Campbell v Telford & Anor [2013] QCAT 620
CITATION: Campbell v Telford & Anor [2013] QCAT 620
PARTIES: Mr Gregory Campbell
(Applicant)
v
Mr Mark Telford
Ms Nynke Heida
(Respondents)
APPLICATION NUMBER: BDL342-12
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Allen
DELIVERED ON: 14 November 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. Mr Telford and Ms Heida are ordered to
pay Mr Campbell the amount of $3,609.75
in default interest within 14 days of the
date of this order.
2. Mr Telford and Ms Heida are ordered to
pay Mr Campbell the amount of $9,811.84
in debt collection costs within 14 days of
the date of this order.
CATCHWORDS: BUILDING DISPUTE – default interest and debt
collection costs – contractual right to costs
Lida Build Pty Ltd v Miller & Anor [2013] QCATA
139
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] This decision relates to interest and debt recovery costs to which Mr
Campbell became entitled to as a result of Tribunal’s decision of 7 August
2013 in respect of a building dispute between the parties. The Tribunal
-- 1 of 3 --
2
awarded Mr Campbell an amount of $21,419.10 in respect of his final
progress claim and he became entitled to default interest and recovery
costs in respect of this amount in accordance with the contract between
the parties.
[2] The entitlement to and calculation of default interest is contained in clause
33 of the general conditions of the contract as follows “if the owner does
not pay any amount owing to the builder in full by the due date, then the
owner must pay default interest on such amount that is unpaid from time
to time”. Default interest is defined in clause 38 of the general conditions
as “the annual rate equal to the Commonwealth Bank overdraft index rate:
quarterly charging cycle plus 5%”.
[3] The parties were directed to file submissions in regard to the amount
payable in respect of default interest. Woods Hatcher, Solicitors and
Attorneys on behalf of Mr Campbell calculated his entitlement to default
interest as $3,609.75 on the basis that the tax invoice in question No
M2013 was issued on 25 June 2012 and was due and payable on 2 July
2012. The number of days between that date and the date of the decision
is 401 and the applicable rate of interest is 15.34% which is the relevant
CBA rate plus 5%. The Tribunal is satisfied that calculation is on its face
correct.
[4] Industry Lawyers made submissions on behalf of Mr Telford and Ms
Heida. The submissions attempt to re-enliven issues about when practical
completion occurred. This was dealt with in the reasons and it is clearly
stated that practical completion occurred on 25 June 2012 and further that
Mr Telford has accepted that the amount of $21,419.10 is due and
payable. It is then submitted that interest should if payable only be
payable from the date of the hearing on the basis that it was only at the
hearing that certain evidence in regard to the sarking became apparent at
the hearing. The interest rate supplied on behalf of Mr Telford and Ms
Heida is substantially less than that of Mr Campbell’s but only related to
the period around 14 August 2013.
[5] Mr Telford had accepted practical completion on 25 June 2012 and that
the tax invoice was payable. In which case default interest is payable from
the date that payment was due in accordance with clause 33 of the
general conditions. The interest rate submitted on behalf of Mr Campbell
is preferred as it covers the whole period of 401 days for which interest is
payable. Therefore the Tribunal is satisfied that default interest is payable
in respect of tax invoice M2013 in the amount of $3,609.75.
[6] Mr Telford and Ms Heida are ordered to pay Mr Campbell the amount of
$3,609.75 in default interest within 14 days of the date of this order.
[7] The entitlement to Debt Collection Costs is contained in clause 34 of the
contract general conditions as follows “the owner must pay to the builder
any debt collection costs, including any legal fees on a solicitor and own
client basis, associated with recovering or the attempted recovery of an
amount under this contract”.
-- 2 of 3 --
3
[8] Woods Hatcher submitted in regard to the debt collection costs that the
following amounts should be allowed:-
a) QCAT application fee $275.00
b) Solicitor and own clients
costs from the date of initial instructions $9,536.84
Total $9,811.84
[9] Woods Hatcher notes that Mr Telford and Ms Heida were represented up
to the a certain point in the proceeding and that detailed consideration was
required to be given to responding to the counterclaim and in all the
circumstances of the complexity of the matter Mr Campbell is entitled to
recover his costs.
[10] Industry Lawyers submit that the costs should be set as nil and refers to s
100 of the Queensland Civil and Administrative Tribunal Act 2009, which
is the Tribunal’s general cost provision and further that the amount would
have been a minor debt and therefore only the costs available under Rule
84 of the Tribunal’s rules should apply. It was also submitted that the costs
should be apportioned between the debt recovery and the counterclaim.
[11] As was made clear in the primary decision the costs available under
clause 34 of the general conditions are not subject to s100 of the QCAT
Act1. Even if the claim had have been filed as a minor debt the costs
would have been allowable on the contractual basis. The counterclaim
was either withdrawn in parts or dismissed. The Tribunal is satisfied that
all of the costs incurred relate to the recovery of the amount due and
owing as Mr Telford and Ms Heida were not successful in regard to the
counterclaim and it was accepted at the hearing that the tax invoice was
payable.
[12] The tax invoice should have been paid and the fact it wasn’t gave Mr
Campbell to have his costs assessed in accordance with clause 34 of the
general conditions. If the tax invoice had been paid and Mr Telford and Ms
Heida had brought a claim for defective building work then costs would
have been determined under s100 of the QCAT Act.
[13] Mr Telford and Ms Heida are ordered to pay Mr Campbell the amount of
$9,811.84 in debt collection costs within 14 days of the date of this order.
1 Lida Build Pty Ltd v Miller & Anor [2013] QCATA 139.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/620