concrete sceptic tank and 7200L holding tank.
That included, in my view, all of the plumbing requirements for the
installation. In my view, the use of the term “full installation” makes that
clear.
[18] The accepted quote however makes it clear that electrical supply in
connection with the system, plumbing from the house into the system and
removal or spreading of excess soil and council application fees was
excluded.
[19] Mr Bellamy has not in my view proved that there was any extra excavation
required outside of that excavation which was included in the price.
[20] In my view the costs of the alarm posts as required along with a light and
float were included in the “full installation”.
[21] The electrical work was specifically excluded as was plumbing from the
house into the system. In my view the latter included plumbing under the
house.
[22] The claim made by the applicant is a claim made as a minor civil dispute
claim and in particular a minor debt claim in the minor civil dispute
jurisdiction of QCAT.
[23] The Tribunal may exercise its jurisdiction for a minor civil dispute if a
relevant person has, under the Queensland Civil and Administrative
Tribunal Act 2009 (QCAT Act), applied to the Tribunal to deal with the
dispute.1
[24] A relevant person relevantly includes –
(a) For a claim to recover a debt or liquidate demanded money – a person to
whom the debt is owed or money is payable;
(b) Subject to paragraph c to j, for a claim arising out of contract between a
consumer and a trader, - the consumer.
1 QCAT Act s 12.
-- 4 of 5 --
5
[25] Despite what I have said above about the electrical work being excluded
from the accepted quote and the plumbing work under the house also
being excluded, I am not satisfied that Ms Burbage understood that she
was being asked to agree to further charges or did agree to further
charges in the telephone conversation of 30 July. In fact, on hearing
Ms Burbage, I came to the view that there was a certain amount of
confusion.
[26] I was not told of any prices being mentioned to Ms Burbage nor of any
extent of extra work which was required. I find that there was no
agreement between Ms Burbage and the applicant that Ms Burbage would
pay any liquidated amount or otherwise for the work claimed.
[27] In my view, the applicant has not established that there is a debt owed or
money payable.
[28] Further, in my view, this work was regulated under the Domestic Building
Contracts Act 2000. Domestic building work includes the renovation,
alteration, extension, improvement of repair of a home.2 It also includes
work associated with the renovation, alteration, extension, improvement of
repair of a home and includes the provision of services or facilities to the
home or the property on which the home is situated.
[29] In my view the work which was undertaken here is covered by the
Domestic Building Contracts Act.
[30] Section 26 of the Domestic Building Contracts Act requires a regulated
contract to be put into a written form. Section 27 provides for the general
contents of contracts. The contract here was, it being for work greater than
the regulated amount, a regulated contract.
[31] Any variations to contracts are required to be in writing.3 That has not
occurred here. Section 84 of that Act provides for the right of a building
contractor to recover an amount for a variation. The applicant has not
complied with the requirements of the Domestic Building Contracts Act
with respect to variations and in such a case the building contractor may
only recover an amount for the variation with the Tribunal‟s approval given
on an application made as provided under the QCAT Act to the Tribunal
by the building contractor. That has not occurred here.
[32] I am not satisfied that there is a debt owed for the reasons that I have
given above or that the money is payable. The application is dismissed.
2 Domestic Building Contracts Act 2000 s 8.
3 Domestic Building Contracts Act 2000 s 79.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/649