Chow v Sunstate Design & Construct Pty Ltd [2013] QCAT 616
CITATION: Chow v Sunstate Design & Construct Pty Ltd
[2013] QCAT 616
PARTIES: Mr Jerald Chow
(Applicant)
v
Sunstate Design & Construct Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL084-13
MATTER TYPE: Building matters
HEARING DATE: 11 November 2013
HEARD AT: Brisbane
DECISION OF: Member Roney
DELIVERED ON: 11 November 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. I allow the Applicant’s claim as follows:
(1) Reimbursement of monies paid under the
contract $15,629.14
(2) Rectification costs $ 9,800.00
(3) Rental claim $ 6,000.00
(4) Filing fee $ 275.00
$31,704.14
2. I order the respondent to pay the
applicant the sum of $31,704.14 within
3 months.
CATCHWORDS: Building matters – Termination of contract –
lawfulness thereof – damages
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Jerald Chow appeared in person
RESPONDENT: Sunstate Design & Construct Pty Ltd
represented by Ric Chan
-- 1 of 4 --
2
REASONS FOR DECISION
[1] This is a dispute about the demolition of an existing deck and the
construction of a new one to an unoccupied dwelling at Saunders Street,
Indooroopilly. There is a contract in existence between the parties,
the applicant and the respondent, dated 31 July 20131 for an agreed fixed
price of $43,499.00.
[2] The contract type is a home brand Sunstate Design & Construct contract
with some 20 pages of conditions, nowhere is the term “design” and
“construct” defined. It includes a payment schedule, it includes
specification, sketch plan and some generic computer generated
drawings. These drawings, on the evidence, which I accept, did not
provide sufficient detail or specification for construction; they contemplated
further drawings being prepared which met the applicant’s requirements.
There appears on the evidence before me to be general consensus that
this was the case, that at some future time the parties would be forced to
come together again to agree on some greater detail. The further
agreement which should have taken place, I find it was the builder’s
obligation to obtain, but he did not so obtain on the evidence which
I accept.
[3] The question for the Tribunal’s determination today is whether the contract
termination by the applicant was lawful. The applicant purported to do this
by letter dated 30 November 2012.
[4] Today has been a hearing, the time for mediation or further discussion is
long past. This is a regretful situation however the Tribunal’s function
today is to make a determination. In relation to the question of whether
the termination by the applicant was correct, in summary I find that it was.
I find that the builder, the respondent, by his conduct had repudiated the
contract in the following respects:
1. Failing to provide plans or specifications which were capable of
forming working documents for the purpose of construction, until after
that construction had commenced.
2. Failing to provide working documents which were reasonably
consistent with the drawings and specifications identified as part of
the contract documents on 31 July 2012.
3. Failing to build in a manner reasonably consistent with those existing
contract documents as at 31 July 2012.
4. Failing to install a lysaght metal flooring system as that was the
system as represented by the contract that the builder would provide.
5. Failing to obtain Council approval for a plan to be constructed in
accordance with the contract.
6. Obtaining Council approval for a plan, which the builder accepted in
evidence, that he was not intending to build.
1 Exhibit 1 in the proceedings.
-- 2 of 4 --
3
7. Making demand for payment of the second stage payment,
the statutory approval payment, when that stage had not been
completed in that the plans submitted to Council for approval and
in fact approved were not the plans the structure was to be built in
accordance with.
[5] I find that the applicant was entitled to accept that repudiation which I find
he did by his letter of termination dated 30 November 2012.
[6] I find that the applicant lawfully terminated the contract and that he is
entitled to damages for breach of contract.
[7] I accept the evidence of Mr Leonard for the applicant that what is in
existence at the site has not been constructed in accordance with the
working drawings, is defective, of no use and, should be demolished.
[8] I find that the documents provided by Fast Track to obtain Council
approval did not represent what the homeowner applicant had agreed
upon and were generic documents produced by that firm that did not make
adequate reference to the home owners requirements. The origin of the
problem in this dispute has been the builder’s failure to provide proper
engineering documents at the time of execution of the contract.
[9] Specifically I reject the evidence or Mr Kosch and Mr Chan that:
a) the applicant knew he was not going to get a structure built in
accordance with the plan;
b) that the applicant knew that he was not going to get a lysaght flooring
system although mention of that product is referenced in the contract
documents by 31 July 2013 and the further design documents of
8 August 2013;
c) that the applicant authorised the construction of the structure that has
been built on his property; and
d) that the structure as erected is sound from an engineering point, as
neither party is qualified to give that evidence.
[10] I find the respondent is in breach of contract and has no entitlement to be
paid at all but in any event, I find that the value of the work performed is
nil.
[11] By way of damages the applicant seeks reimbursement of monies paid
less demolition fees. The applicant seeks an amount calculated as
$17,129.41 less $1,500.00, a sub total of $15,629.14.
-- 3 of 4 --
4
[12] I allow that amount to the applicant. The applicant also seeks an amount
of $9,800.00 being:
$ 600.00 for gas repairs;
$4,000.00 for replacement of stirrup post anchors;
$3,200.00 for replacement of columns; and
$2,000.00 for the restoration of gutters.
[13] This brings a total of $9,800.00. I likewise allow that amount to the
applicant.
[14] The applicant further brings a claim for damages based upon his inability
to occupy the premises for a period of 10 months from January this year at
a rate of $2,000.00.
[15] In relation to the claim for rental premises, it seems to my mind that there
has been some delay in prosecuting this matter to get to this point today.
While I do not say that it is the applicant’s fault, I do not know that the
respondent should be entirely responsible for that. Some delay, I expect,
is occasioned through the procedure of making application at QCAT and
moving through the normal protocols of the Tribunal. It seems likely on
balance that the additional cost occasioned to the applicants has been by
reason of the delay in the construction being finalised and the advice that
they were given about not proceeding with another contract. However, in
fairness, what I am going to allow to the applicants is an amount
commensurate with 3 months rental, an amount which I calculate at
$6,000.00 in addition to the other claims I’ve allowed. I further allow to
them the filing fee at the Tribunal which they seek of $275.00.
[16] As I say I have taken the unusual step of ex tempore reasons in this
matter because I think there is some urgency to it having regard to the
state the house is in and as we move almost into a Christmas period
where there will be very little opportunity for anything to be done.
[17] In summary I allow the Applicant’s claim as follows:
(1) Reimbursement of monies paid under the contract $15,629.14
(2) Rectification costs $ 9,800.00
(3) Rental claim $ 6,000.00
(4) Filing fee $ 275.00
$31,704.14
[18] I order the respondent to pay the applicant the sum of $31,704.14 within
3 months.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/616